Integral concrete pouring and guiding device for prefabricating box culvert sections

By designing an integrated concrete pouring guide device for prefabricating box culvert segments, the problems of slow pouring speed and high transportation costs are solved, efficient concrete pouring and resource saving are achieved, and the level of construction technology is improved.

CN221850627UActive Publication Date: 2024-10-18ROAD & BRIDGE INT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323624009.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-10-18
Estimated Expiration
2033-12-29

Smart Images

  • Figure CN221850627U_ABST
    Figure CN221850627U_ABST
Patent Text Reader

Abstract

The utility model discloses a concrete integral type pouring material guiding device for box culvert section prefabrication, and relates to the technical field of box culvert section prefabrication construction. Comprising a bottom bracing inclined frame body; the hopper connecting pipe body is fixedly connected and assembled to the top position of the bottom supporting inclined frame body, a material bearing opening is formed in the top end of the hopper connecting pipe body, and a sealing bottom plate is fixedly connected and assembled to the bottom end of the hopper connecting pipe body; the number of the flow dividing pipe bodies is four, the four sets of flow dividing pipe bodies are fixedly connected and assembled to the bottom side portion of the hopper connecting pipe body at intervals, and the vertical faces where every two adjacent sets of flow dividing pipe bodies are located are perpendicular to each other; and the four groups of shunting pipe bodies are respectively communicated with the interior of the hopper connecting pipe body. The technical problems that in the prior art, when concrete pouring is conducted for box culvert section prefabrication, the overall pouring speed is too low, the efficiency is too low, and manpower resources and the transportation cost are prone to being wasted are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of box culvert segment construction, in particular to an integral concrete pouring and guiding device for prefabricating box culvert segments. Background Art

[0002] At present, when pouring concrete to form the vertical prefabricated segments of prefabricated box culverts, the pouring process is to use a gantry crane to lift the hopper to pour concrete on each side of the box body one by one. As a result, the wall thickness of each side of the box culvert is only 40 cm. In order to prevent the concrete from partially overflowing to the outside of the formwork, the pouring rate cannot be too fast. Usually, the discharge port of the concrete hopper is only opened 1 / 3, and the overall pouring rate is too slow and the efficiency is too low.

[0003] Moreover, each section of the assembled box culvert requires about 13m 3 C45 concrete, in order to avoid direct transportation of 13m 3 When pouring concrete, the waiting time for concrete pouring is too long, which affects the quality of concrete. Therefore, tank trucks are needed to transport the concrete in two batches to match the construction speed on site, which seriously wastes human resources and transportation costs. Utility Model Content

[0004] To this end, the utility model provides an integral concrete pouring and guiding device for prefabricated box culvert segments to solve the technical problems in the prior art of concrete pouring for prefabricated box culvert segments, that is, the overall pouring rate is too slow, the efficiency is too low, and human resources and transportation costs are easily wasted.

[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0006] A concrete integral pouring and guiding device for prefabrication of box culvert segments, comprising:

[0007] Bottom support diagonal frame body;

[0008] A hopper pipe body is fixedly assembled at the top position of the bottom support inclined frame body, and a material receiving opening is formed at the top end of the hopper pipe body, and a sealing bottom plate is fixedly assembled at the bottom end of the hopper pipe body;

[0009] The diverter pipe bodies are provided with four groups, and the four groups of diverter pipe bodies are fixedly installed at intervals on the bottom side of the hopper connecting pipe body, and the vertical surfaces where two adjacent groups of diverter pipe bodies are located are arranged perpendicularly; the four groups of diverter pipe bodies are connected to the inside of the hopper connecting pipe body respectively.

[0010] On the basis of the above technical solution, the utility model is further described as follows:

[0011] As a further solution of the utility model, the bottom support diagonal frame body includes a plurality of first angle steel bodies;

[0012] A plurality of the first angle steel bodies are respectively erected and fixedly connected to the bottom of the hopper pipe body in an oblique manner.

[0013] As a further solution of the utility model, the top ends of a plurality of the first angle steel bodies are respectively fixedly assembled to the bottom of the connection position between the hopper pipe body and the four groups of the diversion pipe bodies.

[0014] As a further solution of the utility model, it also includes:

[0015] The bottom support reinforcement frame includes a plurality of second angle steel bodies;

[0016] A plurality of the second angle steel bodies are all arranged to extend transversely, and each of the second angle steel bodies is fixedly connected and arranged between the bottom side portions of two adjacent first angle steel bodies.

[0017] As a further solution of the utility model, the hopper pipe body is configured as a vertically extending cylindrical pipe structure;

[0018] The four groups of diversion pipe bodies are cross-shaped and fixedly assembled at even intervals on the bottom side of the cylindrical hopper pipe body;

[0019] The four groups of diversion pipe bodies are all arranged to be tilted downward;

[0020] The inclination angle of the four groups of diversion pipe bodies based on the horizontal direction is not less than 30°.

[0021] As a further solution of the utility model, a material receiving and diverting frame is also fixedly mounted inside the hopper connecting pipe body.

[0022] As a further solution of the utility model, the material receiving and diverting frame is arranged as a cross-shaped plate structure, the cross-shaped material receiving and diverting frame is arranged to extend vertically, and the four groups of vertical edges of the cross-shaped material receiving and diverting frame are respectively fixedly assembled and connected with the inner wall of the hopper pipe body;

[0023] Four groups of diversion channels are formed between the inner wall of the hopper pipe body and the cross-shaped material receiving and diversion frame body, and the four groups of diversion channels are connected and arranged one by one with the four groups of diversion pipe bodies.

[0024] As a further solution of the utility model, a clot crushing structure is fixedly mounted inside the four groups of diversion channels formed correspondingly between the inner wall of the hopper connecting pipe body and the material receiving and diversion frame body.

[0025] As a further solution of the utility model, the clot breaking structure is configured as a clot breaking rod and / or a clot breaking vertical plate;

[0026] The two ends of the clot-breaking rod and / or the clot-breaking vertical plate are respectively and one-to-one correspondingly fixedly assembled with the inner wall of the hopper connecting pipe body and the material receiving and diverting frame body.

[0027] As a further solution of the utility model, the top edges of the clot-breaking rod and / or the clot-breaking vertical plate are all arranged in an inclined manner with the inner side higher and the outer side lower.

[0028] The utility model has the following beneficial effects:

[0029] The device can be used as the elevated assembly foundation of the overall device through the cooperation of the bottom support inclined frame body and the bottom support reinforcement frame body, and can be effectively elevated to the inner side of the inner casting formwork, and can also use the top receiving port of the hopper pipe body to directly connect to the discharge port of the external hopper to realize direct discharge, and then the concrete passes through four groups of diversion pipe bodies respectively extending outward to the inner and outer formworks of the box culvert to simultaneously cast the box body on all sides, thereby achieving uniform and symmetrical casting of the box culvert wall body on all sides, while improving the efficiency of concrete casting, each section of the box culvert concrete can be transported to the site at one time, saving concrete transportation and labor costs, reducing the intensity of concrete casting operations, and being able to ensure the continuity of concrete casting, ensuring the construction quality of the box body concrete, and to a certain extent improving the construction technology level of prefabricated box culverts, and is generally suitable for the vertical prefabricated concrete casting construction of box culvert segments, improving functional practicality, and having strong economic benefits and promotion value. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] In order to more clearly illustrate the implementation methods of the utility model or the technical solutions in the prior art, the drawings required for the implementation methods or the description of the prior art will be briefly introduced below. The structures, proportions, sizes, etc. illustrated in this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read. Any structural modification, change in proportional relationship or adjustment of size should still fall within the scope of the technical contents disclosed in the utility model without affecting the effects and purposes that can be achieved by the utility model.

[0031] Figure 1 This is a schematic diagram of the overall axonometric structure of an integral concrete casting and guiding device for prefabricating box culvert segments provided in Example 1 of the utility model.

[0032] Figure 2 This is a schematic diagram of the overall axonometric structure of an integral concrete casting and guiding device for prefabricating box culvert segments provided in Example 2 of the utility model.

[0033] Figure 3 This is a schematic diagram of the overall axonometric structure of an integral concrete casting and guiding device for prefabricating box culvert segments provided in Example 3 of the utility model.

[0034] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0035] A bottom support inclined frame body 1; a bottom support reinforcement frame body 2; a hopper pipe body 3; a diverter pipe body 4; a material receiving and diverter frame body 5; a diverter channel 6; and a clot breaking structure 7. DETAILED DESCRIPTION

[0036] The following is a specific embodiment of the present invention. People familiar with the technology can easily understand the other advantages and functions of the present invention from the contents disclosed in this specification. Obviously, the described embodiment is a part of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0037] The terms such as "upper", "lower", "left", "right", and "middle" used in this specification are only for the convenience of description and are not intended to limit the scope of the present invention. Changes or adjustments to their relative relationships shall be deemed to be within the scope of the present invention without substantially changing the technical content.

[0038] Example 1

[0039] like Figure 1 As shown, the embodiment of the utility model provides a concrete integral pouring and guiding device for prefabricating box culvert segments, comprising a bottom support inclined frame body 1, a bottom support reinforcement frame body 2, a hopper pipe body 3 and a diverter pipe body 4, which is used to cooperate with the bottom support inclined frame body 1 and the bottom support reinforcement frame body 2 as the elevated assembly basis of the overall device, and effectively realize the elevation to the inner side of the casting inner template, and at the same time, the top receiving port of the hopper pipe body 3 can be directly connected to the discharge port of the external hopper to realize direct discharge, and then the concrete passes through four groups and extends outward to the inner and outer templates of the box culvert respectively. The diversion pipe body 4 between the two sides is simultaneously cast around the box body, thereby achieving uniform and symmetrical casting of the box culvert wall body around the four sides, while improving the concrete casting efficiency, each section of the box culvert concrete can be transported to the site at one time, saving concrete transportation and labor costs, reducing the intensity of concrete casting operations, and ensuring the continuity of concrete casting, ensuring the quality of box body concrete construction, to a certain extent, improving the construction technology level of prefabricated box culverts, and is generally applicable to the vertical prefabricated concrete casting construction of box culvert segments, with strong economic benefits and promotion value. The specific settings are as follows:

[0040] Please refer to Figure 1The bottom support diagonal frame body 1 includes a plurality of first angle steel bodies that are respectively obliquely elevated, and the bottom support reinforcement frame body 2 includes a plurality of second angle steel bodies that are transversely arranged, and each of the second angle steel bodies is fixedly connected and arranged between the bottom side parts of two adjacent first angle steel bodies, so as to form at least one group of triangular support frames by utilizing the bottom support reinforcement frame body 2, thereby significantly improving the elevation and stability of the bottom support diagonal frame body 1.

[0041] Please continue to refer to Figure 1 The hopper connecting pipe body 3 is configured as a vertically extending cylindrical tube structure, the top end of the cylindrical hopper connecting pipe body 3 is formed with a receiving port for connecting to an external hopper discharge port, and the bottom end of the cylindrical hopper connecting pipe body 3 is fixedly assembled with a sealing bottom plate.

[0042] The diverter pipe bodies 4 are provided with four groups, and the four groups of diverter pipe bodies 4 are cross-shaped and evenly spaced and fixedly assembled on the bottom side of the cylindrical hopper pipe body 3, and the four groups of diverter pipe bodies 4 are respectively connected to the interior of the cylindrical hopper pipe body 3, so that after the concrete flows through the hopper pipe body 3, it continues to extend outward along the four groups of diverter pipe bodies 4 between the inner and outer formworks of the box culvert, and the box body is cast around at the same time, thereby achieving uniform casting of the box culvert wall around, and improving the concrete casting efficiency of the box culvert.

[0043] As a preferred solution of this embodiment, the diverter pipe body 4 is tilted downward, and the tilt angle of the diverter pipe body 4 based on the horizontal direction is not less than 30°, so that the inclined diverter pipe body 4 can make the concrete inside it more easily flow out to the casting position under the action of its own gravity.

[0044] As another preferred scheme of the present embodiment, the top ends of several of the first angle steel bodies are respectively fixedly assembled at the bottom of the connection position between the hopper connecting pipe body 3 and the four groups of the diversion pipe bodies 4, so that the several first angle steel bodies can not only play the established height support function for the hopper connecting pipe body 3, but also play the supporting function for the four groups of diversion pipe bodies 4, thereby enhancing the stability of the diversion casting.

[0045] Example 2

[0046] In Example 2, the same symbols are given to the same structures as in Example 1, and the same descriptions are omitted. Example 2 is improved on the basis of Example 1, please refer to Figure 2The interior of the hopper pipe body 3 is also fixedly equipped with a material receiving and diverting frame 5; specifically, the material receiving and diverting frame 5 is arranged as a cross-shaped plate structure, the cross-shaped material receiving and diverting frame 5 is vertically extended, and the four groups of vertical edges of the cross-shaped material receiving and diverting frame 5 are respectively fixedly assembled and connected with the inner wall of the hopper pipe body 3; four groups of diversion channels 6 are formed between the inner wall of the hopper pipe body 3 and the cross-shaped material receiving and diverting frame 5, and the four groups of diversion channels 6 are respectively connected and connected with the four groups of diversion pipe bodies 4 in a one-to-one correspondence; it is used to achieve that when concrete flows through the hopper pipe body 3, it can be diverted to the four groups of diversion channels 6 by the material receiving and diverting frame 5 with the help of its own gravity, and further flow to the four groups of diversion pipe bodies 4 accordingly, thereby effectively reducing the uneven diversion of concrete when the whole structure falls to the bottom of the hopper pipe body 3 due to the difficulty in maintaining absolute levelness.

[0047] Example 3

[0048] In Example 3, the same symbols are given to the same structures as in Example 1 and Example 2, and the same descriptions are omitted. Example 3 is improved on the basis of Example 2. Please refer to Figure 3 A clot crushing structure 7 is also fixedly installed inside the four groups of diversion channels 6 formed correspondingly between the inner wall of the hopper connecting pipe body 3 and the material receiving and diverting frame body 5; specifically, the clot crushing structure 7 is configured as a clot crushing rod and / or a clot crushing vertical plate, and the two end portions of the clot crushing rod and / or the clot crushing vertical plate are respectively and one-to-one fixedly installed and connected between the inner wall of the hopper connecting pipe body 3 and the material receiving and diverting frame body 5, and the top edges of the clot crushing rod and / or the clot crushing vertical plates are all inclined with the inside being higher and the outside being lower, so as to significantly reduce concrete agglomeration and improve diversion uniformity.

[0049] Although the utility model has been described in detail above with general descriptions and specific embodiments, it is obvious to those skilled in the art that some modifications or improvements can be made to the utility model. Therefore, these modifications or improvements made without departing from the spirit of the utility model are within the scope of protection claimed by the utility model.

Claims

1. A concrete integral pouring and guiding device for prefabrication of box culvert segments, It is characterized in that include: Bottom support diagonal frame body; A hopper pipe body is fixedly assembled at the top position of the bottom support inclined frame body, and a material receiving opening is formed at the top end of the hopper pipe body, and a sealing bottom plate is fixedly assembled at the bottom end of the hopper pipe body; The diverter pipe bodies are provided with four groups, and the four groups of diverter pipe bodies are fixedly installed at intervals on the bottom side of the hopper connecting pipe body, and the vertical surfaces where two adjacent groups of diverter pipe bodies are located are arranged perpendicularly; the four groups of diverter pipe bodies are connected to the inside of the hopper connecting pipe body respectively.

2. The integral concrete pouring and guiding device for prefabricating box culvert segments according to claim 1, It is characterized in that The bottom support diagonal frame body includes a plurality of first angle steel bodies; A plurality of the first angle steel bodies are respectively erected and fixedly connected to the bottom of the hopper pipe body in an oblique manner.

3. The integral concrete pouring and guiding device for prefabricating box culvert segments according to claim 2, It is characterized in that The top ends of a plurality of the first angle steel bodies are respectively fixedly assembled to the bottom of the connection position between the hopper pipe body and the four groups of the diversion pipe bodies.

4. The integral concrete pouring and guiding device for prefabricating box culvert segments according to claim 2, It is characterized in that Also includes: The bottom support reinforcement frame includes a plurality of second angle steel bodies; A plurality of the second angle steel bodies are all arranged to extend transversely, and each of the second angle steel bodies is fixedly connected and arranged between the bottom side portions of two adjacent first angle steel bodies.

5. The integral concrete pouring and guiding device for prefabrication of box culvert segments according to claim 1, It is characterized in that The hopper pipe body is configured as a vertically extending cylindrical pipe structure; The four groups of diversion pipe bodies are cross-shaped and fixedly assembled at even intervals on the bottom side of the cylindrical hopper pipe body; The four groups of diversion pipe bodies are all arranged to be tilted downward; The inclination angle of the four groups of diversion pipe bodies based on the horizontal direction is not less than 30°.

6. The integral concrete pouring and guiding device for prefabrication of box culvert segments according to claim 1, It is characterized in that A material receiving and diverting frame is also fixedly mounted inside the hopper pipe body.

7. The integral concrete pouring and guiding device for prefabricating box culvert segments according to claim 6, It is characterized in that The material receiving and diverting frame is configured as a cross-shaped plate structure, the cross-shaped material receiving and diverting frame is vertically extended, and the four groups of vertical edges of the cross-shaped material receiving and diverting frame are respectively fixedly assembled and connected with the inner wall of the hopper pipe body; Four groups of diversion channels are formed between the inner wall of the hopper pipe body and the cross-shaped material receiving and diversion frame body, and the four groups of diversion channels are connected and arranged one by one with the four groups of diversion pipe bodies.

8. The integral concrete pouring and guiding device for prefabricating box culvert segments according to claim 7, It is characterized in that A clot crushing structure is also fixedly mounted inside the four groups of diversion channels formed correspondingly between the inner wall of the hopper pipe body and the material receiving and diversion frame body.

9. The integral concrete pouring and guiding device for prefabricating box culvert segments according to claim 8, It is characterized in that The clot breaking structure is configured as a clot breaking rod and / or a clot breaking vertical plate; The two ends of the clot-breaking rod and / or the clot-breaking vertical plate are respectively and one-to-one correspondingly fixedly assembled with the inner wall of the hopper connecting pipe body and the material receiving and diverting frame body.

10. The integral concrete pouring and guiding device for prefabrication of box culvert segments according to claim 9, It is characterized in that The top edges of the clot-breaking rod and / or the clot-breaking vertical plate are all arranged in an inclined manner with the inner side higher and the outer side lower.