Grouting device for road and bridge construction

By introducing stirring and heating functions into the grouting device, the problem of cement and concrete solidification is solved, the grouting efficiency is improved, and particles are processed through the filter assembly to achieve more efficient road and bridge repairs.

CN221855231UActive Publication Date: 2024-10-18WUHAN XINLETU DECORATION ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202322957575.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-01
Publication Date
2024-10-18
Estimated Expiration
2033-11-01

AI Technical Summary

Technical Problem

The existing grouting device requires manual mixing of cement and concrete during use, and the material is easily solidified if left for too long, affecting work efficiency.

Method used

A grouting device including a stirring component, a grouting component and a filter component is designed. The mixing shaft and heating rod are used to fully stir and heat the cement and concrete to prevent solidification, and the filter component is used to process larger particles and improve the quality of the material. Liquidity and stability.

Benefits of technology

It effectively prevents cement and concrete from solidifying, reduces manual mixing time, improves grouting efficiency, solves the problem of mixing shaft jamming caused by larger particles, and simplifies the road and bridge repair process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221855231U_ABST
    Figure CN221855231U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of road and bridge construction, in particular to a grouting device for road and bridge construction. The technical problems that in the using process of a grouting device, cement, concrete and slurry need to be manually stirred to repair roads and bridges, and the cement, the concrete and the slurry added into the grouting device are prone to being solidified due to the fact that the placement time is too long are solved. According to the technical scheme, the grouting device for road and bridge construction comprises an outer frame assembly. When a road bridge needs to be repaired, the outer frame assembly is pulled, the grouting device can be pulled to an area where the grouting device needs to work, the filtering assembly is installed at the upper end of the stirring assembly, cement, concrete and slurry are poured into the stirring assembly, and the cement, the concrete and the slurry can be stirred and heated; cement, concrete and slurry can be fully mixed, after stirring is completed, the grouting assembly is started, and the slurry can be injected into an area needing to be repaired.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of road and bridge construction, and specifically relates to a grouting device for road and bridge construction. Background Art

[0002] Grouting technology can be divided into two categories: static pressure grouting and high-pressure jet grouting. However, according to the mechanism of action of slurry on soil, grouting pressure of geological conditions, movement form of slurry and alternative methods, grouting technology can be divided into four categories: penetration grouting, splitting grouting, compaction grouting and jet grouting. Grouting devices are needed for grouting work during road and bridge construction. However, during the use of grouting devices in the prior art, cement, concrete and slurry need to be manually stirred to repair roads and bridges. Moreover, the cement, concrete and slurry added to the grouting device are left for too long, which can easily lead to the solidification of cement, concrete and slurry, affecting the normal operation of the grouting device, thereby greatly increasing the working time. Utility Model Content

[0003] In order to overcome the problem that during the use of the grouting device, cement, concrete and slurry need to be manually stirred to repair roads and bridges, and the cement, concrete and slurry added to the grouting device are left for too long, it is easy to cause the cement, concrete and slurry to solidify.

[0004] The technical solution of the utility model is: a grouting device for road and bridge construction, comprising an outer frame component; further comprising a stirring component, a grouting component and a filtering component; a stirring component for stirring and storing cement, concrete and slurry is fixedly arranged on the upper end of the outer frame component; a grouting component for grouting slurry after stirring is fixedly arranged on the inner wall of the upper end of the outer frame component; a filtering component for filtering larger particles in cement, concrete and slurry is movably arranged on the upper end of the stirring component.

[0005] Preferably, when a road or bridge needs to be repaired, the outer frame assembly is pulled to pull the grouting device to the area where work is required, the filter assembly is installed on the upper end of the stirring assembly, cement, concrete and slurry are poured into the stirring assembly, and the stirring assembly is turned on to stir and heat the cement, concrete and slurry, so that the cement, concrete and slurry can be fully mixed, thereby improving the fluidity or stability of the material. After the stirring is completed, the grouting assembly is turned on to inject the slurry into the area that needs to be repaired.

[0006] Preferably, the outer frame assembly includes a workbench, a first trough body, a handle, a second trough body, a tripod, a fixed plate and rubber wheels; a handle is fixedly installed on the upper end of the workbench; a fixed plate is fixedly installed on the lower end of the workbench; tripods are rotatably installed at the four corner edges of the lower end of the fixed plate; rubber wheels are rotatably installed on the inner walls of the front and rear ends of the tripod; the first trough body is penetrated through the upper and lower ends of the workbench; the second trough body is penetrated through the upper and lower ends of the workbench. In order to facilitate pulling the grouting device to the area where grouting is required, holding the handle and pulling the handle can make the handle drive the rubber wheel to rotate, thereby facilitating pulling the grouting device to the area where grouting is required.

[0007] Preferably, the stirring assembly includes a tank body, a hopper, a stirring shaft, a stirring blade, a bearing, a first placement groove, a heating rod, a first pulley, a motor, a placement block, a second pulley, a rubber belt, a second placement groove and a third placement groove; a placement block is fixedly installed on the upper end of the workbench; the tank body is fixedly installed on the upper end of the placement block; the upper end of the tank body is fixedly installed with the hopper; the interior of the hopper and the interior of the tank body are interconnected, and in order to quickly pour cement, concrete and slurry into the tank body, by setting up the hopper, cement, concrete and slurry can be poured into the hopper, so that the cement, concrete and slurry fall into the tank body along the inner wall of the hopper, thereby quickly pouring cement, concrete and slurry into the tank body.

[0008] Preferably, bearings are fixedly installed on the left and right ends of the tank body; a stirring shaft is rotatably installed on the inner wall of the bearing; evenly distributed stirring blades are fixedly installed on the outer wall of the stirring shaft; the right end of the stirring shaft passes through the right end of the tank body and a first pulley is fixedly installed; the upper end of the fixed plate is fixedly installed with a motor; the output shaft of the motor is fixedly installed with a second pulley; the outer wall of the second pulley is rotatably installed with a rubber belt; the second pulley passes through the first groove body and is rotatably connected to the first pulley through the rubber belt. In order to fully mix the cement, concrete and slurry, the motor is turned on so that the output shaft of the motor drives the second pulley to rotate, and the rotation of the second pulley can drive the first pulley to rotate, so that the first pulley drives the stirring shaft to rotate, and the rotation of the stirring shaft can cause the stirring blades to stir the cement, concrete and slurry in the tank body, thereby fully mixing the cement, concrete and slurry.

[0009] Preferably, a first placement groove is fixedly opened in the wall layer of the tank body and is evenly distributed; a heating rod is fixedly installed on the inner wall of the first placement groove; a second placement groove is opened through the upper and lower ends of the placement block; a third placement groove is fixedly opened at the front end of the placement block. In order to prevent the cement, concrete and slurry from solidifying, the heating rod is turned on during the mixing process, so that the cement, concrete and slurry can be heated during the mixing process, thereby preventing the cement, concrete and slurry from solidifying.

[0010] Preferably, the grouting assembly includes a hopper, a limiting groove, a pump body, a first connecting plate, a second connecting plate, a baffle, a liquid outlet pipe and a connecting pipe; the hopper is fixedly installed at the lower end of the tank body; the interior of the hopper is interconnected with the interior of the tank body; the outer wall of the hopper is fitted with the inner wall of the second placement groove; the outer wall of the hopper is fitted with the outer wall of the second tank body; a limiting groove is fixedly provided at the rear end of the hopper; the interior of the limiting groove is interconnected with the interior of the hopper; a baffle is movably installed on the inner wall of the third placement groove; the baffle passes through the third placement groove and fits with the inner wall of the limiting groove. In order to allow the cement, concrete and slurry to be discharged from the tank body after mixing, the baffle can be pulled to slide backward along the inner wall of the limiting groove, so that the baffle is away from the inner wall of the hopper, thereby allowing the cement, concrete and slurry to be discharged along the inner wall of the hopper.

[0011] Preferably, a pump body is fixedly installed on the upper end of the fixed plate; a connecting pipe is fixedly installed on the liquid inlet port of the pump body; a second connecting plate is fixedly installed on the outer wall of the connecting pipe; a first connecting plate is fixedly installed on the lower end of the dropping hopper; the inner wall of the first connecting plate and the interior of the dropping hopper are mutually connected; the lower end of the first connecting plate is connected to the upper end of the second connecting plate; a liquid outlet pipe is fixedly installed on the liquid outlet port of the pump body, and in order to grout the roads and bridges that need to be repaired, the liquid outlet pipe can be pulled to the area that needs to be repaired, and the pump body can be opened so that the pump body can draw the slurry in the dropping hopper to the area that needs to be repaired, thereby grouting the roads and bridges that need to be repaired.

[0012] Preferably, the filter assembly includes a filter bucket, a first filter plate, a second filter plate, a first through hole, a second through hole, a first slot and a second slot; the filter bucket is movably installed on the upper end of the feed hopper; the first filter plate is fixedly installed on the inner wall of the filter bucket; the second filter plate is fixedly installed on the inner wall of the filter bucket; the first through hole is penetrated at the upper and lower ends of the first filter plate; the second through hole is penetrated at the upper and lower ends of the second filter plate; the inner diameter of the first through hole is larger than the inner diameter of the second through hole; the first slot is fixedly opened at the lower end of the filter bucket; the second slot is fixedly opened on the upper inner wall of the first slot; the inner wall of the structure formed by the first slot and the second slot fits with the inner and outer walls of the upper end of the feed hopper, in order to quickly install the filter bucket, the filter bucket can be placed on the upper end of the feed hopper, the right end of the feed hopper is inserted into the second slot, the filter bucket is pushed to the left and pressed downward, so that the inner wall of the structure formed by the first slot and the second slot fits with the inner and outer walls of the upper end of the feed hopper, so that the filter bucket can be quickly installed.

[0013] Beneficial effects of the utility model:

[0014] In order to prevent the slurry in the grouting device from solidifying, cement, concrete and slurry are poured into the hopper so that the cement, concrete and slurry fall into the tank along the inner wall of the hopper, and the motor is turned on so that the output shaft of the motor drives the second pulley to rotate, and the rotation of the second pulley can drive the first pulley to rotate, so that the first pulley drives the stirring shaft to rotate, and the rotation of the stirring shaft can make the stirring blade stir the cement, concrete and slurry in the tank, so that the cement, concrete and slurry are fully stirred, and the heating rod is turned on during the stirring process, so that the cement, concrete and slurry can be heated during the stirring process, thereby preventing the cement, concrete and slurry from solidifying, so as to solve the problem that the cement, concrete and slurry added to the grouting device are left for too long, which easily leads to the solidification of the cement, concrete and slurry and affects the normal operation of the grouting device;

[0015] In order to facilitate the repair of roads and bridges, hold the handle and pull the handle, so that the handle can drive the rubber wheel to rotate, thereby facilitating the grouting device to be pulled to the area that needs grouting, and then pull the baffle to make the baffle slide backward along the inner wall of the limit groove, so that the baffle is away from the inner wall of the hopper, so that cement, concrete and slurry can flow along the inner wall of the hopper to the inlet port of the pump body, pull the liquid outlet pipe to the area that needs to be repaired, and turn on the pump body so that the pump body can draw the slurry in the hopper to the area that needs to be repaired, so as to grout the roads and bridges that need to be repaired, so as to solve the problem that during the use of the grouting device, cement, concrete and slurry need to be manually stirred to repair roads and bridges.

[0016] In order to prevent the stirring shaft from getting stuck due to larger particles when mixing cement, concrete and slurry, the filter bucket can be placed on the upper end of the feed hopper, the right end of the feed hopper is inserted into the second slot, the filter bucket is pushed to the left and then pressed downward, so that the inner wall of the structure formed by the first slot and the second slot fits with the inner and outer walls of the upper end of the feed hopper, so that the filter bucket can be quickly installed, and cement, concrete and slurry are poured into the filter bucket, which can make the cement, concrete and slurry be filtered through the first filter plate and the second filter plate and fall into the feed hopper, so as to filter the larger particles in the cement, concrete and slurry, so as to solve the problem of the stirring shaft getting stuck due to larger particles when mixing cement, concrete and slurry. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 What is shown is a three-dimensional structural schematic diagram of a grouting device for road and bridge construction of the utility model;

[0018] Figure 2 What is shown is a three-dimensional structural cross-sectional view of a grouting device for road and bridge construction of the utility model;

[0019] Figure 3What is shown is a three-dimensional structural diagram of an outer frame assembly of a grouting device for road and bridge construction of the utility model;

[0020] Figure 4 The present invention shows a schematic diagram of the three-dimensional structure of a mixing assembly of a grouting device for road and bridge construction;

[0021] Figure 5 The present invention shows a schematic diagram of the three-dimensional structure of a grouting assembly of a grouting device for road and bridge construction of the present invention;

[0022] Figure 6 What is shown is a schematic diagram of the three-dimensional structure disassembly of a filter component of a grouting device for road and bridge construction of the utility model.

[0023] The markings in the accompanying drawings are: 1-outer frame assembly, 2-stirring assembly, 3-grouting assembly, 4-filter assembly, 101-workbench, 102-first tank body, 103-handle, 104-second tank body, 105-support frame, 106-fixed plate, 107-rubber wheel, 201-tank body, 202-feed hopper, 203-stirring shaft, 204-stirring blade, 205-bearing, 206-first placement groove, 207-heating rod, 208-first pulley, 209-motor, 210-placement Placement block, 211-second pulley, 212-rubber belt, 213-second placement groove, 214-third placement groove, 301-drop hopper, 302-limiting groove, 303-pump body, 304-first connecting plate, 305-second connecting plate, 306-baffle, 307-liquid outlet pipe, 308-connecting pipe, 401-filter hopper, 402-first filter plate, 403-second filter plate, 404-first through hole, 405-second through hole, 406-first card slot, 407-second card slot. Implementation

[0024] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0025] See also Figure 1-2 The utility model provides an embodiment: a grouting device for road and bridge construction, including an outer frame component 1; also including a stirring component 2, a grouting component 3 and a filtering component 4; the upper end of the outer frame component 1 is fixedly provided with a stirring component 2 for stirring and storing cement, concrete and slurry; the upper end inner wall of the outer frame component 1 is fixedly provided with a grouting component 3 for grouting the slurry after stirring; the upper end of the stirring component 2 is movably provided with a filtering component 4 for filtering larger particles in cement, concrete and slurry.

[0026] See also Figure 3In this embodiment, the outer frame assembly 1 includes a workbench 101, a first trough body 102, a handle 103, a second trough body 104, a tripod 105, a fixing plate 106 and a rubber wheel 107; the handle 103 is fixedly installed on the upper end of the workbench 101; the fixing plate 106 is fixedly installed on the lower end of the workbench 101; the tripod 105 is rotatably installed at the four corners of the lower end of the fixing plate 106; the rubber wheels 107 are rotatably installed on the inner walls of the front and rear ends of the tripod 105; the first trough body 102 is penetrated at the upper and lower ends of the workbench 101; the second trough body 104 is penetrated at the upper and lower ends of the workbench 101.

[0027] See also Figure 4 In this embodiment, the stirring assembly 2 includes a tank body 201, a hopper 202, a stirring shaft 203, a stirring blade 204, a bearing 205, a first placement groove 206, a heating rod 207, a first pulley 208, a motor 209, a placement block 210, a second pulley 211, a rubber belt 212, a second placement groove 213 and a third placement groove 214; a placement block 210 is fixedly installed on the upper end of the workbench 101; the tank body 201 is fixedly installed on the upper end of the placement block 210; the hopper 202 is fixedly installed on the upper end of the tank body 201; the interior of the hopper 202 and the interior of the tank body 201 are mutually connected; bearings 205 are fixedly installed on the left and right ends of the tank body 201; the stirring shaft 203 is rotatably installed on the inner wall of the bearing 205; the outer wall of the stirring shaft 203 A stirring blade 204 is fixedly installed with uniform distribution; the right end of the stirring shaft 203 passes through the right end of the tank body 201 and is fixedly installed with a first pulley 208; a motor 209 is fixedly installed on the upper end of the fixed plate 106; a second pulley 211 is fixedly installed on the output shaft of the motor 209; a rubber belt 212 is rotatably installed on the outer wall of the second pulley 211; the second pulley 211 passes through the first tank body 102 and is rotatably connected to the first pulley 208 through the rubber belt 212; a first placement groove 206 that is uniformly distributed is fixedly opened in the wall layer of the tank body 201; a heating rod 207 is fixedly installed on the inner wall of the first placement groove 206; a second placement groove 213 is opened through the upper and lower ends of the placement block 210; a third placement groove 214 is fixedly opened at the front end of the placement block 210.

[0028] See also Figure 5In this embodiment, the grouting assembly 3 includes a hopper 301, a limiting groove 302, a pump body 303, a first connecting plate 304, a second connecting plate 305, a baffle 306, a liquid outlet pipe 307 and a connecting pipe 308; the hopper 301 is fixedly installed at the lower end of the tank body 201; the interior of the hopper 301 is interconnected with the interior of the tank body 201; the outer wall of the hopper 301 is in contact with the inner wall of the second placement groove 213; the outer wall of the hopper 301 is in contact with the outer wall of the second tank body 104; the limiting groove 302 is fixedly provided at the rear end of the hopper 301; the interior of the limiting groove 302 is interconnected with the interior of the hopper 301; the A baffle plate 306 is movably installed on the inner wall of the third placement groove 214; the baffle plate 306 passes through the third placement groove 214 and fits with the inner wall of the limit groove 302; the pump body 303 is fixedly installed on the upper end of the fixed plate 106; the liquid inlet port of the pump body 303 is fixedly installed with a connecting pipe 308; the outer wall of the connecting pipe 308 is fixedly installed with a second connecting plate 305; the lower end of the drop hopper 301 is fixedly installed with a first connecting plate 304; the inner wall of the first connecting plate 304 and the interior of the drop hopper 301 are mutually connected; the lower end of the first connecting plate 304 is connected to the upper end of the second connecting plate 305; the liquid outlet port of the pump body 303 is fixedly installed with a liquid outlet pipe 307.

[0029] See also Figure 6 In this embodiment, the filter assembly 4 includes a filter bucket 401, a first filter plate 402, a second filter plate 403, a first through hole 404, a second through hole 405, a first slot 406 and a second slot 407; the filter bucket 401 is movably installed on the upper end of the feed hopper 202; the first filter plate 402 is fixedly installed on the inner wall of the filter bucket 401; the second filter plate 403 is fixedly installed on the inner wall of the filter bucket 401; the first through hole 404 is penetrated at the upper and lower ends of the first filter plate 402; the second through hole 405 is penetrated at the upper and lower ends of the second filter plate 403; the inner diameter of the first through hole 404 is greater than the inner diameter of the second through hole 405; the first slot 406 is fixedly opened at the lower end of the filter bucket 401; the second slot 407 is fixedly opened on the upper inner wall of the first slot 406; the inner wall of the structure formed by the first slot 406 and the second slot 407 is in contact with the inner and outer walls of the upper end of the feed hopper 202.

[0030] When working, hold the handle 103 and pull the handle 103, so that the handle 103 can drive the rubber wheel 107 to rotate, thereby facilitating the grouting device to be pulled to the area where grouting is required, place the filter bucket 401 on the upper end of the feed hopper 202, insert the right end of the feed hopper 202 into the second slot 407, push the filter bucket 401 to the left and press it downward, so that the inner wall of the structure formed by the first slot 406 and the second slot 407 fits with the inner and outer walls of the upper end of the feed hopper 202, so that the filter bucket 401 can be quickly installed, and cement, concrete and slurry are poured into the filter bucket 401, so that the cement, concrete and slurry can be filtered through the first filter plate 402 and the second filter plate 403, and larger particles in the cement, concrete and slurry can be filtered, and the filtered cement, concrete and slurry fall into the tank body 201 along the inner wall of the feed hopper 202;

[0031] Then, the motor 209 is turned on, so that the output shaft of the motor 209 drives the second pulley 211 to rotate, and the rotation of the second pulley 211 can drive the first pulley 208 to rotate, so that the first pulley 208 drives the stirring shaft 203 to rotate, and the rotation of the stirring shaft 203 can make the stirring blade 204 stir the cement, concrete and slurry in the tank body 201, so that the cement, concrete and slurry are fully stirred, and the heating rod 207 is turned on during the stirring process, so that the cement, concrete and slurry can be heated during the stirring process, so as to prevent the cement, concrete and slurry from solidifying;

[0032] When the road or bridge needs to be repaired, the baffle 306 is pulled to slide backward along the inner wall of the limiting groove 302, so that the baffle 306 is away from the inner wall of the hopper 301, so that the cement, concrete and slurry can flow along the inner wall of the hopper 301 to the feed port of the pump body 303, and the liquid outlet pipe 307 is pulled to the area that needs to be repaired, and the pump body 303 is turned on, so that the pump body 303 draws the slurry in the hopper 301 to the area that needs to be repaired, so that grouting can be performed on the road or bridge that needs to be repaired.

[0033] Through the above steps, when the road bridge needs to be repaired, the outer frame assembly 1 is pulled to pull the grouting device to the area where work is required, the filter assembly 4 is installed to the upper end of the stirring assembly 2, and the cement, concrete and slurry are poured into the stirring assembly 2. The stirring assembly 2 is turned on to stir and heat the cement, concrete and slurry, so that the cement, concrete and slurry can be fully mixed, thereby improving the fluidity or stability of the material. After the stirring is completed, the grouting assembly 3 is turned on to inject the slurry into the area that needs to be repaired.

[0034] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of those skilled in the art without departing from the purpose of the present invention.

Claims

1. A grouting device for road and bridge construction, comprising an outer frame assembly (1); Features: The invention also comprises a stirring assembly (2), a grouting assembly (3) and a filtering assembly (4); the stirring assembly (2) for stirring and storing cement, concrete and slurry is fixedly arranged at the upper end of the outer frame assembly (1); the grouting assembly (3) for grouting the slurry after stirring is fixedly arranged on the inner wall of the upper end of the outer frame assembly (1); the filtering assembly (4) for filtering larger particles in cement, concrete and slurry is movably arranged at the upper end of the stirring assembly (2); the stirring assembly (2) comprises a tank body (201), a hopper (202), a stirring shaft (203), a stirring blade (204) and a stirring blade (205). ), a bearing (205), a first placement groove (206), a heating rod (207), a first pulley (208), a motor (209), a placement block (210), a second pulley (211), a rubber belt (212), a second placement groove (213) and a third placement groove (214); a placement block (210) is fixedly mounted on the upper end of the workbench (101); a tank body (201) is fixedly mounted on the upper end of the placement block (210); a hopper (202) is fixedly mounted on the upper end of the tank body (201); the interior of the hopper (202) and the interior of the tank body (201) are mutually connected.

2. A grouting device for road and bridge construction according to claim 1, Features: The outer frame assembly (1) comprises a workbench (101), a first trough (102), a handle (103), a second trough (104), a support frame (105), a fixing plate (106) and a rubber wheel (107); the handle (103) is fixedly mounted on the upper end of the workbench (101); the fixing plate (106) is fixedly mounted on the lower end of the workbench (101); the support frames (105) are rotatably mounted at the four corner edges of the lower end of the fixing plate (106); the rubber wheels (107) are rotatably mounted on the inner walls at the front and rear ends of the support frame (105); the first trough (102) is penetrated through the upper and lower ends of the workbench (101); the second trough (104) is penetrated through the upper and lower ends of the workbench (101).

3. A grouting device for road and bridge construction according to claim 1, Features: Bearings (205) are fixedly installed at the left and right ends of the tank body (201); a stirring shaft (203) is rotatably installed on the inner wall of the bearing (205); stirring blades (204) are fixedly installed on the outer wall of the stirring shaft (203) and are evenly distributed; the right end of the stirring shaft (203) passes through the right end of the tank body (201) and is fixedly installed with a first pulley (208); a motor (209) is fixedly installed on the upper end of the fixing plate (106); a second pulley (211) is fixedly installed on the output shaft of the motor (209); a rubber belt (212) is rotatably installed on the outer wall of the second pulley (211); the second pulley (211) passes through the first slot body (102) through the rubber belt (212) and is rotatably connected to the first pulley (208).

4. A grouting device for road and bridge construction according to claim 3, Features: The wall layer of the tank body (201) is fixedly provided with uniformly distributed first placement grooves (206); a heating rod (207) is fixedly installed on the inner wall of the first placement groove (206); the placement block (210) is provided with second placement grooves (213) penetrating the upper and lower ends; and the front end of the placement block (210) is fixedly provided with a third placement groove (214).

5. A grouting device for road and bridge construction according to claim 2, Features: The grouting assembly (3) comprises a hopper (301), a limiting groove (302), a pump body (303), a first connecting plate (304), a second connecting plate (305), a baffle (306), a liquid outlet pipe (307) and a connecting pipe (308); the hopper (301) is fixedly mounted on the lower end of the tank body (201); the interior of the hopper (301) and the interior of the tank body (201) are mutually connected; the outer wall of the hopper (301) and the second placement groove ( The inner wall of the third placement groove (213) is in contact with the outer wall of the second trough body (104); the outer wall of the drop hopper (301) is in contact with the outer wall of the second trough body (104); a limiting groove (302) is fixedly provided at the rear end of the drop hopper (301); the interior of the limiting groove (302) and the interior of the drop hopper (301) are interconnected; a baffle (306) is movably installed on the inner wall of the third placement groove (214); the baffle (306) passes through the third placement groove (214) and is in contact with the inner wall of the limiting groove (302).

6. A grouting device for road and bridge construction according to claim 5, Features: A pump body (303) is fixedly mounted on the upper end of the fixed plate (106); a connecting pipe (308) is fixedly mounted on the liquid inlet port of the pump body (303); a second connecting plate (305) is fixedly mounted on the outer wall of the connecting pipe (308); a first connecting plate (304) is fixedly mounted on the lower end of the drop hopper (301); the inner wall of the first connecting plate (304) and the interior of the drop hopper (301) are interconnected; the lower end of the first connecting plate (304) is connected to the upper end of the second connecting plate (305); and a liquid outlet pipe (307) is fixedly mounted on the liquid outlet port of the pump body (303).

7. A grouting device for road and bridge construction according to claim 2, Features: The filter assembly (4) comprises a filter hopper (401), a first filter plate (402), a second filter plate (403), a first through hole (404), a second through hole (405), a first clamping groove (406) and a second clamping groove (407); the filter hopper (401) is movably mounted on the upper end of the feed hopper (202); the first filter plate (402) is fixedly mounted on the inner wall of the filter hopper (401); the second filter plate (403) is fixedly mounted on the inner wall of the filter hopper (401); the upper and lower ends of the first filter plate (402) are fixedly mounted on the inner wall of the filter hopper (401); A first through hole (404) is formed through both ends; a second through hole (405) is formed through both upper and lower ends of the second filter plate (403); the inner diameter of the first through hole (404) is greater than the inner diameter of the second through hole (405); a first clamping groove (406) is fixedly formed at the lower end of the filter hopper (401); a second clamping groove (407) is fixedly formed on the inner wall of the upper end of the first clamping groove (406); the inner wall of the structure formed by the first clamping groove (406) and the second clamping groove (407) is in contact with the inner and outer walls of the upper end of the feed hopper (202).