Movable quick mounting temporary bridge

By designing a double-layer hollow bridge body and a portable bridge with a mobile mechanism, the problem of time-consuming and labor-intensive movement and installation of the portable bridge and insufficient carrying capacity has been solved. It has achieved efficient and fast installation and improved safety, and can adapt to the needs of various scenarios.

CN221855255UActive Publication Date: 2024-10-18HUANENG YARLUNG TSANGPO RIVER HYDROPOWER DEV INVESTMENT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323518456.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-22
Publication Date
2024-10-18
Estimated Expiration
2033-12-22

AI Technical Summary

Technical Problem

The existing bridge structure has the problems of being time-consuming and labor-intensive to move and install, has limited bearing capacity, and is not very safe. It is difficult to arrange and dismantle quickly, and it occupies a large area.

Method used

A mobile quick-installation bridge is designed that includes a double-layer hollow bridge body and a moving mechanism. The moving mechanism realizes the rapid movement and installation of the bridge body through connectors, casters, springs and connecting rod components. The bridge body can be retracted internally to reduce space. occupy, and extend the length of the bridge through bolted connections.

Benefits of technology

It improves the load-bearing capacity and safety of the bridge, reduces the time for manually installing the moving mechanism, realizes fast movement and flexible connection, and adapts to the needs of different scenarios.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221855255U_ABST
    Figure CN221855255U_ABST
Patent Text Reader

Abstract

The utility model discloses a mobile quick installation temporary bridge relates to building construction bridge technical field, including bridge body and moving mechanism, said moving mechanism with said bridge body is installed, said bridge body is the double-layer hollow structure, said moving mechanism is evenly arranged on the bottom of said bridge body, said moving mechanism includes connecting piece and caster, said connecting piece is connected with said caster, said connecting piece is connected with said caster. The moving mechanism is connected with the bridge body through the connecting piece, the moving mechanism is provided with a spring and a connecting rod assembly, and the moving mechanism retracts into the bridge body through the spring and the connecting rod assembly. According to the utility model, the bearing capacity and the safety of the bridge body can be provided, the bridge body can be quickly moved, the manual installation time is reduced, and the space utilization is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction bridges, in particular to a mobile quick-installation temporary bridge. Background Art

[0002] If the comprehensive pipe gallery is constructed by open excavation, according to the linear foundation pit characteristics of the pipe gallery, the original road traffic is often blocked due to the excavation of the foundation pit. Therefore, a temporary bridge needs to be set up above the excavation to meet the construction transportation and daily traffic needs. At present, most temporary bridges are fixed simple supported structures. When there is no lifting equipment, it is very inconvenient to use them. They cannot be moved and arranged quickly according to needs. At the same time, the installation and removal time is long and the site occupies a large area.

[0003] The existing Chinese patent with the authorization announcement number CN210946446U discloses a mobile temporary bridge, which belongs to the field of construction technology. The scheme includes a temporary bridge and a mobile structure arranged under the temporary bridge, and the temporary bridge above can be moved by the mobile mechanism at the bottom. However, the problem with this scheme is that the mobile structure and the temporary bridge are separate structures, and each time the temporary bridge is moved and placed, the mobile mechanism needs to be manually installed on the temporary bridge, which is time-consuming and labor-intensive. At the same time, the temporary bridge in the scheme is a single-layer plate structure with limited bearing capacity and low safety factor.

[0004] Therefore, there is an urgent need for a movable temporary bridge that can be quickly arranged and installed, reducing manpower while increasing the carrying capacity and improving safety. Utility Model Content

[0005] The utility model aims to provide a mobile quick-install temporary bridge to solve the problems existing in the background technology.

[0006] The purpose of this utility model is achieved through the following technical solutions:

[0007] A mobile quick-installation temporary bridge comprises a bridge body and a mobile mechanism, wherein the mobile mechanism is installed with the bridge body, the bridge body is a double-layer hollow structure, the mobile mechanism is evenly arranged at the bottom of the bridge body, the mobile mechanism comprises a connecting piece and casters, the mobile mechanism is connected to the bridge body via the connecting piece, the mobile mechanism is provided with a spring and a connecting rod assembly, and the mobile mechanism is retracted into the bridge body via the spring and the connecting rod assembly.

[0008] Furthermore, the bridge body includes an upper plate, a lower plate and a support plate, the support plate is vertically fixed between the upper plate and the lower plate, and the lower plate is provided with an installation space adapted to the moving mechanism.

[0009] Furthermore, the connecting member includes a connecting column, a connecting plate, a connecting shaft and a support block, one end of the connecting column is connected to the upper plate, the other end of the connecting column is connected to the mounting plate, the connecting shaft and the support block are located below the connecting plate, the support blocks are located at both ends of the connecting shaft, the caster is located between the two support blocks and is sleeved on the connecting shaft, the support block is an L-shaped structure, one end of the spring is connected to the bottom of the connecting plate, the other end of the spring is connected to the upper end of the support block, the connecting rod assembly is located on the side of the support block away from the caster, one end of the connecting rod assembly is connected to the connecting shaft, and the other end of the connecting rod assembly is connected to the bottom of the connecting plate.

[0010] Furthermore, the connecting column is provided with an upper limit plate and a lower limit plate, the upper plate is located between the upper limit plate and the lower limit plate, the connecting column is movably connected to the upper plate, and the connecting column is fixedly connected to the mounting plate.

[0011] Furthermore, bolts and bolts are provided on the support plates at the front and rear ends of the bridge body, and two adjacent bridge bodies are connected by the bolts and bolts.

[0012] The beneficial effects of the utility model are:

[0013] 1) Improve the load-bearing capacity and safety. The double-layer bridge body and support plate can improve the overall bending resistance and load-bearing capacity of the bridge body, and also provide contraction space for the mobile mechanism and provide space utilization.

[0014] 2) The bridge can be moved quickly, reducing the time for manual installation of the mobile mechanism. When there is no heavy object on the bridge, it can be moved by the mobile mechanism. When there is a heavy object on the bridge, the mobile mechanism will retract into the inside of the bridge.

[0015] 3) Multiple bridge bodies can be connected to meet the needs of different scenarios. Two adjacent bridge bodies can be connected to the front and rear support plates and connected through screw holes and bolts to extend the length of the bridge body. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a side schematic diagram of a mobile quick-install temporary bridge of the utility model;

[0017] Figure 2 It is a schematic diagram of the moving mechanism in the utility model;

[0018] Figure 3 This is a top view of a mobile quick-install bridge of the utility model;

[0019] In the figure, 1-bridge body, 101-upper plate, 102-lower plate, 103-support plate, 2-moving mechanism, 201-connecting column, 2011-upper limit plate, 2012-lower limit plate, 202-connecting plate, 203-connecting shaft, 204-castor, 205-spring, 206-connecting rod assembly, 207-support block, 3-screw hole, 4-bolt. DETAILED DESCRIPTION

[0020] The following will be combined with the embodiments to clearly and completely describe the technical solution of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the utility model.

[0021] See also Figure 1-Figure 3 , the utility model provides a technical solution:

[0022] like Figure 1-Figure 3 As shown, a mobile quick-installation temporary bridge includes a bridge body 1 and a moving mechanism 2, wherein the moving mechanism 2 is installed with the bridge body 1, and the bridge body 1 is a double-layer hollow structure. The moving mechanism 2 is evenly arranged at the bottom of the bridge body 1, and the moving mechanism 2 includes a connecting piece and casters 204, wherein the moving mechanism 2 is connected to the bridge body 1 via the connecting piece, and the moving mechanism 2 is provided with a spring 205 and a connecting rod assembly 206, wherein the moving mechanism 2 is retracted into the bridge body 1 via the spring 205 and the connecting rod assembly 206.

[0023] Through the above technical scheme, the double-layer bridge body 1 structure improves the bearing capacity of the temporary bridge, improves the bending resistance, and improves the safety. At the same time, the mobile mechanism 2 can quickly transfer the bridge body 1 to improve the timeliness of the layout. When the bridge body 1 is arranged in place, the mobile mechanism 2 can be retracted into the bridge body 1, reducing space occupancy. At the same time, there is no need to manually disassemble the mobile mechanism 2, thereby improving the installation efficiency.

[0024] Furthermore, the bridge body 1 includes an upper plate 101 , a lower plate 102 and a support plate 103 , the support plate 103 is vertically fixed between the upper plate 101 and the lower plate 102 , and an installation space adapted to the moving mechanism 2 is provided on the lower plate 102 .

[0025] Through the above technical solution, the double-layer bridge body 1 structure greatly improves the bearing capacity and safety of the bridge body 1. The safety of the bridge body 1 is further improved by the support plate 103. At the same time, the lower plate 102 is provided with an installation space to facilitate the retraction and extension of the moving mechanism 2, thereby improving space utilization.

[0026] Furthermore, the connecting member includes a connecting column 201, a connecting plate 202, a connecting shaft 203 and a support block 207, one end of the connecting column 201 is connected to the upper plate 101, the other end of the connecting column 201 is connected to the mounting plate, the connecting shaft 203 and the support block 207 are located below the connecting plate 202, the support block 207 is located at both ends of the connecting shaft 203, the caster 204 is located between the two support blocks 207 and is sleeved on the connecting shaft 203, the support block 207 is an L-shaped structure, one end of the spring 205 is connected to the bottom of the connecting plate 202, the other end of the spring 205 is connected to the upper end of the support block 207, the connecting rod assembly 206 is located on the side of the support block 207 away from the caster 204, one end of the connecting rod assembly 206 is connected to the connecting shaft 203, and the other end of the connecting rod assembly 206 is connected to the bottom of the connecting plate 202.

[0027] According to the above technical solution, when no heavy objects pass through the bridge body 1, the bottom of the caster 204 extends out of the lower plate 102, and since the caster 204 is sleeved on the connecting shaft 203 and can rotate around the shaft, the bridge body 1 can be moved by the caster 204. After the bridge body 1 is moved to the designated position, vehicles begin to pass over the bridge body 1. At this time, the caster 204 is subjected to the gravity above the bridge body 1, and the connecting shaft 203 is provided with a support block 207, and the support block 207 is connected to the connecting plate 202 through a spring 205, so that when the caster 204 is subjected to force, the support block 207 can be driven to squeeze the spring 205, thereby collecting the caster 204 into the bridge body 1. At the same time, the connecting rod assembly 206 plays a certain supporting role on the caster 204 when the bridge body 1 is not under force. Under the elastic force of the opened spring 205, the connecting rod assembly 206 is in an open state. Through the feature of the movable connection at the hinge of the connecting rod assembly 206, the connecting shaft 203 and the support plate 103 are stretched apart. When the caster 204 is subjected to force and the spring 205 is compressed, the connecting rod assembly 206 also contracts accordingly.

[0028] Furthermore, the connecting column 201 is provided with an upper limit plate 2011 and a lower limit plate 2012, the upper plate 101 is located between the upper limit plate 2011 and the lower limit plate 2012, the connecting column 201 is movably connected to the upper plate 101, and the connecting column 201 is fixedly connected to the mounting plate.

[0029] Through the above technical solution, the upper plate 101 is located between the upper limit plate 2011 and the lower limit plate 2012, so that the connecting column 201 will not fall off the upper plate 101, and at the same time, the upper plate 101 is movably connected to the connecting column 201, so that the direction of the bottom caster 204 can be adjusted through the connecting column 201, so that the caster 204 can be turned at any time as a universal wheel. At the same time, due to the lower limit plate 2012, when there is a heavy object above the upper plate 101, the upper plate 101 will drive the connecting column 201 and the bottom caster 204 downward through the lower limit plate 2012, and when the bottom of the caster 204 touches the ground, the spring 205 will be compressed by the reaction force, thereby causing the caster 204 to retract into the bridge body 1.

[0030] Furthermore, screw holes 3 and bolts 4 are provided on the support plates 103 at the front and rear ends of the bridge body 1 , and two adjacent bridge bodies 1 are connected via the screw holes 3 and bolts 4 .

[0031] Through the above technical solution, two adjacent bridge bodies 1 can be connected to the support plates 103 at the front and rear ends and connected through screw holes 3 and bolts 4, so that the length of the bridge body 1 can be extended to meet the usage requirements of different scenarios.

[0032] The above is only a preferred embodiment of the utility model. It should be understood that the utility model is not limited to the form disclosed herein, and should not be regarded as excluding other embodiments, but can be used in various other combinations, modifications and environments, and can be modified within the scope of the concept described herein through the above teachings or the technology or knowledge of the relevant field. The changes and modifications made by those skilled in the art do not deviate from the spirit and scope of the utility model, and should be protected by the claims attached to the utility model.

Claims

1. A mobile quick-installation temporary bridge, comprising a bridge body (1) and a moving mechanism (2), wherein the moving mechanism (2) is installed on the bridge body (1), and is characterized in that: The bridge body (1) is a double-layer hollow structure. The moving mechanism (2) is evenly arranged at the bottom of the bridge body (1). The moving mechanism (2) comprises a connecting piece and a caster (204). The moving mechanism (2) is connected to the bridge body (1) via the connecting piece. The moving mechanism (2) is provided with a spring (205) and a connecting rod assembly (206). The moving mechanism (2) is retracted into the bridge body (1) via the spring (205) and the connecting rod assembly (206).

2. The mobile quick-install bridge according to claim 1 is characterized in that: The bridge body (1) comprises an upper plate (101), a lower plate (102) and a support plate (103); the support plate (103) is vertically fixed between the upper plate (101) and the lower plate (102); and an installation space adapted to the moving mechanism (2) is provided on the lower plate (102).

3. The mobile quick-install bridge according to claim 2 is characterized in that: The connecting member comprises a connecting column (201), a connecting plate (202), a connecting shaft (203) and a supporting block (207); one end of the connecting column (201) is connected to the upper plate (101); the other end of the connecting column (201) is connected to the mounting plate; the connecting shaft (203) and the supporting block (207) are located below the connecting plate (202); the supporting blocks (207) are located at both ends of the connecting shaft (203); the caster (204) is located between the two supporting blocks (207) and is sleeved thereon. On the connecting shaft (203), the supporting block (207) is an L-shaped structure, one end of the spring (205) is connected to the bottom of the connecting plate (202), and the other end of the spring (205) is connected to the upper end of the supporting block (207); the connecting rod assembly (206) is located on a side of the supporting block (207) away from the caster (204); one end of the connecting rod assembly (206) is connected to the connecting shaft (203), and the other end of the connecting rod assembly (206) is connected to the bottom of the connecting plate (202).

4. The mobile quick-install bridge according to claim 3 is characterized in that: The connecting column (201) is provided with an upper limit plate (2011) and a lower limit plate (2012), the upper plate (101) is located between the upper limit plate (2011) and the lower limit plate (2012), the connecting column (201) is movably connected to the upper plate (101), and the connecting column (201) is fixedly connected to the mounting plate.

5. The mobile quick-install bridge according to claim 1 is characterized in that: Screw holes (3) and bolts (4) are provided on the support plates (103) at the front and rear ends of the bridge body (1), and two adjacent bridge bodies (1) are connected via the screw holes (3) and the bolts (4).