Soil layer settlement detection device for bridge and tunnel engineering construction
By designing a soil settlement detection device that includes detection pits, connecting plates, pipe sleeves, detection rods and alarm components, real-time monitoring of soil settlement is realized using pressure sensors and detection ropes, which solves the problem of low accuracy and low accuracy of traditional detection devices. Monitoring efficiency issues have been improved by improving monitoring efficiency and accuracy.
Patent Information
- Application Number
- CN202420727315.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-10
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2034-04-10
AI Technical Summary
The accuracy of traditional soil settlement detection devices is limited by human factors and equipment accuracy. It cannot accurately reflect soil settlement conditions in real time, has low monitoring efficiency, and cannot meet the needs of timely monitoring.
A soil settlement detection device is designed that includes detection pits, connecting plates, pipe sleeves, detection rods, counterweights, hooks and alarm components. It uses pressure sensors to sense soil settlement through detection ropes and alert workers in real time.
It achieves real-time and accurate monitoring of soil settlement, improves monitoring efficiency, reduces manpower and material investment, and meets the need for timely monitoring.
Smart Images

Figure CN221855477U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of bridge and tunnel engineering, in particular to a soil layer settlement detection device for bridge and tunnel engineering construction. Background Art
[0002] Bridge and tunnel engineering is an important branch of civil engineering, mainly involving the design, construction and maintenance of transportation infrastructure such as bridges and tunnels. Bridge and tunnel engineering plays a vital role in urban transportation construction and national infrastructure construction. They connect road networks in different regions and facilitate people's travel and cargo transportation.
[0003] During the construction of bridge and tunnel projects, workers need to conduct settlement detection on the soil layer at the construction site in advance, so a settlement detection device is needed. Traditional soil settlement detection devices usually use measuring poles or measuring points for monitoring. Their accuracy is limited by human factors and the accuracy of measuring equipment. They cannot reflect the soil settlement in real time and accurately, and require manual regular inspections. This consumes a lot of manpower and material resources, has low monitoring efficiency, and cannot meet the needs of timely monitoring of soil settlement changes. Utility Model Content
[0004] The purpose of the utility model is to provide a soil settlement detection device for bridge and tunnel engineering construction to solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a soil settlement detection device for bridge and tunnel engineering construction, comprising a detection pit, and also comprising: a connecting plate arranged at the top of the detection pit, a pipe sleeve is inserted into the inner cavity of the connecting plate, a limiting groove is provided on the top of the pipe sleeve, a detection rod is inserted into the inner cavity of the pipe sleeve, a counterweight block is provided at the bottom of the detection rod, and a hook is fixedly connected to the top of the detection rod; an alarm component is arranged on the surface of the pipe sleeve for reminding staff when the soil layer settles.
[0006] Preferably, the alarm assembly includes two positioning plates, and opposite sides of the two positioning plates are fixedly connected to the pipe sleeve. The tops of the two positioning plates are fixedly connected to adjustment rods, and a detection rope is provided on the surface of one of the adjustment rods, and the surface of the detection rope is in contact with the inner cavity of the hook.
[0007] Preferably, a pressure sensor is fixedly connected to the other side of the detection rope, and one side of the pressure sensor is connected to another adjustment rod.
[0008] Preferably, a positioning ring is sleeved on the bottom of the surface of the adjusting rod, and the bottom of the positioning ring is fixedly connected to the positioning plate.
[0009] Preferably, a movable sleeve is fixedly connected to the top of the positioning plate, and a positioning pin is inserted into the inner cavity of the movable sleeve.
[0010] Preferably, a connecting strip is fixedly connected to the surface of the detection rod, and the surface of the connecting strip is movably connected to the inner cavity of the limiting groove.
[0011] Preferably, a scraper shell is fixedly connected to the bottom of the tube sleeve, and the number of the scraper shells is three.
[0012] Compared with the prior art, the beneficial effects of the utility model are as follows:
[0013] The utility model first inserts the pipe sleeve into the interior of the connecting plate and extends it into the detection pit, then inserts the detection rod into the interior of the pipe sleeve, when it is inserted to a certain position, the counterweight block at the bottom of the detection rod will contact the bottom of the inner cavity of the detection pit, then the staff can adjust the height of the adjustment rod according to the position of the hook at the top of the pipe sleeve, when the position of the detection rope is level with the position of the hook, the detection rope is moved to the inside of the hook, when the soil layer settles, the detection rod will move downward by gravity, then the hook will pull the detection rope downward, the detection rope is connected to a pressure sensor, when the detection rope is pulled, the pressure sensor will be under pressure and alarm, then the staff can know the settlement of the soil layer. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 A schematic diagram of the structure of a soil settlement detection device for bridge and tunnel engineering construction provided by the utility model;
[0015] Figure 2 A schematic diagram of the structure of the pipe sleeve and the detection rod provided by the utility model;
[0016] Figure 3 A schematic diagram of the structure of the alarm assembly provided by the utility model;
[0017] Figure 4 This is a schematic diagram of the structural disassembly of the pipe sleeve and the detection rod provided by the utility model.
[0018] In the figure: 1. detection pit; 2. connecting plate; 3. alarm component; 301. positioning plate; 302. adjusting rod; 303. pressure sensor; 304. detection rope; 305. positioning ring; 306. movable sleeve; 307. positioning nail; 4. pipe sleeve; 5. limiting groove; 6. detection rod; 7. connecting strip; 8. hook; 9. counterweight block; 10. scraper shell. DETAILED DESCRIPTION
[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0020] See also Figure 1-4 As shown, a soil settlement detection device for bridge and tunnel engineering construction includes a detection pit 1, and also includes: a connecting plate 2 arranged on the top of the detection pit 1, a pipe sleeve 4 is inserted into the inner cavity of the connecting plate 2, a limiting groove 5 is provided on the top of the pipe sleeve 4, a detection rod 6 is inserted into the inner cavity of the pipe sleeve 4, a counterweight block 9 is provided at the bottom of the detection rod 6, and a hook 8 is fixedly connected to the top of the detection rod 6; an alarm component 3 is arranged on the surface of the pipe sleeve 4 for reminding the staff when the soil layer settles.
[0021] refer to Figure 1 , Figure 2 and Figure 3 As shown, the alarm component 3 includes a positioning plate 301, and the number of the positioning plates 301 is two. The opposite sides of the two positioning plates 301 are fixedly connected to the pipe sleeve 4, and the tops of the two positioning plates 301 are fixedly connected with adjusting rods 302. The surface of one of the adjusting rods 302 is provided with a detection rope 304, and the surface of the detection rope 304 contacts the inner cavity of the hook 8. The other side of the detection rope 304 is fixedly connected with a pressure sensor 303, and one side of the pressure sensor 303 is connected to the other adjusting rod 302. The bottom sleeve of the surface of the adjusting rod 302 is provided with a positioning ring 305, and the bottom of the positioning ring 305 is fixedly connected to the positioning plate 301. The top of the positioning plate 301 is fixedly connected with a movable sleeve 306, and the inner cavity of the movable sleeve 306 is inserted with a positioning nail 307.
[0022] It should be noted that: first, the staff adjusts the height of the adjusting rod 302 according to the position of the hook 8 at the top of the pipe sleeve 4. When the position of the detection rope 304 is level with the position of the hook 8, the detection rope 304 is moved to the inside of the hook 8. When the soil layer settles, the detection rod 6 will move downward by gravity. At this time, the hook 8 will pull the detection rope 304 downward. The detection rope 304 is connected to the pressure sensor 303. When the detection rope 304 is pulled, the pressure sensor 303 will be under pressure and alarm. At this time, the staff can know the settlement of the soil layer. By setting the pressure sensor 303, it is convenient for the staff to know the settlement of the soil layer in time. By setting the positioning ring 305, the adjusting rod 302 is positioned. By setting the movable sleeve 306 and the positioning nail 307, the positioning plate 301 is positioned.
[0023] refer to Figure 2, Figure 3 and Figure 4 As shown, a connecting strip 7 is fixedly connected to the surface of the detection rod 6, and the surface of the connecting strip 7 is movably connected to the inner cavity of the limiting groove 5. A scraping shell 10 is fixedly connected to the bottom of the sleeve 4, and the number of the scraping shells 10 is three.
[0024] It should be noted that: by providing the connecting strip 7, a role of limiting the detection rod 6 is played, and by providing the scraping shell 10, a role of scraping the dirt on the lower surface of the detection rod 6 is played.
[0025] Working principle: When the staff needs to detect the soil layer, first dig a detection pit 1 at the position to be detected, and then place the connecting plate 2 on the top of the detection pit 1. At this time, the staff will insert the pipe sleeve 4 into the inside of the connecting plate 2 and extend it into the detection pit 1. Then the staff can insert the detection rod 6 into the inside of the pipe sleeve 4. When it is inserted to a certain position, the counterweight block 9 at the bottom of the detection rod 6 will contact the bottom of the inner cavity of the detection pit 1. At this time, the staff can adjust the height of the adjustment rod 302 according to the position of the hook 8 at the top of the pipe sleeve 4. When the position of the detection rope 304 is level with the position of the hook 8, the detection rope 304 is moved to the inside of the hook 8. When the soil layer settles, the detection rod 6 will move downward by gravity. At this time, the hook 8 will pull the detection rope 304 downward. The detection rope 304 is connected to the pressure sensor 303. When the detection rope 304 is pulled, the pressure sensor 303 will be under pressure and alarm. At this time, the staff can know the settlement of the soil layer.
[0026] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0027] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A soil settlement detection device for bridge and tunnel engineering construction, comprising a detection pit (1), characterized in that: Also includes: A connecting plate (2) is arranged at the top of the detection pit (1), a pipe sleeve (4) is inserted into the inner cavity of the connecting plate (2), a limiting groove (5) is provided at the top of the pipe sleeve (4), a detection rod (6) is inserted into the inner cavity of the pipe sleeve (4), a counterweight block (9) is arranged at the bottom of the detection rod (6), and a hook (8) is fixedly connected to the top of the detection rod (6); An alarm component (3) is arranged on the surface of the pipe sleeve (4) and is used to alert workers when the soil layer settles.
2. The soil settlement detection device for bridge and tunnel engineering construction according to claim 1 is characterized by: The alarm component (3) comprises a positioning plate (301), wherein the number of the positioning plates (301) is two, and the opposite sides of the two positioning plates (301) are fixedly connected to the pipe sleeve (4), and the tops of the two positioning plates (301) are fixedly connected to adjustment rods (302), and a detection rope (304) is arranged on the surface of one of the adjustment rods (302), and the surface of the detection rope (304) is in contact with the inner cavity of the hook (8).
3. The soil settlement detection device for bridge and tunnel engineering construction according to claim 2 is characterized by: The other side of the detection rope (304) is fixedly connected to a pressure sensor (303), and one side of the pressure sensor (303) is connected to another adjustment rod (302).
4. The soil settlement detection device for bridge and tunnel engineering construction according to claim 2 is characterized by: A positioning ring (305) is sleeved on the bottom of the surface of the adjusting rod (302), and the bottom of the positioning ring (305) is fixedly connected to the positioning plate (301).
5. The soil settlement detection device for bridge and tunnel engineering construction according to claim 2 is characterized by: A movable sleeve (306) is fixedly connected to the top of the positioning plate (301), and a positioning pin (307) is inserted into the inner cavity of the movable sleeve (306).
6. The soil settlement detection device for bridge and tunnel engineering construction according to claim 1 is characterized by: A connecting strip (7) is fixedly connected to the surface of the detection rod (6), and the surface of the connecting strip (7) is movably connected to the inner cavity of the limiting groove (5).
7. The soil settlement detection device for bridge and tunnel engineering construction according to claim 1 is characterized by: The bottom of the pipe sleeve (4) is fixedly connected with a scraper shell (10), and the number of the scraper shells (10) is three.