Pulse dredging device for ore storage bin

By combining the pulse dredging mechanism and vibration components in the ore bin, and using high-pressure air pulses and vibrations to disperse materials, the problem of long-term vibration caused by material adhesion in the existing technology is solved, rapid unblocking and efficient flow are achieved, and the ore efficiency is improved. Warehouse dredging efficiency and stability.

CN221875116UActive Publication Date: 2024-10-22FUSHUN TIANQI ELECTROMAGNETIC TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323588907.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-27
Publication Date
2024-10-22
Estimated Expiration
2033-12-27

AI Technical Summary

Technical Problem

The existing ore bin deblocking device needs to vibrate for a long time when the material adheres to the inner wall, resulting in low efficiency and unable to effectively solve the ore bin clogging problem.

Method used

A pulse unblocking device for the mine silo is designed, which combines a pulse unblocking mechanism and a vibration component. Through high-pressure air pulses and different frequency vibrations, it instantly disperses and loosens attached materials and relieves blockages. It is also equipped with a collection frame and a support structure to improve stability and Cleaning efficiency.

Benefits of technology

It can quickly remove the blockage of the ore silo, restore the normal flow of materials, improve the dredging efficiency, reduce the cleaning time, and enhance the stability of the equipment and the convenience of cleaning.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221875116U_ABST
    Figure CN221875116U_ABST
Patent Text Reader

Abstract

The utility model discloses an ore storage bin pulse dredging device which comprises an ore storage bin body and a discharging opening, the discharging opening is formed in the bottom of the ore storage bin body, a pulse dredging mechanism for dredging the discharging opening is arranged in the ore storage bin body, and a vibration assembly for improving the dredging efficiency of the pulse dredging mechanism is arranged outside the ore storage bin body. By arranging the pulse dredging mechanism, during use, the pulse dredging mechanism generates high-pressure air pulses, then the high-pressure air pulses are released into the ore storage bin, high-speed airflow generated by the high-pressure air pulses can instantly scatter or impact material particles attached to the wall of the ore storage bin, the material particles are loosened and fall off, and therefore blockage is relieved or relieved; and normal flowing of the materials is recovered.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical direction of ore bin blockage relief, and specifically relates to an ore bin pulse blockage relief device. Background Art

[0002] A silo is a structure used for short-term storage and loading of ore. When materials are discharged from the silo, they often encounter blockage problems caused by material agglomeration or accumulation in the silo, which may affect the normal flow and transportation of materials.

[0003] The existing patent (Announcement No.: CN208181832U) is a powder ore bin dredging device, which installs two sets of powder ore bin dredging energy oscillators inside the powder ore bin close to the discharge port. When the discharge port inside the powder ore bin is blocked, dredging and unblocking are carried out to achieve the advantages of safe, efficient and real-time dredging, improve efficiency and reduce costs.

[0004] Although this patent has the function of dredging the ore bin, it can only dredge the ore bin by vibration when in use. When the material adheres to the inner wall of the ore bin and is difficult to remove, it takes a long time of vibration to dredge the ore bin, which wastes a lot of time and affects work efficiency. Utility Model Content

[0005] The utility model aims to provide a pulse blockage dredging device for an existing ore bin to solve the problems raised in the above-mentioned background technology.

[0006] In order to solve the above technical problems, the utility model provides the following technical solutions: a pulse dredging device for a ore bin, comprising a ore bin body and a discharge port, wherein the discharge port is opened at the bottom of the ore bin body, a pulse dredging mechanism for dredging the discharge port is arranged inside the ore bin body, and a vibration component for improving the dredging efficiency of the pulse dredging mechanism is arranged outside the ore bin body;

[0007] The pulse dredging mechanism includes a pulse generator, an air compressor, a connecting pipe, an air collecting chamber and an exhaust groove. The pulse generator and the air compressor are both bolted to the top of the ore bin body, the connecting pipe is fixedly connected to the output end of the air compressor, the air collecting chamber is bolted to the inside of the discharge port, the exhaust groove is opened on the outer wall of the air collecting chamber, the pulse generator is connected to the air compressor by electrical signals, and one end of the connecting pipe is connected to the inside of the air collecting chamber.

[0008] The utility model further describes that the vibration assembly includes an electric vibrator, a mounting block and a bolt, the electric vibrator is arranged on one side of the ore bin body, the mounting block is welded to the outer wall of the electric vibrator, the bolt is threadedly connected to the inside of the mounting block, and one end of the bolt extends into the wall of the ore bin body and is threadedly connected to the ore bin body.

[0009] The utility model further illustrates that a support ring is welded on the outer wall of the ore bin body, and three support legs for improving the stability of the ore bin body are evenly distributed on the bottom of the support ring.

[0010] The utility model further illustrates that a collection frame for collecting materials generated during dredging is arranged below the ore bin body.

[0011] The utility model further illustrates that two support blocks are bolted to the outer wall of the collection frame, and a handle for moving the collection frame is rotatably connected to the side wall of the support block.

[0012] The utility model further describes that a fixing plate is welded to the bottom of the supporting leg, and a screw groove is opened on the top of the fixing plate for fixing the fixing plate, and the number of the screw grooves is four.

[0013] The utility model further illustrates that two stabilizing plates are bolted to the outer wall of the ore bin body to improve the stability of the connecting pipe during exhaust.

[0014] Compared with the prior art, the beneficial effects achieved by the utility model are: the utility model,

[0015] (1) By setting up a pulse dredging mechanism, the pulse dredging mechanism generates high-pressure air pulses when in use, and then releases the high-pressure air pulses into the ore bin. The high-speed airflow generated by these high-pressure air pulses can instantly break up or impact the material particles attached to the wall of the ore bin, loosening and falling them, thereby removing or alleviating the blockage and restoring the normal flow of the material.

[0016] (2) By setting up a vibration component, the vibration component can apply vibrations of different types and frequencies to the outer wall of the ore bin body when in use, which helps to loosen and dredge materials attached to the wall or bottom of the ore bin, thereby improving the dredging effect of the pulse dredging mechanism. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0018] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0019] Figure 2 It is a schematic diagram of the structure of the vibration assembly provided by the embodiment of the utility model;

[0020] Figure 3 It is a left view provided by an embodiment of the utility model;

[0021] Figure 4 The utility model embodiment provides Figure 3 The three-dimensional cross-section view at AA in the middle;

[0022] Figure 5 It is a structural schematic diagram provided by an embodiment of the utility model;

[0023] Figure 6 The utility model embodiment provides Figure 4 The enlarged view of point A in the middle;

[0024] Figure 7 The utility model embodiment provides Figure 5 Enlarged view of point B in the middle.

[0025] In the figure: 1. ore bin body; 2. discharge port; 3. pulse dredging mechanism; 4. vibration assembly; 5. support ring; 6. support leg; 7. collection frame; 8. support block; 9. handle; 10. fixing plate; 11. screw groove; 12. stabilizing plate; 301. pulse generator; 302. air compressor; 303. connecting pipe; 304. air collecting chamber; 305. exhaust groove; 401. electric vibrator; 402. mounting block; 403. bolt. DETAILED DESCRIPTION

[0026] The following is a further non-limiting detailed description of the technical solution of the utility model in conjunction with the preferred embodiments and the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0027] See also Figure 1-7 The utility model provides a technical solution: a pulse dredging device for a mine bin, comprising a mine bin body 1 and a discharge port 2, the discharge port 2 being opened at the bottom of the mine bin body 1, a pulse dredging mechanism 3 for dredging the discharge port 2 being arranged inside the mine bin body 1, and a vibration component 4 for improving the dredging efficiency of the pulse dredging mechanism 3 being arranged outside the mine bin body 1;

[0028] The pulse dredging mechanism 3 includes a pulse generator 301, an air compressor 302, a connecting pipe 303, an air collecting chamber 304 and an exhaust groove 305. The pulse generator 301 and the air compressor 302 are both bolted to the top of the ore bin body 1, the connecting pipe 303 is fixedly connected to the output end of the air compressor 302, the air collecting chamber 304 is bolted to the inside of the discharge port 2, and the exhaust groove 305 is opened on the outer wall of the air collecting chamber 304. The pulse generator 301 is connected to the air compressor 302 by electrical signals, and one end of the connecting pipe 303 is connected to the inside of the air collecting chamber 304.

[0029] The above scheme is adopted: by setting up a pulse generator 301, an air compressor 302, a connecting pipe 303, an air collecting chamber 304 and an exhaust groove 305, when in use, the air compressor 302 compresses atmospheric air into high-pressure air, and then discharges the compressed air into the interior of the connecting pipe 303 through the pulse generator 301, and then discharges it into the interior of the discharge port 2 through the air collecting chamber 304 and the exhaust groove 305, thereby breaking up the materials attached to the inner wall of the discharge port 2, loosening it and making it fall off, thereby removing or reducing the blockage and restoring the normal flow of the material.

[0030] refer to Figure 7 The vibration assembly 4 includes an electric vibrator 401, a mounting block 402 and a bolt 403. The electric vibrator 401 is arranged on one side of the ore bin body 1. The mounting block 402 is welded to the outer wall of the electric vibrator 401. The bolt 403 is threadedly connected to the inside of the mounting block 402. One end of the bolt 403 extends into the wall of the ore bin body 1 and is threadedly connected to the ore bin body 1.

[0031] The above scheme is adopted: by setting the electric vibrator 401, the mounting block 402 and the bolt 403, when in use, the electric vibrator 401 can apply vibrations of different types and frequencies to the outer wall of the ore bin body 1, which helps to loosen and dredge the materials attached to the wall or bottom of the ore bin, thereby improving the dredging effect of the pulse dredging mechanism 3.

[0032] refer to Figure 1 A support ring 5 is welded on the outer wall of the ore bin body 1 , and three support legs 6 for improving the stability of the ore bin body 1 are evenly distributed on the bottom of the support ring 5 .

[0033] By adopting the above solution, by providing the support ring 5 and the support legs 6, the support legs 6 can improve the stability of the ore bin body 1 during use, and prevent the ore bin body 1 from falling or shaking.

[0034] refer to Figure 1 A collecting frame 7 for collecting materials generated during dredging is provided below the ore bin body 1.

[0035] The above solution is adopted: by providing a collecting frame 7, after the materials on the inner wall of the discharge port 2 are cleaned off, the collecting frame 7 can collect them to prevent the materials from scattering and making it difficult to clean the ground.

[0036] refer to Figure 1 Two support blocks 8 are bolted to the outer wall of the collecting frame 7, and a handle 9 for moving the collecting frame 7 is rotatably connected to the side wall of the support block 8.

[0037] With the above solution, by providing the support block 8 and the handle 9 , when the collecting frame 7 is moved, the collecting frame 7 can be quickly moved by the handle 9 .

[0038] refer to Figure 1 A fixing plate 10 is welded to the bottom of the supporting leg 6, and a screw groove 11 for fixing the fixing plate 10 is opened on the top of the fixing plate 10, and the number of the screw grooves 11 is four.

[0039] The above solution is adopted: by providing the fixing plate 10 and the screw groove 11, when in use, the external screws are screwed into the inside of the screw groove 11, so as to facilitate fixing the support legs 6 and the mine bin body 1 on the ground, thereby further improving the stability of the mine bin body 1.

[0040] refer to Figure 1 Two stabilizing plates 12 are bolted to the outer wall of the ore bin body 1 to improve the stability of the connecting pipe 303 during exhaust.

[0041] The above solution is adopted: by providing the stabilizing plate 12, the stabilizing plate 12 can support the connecting pipe 303 during use, and prevent the connecting pipe 303 from shaking when gas flows inside the connecting pipe 303, thereby improving the stability of the connecting pipe 303.

[0042] The working principle of this utility model:

[0043] When in use, the air compressor 302 compresses atmospheric air into high-pressure air, and then discharges the compressed air into the interior of the connecting pipe 303 through the pulse generator 301. At this time, the stabilizing plate 12 can support the connecting pipe 303 to prevent the connecting pipe 303 from shaking when there is gas flowing inside the connecting pipe 303, thereby improving the stability of the connecting pipe 303. Then, the air is discharged into the interior of the discharge port 2 through the air collecting cavity 304 and the exhaust groove 305, thereby breaking up the materials attached to the inner wall of the discharge port 2, loosening them and causing them to fall off. Thereby, the blockage is released or alleviated, and the normal flow of materials is restored. Then, the electric vibrator 401 can apply vibrations of different types and frequencies to the outer wall of the ore bin body 1, which helps to loosen and dredge the materials attached to the wall or bottom of the ore bin, thereby further improving the dredging effect. When the ore bin body 1 is cleaned, the support legs 6 can improve the stability of the ore bin body 1 to prevent the ore bin body 1 from falling or shaking. After the materials on the inner wall of the discharge port 2 are cleaned up, the collection frame 7 can collect them to prevent the materials from scattering and making it difficult to clean the ground.

[0044] In the description of the present invention, it should be understood that the terms "upper", "lower", "front", "back", "left", "right", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.

[0045] Finally, it should be pointed out that the above embodiments are only used to illustrate the technical solutions of the utility model, rather than to limit them. Although the utility model is described in detail with reference to the above embodiments, a person skilled in the art should understand that the technical solutions described in the above embodiments can still be modified, or some of the technical features can be replaced by equivalents, and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the utility model.

Claims

1. A pulse blockage clearing device for an ore bin, comprising an ore bin body (1) and a discharge port (2). Features: The discharge port (2) is opened at the bottom of the ore bin body (1); a pulse dredging mechanism (3) for dredging the discharge port (2) is arranged inside the ore bin body (1); and a vibration component (4) for improving the dredging efficiency of the pulse dredging mechanism (3) is arranged outside the ore bin body (1); The pulse dredging mechanism (3) comprises a pulse generator (301), an air compressor (302), a connecting pipe (303), an air collecting chamber (304) and an exhaust groove (305); the pulse generator (301) and the air compressor (302) are both bolted to the top of the ore bin body (1); the connecting pipe (303) is fixedly connected to the output end of the air compressor (302); the air collecting chamber (304) is bolted to the inside of the discharge port (2); the exhaust groove (305) is provided on the outer wall of the air collecting chamber (304); the pulse generator (301) is electrically connected to the air compressor (302); and one end of the connecting pipe (303) is in communication with the inside of the air collecting chamber (304).

2. The pulse blockage clearing device for ore bin according to claim 1, Features: The vibration assembly (4) comprises an electric vibrator (401), a mounting block (402) and a bolt (403); the electric vibrator (401) is arranged on one side of a mine bin body (1); the mounting block (402) is welded to the outer wall of the electric vibrator (401); the bolt (403) is threadedly connected to the inside of the mounting block (402); one end of the bolt (403) extends into the wall of the mine bin body (1) and is threadedly connected to the mine bin body (1).

3. The pulse blockage clearing device for ore bin according to claim 1, Features: A support ring (5) is welded on the outer wall of the ore bin body (1), and three support legs (6) for improving the stability of the ore bin body (1) are evenly distributed on the bottom of the support ring (5).

4. The pulse blockage clearing device for ore bin according to claim 1, Features: A collection frame (7) for collecting materials generated during dredging is provided below the ore bin body (1).

5. The pulse blockage clearing device for ore bin according to claim 4, Features: Two support blocks (8) are bolted to the outer wall of the collection frame (7), and a handle (9) for facilitating the movement of the collection frame (7) is rotatably connected to the side wall of the support block (8).

6. The pulse blockage clearing device for ore bin according to claim 3, Features: A fixing plate (10) is welded to the bottom of the supporting leg (6), and a screw groove (11) is provided on the top of the fixing plate (10) for facilitating fixing of the fixing plate (10), and the number of the screw grooves (11) is four.

7. The pulse blockage clearing device for ore bin according to claim 1, Features: Two stabilizing plates (12) are bolted to the outer wall of the ore bin body (1) to improve the stability of the connecting pipe (303) during exhaust.