Gas pressure testing system under influence of water pressure of coal seam containing confined water
By setting up water return pipes, grouting pipes and damping water discharge pipes in the borehole to monitor water pressure changes, the problem of long time and high cost of gas pressure testing in coal seams containing confined water is solved, and measurement accuracy and efficiency are achieved.
Patent Information
- Application Number
- CN202420564931.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-22
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2034-03-22
AI Technical Summary
In coal seams containing confined water, existing gas pressure testing methods take a long time, are costly, and are inaccurate, affecting the measurement results.
Set up water return pipes, grouting pipes and damping water discharge pipes in the borehole, monitor water pressure changes through valves and pressure gauge systems, and analyze water inflow to accurately determine the gas pressure in the coal seam.
A gas pressure test with low measurement cost, short time and accurate results is realized, which solves the problems of large error, high cost and long time of the existing methods.
Smart Images

Figure CN221838314U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of coal seam pressure measurement, and in particular relates to a gas pressure testing system under the influence of water pressure in a coal seam containing pressurized water. Background Art
[0002] At present, my country has invented a variety of gas pressure measurement methods. The first is the actual measurement method, that is, drilling through the layer, grouting and sealing the hole to measure the coal seam gas pressure; the second is the indirect method, that is, using fresh coal samples to measure the coal seam gas content, and then using the Langmuir equation to reverse the coal seam gas pressure. Among them, the actual measurement method is divided into cement mortar soil sealing method and capsule mucus sealing method according to the sealing method. According to the gas pressure recovery process, it can be divided into active pressure measurement method and passive pressure measurement method. The active pressure measurement method actively replenishes gas to the gas chamber after sealing the hole to make up for the loss of gas in the coal around the borehole during drilling and sealing, shortening the gas pressure recovery time and making the pressure measurement time shorter. The passive pressure measurement method relies entirely on the migration of coal seam gas around the borehole into the borehole to achieve gas pressure balance, and it takes a long time to complete the pressure measurement.
[0003] However, due to the large number of coal seams, complex coal-forming environment, and diverse coal seam occurrence conditions, some coal seams contain pressurized water, or the coal seams are hydraulically connected to nearby aquifers, which are called coal seams containing pressurized water. When measuring gas pressure, whether the active method or the passive method is used, the measurement time will be prolonged, the measurement cost will increase, and the measurement effect will be affected. Therefore, a gas pressure test system that can be used under the influence of water pressure in coal seams containing pressurized water is needed. Utility Model Content
[0004] In order to solve the deficiencies in the prior art, the utility model provides a gas pressure testing system under the influence of water pressure in a coal seam containing pressurized water. A return water pipe, a grouting pipe and a damping drain pipe are arranged in a borehole, grouting and hole sealing are performed with the cooperation of various pipelines and corresponding valves, and the water pressure change in the borehole is observed by a water pressure gauge on the return water pipe and a gas water pressure gauge on the grouting pipe to judge the water gushing amount of the borehole, and then the gas pressure in the coal seam is accurately determined through analysis.
[0005] In order to solve the above technical problems, the utility model adopts the following technical solutions:
[0006] The gas pressure testing system under the influence of water pressure in coal seams containing confined water includes a return pipe, a grouting pipe and a damping water discharge pipe inserted in a vertical borehole;
[0007] The return pipe is provided with a return valve, a post valve and a water pressure gauge, the grouting pipe is connected to a grouting pump, the grouting pipe is provided with a grouting valve and a gas water pressure gauge, the damping drain pipe is provided with a damping drain device for controlling the water discharge amount, and a drain valve is provided at the bottom of the damping drain pipe;
[0008] The post-stage valve is arranged below the return valve, the water pressure gauge is arranged between the return valve and the post-stage valve, and the gas water pressure gauge is arranged above the grouting valve;
[0009] The drain valve, post-valve, water pressure gauge, grouting valve, gas pressure gauge and drain valve are located outside the borehole, and the damping drain is located inside the borehole.
[0010] The damping drain device includes a fixing seat whose outer circle is fixedly connected to the inner circle of the damping drain pipe, an upper crossbeam arranged above the fixing seat, a lower crossbeam arranged below the fixing seat, a guide slide bar fixedly connected to the upper crossbeam at the upper end, a drain hole opened along the center line of the fixing seat and transparent up and down, a drain plug slidably connected to the guide slide bar for blocking the drain hole, a damping spring whose upper and lower ends are respectively press-fitted with the drain plug and the lower crossbeam, the guide slide bar is vertically arranged along the center line of the drain hole, a guide hole with an open top is opened in the drain plug, and the lower part of the guide slide bar extends into the guide hole.
[0011] A conical sealing surface connected to the lower port of the drain hole is arranged at the lower part of the fixing seat, and the drain plug includes a cylindrical part and a truncated cone part arranged above the cylindrical part, and a conical sealing part crimped and sealed with the sealing surface is arranged between the cylindrical part and the truncated cone part.
[0012] The return water pipe, the grouting pipe and the damping water discharge pipe are fixed in the borehole through a sealing material layer arranged at the lower part of the borehole.
[0013] The sealing material layer comprises a lower wooden wedge layer and an upper veil layer.
[0014] The upper end of the grouting pipe is 1 to 2 meters higher than the upper end of the return pipe;
[0015] The outer diameters of the grouting pipe and the return pipe are 15 to 20 mm;
[0016] The inner diameter of the damping drain pipe is 20-30 mm.
[0017] By adopting the above technical scheme, when installing and testing the gas pressure testing system of the utility model, firstly, a through-layer drill hole is constructed in the rock tunnel of the coal seam bottom plate and tightly sealed. When grouting and sealing the hole, it is necessary to insert a return pipe, a grouting pipe and a damping drain pipe into the borehole, and the lower part of the borehole is sealed with sealing materials. A return valve, a grouting valve and a drain valve are respectively installed on the return pipe, the grouting pipe and the damping drain pipe, a damping drain device is arranged inside the damping drain pipe, and a grouting pump connected to the grouting pipe is used to inject grout into the borehole. During the grouting process, the valve of the return pipe is kept in an open state to ensure the normal discharge of water gushing from the aquifer. After the grouting and sealing is completed, a gas water pressure gauge is installed above the grouting valve on the grouting pipe; a water pressure gauge and a later valve are installed below the return valve on the return pipe; after the installation is completed, if there is no water gushing out of the borehole, the return valve and the later valve of the return pipe are closed; if there is water gushing out of the borehole, the return valve and the later valve of the return pipe are closed and the drain valve at the bottom of the damping drain pipe is opened to perform damping draining until the pressurized water in the borehole is drained. After the damping draining is performed until the pressurized water is drained, the drain valve on the damping drain pipe is closed in time, and finally the water pressure gauge and the gas water pressure gauge are observed and compared, so as to accurately analyze and determine the wall pressure in the coal seam containing pressurized water.
[0018] In summary, the utility model has the characteristics of low measurement cost, short measurement time and accurate measurement results. By arranging a return pipe, a grouting pipe and a damping drain pipe in the borehole, grouting and sealing the hole are carried out with the cooperation of each pipeline and the corresponding valves, and the water pressure change in the borehole is observed by the water pressure gauge on the return pipe and the gas water pressure gauge on the grouting pipe, the water gushing amount of the borehole is judged, and then the gas pressure in the coal seam is accurately analyzed and determined, which effectively solves the technical problems of large errors, high costs and long measurement time of the existing measurement methods. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a structural schematic diagram of the utility model;
[0020] Figure 2 yes Figure 1 Enlarged view of part A in the middle.
[0021] Figure 3 It is a structural schematic diagram of a damping water discharger of the utility model with relatively low water pressure.
[0022] Figure 4 It is a structural schematic diagram of a damping water discharger with a relatively large water pressure of the utility model.
[0023] Figure 5 It is a structural schematic diagram of a high water pressure damping water discharger of the utility model.
[0024] Figure 6 It is a structural schematic diagram of a water drain plug of the utility model.
[0025] Figure 7 It is a structural schematic diagram of the fixing seat of the utility model. DETAILED DESCRIPTION Example
[0026] like Figure 1-7 As shown, the gas pressure testing system under the influence of water pressure in coal seams containing pressurized water of the utility model comprises a return pipe 41, a grouting pipe 42 and a damping water discharge pipe 43 inserted in a vertical borehole 4;
[0027] The return pipe 41 is provided with a return valve 411, a post valve 413 and a water pressure gauge 412, the grouting pipe 42 is connected to a grouting pump 422, the grouting pipe 42 is provided with a grouting valve 421 and a gas pressure gauge 423, the damping drain pipe 43 is installed with a damping drain device 432 for controlling the drain volume, and a drain valve 431 is provided at the bottom of the damping drain pipe 43;
[0028] The return valve 411, the post-valve 413, the water pressure gauge 412, the grouting valve 421, the gas pressure gauge 423 and the drain valve 431 are located outside the orifice of the borehole 4, and the damping drain 432 is located inside the borehole 4;
[0029] The later stage valve 413 is arranged below the return valve 411 , the water pressure gauge 412 is arranged between the return valve 411 and the later stage valve 413 , and the gas pressure gauge 423 is arranged above the grouting valve 421 .
[0030] The damping drain device 432 includes a fixed seat 321 whose outer circle is fixedly connected to the inner circle of the damping drain pipe 43, an upper beam 322 arranged above the fixed seat 321, a lower beam 326 arranged below the fixed seat 321, a guide slide bar 323 whose upper end is fixedly connected to the upper beam 322, a drain hole 3211 opened along the center line of the fixed seat 321 and transparent from top to bottom, a drain plug 324 slidably connected to the guide slide bar 323 for blocking the drain hole 3211, and a damping spring 325 whose upper and lower ends are press-fitted with the drain plug 324 and the lower beam 326 respectively, the guide slide bar 323 is vertically arranged along the center line of the drain hole 3211, and a guide hole with an open top is opened in the drain plug 324, and the lower part of the guide slide bar 323 extends into the guide hole.
[0031] The lower part of the fixing seat 321 is provided with a conical sealing surface 3212 connected to the lower end of the drain hole 3211. The drain plug 324 includes a cylindrical portion 241 and a frustum portion 242 arranged above the cylindrical portion 241. A conical sealing portion 243 is provided between the cylindrical portion 241 and the frustum portion 242 and is crimped and sealed with the sealing surface 3212.
[0032] The return pipe 41 , the grouting pipe 42 and the damping drain pipe 43 are fixed in the borehole 4 through a sealing material layer 44 arranged at the lower part of the borehole 4 .
[0033] The sealing material layer 44 includes a lower wood wedge layer 441 and an upper veil layer 442 .
[0034] The upper end of the grouting pipe 42 is 1 to 2 meters higher than the upper end of the return pipe 41;
[0035] The outer diameters of the grouting pipe 42 and the return pipe 41 are 15 to 20 mm;
[0036] The inner diameter of the damping drain pipe 43 is 20-30 mm.
[0037] When the gas pressure testing system under the influence of water pressure in coal seams containing pressurized water is installed and used, Figure 1 As shown in the figure, there is a coal seam 3 containing pressurized water between the coal seam roof 1 and the coal seam floor 2, and a through-layer borehole 4 is constructed in the rock tunnel of the coal seam floor 2; firstly, the through-layer borehole 4 is constructed in the rock tunnel of the coal seam floor 2, which can effectively prevent the influence of the development of coal seam fissures. In order to prevent the leakage of pressurized gas in the coal seam through various primary and secondary fissures in the coal and rock layers and make the measured result smaller than the actual gas pressure, it is necessary to strictly seal the borehole 4, and adopt the cement mortar sealing method or the capsule mucus sealing method; according to the actual water volume of the borehole 4 (m 3 / h) and water pressure (MPa), in order to ensure that the pressure-testing borehole 4 has sufficient grouting and sealing length and sealing strength, can resist water pressure and gas pressure damage, and ensure that the sealing quality meets the airtightness requirements, the vertical height of the borehole 4 in this application is 20m, the vertical height of the sealing section is 15m, the slope of the borehole 4 is 40°, and the vertical height of the air chamber 46 should be approximately equal to 3m. In order to be able to install the return pipe 41, grouting pipe 42 and damping drain pipe 43, etc., the diameter of the pressure-testing borehole 4 in this application should be greater than or equal to the conventional borehole 4 diameter of 91mm, with 95mm being the most preferred, and the grouting pipe 42 is one to two meters higher than the return pipe 41.
[0038] When grouting and sealing the hole, it is necessary to insert a return pipe 41, a grouting pipe 42 and a damping drain pipe 43 into the borehole 4, and use a sealing material 44 to seal the lower part of the borehole 4. A return valve 411, a grouting valve 421 and a drain valve 431 are installed on the return pipe 41, the grouting pipe 42 and the damping drain pipe 43, respectively. A damping drain 432 is arranged inside the damping drain pipe 43, and a grouting pump 422 connected to the grouting pipe 42 is used to inject grout into the borehole 4. During the grouting process, the valve of the return pipe 41 is kept in an open state to ensure the normal discharge of the aquifer water. If the return pipe 41 still discharges the aquifer water after the grouting is completed, the valve of the return pipe 41 is kept in an open state; if the return pipe 41 does not discharge the aquifer water after the grouting is completed, the valve of the return pipe 41 is closed to prevent the discharge of gas. According to the predicted coal seam gas pressure, water pressure, and water inflow of borehole 4, in order to ensure the normal discharge of water in the pressurized aquifer in borehole 4 without destroying the strength growth of cement mortar 45 sealing material 44 during the sealing process and the process of sealing completion but cement mortar 45 sealing material 44 strength growth, the grouting pipe 42 is 1-2m longer than the return pipe 41, and the inner end of the return pipe 41 should be 1-2m higher than the sealing section. A drain valve 431 is installed at the lower end of the damping drain pipe 43, which is 3m away from the bottom of the roof hole. According to the conventional grouting and sealing of coal mines, the diameters of the grouting pipe 42 and the return pipe 41 are selected to be ф18m. In order to ensure that the pressure measurement system is not damaged when the water pressure is the highest, multiple repeated grouting methods should be used to ensure that the sedimentation height of cement and sand after the sealing mud is precipitated reaches more than 15m of the designed vertical height of the sealing section.
[0039] After the grouting and sealing is completed, a gas water pressure gauge 423 is installed above the grouting valve 421 on the grouting pipe 42; a water pressure gauge 412 and a post-valve 413 are installed below the return valve 411 on the return pipe 41; the accuracy of the gas water pressure gauge 423 is better than level 1.5, and the accuracy of the gas pressure measurement result should reach 0.02-0.04MPa according to 1.0%. According to the water column pressure P = water column height H × water density ρ, to meet the gas pressure measurement accuracy, it is necessary to observe the influence of the 2-4m high water column pressure on the gas pressure measurement result. The minimum scale of the water pressure gauge 412 is 0.02-0.05MPa. The range of this type of water pressure gauge is generally small, and may not be much higher than the gas pressure.
[0040] After the installation is completed, if there is no water gushing out of the borehole 4, the return valve 411 and the later valve 413 of the return pipe 41 are closed; if there is water gushing out of the borehole 4, the return valve 411 and the later valve 413 of the return pipe 41 are closed and the drain valve 431 at the lower part of the damping drain pipe 43 is opened to perform damping draining until the pressurized water in the borehole 4 is drained, and the drain valve 431 of the damping drain pipe 43 is closed after draining; after the damping draining is performed until the pressurized water is drained, the drain valve 431 on the damping drain pipe 43 is closed in time, and finally Observe and compare the water pressure gauge 412 and the gas water pressure gauge 423, and then accurately analyze and determine the wall pressure in the coal seam 3 containing pressurized water. The specific analysis process is: if it is observed that the amount of water discharged from the damping drain pipe 43 is significantly reduced or even exhausted, causing the damping spring 325 at the bottom of the damping drain 432 to return to its initial state, it is judged that the pressurized water in the surrounding coal rock mass that is hydraulically connected to the borehole 4 has been basically drained, and the drain valve 431 of the damping drain pipe 43 should be closed in time to prevent a large amount of gas from being discharged and affecting the pressure measurement. Open the drain valve 431 of the return pipe 41, close the late valve 413 of the return pipe 41, and observe the water pressure gauge 412; at this time, if the readings of the water pressure gauge 412 and the gas water pressure gauge 423 both increase and then stabilize, and the reading of the water pressure gauge 412 after stabilization is lower than the maximum water pressure, there is a stable difference H between the readings of the water pressure gauge 412 and the gas water pressure gauge 423. 水 ρ 水 , there is no water in the coal seam, and the reading of the water pressure gauge 412 is P 1水 is the relative gas pressure of the coal seam; if the readings of the water pressure gauge 412 and the gas water pressure gauge 423 both increase and then stabilize, and the reading P2 of the water pressure gauge 412 after stabilization is lower than the maximum water pressure, the stable difference between the readings of the water pressure gauge 412 and the gas water pressure gauge 423 is less than H 水 ρ 水 , is ΔH 水 ρ 水 , a small amount of water will appear in the coal seam, and the height of the water column in the return pipe 41 will increase to H 2水 =H 水 -ΔH 水 , gas pressure is P 2水 =P2-H 2水 ρ 水 If the readings of the water pressure gauge 412 and the gas water pressure gauge 423 both increase and then stabilize, and the readings P3 of the water pressure gauge 412 and the stabilized readings are lower than the maximum water pressure, and there is no difference between the readings of the water pressure gauge 412 and the gas water pressure gauge 423, then a large amount of water appears in the coal seam, filling the return pipe 41 and occupying part of the gas chamber 46, and the gas pressure P 3水 =P3-H 水 ρ 水 .
[0041] The utility model has the characteristics of low measurement cost, short measurement time and accurate measurement result. By arranging a return pipe, a grouting pipe and a damping drain pipe in the borehole, grouting and sealing the hole are carried out with the cooperation of various pipelines and corresponding valves, and the water pressure change in the borehole is observed by the water pressure gauge on the return pipe and the gas water pressure gauge on the grouting pipe, the water inflow of the borehole is judged, and then the gas pressure in the coal seam is accurately analyzed and determined, which effectively solves the technical problems of large error, high cost and long measurement time of the existing measurement method.
[0042] This embodiment does not impose any formal restrictions on the shape, material, structure, etc. of the utility model. Any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the utility model are within the protection scope of the technical solution of the utility model.
Claims
1. Gas pressure testing system under the influence of water pressure in coal seams containing confined water, characterized by: It includes a return pipe, a grouting pipe and a damping drain pipe inserted in a vertical borehole; The return pipe is provided with a return valve, a post valve and a water pressure gauge, the grouting pipe is connected to a grouting pump, the grouting pipe is provided with a grouting valve and a gas water pressure gauge, the damping drain pipe is provided with a damping drain device for controlling the water discharge amount, and a drain valve is provided at the bottom of the damping drain pipe; The post-stage valve is arranged below the return valve, the water pressure gauge is arranged between the return valve and the post-stage valve, and the gas water pressure gauge is arranged above the grouting valve; The drain valve, post-valve, water pressure gauge, grouting valve, gas pressure gauge and drain valve are located outside the borehole, and the damping drain is located inside the borehole.
2. The gas pressure testing system under the influence of water pressure in a coal seam containing pressurized water according to claim 1 is characterized in that: The damping drain device includes a fixing seat whose outer circle is fixedly connected to the inner circle of the damping drain pipe, an upper crossbeam arranged above the fixing seat, a lower crossbeam arranged below the fixing seat, a guide slide bar fixedly connected to the upper crossbeam at the upper end, a drain hole opened along the center line of the fixing seat and transparent up and down, a drain plug slidably connected to the guide slide bar for blocking the drain hole, a damping spring whose upper and lower ends are respectively press-fitted with the drain plug and the lower crossbeam, the guide slide bar is vertically arranged along the center line of the drain hole, a guide hole with an open top is opened in the drain plug, and the lower part of the guide slide bar extends into the guide hole.
3. The gas pressure testing system under the influence of water pressure in a coal seam containing pressurized water according to claim 2 is characterized in that: A conical sealing surface connected to the lower port of the drain hole is arranged at the lower part of the fixing seat, and the drain plug includes a cylindrical part and a truncated cone part arranged above the cylindrical part, and a conical sealing part crimped and sealed with the sealing surface is arranged between the cylindrical part and the truncated cone part.
4. The gas pressure testing system under the influence of water pressure in a coal seam containing pressurized water according to claim 1 is characterized in that: The return water pipe, the grouting pipe and the damping water discharge pipe are fixed in the borehole through a sealing material layer arranged at the lower part of the borehole.
5. The gas pressure testing system under the influence of water pressure in a coal seam containing pressurized water according to claim 4 is characterized in that: The sealing material layer comprises a lower wooden wedge layer and an upper veil layer.
6. The gas pressure testing system under the influence of water pressure in a coal seam containing confined water according to claim 1 is characterized in that: The upper end of the grouting pipe is 1 to 2 meters higher than the upper end of the return pipe; The outer diameters of the grouting pipe and the return pipe are 15 to 20 mm; The inner diameter of the damping drain pipe is 20-30 mm.
Citation Information
Cited By
Method for measuring damping drainage gas pressure of coal seam containing confined water
CN117988830A