Deep sea jacket

By dividing the jacket structure into underwater and above-water parts and connecting them through plug-in components, the problem of insufficient stability and height of the ultra-high and overweight jacket during processing, transportation and hoisting is solved, and lower manufacturing costs are achieved. and safer transportation.

CN221838469UActive Publication Date: 2024-10-15HONGHUA OFFSHORE OIL & GAS EQUIP JIANGSU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420540874.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-20
Publication Date
2024-10-15
Estimated Expiration
2034-03-20

AI Technical Summary

Technical Problem

The ultra-high and overweight jacket wind turbine foundation faces problems such as insufficient hardware facilities, poor stability, and insufficient lifting height during processing, transportation, and offshore installation.

Method used

Design a deep-sea jacket. The structure is divided into two parts: underwater and above water. They are connected through plug-in components, including plug tips and slots. The fixing method is grouting and welding. The lower jacket is fixed on the seabed, and the upper jacket is fixed on the seabed. The frame is connected to it, and the ship parts and cable tubes are installed to reduce the offshore lifting height.

Benefits of technology

It effectively reduces the offshore lifting height, expands the options for processing plants, reduces manufacturing costs, and improves transportation safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221838469U_ABST
    Figure CN221838469U_ABST
Patent Text Reader

Abstract

The utility model discloses a deep sea jacket which comprises a platform, the lower end of the platform is provided with a lower jacket which is located underwater and installed on a seabed, the upper end of the platform is provided with an upper jacket which is located at the upper end of the water surface and used for installing a draught fan, and the upper end of the lower jacket is connected with the lower end of the upper jacket through a plug-in assembly. The jacket fan foundation structure is simple and reasonable in design, the jacket fan foundation structure is designed into the underwater part and the overwater part, the two parts are in butt joint above the water surface, the offshore hoisting height can be reduced by about 30 meters, the problem that the offshore hoisting floating crane is not enough in hoisting height is solved, after the jacket fan foundation structure is constructed by dividing the jacket fan foundation structure into the two parts, the selection range of processing factories is wider, and the construction cost is reduced. The manufacturing cost is lower, and the transportation is safer.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of offshore wind turbine equipment, in particular to a deep sea conductor frame. Background Art

[0002] As wind power gradually develops towards deep sea, the structural design of the jacket wind turbine foundation will inevitably become larger in size, higher in height, and heavier in tonnage. The ultra-high and ultra-heavy jacket wind turbine foundation will face a series of problems, such as: the hardware facilities of the processing plant cannot meet the processing and manufacturing requirements; the center of gravity is too high and the stability is not enough for offshore transportation; the floating crane cannot be hoisted at a high enough height during offshore installation, etc. Utility Model Content

[0003] The utility model aims to provide a deep sea jacket to solve the problems raised in the above background technology.

[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a deep-sea conductor frame, comprising a platform, wherein a lower conductor frame located underwater and installed on the seabed is provided at the lower end of the platform, and an upper conductor frame located above the water surface and used for installing a wind turbine is provided at the upper end of the platform, wherein the upper end of the lower conductor frame is connected to the lower end of the upper conductor frame by setting a plug-in assembly.

[0005] Preferably, the plug-in assembly includes a plurality of plug tips and a plurality of slots matching the plug tips, the plug tips are arranged on four sides of the lower end of the upper conductor frame, and the slots are arranged on four sides of the upper end of the lower conductor frame, and the upper conductor frame and the lower conductor frame are connected by inserting the plug tips into the slots.

[0006] Preferably, the number of the plug tips and the number of the slots are both 4, and the plug tips are designed to be one long and three short.

[0007] Preferably, the insert tip and the slot are fixed by grouting or welding or a combination of both.

[0008] Preferably, the lower end of the lower conductor frame is fixed by inserting a foundation steel pipe pile driven into the seabed.

[0009] Preferably, a mooring member is provided on one side of the platform, and one-fifth, one-third and two-thirds of the mooring member from bottom to top are low water level, sea level and high water level respectively.

[0010] Preferably, the height of the lower conductor frame is 70-100 meters, and the height of the upper conductor frame is 25-35 meters. Both the lower conductor frame and the upper conductor frame are provided with cable pipes, and the cable pipes are trumpet-shaped. A ladder is provided on one side of the upper conductor frame.

[0011] Compared with the prior art, the beneficial effects of the utility model are:

[0012] The deep-sea jacket has a wind turbine foundation structure designed as two parts, an underwater part and an above-water part, which are butt-jointed above the water surface, so that the offshore hoisting height can be reduced by about 30 meters, solving the problem of insufficient lifting height of the floating crane for offshore hoisting. Moreover, after being built in two parts, the selection of processing plants is wider, the manufacturing cost is lower, and the transportation is safer. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is the overall front view of the utility model;

[0014] Figure 2 This is a front view of the lower conductor frame of the utility model;

[0015] Figure 3 This is a front view of the upper conductor frame of the utility model;

[0016] Figure 4 This is a schematic diagram of the plug tip of the utility model being inserted into the slot.

[0017] In the figure: 1. Platform; 2. Lower conductor rack; 3. Upper conductor rack; 4. Plug tip; 5. Slot; 6. Mooring; 7. Cable pipe; 8. Ladder. DETAILED DESCRIPTION

[0018] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0019] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicating orientations or positional relationships are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0020] In the description of this patent, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "setting" should be understood in a broad sense, for example, it can be fixed connection, setting, or detachable connection, setting, or integrated connection, setting. For ordinary technicians in this field, the specific meanings of the above terms in this patent can be understood according to specific circumstances.

[0021] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, the meaning of "several" is two or more, unless otherwise clearly and specifically defined.

[0022] Example

[0023] See also Figure 1-4 The utility model provides a technical solution for a deep-sea jacket: it includes a platform 1, the lower end of the platform 1 is provided with a lower jacket 2 installed underwater on the seabed, the upper end of the platform 1 is provided with an upper jacket 3 located above the water surface for installing a wind turbine, and the upper end of the lower jacket 2 is connected with the lower end of the upper jacket 3 by installing a plug-in assembly.

[0024] The plug-in assembly includes a plurality of plug tips 4 and a plurality of slots 5 matching the plug tips 4. The plug tips 4 are fixed on the four sides of the lower end of the upper conduit frame 3, and the slots 5 are opened on the four sides of the upper end of the lower conduit frame 2. The upper conduit frame 3 and the lower conduit frame 2 are connected by inserting the plug tips 4 into the slots 5.

[0025] The number of the plug tips 4 and the number of the slots 5 are both 4, and the plug tips 4 are designed to be one long and three short, which is convenient for the positioning of the upper conductor frame 3 and the lower conductor frame 2 for splicing.

[0026] The insertion tip 4 and the slot 5 are fixed together by grouting and welding, which can effectively increase the stability of the insertion of the insertion tip 4 into the slot 5 .

[0027] The lower end of the lower conductor frame 2 is fixed by inserting and driving a foundation steel pipe pile into the seabed.

[0028] A mooring member 6 is fixed to one side of the platform 1, and one-fifth, one-third and two-thirds of the mooring member 6 from bottom to top are low water level, sea level and high water level respectively, ensuring that the ship can be effectively docked on the mooring member 6 when docking.

[0029] The height of the lower conductor frame 2 is 70-100 meters, and the height of the upper conductor frame 3 is 25-35 meters. Cable pipes 7 are welded on the lower conductor frame 2 and the upper conductor frame 3. The cable pipes 7 are trumpet-shaped. The submarine cable traction wire ropes are threaded separately on land. After the upper and lower sections are closed at sea, the wire ropes are connected into a whole with buckles. The upper and lower sections of ICCP and stress monitoring wires are connected with quick connectors. A ladder 8 is welded on one side of the upper conductor frame 3.

[0030] When the device is in use, the lower conductor frame 2 and the upper conductor frame 3 are constructed separately in the processing plant, and are hoisted and closed separately at sea. First, the lower end of the lower conductor frame 2 is fixed to the foundation steel pipe pile driven into the seabed, and then the upper conductor frame 3 is hoisted, and the plug tip 4 is aligned with the slot 5 and inserted into the slot 5 to achieve the splicing of the lower conductor frame 2 and the upper conductor frame 3, and then the contact part of the plug tip 4 and the slot 5 is welded and grouted to achieve fixation. The device designs the conductor frame fan foundation structure into two parts, an underwater part and an above-water part. The two parts are butt-jointed above the water surface, which can reduce the offshore hoisting height by about 30 meters, solving the problem of insufficient lifting height of the floating crane for offshore hoisting. After being constructed in two parts, the processing plant has a wider range of choices, lower manufacturing costs, and safer transportation.

[0031] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only preferred examples of the utility model and are not used to limit the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection of the utility model is defined by the attached claims and their equivalents.

Claims

1. A deep sea jacket, comprising a platform (1), characterized in that: The lower end of the platform (1) is provided with a lower conductor frame (2) located underwater and installed on the seabed, and the upper end of the platform (1) is provided with an upper conductor frame (3) located above the water surface and used to install a wind turbine, and the upper end of the lower conductor frame (2) is connected to the lower end of the upper conductor frame (3) by providing a plug-in assembly.

2. The deep sea jacket according to claim 1, characterized in that: The plug-in assembly comprises a plurality of plug tips (4) and a plurality of slots (5) matching the plug tips (4); the plug tips (4) are arranged on four sides of the lower end of the upper conduit frame (3); the slots (5) are arranged on four sides of the upper end of the lower conduit frame (2); the upper conduit frame (3) and the lower conduit frame (2) are connected by inserting the plug tips (4) into the slots (5).

3. The deep sea jacket according to claim 2, characterized in that: The number of the plug tips (4) and the number of the slots (5) are both four, and the plug tips (4) are designed to be one long and three short.

4. The deep sea jacket according to claim 2, characterized in that: The insert tip (4) and the slot (5) are fixed by grouting or welding or a combination of the two.

5. The deep sea jacket according to claim 1, characterized in that: The lower end of the lower conductor frame (2) is fixed by inserting a foundation steel pipe pile driven into the seabed.

6. The deep sea jacket according to claim 1, characterized in that: A mooring member (6) is provided on one side of the platform (1), and one-fifth, one-third and two-thirds of the mooring member (6) from bottom to top are respectively low water level, sea level and high water level.

7. The deep sea jacket according to claim 1, characterized in that: The height of the lower conductor frame (2) is 70-100 meters, and the height of the upper conductor frame (3) is 25-35 meters. Both the lower conductor frame (2) and the upper conductor frame (3) are provided with cable pipes (7), and the cable pipes (7) are in a trumpet shape. A ladder (8) is provided on one side of the upper conductor frame (3).