Quickly-erected temporary steel bridge

By adopting the design of support beams and rolling mechanisms in the access bridge, the problem of low erection efficiency of existing access bridges is solved, the rapid movement and fixation of steel plates is realized, adaptability to complex sites, and construction efficiency is improved.

CN221855257UActive Publication Date: 2024-10-18HUANENG YARLUNG TSANGPO RIVER HYDROPOWER DEV INVESTMENT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323518449.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-22
Publication Date
2024-10-18
Estimated Expiration
2033-12-22

AI Technical Summary

Technical Problem

In construction, the erection efficiency of existing bridges is low. Especially in the absence of lifting equipment, it is difficult to move the steel plates to both ends of the trench or foundation pit for construction, and the lifting equipment occupies a large space, making it difficult to cope with complex sites.

Method used

A quick-erected steel bridge is designed, using support beams and rolling mechanisms. Mounting grooves and rolling mechanisms are provided on both sides of the support beams. The springs and universal ball structures enable the convenient movement of the steel plates. The support beams can be expanded through connecting blocks and bolts. , the steel plate is expanded through the connecting plate, reducing manpower requirements.

Benefits of technology

It realizes the rapid movement and fixation of steel plates, saves manpower, adapts to complex sites, improves work efficiency and installation speed, and reduces dependence on large hoisting equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221855257U_ABST
    Figure CN221855257U_ABST
Patent Text Reader

Abstract

The utility model discloses a quick erection temporary steel bridge, which relates to the field of building construction temporary bridges, and comprises a steel plate and support beams, the support beams are symmetrically arranged on the left side and the right side of the steel plate, a plurality of mounting grooves are uniformly arranged on the support beams along the axis direction, rolling mechanisms are arranged in the mounting grooves, and the steel plate moves through the rolling mechanisms. A spring is arranged between the rolling mechanism and the mounting groove, and the rolling mechanism compresses the spring to be contracted into the mounting groove when bearing pressure exceeding the dead weight of the steel plate. The steel plate is easy to lay, manpower is saved, bridge deck laying operation can be completed without large hoisting equipment, and the bridge deck laying device can adapt to complex field environments.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of temporary bridges in building construction, in particular to a fast-erecting steel temporary bridge. Background Art

[0002] If the comprehensive pipe corridor is constructed by open excavation, according to the linear foundation pit characteristics of the pipe corridor, the original road traffic is often blocked due to the excavation of the foundation pit. Therefore, a temporary bridge needs to be set up above the excavation to meet the construction transportation and daily traffic needs. At present, most temporary bridges are fixed simple supported structures, and the construction of simple temporary bridges is generally completed by erecting steel plates on site.

[0003] However, when there is no lifting equipment, it is very inconvenient to transfer the steel plate, and it is difficult to move it to the two ends of the trench or foundation pit to complete the construction, resulting in low installation efficiency; when lifting equipment is used, it occupies a large area and it is difficult to cope with complex on-site scenes.

[0004] Therefore, there is an urgent need for a temporary bridge that can be quickly erected, so that the steel plates can be quickly connected to both ends of the trench or foundation pit, without the need for lifting equipment and reducing manpower. Utility Model Content

[0005] The utility model aims to provide a quick-erecting steel temporary bridge to solve the problems existing in the background technology.

[0006] The purpose of this utility model is achieved through the following technical solutions:

[0007] A quick-erect steel temporary bridge comprises a steel plate and a support beam, wherein the support beam is symmetrically arranged on the left and right sides of the steel plate, a plurality of installation grooves are evenly arranged on the support beam along the axial direction, a rolling mechanism is arranged in the installation groove, the steel plate moves through the rolling mechanism, a spring is arranged between the rolling mechanism and the installation groove, and when the rolling mechanism is subjected to a pressure exceeding the dead weight of the steel plate, the spring is compressed and retracted into the installation groove.

[0008] Furthermore, the rolling mechanism includes a mounting seat and a universal ball, the universal ball is located at the exact center of the mounting seat, the highest point of the universal ball extends out of the mounting seat, a ball layer is provided between the universal ball and the mounting seat, a plurality of balls are provided in the ball layer, the universal ball is rollingly connected to the mounting seat through the ball layer, the size of the mounting seat is adapted to the size of the mounting groove, one end of the spring is fixed to the bottom of the mounting seat, and the other end of the spring is fixed to the bottom plate of the mounting groove.

[0009] Furthermore, the support beam is provided with a first screw hole and a first bolt, the first screw hole is located between two adjacent mounting grooves, the steel plate is provided with a second screw hole corresponding to the size interval of the first screw hole, and the steel plate is threadedly connected to the support beam through the first screw hole, the second screw hole and the first bolt.

[0010] Furthermore, connecting blocks are provided on the outer walls of the front and rear ends of the support beam, and a third screw hole and a third bolt are provided on the connecting block, and two adjacent support beams are threadedly connected through the third screw hole and the third bolt.

[0011] Furthermore, a limit plate is provided at the outer upper end of the support beam, and the limit plate is higher than the height of the universal ball extending out of the installation slot.

[0012] Furthermore, connecting plates are provided at the bottom of the front and rear ends of the steel plate, the width of the connecting plates is smaller than the width of the left and right support beams, and the height of the connecting plates is lower than the height of the support beams.

[0013] Furthermore, a fourth screw hole and a fourth bolt are provided on the connecting plate, and two adjacent steel plates are threadedly connected via the fourth screw hole and the fourth bolt.

[0014] The beneficial effects of the utility model are:

[0015] 1) Save manpower and do not require lifting equipment. Set up the left and right support beams at both ends of the trench or foundation pit, then place the spliced ​​steel plates on the support beams, and move them to the top of the trench or foundation pit through the rolling mechanism on the support beams to complete the layout of the temporary bridge. Since the support beams are not large and are not easy to erect, the rolling mechanism facilitates the movement of heavy steel plates.

[0016] 2) Adapt to complex on-site environments, facilitate disassembly and assembly, and improve work efficiency. The support beam can be expanded through the connecting block, and the steel plate can also be expanded through the connecting plate. At the same time, the support beam can provide support for the steel plate. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a top view of a quick-erected steel temporary bridge of the utility model;

[0018] Figure 2 This is a front view of a quick-erecting steel temporary bridge of the utility model;

[0019] Figure 3 It is a schematic diagram of the steel plate of the utility model when sliding on the support beam;

[0020] Figure 4 This is a schematic diagram of the utility model when the steel plate is fixed on the support beam;

[0021] Figure 5 It is a cross-sectional view of the support beam in the utility model;

[0022] Figure 6 It is a schematic diagram of the splicing of steel plates in the utility model;

[0023] In the figure, 1-steel plate, 101-connecting plate, 102-fourth bolt, 2-support beam, 201-first screw hole, 202-first bolt, 203-connecting block, 204-third bolt, 205-mounting groove, 206-spring, 207-limiting plate, 3-rolling mechanism, 301-universal ball, 302-mounting seat, 303-ball layer. DETAILED DESCRIPTION

[0024] The following will be combined with the embodiments to clearly and completely describe the technical solution of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the utility model.

[0025] See also Figure 1-Figure 6 , the utility model provides a technical solution:

[0026] like Figure 1-Figure 6 As shown, a quick-erected steel temporary bridge comprises a steel plate 1 and a support beam 2. The support beam 2 is symmetrically arranged on the left and right sides of the steel plate 1. A plurality of mounting grooves 205 are evenly arranged on the support beam 2 along the axial direction. A rolling mechanism 3 is arranged in the mounting groove 205. The steel plate 1 moves through the rolling mechanism 3. A spring 206 is arranged between the rolling mechanism 3 and the mounting groove 205. When the rolling mechanism 3 is subjected to a pressure exceeding the dead weight of the steel plate 1, the spring 206 is compressed and retracted into the mounting groove 205.

[0027] Through the above technical solution, the left and right support beams 2 are set up at both ends of the trench or foundation pit, and then the spliced ​​steel plate 1 is placed on the support beam 2, and moved to the top of the trench or foundation pit through the rolling mechanism 3 on the support beam 2 to complete the layout of the temporary bridge. Since the support beam 2 is not large and is not convenient for erection, the heavy steel plate 1 is conveniently moved through the rolling mechanism 3, saving manpower, and the bridge deck laying operation can be completed without the use of large-scale lifting equipment, which can adapt to complex on-site environments. At the same time, the support beam 2 can further improve the support for the steel plate 1 and improve safety.

[0028] Furthermore, the rolling mechanism 3 includes a mounting seat 302 and a universal ball 301, the universal ball 301 is located at the exact center of the mounting seat 302, the highest point of the universal ball 301 extends out of the mounting seat 302, a ball layer 303 is provided between the universal ball 301 and the mounting seat 302, a plurality of balls are provided in the ball layer 303, the universal ball 301 is rollingly connected to the mounting seat 302 through the ball layer 303, the size of the mounting seat 302 is adapted to the size of the mounting groove 205, one end of the spring 206 is fixed to the bottom of the mounting seat 302, and the other end of the spring 206 is fixed to the bottom plate of the mounting groove 205.

[0029] Through the above technical scheme, when the steel plate 1 is not placed on the support beam 2, the upper surface of the mounting seat 302 is flush with the upper surface of the support beam 2, and the universal ball 301 extends out of the mounting seat 302 and the mounting groove 205; when the steel plate 1 is placed on the universal ball 301, it plays a supporting role through the spring 206. At this time, the universal ball 301 is still exposed outside the mounting groove 205, and the steel plate 1 can slide through the universal ball 301 and the ball layer 303; when there is a heavy object on the steel plate 1 or the steel plate 1 and the support beam 2 are fastened by bolts, the universal ball 301 is subjected to the pressure from the steel plate 1 and drives the mounting seat 302 to squeeze the spring 206. At this time, the universal ball 301 and the mounting seat 302 are retracted into the mounting groove 205, and the steel plate 1 is abutted against the support beam 2, and the steel plate 1 cannot slide.

[0030] Furthermore, the support beam 2 is provided with a first screw hole 201 and a first bolt 202, the first screw hole 201 is located between two adjacent mounting grooves 205, the steel plate 1 is provided with a second screw hole corresponding to the size interval of the first screw hole 201, and the steel plate 1 is threadedly connected to the support beam 2 through the first screw hole 201, the second screw hole and the first bolt 202.

[0031] Through the above technical solution, after the steel plate 1 slides and is arranged on the support beam 2, the second screw hole on the steel plate 1 is aligned with the first screw hole 201 and then fixed with the first bolt 202. At this time, the steel plate 1 will not slide anymore, and the steel plate 1 and the support beam 2 are fixed as a whole to ensure the overall stability, so that the horizontal force on the steel plate 1 during driving will not cause the steel plate 1 to slide on the support beam 2, ensuring the safety of the bridge deck. At the same time, the support beam 2 can be anchored on the ground by screws to further improve the overall connection strength of the bridge body.

[0032] Furthermore, a connecting block 203 is provided on the outer wall of the front and rear ends of the support beam 2 , and a third screw hole and a third bolt 204 are provided on the connecting block 203 , and two adjacent support beams 2 are threadedly connected through the third screw hole and the third bolt 204 .

[0033] Through the above technical solution, multiple support beams 2 are connected by connecting blocks 203, and the length of the support beam 2 is increased to adapt to grooves of different widths. It can adapt to different usage scenarios and is easy to install and disassemble. At the same time, casters can be set at the bottom of the support beam 2 to facilitate the transportation of the support beam 2.

[0034] Furthermore, a limit plate 207 is provided at the outer upper end of the support beam 2 , and the limit plate 207 is higher than the height of the universal ball 301 extending out of the installation slot 205 .

[0035] Through the above technical solution, when the steel plate 1 is placed on the support beam 2 and moves, the limit plate 207 prevents the steel plate 1 from deviating from the support beam 2.

[0036] Furthermore, connecting plates 101 are provided at the bottom of the front and rear ends of the steel plate 1 , the width of the connecting plate 101 is smaller than the width of the left and right support beams 2 , and the height of the connecting plate 101 is lower than the height of the support beams 2 .

[0037] Furthermore, a fourth screw hole and a fourth bolt 102 are provided on the connecting plate 101 , and two adjacent steel plates 1 are threadedly connected via the fourth screw hole and the fourth bolt 102 .

[0038] Through the above technical solution, the width of the connecting plate 101 is smaller than the distance between the left and right support beams 2, so that the steel plate 1 can slide on the support beam 2 conveniently without being interfered by the connecting plate 101. At the same time, multiple steel plates 1 can be connected through the connecting plate 101, so that the length of the bridge deck can be extended to meet the needs of different scenarios, and it is easy to disassemble and assemble, which can save costs and improve installation efficiency.

[0039] The above is only a preferred embodiment of the utility model. It should be understood that the utility model is not limited to the form disclosed herein, and should not be regarded as excluding other embodiments, but can be used in various other combinations, modifications and environments, and can be modified within the scope of the concept described herein through the above teachings or the technology or knowledge of the relevant field. The changes and modifications made by those skilled in the art do not deviate from the spirit and scope of the utility model, and should be protected by the claims attached to the utility model.

Claims

1. A quick-erecting steel temporary bridge, characterized in that: The invention comprises a steel plate (1) and a support beam (2), wherein the support beam (2) is symmetrically arranged on the left and right sides of the steel plate (1), a plurality of mounting grooves (205) are evenly arranged on the support beam (2) along the axial direction, a rolling mechanism (3) is arranged in the mounting groove (205), the steel plate (1) moves via the rolling mechanism (3), a spring (206) is arranged between the rolling mechanism (3) and the mounting groove (205), and when the rolling mechanism (3) is subjected to a pressure exceeding the deadweight of the steel plate (1), the spring (206) is compressed and retracted into the mounting groove (205).

2. The quick erection steel temporary bridge according to claim 1 is characterized by: The rolling mechanism (3) comprises a mounting seat (302) and a universal ball (301); the universal ball (301) is located at the exact center of the mounting seat (302); the highest point of the universal ball (301) extends out of the mounting seat (302); a ball layer (303) is provided between the universal ball (301) and the mounting seat (302); a plurality of balls are provided in the ball layer (303); the universal ball (301) is rollingly connected to the mounting seat (302) via the ball layer (303); the size of the mounting seat (302) matches the size of the mounting groove (205); one end of the spring (206) is fixed to the bottom of the mounting seat (302); and the other end of the spring (206) is fixed to the bottom plate of the mounting groove (205).

3. The quick erection steel temporary bridge according to claim 1 is characterized by: The support beam (2) is provided with a first screw hole (201) and a first bolt (202); the first screw hole (201) is located between two adjacent mounting grooves (205); the steel plate (1) is provided with a second screw hole having a size interval corresponding to that of the first screw hole (201); the steel plate (1) is threadedly connected to the support beam (2) via the first screw hole (201), the second screw hole and the first bolt (202).

4. The quick erection steel temporary bridge according to claim 1 is characterized by: Connecting blocks (203) are provided on the outer walls of the front and rear ends of the support beam (2), and a third screw hole and a third bolt (204) are provided on the connecting block (203). Two adjacent support beams (2) are threadedly connected via the third screw hole and the third bolt (204).

5. The quick erection steel temporary bridge according to claim 1 is characterized by: A limit plate (207) is provided at the upper outer end of the support beam (2), and the limit plate (207) is higher than the height of the universal ball (301) extending out of the installation slot (205).

6. The quick erection steel temporary bridge according to claim 1 is characterized by: Connecting plates (101) are provided at the bottom of the front and rear ends of the steel plate (1); the width of the connecting plate (101) is smaller than the width of the two left and right support beams (2); and the height of the connecting plate (101) is lower than the height of the support beams (2).

7. The quick erection steel temporary bridge according to claim 6 is characterized by: The connecting plate (101) is provided with a fourth screw hole and a fourth bolt (102), and two adjacent steel plates (1) are threadedly connected via the fourth screw hole and the fourth bolt (102).