Upper pouring device for building concrete structure

By arranging the speaker box and unloading box device on the concrete formwork, the problems of material waste and quality hazards during the pouring of the upper part of the concrete structure are solved, the recycling of concrete and the improvement of construction efficiency are realized, and the improvement of pouring quality is ensured.

CN221837983UActive Publication Date: 2024-10-15SHAANXI NO 11 CONSTR ENG CO
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420391939.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-29
Publication Date
2024-10-15
Estimated Expiration
2034-02-28

AI Technical Summary

Technical Problem

During the pouring process of the upper part of the existing concrete structure of the building, the formwork and pouring of the concrete formwork have problems of material waste, construction inconvenience and quality hazards. In particular, the filling at the top of the structural column is not dense and the repair quality is difficult to control.

Method used

A pouring device for the upper part of the building concrete structure including an installation mechanism and a pouring mechanism is designed. By setting up a speaker box and a discharge box on the concrete formwork, the introduction and recycling of concrete slurry can be achieved to avoid excessive load on the top of the formwork, and through the separation The structure of partitions and inserts ensures the tightness of pouring.

Benefits of technology

It realizes the recycling of concrete, reduces material waste, improves construction quality and efficiency, avoids excessive load on the top of the formwork, and ensures the compactness and repair quality of the top of the structural column.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221837983U_ABST
    Figure CN221837983U_ABST
Patent Text Reader

Abstract

The utility model discloses a pouring device for the upper portion of a building concrete structure. The pouring device comprises a mounting mechanism arranged on a concrete formwork and a pouring mechanism arranged on the mounting mechanism. The mounting mechanism comprises a back plate arranged on the outer side face of the concrete formwork, and a first notch allowing concrete to enter the concrete formwork is formed in the back plate. The pouring mechanism comprises a horn box arranged on the back plate, a second notch matched with the first notch is formed in one face of the horn box, the upper portion of the horn box is open, and a discharging box is arranged on the other face of the horn box. By arranging the mounting mechanism, the horn box can be conveniently mounted on the concrete formwork, so that concrete grout is received and guided into the concrete formwork, pouring of a constructional column or a wall body is achieved, redundant concrete grout in the horn box can flow out through the discharging box, recycling of concrete is achieved, and the construction cost is reduced. And overload of the top of the concrete formwork is avoided, and the using effect is good.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of grouting and pouring construction of columns and walls in building structures, and in particular relates to an upper pouring device for a building concrete structure. Background Art

[0002] The formwork and casting of the secondary structural columns of the building masonry project requires pouring concrete from the reserved holes on the top. Before pouring, a triangular funnel mold made of templates needs to be installed at the hole position. The mouth of the triangular funnel mold should be higher than the upper mouth of the structural column to ensure that the concrete on the top of the structural column is poured on the upper mouth of the structural column to ensure filling and compactness. The same requirements apply to building walls.

[0003] The general construction process is to use a portable electric pick to chisel out the excess exposed concrete after the concrete has finally set, and then use cement mortar to level it. However, the depth of the chiseling is difficult to control, and it is easy to disturb the interior of the newly solidified concrete. The excess concrete will also become construction waste, resulting in material waste, labor and time. In addition, when constructing the concrete formwork, the triangular funnel mold at the mouth is not installed, but the concrete is poured to the bottom of the reserved mouth. When the concrete gradually loses its plasticity after the initial setting, the top of the structural column is filled and blocked, which can easily lead to the top of the structural column being filled loosely, the quality controllability of the mouth blocking repair is poor, labor and time are wasted, and there are quality risks at the top of the structural column. Therefore, a structural column upper pouring device that can recycle concrete and can be used cyclically is needed. Utility Model Content

[0004] The technical problem to be solved by the utility model is to provide a device for pouring the upper part of a building concrete structure in view of the deficiencies in the above-mentioned prior art. The device has a simple structure and a reasonable design. By arranging a mounting mechanism, it is convenient to install the speaker box on the concrete formwork, thereby receiving the concrete slurry and introducing it into the concrete formwork to realize the pouring of the structural column. The excess concrete slurry in the speaker box can flow out through the discharge box, thereby realizing the recycling of the concrete and avoiding excessive load on the top of the concrete formwork, and the use effect is good.

[0005] In order to solve the above technical problems, the technical solution adopted by the utility model is: a device for pouring the upper part of a building concrete structure, characterized in that it comprises a mounting mechanism arranged on a concrete formwork and a pouring mechanism arranged on the mounting mechanism;

[0006] The mounting mechanism comprises a back plate arranged on the outer side of the concrete formwork, a first notch for concrete to enter the interior of the concrete formwork is opened on the back plate, a partition plate is arranged on both sides of the first notch, an L-shaped inner folding plate is arranged on both sides of the first notch close to the concrete formwork, an L-shaped outer folding plate is arranged on both sides of the first notch away from the concrete formwork, and a first plugging plate for shielding the first notch is inserted between the L-shaped inner folding plate and the partition plate;

[0007] The casting mechanism includes a speaker box arranged on the back plate, a support plate for supporting the speaker box is arranged at the bottom of the first slot, a second slot adapted to the first slot is opened on one surface of the speaker box and the upper part is open, folding plates are arranged on both sides of the second slot, the folding plates are inserted between the L-shaped outer folding plate and the partition plate, a discharge box is arranged on the other surface of the speaker box, one surface of the discharge box is communicated with the interior of the speaker box, the other surface of the discharge box is open, and a second plug plate is inserted between the discharge box and the speaker box.

[0008] The above-mentioned upper pouring device for building concrete structure is characterized in that screws anchored in the concrete formwork are penetrated on the back plate.

[0009] The above-mentioned upper pouring device for building concrete structure is characterized in that a first pull plate is arranged on the upper part of the first plug plate, and a second pull plate is arranged on the upper part of the second plug plate.

[0010] The above-mentioned upper pouring device for building concrete structure is characterized in that: a U-shaped clamp for the second plug plate to pass through is provided on the speaker box, the U-shaped clamp is located above the discharge box, and a through hole for the second plug plate to pass through is opened on the upper part of the discharge box, and the second plug plate is close to the outer wall of the speaker box.

[0011] The above-mentioned upper pouring device for building concrete structure is characterized in that a connecting plate is arranged between the two partition plates.

[0012] The above-mentioned upper pouring device for building concrete structure is characterized in that the side of the L-shaped inner folding plate and the first plug plate away from the speaker box is flush with the inner side surface of the concrete template.

[0013] Compared with the prior art, the utility model has the following advantages:

[0014] 1. The utility model is easy and quick to operate. By setting the installation mechanism, it is easy to be installed on the concrete formwork. By setting the partition plate, it is easy to insert the first plug plate on the inner side of the partition plate to achieve the blocking of the first notch, and the folding plate is inserted on the outer side of the partition plate to achieve the installation of the speaker box, so as to avoid the speaker box being affected when the first plug plate is pulled, so that the speaker box is shifted and causes leakage, and the utility model is highly practical.

[0015] 2. The utility model provides a horn box to facilitate receiving concrete slurry, and introduces the concrete slurry into the concrete formwork through the first notch and the second notch, so as to realize the casting of the structural column, and the use effect is good; by providing a discharge box, after the casting of the structural column or the wall is completed, the second plug plate is pulled out to make the excess concrete slurry in the horn box flow out through the discharge box, thereby realizing the recycling of concrete and reducing the weight of the horn box, avoiding excessive load on the top of the concrete formwork, which is not conducive to the stability of the concrete formwork.

[0016] 3. The utility model sets the L-shaped inner folding plate and the first plug plate so that the side away from the speaker box is flush with the inner side of the concrete template, so that after the concrete solidifies and the concrete template is removed, the concrete on the surface of the structure is flush, avoiding the secondary removal of uneven concrete at the grouting port, reducing the construction process, and improving the construction quality and appearance.

[0017] To sum up, the utility model has a simple structure and a reasonable design. By arranging a mounting mechanism, it is convenient to install the speaker box on the concrete formwork, thereby receiving the concrete slurry and introducing it into the concrete formwork to realize the casting of the structural column or wall. The excess concrete slurry in the speaker box can flow out through the unloading box, thereby realizing the recycling of the concrete and avoiding excessive load on the top of the concrete formwork, and the use effect is good.

[0018] The technical solution of the utility model is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a structural schematic diagram of the utility model.

[0020] Figure 2 It is a structural schematic diagram of the installation mechanism of the utility model.

[0021] Figure 3 for Figure 1 Enlarged view of point A.

[0022] Figure 4 for Figure 1 Enlarged view of point B.

[0023] Description of reference numerals:

[0024] 1-concrete formwork; 2-back plate; 3-screws;

[0025] 4-partition plate; 5-connection plate; 6-L-shaped inner folding plate;

[0026] 7-L-shaped outer folding plate; 8-first plug plate; 9-first pull plate;

[0027] 10- pallet; 11- speaker box; 12- discharge box;

[0028] 13-second plug board; 14-first pull board; 15-U-shaped card;

[0029] 16-Folding plate. DETAILED DESCRIPTION

[0030] like Figures 1 to 4 As shown, the utility model comprises a mounting mechanism arranged on a concrete formwork 1 and a casting mechanism arranged on the mounting mechanism.

[0031] The mounting mechanism includes a back plate 2 arranged on the outer surface of the concrete formwork 1, and a first slot for concrete to enter the concrete formwork 1 is opened on the back plate 2, and partition plates 4 are arranged on both sides of the first slot, and L-shaped inner folding plates 6 are arranged on both sides of the first slot close to the concrete formwork 1, and L-shaped outer folding plates 7 are arranged on both sides of the first slot away from the concrete formwork 1, and a first plug plate 8 for covering the first slot is inserted between the L-shaped inner folding plate 6 and the partition plate 4.

[0032] The casting mechanism includes a speaker box 11 arranged on the back plate 2, a support plate 10 for supporting the speaker box 11 is arranged at the bottom of the first notch, a second notch adapted to the first notch is opened on one side of the speaker box 11 and the upper part is open, folding plates 16 are arranged on both sides of the second notch, and the folding plates 16 are inserted between the L-shaped outer folding plate 7 and the partition plate 4, a discharge box 12 is arranged on the other side of the speaker box 11, one side of the discharge box 12 is communicated with the interior of the speaker box 11, and the other side of the discharge box 12 is open, and a second plug plate 13 is inserted between the discharge box 12 and the speaker box 11, such as Figure 3 shown.

[0033] In actual use, by setting up a mounting mechanism, it is convenient to install on the concrete formwork 1, and by setting up a partition plate 4, it is convenient to insert the first plug plate 8 on the inner side of the partition plate 4 to achieve the blocking of the first slot, and the folding plate 16 is inserted on the outer side of the partition plate 4 to achieve the installation of the speaker box 11, so as to avoid affecting the speaker box 11 when pulling the first plug plate 8, causing the speaker box 11 to shift and cause leakage.

[0034] It should be noted that, by providing the speaker box 11, it is convenient to receive concrete slurry, and introduce the concrete slurry into the concrete formwork 1 through the first slot and the second slot, so as to realize the casting of the structural column or the wall, and the use effect is good; by providing the discharge box 12, after the casting of the structural column or the wall is completed, the second plug plate 13 is pulled out, so that the excess concrete slurry in the speaker box 11 flows out through the discharge box 12, so that the recycling of concrete is realized, and the weight of the speaker box 11 is reduced, so as to avoid excessive load on the top of the concrete formwork 1, which is not conducive to the stability of the concrete formwork 1.

[0035] In this embodiment, screws 3 anchored in the concrete formwork 1 are provided on the back plate 2 .

[0036] In actual use, the number of screws 3 is at least four, and the four screws 3 are respectively penetrated at positions close to the four corners of the back plate 2, so as to facilitate more stable installation of the back plate 2 on the concrete formwork 1.

[0037] In this embodiment, a first pull plate 9 is disposed on the upper portion of the first plug plate 8 , and a second pull plate 14 is disposed on the upper portion of the second plug plate 13 .

[0038] In actual use, by setting the first pull plate 9, it is convenient for the technician to pull the first pull plate 9 to realize the movement of the first plug plate 8, so as to insert and pull out the first plug plate 8 between the L-shaped inner folding plate 6 and the partition plate 4; by setting the second pull plate 14, it is convenient for the technician to pull the second pull plate 14 to realize the movement of the second plug plate 13, so as to insert and pull out the second plug plate 13 between the unloading box 12 and the speaker box 11.

[0039] It should be noted that the first pull plate 9 is vertical to the first plug plate 8, and the first pull plate 9 is located on the side of the first plug plate 8 close to the speaker box 11, and the second pull plate 14 is vertical to the second plug plate 13, and the second pull plate 14 is located on the side of the second plug plate 13 away from the speaker box 11, which is convenient for technicians to operate.

[0040] like Figure 4 As shown, in this embodiment, a U-shaped clamp 15 for the second plug plate 13 to pass through is provided on the speaker box 11, and the U-shaped clamp 15 is located above the discharge box 12. A through hole for the second plug plate 13 to pass through is opened on the upper part of the discharge box 12, and the second plug plate 13 is tightly attached to the outer wall of the speaker box 11.

[0041] In actual use, the through hole on the discharge box 12 is U-shaped, which makes it easy for the second plug plate 13 to be close to the outer wall of the speaker box 11 to prevent concrete slurry from flowing out from the gap around the second plug plate 13. The second plug plate 13 is passed through the U-shaped clamp 15 and between the discharge box 12 and the speaker box 11 in turn to achieve the blockage between the discharge box 12 and the speaker box 11, and the U-shaped clamp 15 is used to further limit the second plug plate 13 to prevent the second plug plate 13 from shaking and causing leakage during the concrete pouring process.

[0042] In this embodiment, a connecting plate 5 is provided between the two partition plates 4 .

[0043] In actual use, after the casting of the structural column or wall is completed, the concrete slurry in the speaker box 11 is discharged from the discharge box 12. At this time, the concrete in the structural column or wall will form lateral pressure on the first plug plate 8. By arranging the connecting plate 5 on the outside of the first plug plate 8, not only can the resistance of the first plug plate 8 to the lateral pressure of the concrete be enhanced, but also the structural stability between the two partition plates 4 can be enhanced, which is highly practical.

[0044] In this embodiment, the L-shaped inner folded plate 6 and the first plug plate 8 have a surface away from the speaker box 11 that is flush with the inner side surface of the concrete formwork 1 .

[0045] In actual use, by setting the L-shaped inner folding plate 6 and the first plug plate 8 so that the side away from the speaker box 11 is flush with the inner side of the concrete formwork 1, the concrete on the surface of the structure is flush after the concrete solidifies and the concrete formwork 1 is removed, avoiding the secondary removal of uneven concrete at the grouting port, reducing the construction process, and improving the construction quality and appearance.

[0046] The above is only a preferred embodiment of the present invention and does not constitute any limitation to the present invention. Any simple modification, change and equivalent structural change made to the above embodiments according to the technical essence of the present invention shall still fall within the protection scope of the technical solution of the present invention.

Claims

1. A device for pouring the upper part of a building concrete structure, characterized in that: It comprises a mounting mechanism arranged on a concrete formwork (1) and a casting mechanism arranged on the mounting mechanism; The mounting mechanism comprises a back plate (2) arranged on the outer surface of the concrete formwork (1), the back plate (2) being provided with a first slot for concrete to enter the interior of the concrete formwork (1), partition plates (4) being provided on both sides of the first slot, L-shaped inner folding plates (6) being provided on both sides of the first slot close to the concrete formwork (1), L-shaped outer folding plates (7) being provided on both sides of the first slot away from the concrete formwork (1), and a first plug plate (8) for shielding the first slot being inserted between the L-shaped inner folding plate (6) and the partition plate (4); The casting mechanism comprises a speaker box (11) arranged on the back plate (2); a support plate (10) for supporting the speaker box (11) is arranged at the bottom of the first notch; a second notch adapted to the first notch is opened on one surface of the speaker box (11) and the upper part is open; folding plates (16) are arranged on both sides of the second notch; the folding plates (16) are inserted between the L-shaped outer folding plate (7) and the partition plate (4); a discharge box (12) is arranged on the other surface of the speaker box (11); one surface of the discharge box (12) is communicated with the interior of the speaker box (11); the other surface of the discharge box (12) is open; a second plugging plate (13) is inserted between the discharge box (12) and the speaker box (11).

2. The upper pouring device of a building concrete structure according to claim 1, characterized in that: The back plate (2) is provided with screws (3) which are anchored into the concrete formwork (1).

3. The upper pouring device of a building concrete structure according to claim 1, characterized in that: A first pull plate (9) is arranged on the upper part of the first plug plate (8), and a second pull plate (14) is arranged on the upper part of the second plug plate (13).

4. The upper pouring device of a building concrete structure according to claim 1, characterized in that: The speaker box (11) is provided with a U-shaped clamp (15) for the second plug plate (13) to pass through, and the U-shaped clamp (15) is located above the discharge box (12). The upper part of the discharge box (12) is provided with a through hole for the second plug plate (13) to pass through, and the second plug plate (13) is closely attached to the outer wall of the speaker box (11).

5. The upper pouring device of a building concrete structure according to claim 1, characterized in that: A connecting plate (5) is provided between the two partition plates (4).

6. The upper pouring device for a building concrete structure according to claim 1, characterized in that: The sides of the L-shaped inner folding plate (6) and the first plug plate (8) away from the speaker box (11) are flush with the inner side surface of the concrete formwork (1).