Air pre-heater purging air storage tank and system thereof
By arranging pipe connections and reinforcement components in the air preheater gas storage tank, the strength and adaptability of the gas storage tank are improved, the problems of insufficient structural strength and installation complexity are solved, and efficient air pressure bearing and operational stability are achieved.
Patent Information
- Application Number
- CN202323589836.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2033-12-27
Smart Images

Figure CN221858307U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a gas storage tank, in particular to an air preheater purge gas storage tank and a system thereof. Background Art
[0002] Air preheater, the full name of which is air preheater, is a heat exchanger that uses the exhaust heat of boilers and other devices to preheat. Its function is to reduce the exhaust temperature of boilers and other equipment, improve thermal efficiency, make fuel easy to ignite, burn stably and improve combustion efficiency. As an important heat exchange equipment at the cold end of the boiler, the air preheater faces the problems of scaling, blockage, and reduced heat exchange efficiency caused by various factors such as poor coal quality, low load, and ammonia escape.
[0003] The main reasons for air preheater blockage are as follows: 1) escape of denitrification ammonia; 2) low unit load; 3) oil content in smoke; 4) high sulfur content in coal; 5) high moisture content in smoke.
[0004] The hazards of air preheater blockage: 1) The load capacity of the unit decreases, unplanned shutdowns increase, and the safety of operation is affected; 2) The heat exchange efficiency decreases and the air leakage rate increases, affecting the operating efficiency of the equipment; 3) The power consumption of the fan increases, affecting the economic efficiency of the equipment operation.
[0005] Therefore, it is necessary to purge the scale in the air preheater to avoid clogging of the air preheater. In the purge system, a gas tank is needed to store compressed gas. The air pressure of compressed air is relatively high, and the structural strength of the gas tank itself needs to be large enough. In addition, the installation environment of the gas tank is relatively complex, and the gas tank needs to have a flexible air outlet. In the prior art, as Chinese patent application CN108895300A discloses a gas tank for an air compressor, which is provided with a cylindrical tank body, and the cylindrical tank body is used to store compressed air, but the tank body does not have a structure to strengthen its own strength, and it is easy to cause safety accidents when it continuously stores compressed air with a relatively high pressure.
[0006] In order to solve the above problems, people have been seeking an ideal technical solution. Summary of the invention
[0007] The utility model aims to address the deficiencies of the prior art, thereby providing an air preheater purge gas storage tank and a system thereof with a strength reinforced structure.
[0008] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0009] An air preheater purge gas storage tank comprises a first tank body, a second tank body, a first pipe and a second pipe; the first pipe is connected to the first tank body, and the first pipe is passed through the second tank body, and the inner wall of the first pipe is fixedly connected to the inner wall of the second tank body; the second pipe is connected to the second tank body, and the second pipe is passed through the first tank body, and the inner wall of the second pipe is fixedly connected to the inner wall of the first tank body.
[0010] Furthermore, it also includes a first interface; the first interface is arranged on the first tank body to connect the internal space of the first tank body with the external space; the first interface is coaxially arranged or staggered with the first pipeline.
[0011] Furthermore, it also includes a second interface; the second interface is arranged on the second tank body to connect the internal space of the second tank body with the external space; the second interface is coaxially arranged or staggered with the second pipeline.
[0012] Furthermore, the first interface, the second interface, the first pipeline and the second pipeline constitute a reinforcement component; the reinforcement components are arranged in more than two groups, and the two groups of reinforcement components are arranged in sequence up and down.
[0013] Furthermore, it also includes a first supporting leg; the first supporting leg is fixedly connected to the side wall of the first tank body, and the lowermost end of the first supporting leg is flush with the lowermost end of the first tank body.
[0014] Furthermore, it also includes a second supporting leg; the second supporting leg is fixedly connected to the side wall of the second tank body, and the lowermost end of the second supporting leg is flush with the lowermost end of the second tank body.
[0015] Furthermore, the upper and lower ends of the first tank body and the second tank body are respectively provided with a medium channel communicating with the external space.
[0016] Furthermore, the first pipeline is isolated from the inner space of the second tank.
[0017] Furthermore, the second pipeline is isolated from the inner space of the first tank.
[0018] An air preheater purge system comprises an air energy pulse generating device and an air preheater purge air storage tank as described above; the air energy pulse generating device is connected to the first tank body, and the air energy pulse generating device is connected to the second tank body.
[0019] The utility model has substantial features and progress compared with the prior art, specifically:
[0020] 1. The first tank body and the second tank body of the utility model are provided with the first pipeline and the second pipeline, and the inlet and outlet of the first tank body and the second tank body are flexibly arranged, so that the first tank body and the second tank body can adapt to a more complex on-site environment, thereby increasing the adaptability of the utility model.
[0021] 2. The outer wall of the first pipe is fixedly connected to the tank wall of the second tank body, and the outer wall of the second pipe is fixedly connected to the tank wall of the first tank body. The strength of the first tank body and the second tank body is increased by a simple structure, thereby enhancing the air pressure bearing capacity of the first tank body and the second tank body.
[0022] 3. The lower end of the supporting leg is flush with the lower end of the tank body, which increases the size of the tank body within a limited space and improves the capacity of the tank body. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a front view of the air preheater purge gas storage tank of the utility model embodiment.
[0024] Figure 2 It is a top view of the air preheater purge gas storage tank of the utility model embodiment.
[0025] In the figure:
[0026] 1. First tank body; 2. Second tank body; 3. First pipeline; 4. Second pipeline;
[0027] 5. First supporting leg; 6. Second supporting leg;
[0028] 7. First interface; 8. Second interface;
[0029] 9. Lifting ears. DETAILED DESCRIPTION
[0030] Refer to the following Figure 1 to Figure 2 The technical solution of the utility model is further described in detail through specific implementation methods.
[0031] An air preheater purge gas storage tank comprises a first tank body 1, a second tank body 2, a first pipeline 3 and a second pipeline 4.
[0032] The first pipe 3 is connected to the first tank body 1 , and the first pipe 3 is passed through the second tank body 2 , and the outer wall of the first pipe 3 is fixedly connected to the tank body wall of the second tank body 2 .
[0033] The second pipe 4 is connected to the second tank body 2 , and the second pipe 4 is passed through the first tank body 1 , and the outer wall of the second pipe 4 is fixedly connected to the tank body wall of the first tank body 1 .
[0034] In detail, the first tank body 1 and the second tank body 2 are cylindrical shells arranged vertically. The upper end of the first tank body 1 is provided with a lifting lug 9 for lifting, and the second tank body 2 is also provided with a lifting lug 9 like the first tank body 1. It can be understood that the first pipe 3 and the second pipe 4 can be used as both the inlet channel and the outlet channel of the medium, and can be arranged according to actual needs. The first tank body 1 and the second tank body 2 of the utility model are provided with the first pipe 3 and the second pipe 4, and the inlet and outlet of the first tank body 1 and the second tank body 2 are flexibly arranged, so that the first tank body 1 and the second tank body 2 can adapt to more complex on-site environments, thereby increasing the adaptability of the utility model. The outer wall of the first pipe 3 is fixedly connected to the tank wall of the second tank body 2, and the outer wall of the second pipe 4 is fixedly connected to the tank wall of the first tank body 1, and the strength of the first tank body 1 and the second tank body 2 is increased by using a simple structure, thereby achieving the effect of enhancing the air pressure bearing capacity of the first tank body 1 and the second tank body 2.
[0035] Furthermore, the air preheater purge gas storage tank also includes a first interface 7; the first interface 7 is arranged on the first tank body 1 to connect the internal space of the first tank body 1 with the external space; the first interface 7 is coaxially arranged or staggered with the first pipeline 3.
[0036] Furthermore, the air preheater purge gas storage tank further includes a second interface 8, which is arranged on the second tank body 2 to connect the inner space of the second tank body 2 with the external space. The second interface 8 is coaxially arranged with the second pipeline 4 or staggered.
[0037] The external medium can enter the first tank body 1 through the first interface 7, and the medium in the first tank body 1 can be discharged to the outside through the first interface 7; the external medium can enter the second tank body 2 through the second interface 8, and the medium in the second tank body 2 can be discharged to the outside through the second interface 8. The first interface 7 and the second interface 8 can be connected to other equipment, such as an air compressor, a valve body, etc., by bolts. The medium includes gas, liquid or solid particles, etc.
[0038] Furthermore, the first interface 7, the second interface 8, the first pipeline 3 and the second pipeline 4 form a reinforcement assembly; the reinforcement assembly is provided in two or more groups, and the two groups of reinforcement assemblies are sequentially arranged up and down. Preferably, the reinforcement assembly is provided in two groups.
[0039] In some embodiments, the air preheater purge gas storage tank further includes a first support leg 5; the first support leg 5 is fixedly connected to the side wall of the first tank body 1, and the lowermost end of the first support leg 5 is flush with the lowermost end of the first tank body 1. In detail, two first support legs 5 are provided, and the two first support legs 5 are respectively fixedly connected to the two sides of the first tank body 1.
[0040] Furthermore, the air preheater purge gas storage tank further includes a second support leg 6; the second support leg 6 is fixedly connected to the side wall of the second tank body 2, and the lowermost end of the second support leg 6 is flush with the lowermost end of the second tank body 2. In detail, two second support legs 6 are provided, and the two second support legs 6 are respectively fixedly connected to the two sides of the second tank body 2.
[0041] Furthermore, a medium channel communicating with the external space is disposed at the upper and lower ends of the first tank body 1 and the second tank body 2. Specifically, the medium can flow into or out of the first tank body 1 or the second tank body 2 through the medium channel.
[0042] In some embodiments, the first pipe 3 is isolated from the inner space of the second tank body 2. The pipe wall of the first pipe 3 isolates the inner space of the first pipe 3 from the inner space of the second tank body 2.
[0043] In some embodiments, the second pipe 4 is isolated from the internal space of the first tank body 1. The pipe wall of the second pipe 4 isolates the internal space of the second pipe 4 from the internal space of the first tank body 1. When the medium in the first tank body 1 is discharged from the first pipe 3, it will flow through the interior of the second tank body 2, but the medium flowing out of the first tank body 1 is isolated from the medium in the second tank body 2 through the first pipe 3, and the same is true for the medium flowing out of the second tank body 2 through the second pipe 4. In other embodiments, the first tank body 1 and the second tank body 2 are provided with a connecting pipe, and a switch valve is provided on the connecting pipe. The switch valve is opened to connect the first tank body 1 and the second tank body 2 through the connecting pipe, and the switch valve is closed to block the connecting pipe. In other embodiments, a first through hole is opened on the inner wall of the first pipe 3, and the first through hole connects the first pipe 3 with the second tank body 2. A second through hole is opened on the inner wall of the second pipe 4, and the second through hole connects the second pipe 4 with the first tank body 1.
[0044] An air preheater purge system comprises an air energy pulse generating device, an air compressor and the air preheater purge air storage tank described in any one of the above items.
[0045] The air energy pulse generating device is connected to the first tank body 1 and the second tank body 2 at the same time. The air compressor is connected to the first tank body 1 and the second tank body 2 at the same time. The air compressor compresses the air into the first tank body 1 and the second tank body 2, and the compressed gas in the first tank body 1 can be released by the air energy pulse generating device, and the air energy pulse generating device can release the compressed air at a specific pulse frequency to purge the inside of the air preheater. It is understandable that other auxiliary devices can be installed on the first tank body 1 and the second tank body 2, such as a temperature sensor for detecting the temperature at various locations of the air preheater purge system, an air pressure sensor for detecting the internal air pressure of the first tank body 1 and the second tank body 2 and making appropriate warnings, and a water-gas separator for dehumidifying the air pressure circuit of the air preheater purge system.
[0046] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it, and the various embodiments can be combined within a reasonable range; although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in the relevant field should understand that the specific implementation method of the utility model can still be modified or some technical features can be replaced by equivalents; without departing from the spirit of the technical solution of the utility model, they should all be included in the scope of the technical solution for protection of the utility model.
Claims
1. An air preheater purge gas storage tank, Features: It includes a first tank body, a second tank body, a first pipeline and a second pipeline; The first pipe is connected to the first tank body, and the first pipe is arranged in the second tank body, and the outer wall of the first pipe is fixedly connected to the tank body wall of the second tank body; The second pipe is connected to the second tank body, and the second pipe is passed through the first tank body, and the outer wall of the second pipe is fixedly connected to the tank body wall of the first tank body.
2. The air preheater purge gas storage tank according to claim 1, Features: It also includes a first interface; The first interface is arranged on the first tank body to connect the internal space of the first tank body with the external space; The first interface is coaxially arranged or offsetly arranged with the first pipeline.
3. The air preheater purge gas storage tank according to claim 2, Features: It also includes a second interface; The second interface is arranged on the second tank body to connect the internal space of the second tank body with the external space; The second interface and the second pipeline are coaxially arranged or offsetly arranged.
4. The air preheater purge gas storage tank according to claim 3, Features: The first interface, the second interface, the first pipeline and the second pipeline constitute a reinforcement assembly; The reinforcement components are arranged in two or more groups, and the two groups of reinforcement components are arranged in sequence up and down.
5. The air preheater purge gas storage tank according to claim 1, Features: It also includes a first support leg; The first supporting leg is fixedly connected to the side wall of the first tank body, and the lowermost end of the first supporting leg is flush with the lowermost end of the first tank body.
6. The air preheater purge gas storage tank according to claim 5, Features: It also includes a second support leg; The second supporting leg is fixedly connected to the side wall of the second tank body, and the lowermost end of the second supporting leg is flush with the lowermost end of the second tank body.
7. The air preheater purge gas storage tank according to claim 6, Features: The upper and lower ends of the first tank body and the second tank body are respectively provided with a medium channel communicating with the external space.
8. The air preheater purge gas storage tank according to claim 1, Features: The first pipe is isolated from the inner space of the second tank.
9. The air preheater purge gas storage tank according to claim 1, Features: The second pipeline is isolated from the inner space of the first tank.
10. An air preheater purge system, Features: It comprises an air energy pulse generating device and an air preheater purge air storage tank as claimed in any one of claims 1 to 9 above; The air energy pulse generating device is communicated with the first tank body, and the air energy pulse generating device is communicated with the second tank body.