Garbage truck
By designing a garbage truck with a U-shaped rod frame and ring body clearance, the problem of congestion and pus contamination during the gauze counting process is solved, and the effective storage and counting of congestion and pus in the garbage bag are realized, and convenient garbage disposal is achieved.
Patent Information
- Application Number
- CN202122141490.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2021-09-06
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2031-09-06
AI Technical Summary
During the operation, the used gauze can easily cause congestion and pus to leak out during the counting process, contaminating the tray and counting personnel, and it is difficult to count effectively with the naked eye, increasing the complexity of the cleaning work.
A garbage truck is designed. The bottom plate is provided with a frame surrounded by U-shaped rods. The top is open and equipped with a ring body. The size of the ring body is smaller than the ring body, forming a gap for the socket of garbage bags. The garbage bag The inner wall is flat or inclined to prevent congestion and pus from dripping, the support rod supports the garbage bag, and the universal wheels facilitate movement.
It effectively prevents congestion and pus from contaminating counting personnel and the operating room, simplifies the gauze counting and storage process, and improves the convenience and safety of counting.
Smart Images

Figure CN221875198U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of medical equipment and relates to a garbage truck. Background Art
[0002] In today's life, with the continuous development of medical technology, surgery has become one of the more common treatment methods. It generally uses surgical equipment or instruments to enter human tissues under the operation of doctors or other professionals, and uses external force to eliminate lesions, change structures or implant foreign objects to treat patients.
[0003] During surgery, bleeding is inevitable from the incision at the surgical site. In addition, the doctor uses a scalpel to cut the affected area to discharge blood and pus. Medical staff usually use gauze to absorb the blood and pus that affect the field of vision, so as to make the field of vision of the surgical site clear and ensure that the medical staff can proceed to the next step.
[0004] Used gauze will be piled on a tray for postoperative counting (to prevent gauze from being left inside the patient's body during surgery, and to prevent gauze with pathogens from being left inside the operating room and causing contamination). Since this part of the gauze has sufficient water absorption capacity, when it is temporarily placed on the tray, the blood and pus inside the gauze are very likely to seep out, thereby contaminating other items on the tray; in addition, during the postoperative counting process, medical staff cannot effectively count the piled-up gauze with the naked eye, and generally use tweezers to pick up the pieces one by one for counting. However, during the picking process, the blood and pus in the gauze may drip, and the dripping blood and pus are very likely to splash onto the ground and the counting personnel, and increase the cleaning work of the counting personnel. Summary of the invention
[0005] The utility model aims at the above problems existing in the prior art and proposes a garbage truck. The technical problem to be solved by the utility model is: how to ensure that counting personnel can count the used gauze more conveniently.
[0006] The purpose of the utility model can be achieved through the following technical solutions: a garbage truck, comprising a bottom plate that can be used to carry a garbage can, characterized in that the bottom plate is connected to a frame with an open top formed by a plurality of U-shaped rods, a ring body 1 and a ring body 2 whose size is smaller than the ring body 1 are transversely arranged at the open end of the frame, a gap is provided between the ring body 1 and the ring body 2, and the height of the ring body 2 is equal to or lower than the height of the ring body 1.
[0007] The garbage truck includes a bottom plate, and medical staff can place a garbage can on the bottom plate during surgery. The garbage generated during the operation (such as medical garbage other than dressings and cotton balls) can be thrown into the garbage can after use, so as to ensure effective classification. A frame formed by a plurality of U-shaped rods is provided on the bottom plate, and the top of the frame is opened. Before the operation, medical staff can put the garbage bag into the frame through the open end of the frame, so that gauze, cotton balls, etc. during the operation can be collected in the garbage bag. In addition, a ring body 1 and a ring body 2 are provided at the top of the frame. The size of the ring body 2 is smaller than that of the ring body 1, so that a gap can be formed between the ring body 1 and the ring body 2, and the setting height of the ring body 2 is equal to Or lower than ring body one so that the gap formed between ring body one and the ring body is flat or inclined, and further, after the garbage bag is put into the frame, the circumferential inner wall corresponding to the garbage bag and the gap (that is, the abutment surface of the garbage bag for placing used gauze) is flat or inclined, and when the used gauze is placed on the abutment surface, the blood and pus absorbed inside the gauze itself will not flow out of the garbage bag, effectively avoiding the blood and pus from contaminating the clothes of the counting personnel during the subsequent counting work, ensuring the convenience of counting the gauze, and after the counting personnel have counted the number of gauze and confirmed that it is correct, they can directly pull up the bag mouth to make each gauze fall into the garbage bag, thereby ensuring that the counting and centralized storage of the used gauze is more convenient.
[0008] In the above-mentioned garbage truck, the gaps have the same circumferential width.
[0009] The circumferential width of the gap is the same, so that the circumferential width of the abutment surface formed by the inner wall of the garbage bag near the bag opening inside the frame is the same, preventing the edges of the gauze placed on the abutment surface from extending out of the bag opening of the garbage bag, and preventing the blood and pus in the gauze from dripping out of the garbage bag.
[0010] In the above-mentioned garbage truck, both ends of several U-shaped rods are fixedly connected to the two outer walls of the ring body, and several support rods are arranged at intervals in the gap. One end of the support rod is fixedly connected to an outer wall of the ring body, and the other end is fixedly connected to the end of the U-shaped rod.
[0011] Both ends of the U-shaped rod are fixedly connected to the two outer sides of the ring body, and a number of support rods are arranged at intervals in the gap, so that the bag mouth of the garbage bag mounted in the frame can be supported, to prevent the gauze from being too heavy to crush the abutment surface and causing the gauze to fall from the gap to the bottom plate, thereby preventing the blood and pus in the gauze from splashing and causing pollution to the operating room, and one end of the support rod is fixedly connected to an outer side wall of the ring body, and the other end is fixedly connected to the end of the U-shaped rod, to ensure the stability of the support rod connection.
[0012] In the above-mentioned garbage truck, a sliding rod is vertically arranged on one side of the bottom plate, and the frame is located above the bottom plate and close to one side edge of the bottom plate. A ring that can be sleeved on the sliding rod and slide is fixed on the outer wall of one of the U-shaped rods, and a threaded hole is opened on one side of the ring. A locking bolt that can press against the outer wall of the sliding rod to position the frame is threadedly connected in the threaded hole.
[0013] The bottom plate has a frame with a vertically arranged sliding rod on one side, and the frame is located above the bottom plate and close to one side edge of the bottom plate. If the bottom of the garbage bag is damaged or the blood and pus in the gauze drip from the bag mouth to the outside, the tray can also play a role of receiving and preventing the blood and pus from dripping onto the ground. A ring is fixed on the outer wall of one of the U-shaped rods that enclose the frame. The ring is sleeved on the sliding rod and can slide up and down, so that the height of the frame can be adjusted, so that the different needs of medical staff can be met during the operation. A threaded hole is provided on one side of the ring, and a locking bolt is threadedly connected to the threaded hole. When the frame is adjusted to the height required by the medical staff, the locking bolt can be tightened inwardly so that the locking bolt is pressed against the outer wall of the sliding rod, thereby positioning the frame and ensuring the stability of the frame when it is in use.
[0014] In the above-mentioned garbage truck, universal wheels are provided at the circumferential corners of the bottom of the base plate.
[0015] Universal wheels are arranged around the bottom of the base plate to ensure that the garbage truck can be moved labor-savingly and conveniently, and can also be integrated and stored to save space.
[0016] Compared with the prior art, this garbage truck has the following advantages:
[0017] 1. The garbage truck includes a bottom plate for carrying a garbage bin, one side of the bottom plate is provided with a frame formed by a plurality of U-shaped rods, the top end of the frame is open, and a ring body 1 and a ring body 2 are provided at the top end of the frame, the size of the ring body 2 is smaller than the ring body 1 and the height is equal to or lower than the ring body 1, so that a gap can be formed between the ring body 1 and the ring body 2, and the circumferential inner side walls close to the opening end are abutted against the inner walls of the ring body 1 and the ring body 2, so that the inner side wall of the garbage bag between the ring body 1 and the ring body 2 forms an abutment surface for placing gauze, so that the counting personnel can directly count the number of gauze in the subsequent postoperative counting work, and after the gauze number is counted and confirmed to be correct, the bag mouth can be directly pulled up to make each gauze fall into the garbage bag, thereby ensuring that the counting and centralized storage of used gauze are more convenient.
[0018] Second, the circumferential width of the gap is the same, so that the circumferential width of the abutment surface formed by the garbage bag placed in the frame is the same, preventing the edges of the gauze placed on the abutment surface from sticking out of the garbage bag mouth, preventing the blood and pus in the gauze from dripping out of the garbage bag, and ensuring the convenience of counting the gauze.
[0019] 3. Both ends of the U-shaped rod are fixedly connected to the two outer sides of the ring body, and a number of support rods are arranged at intervals in the gap, one end of the support rod is fixedly connected to the first side of the ring body, and the other end is fixedly connected to the end of the U-shaped rod, so that when the garbage bag is put into the frame, the circumferential side wall at the bag mouth can be supported, so as to avoid the excessive weight of the gauze from crushing the abutment surface and causing the gauze to fall from the gap to the bottom plate, thereby preventing the blood and pus in the gauze from splashing and causing pollution in the operating room.
[0020] Fourth, the bottom plate has a frame with a vertically arranged sliding rod on one side, and the frame is located above the bottom plate and close to one side edge to ensure that the bottom plate can also play a supporting role. A ring is fixed on the outer wall of one of the U-shaped rods, and the ring is sleeved on the sliding rod and can slide up and down, so that the height of the frame can be adjusted to meet the different needs of medical staff during the operation. A threaded hole is provided on one side of the ring, and a locking bolt is threadedly connected to the threaded hole. The locking bolt is used to tighten the outer wall of the sliding rod to position the frame and ensure the stability of the frame when it is in use. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 This is the structure diagram of the garbage truck Figure 1 .
[0022] Figure 2 This is the structure diagram of the garbage truck Figure 2 .
[0023] Figure 3 It is a structural diagram of the frame and its partial enlarged diagram.
[0024] In the figure, 1, base plate; 2, frame; 2a, U-shaped rod; 2b, ring body 1; 2c, ring body 2; 2d, collar; 2d1, threaded hole; 2d11, locking bolt; 3, slide rod; 4, universal wheel; 5, gap; 5a, support rod. DETAILED DESCRIPTION
[0025] The following are specific embodiments of the present invention and the accompanying drawings to further describe the technical solution of the present invention, but the present invention is not limited to these embodiments.
[0026] like Figure 1-3 As shown, the garbage truck includes a rectangular bottom plate 1, a universal wheel 4 is arranged at the circumferential corner of the bottom of the bottom plate 1, a cylindrical slide rod 3 is welded and fixed to one side of the bottom plate 1, and the garbage truck also includes a frame 2, as shown in FIG. Figure 3As shown, the frame 2 is specifically formed by three U-shaped rods 2a, the bottom end of which is hollowed out circumferentially and the top end is open, and a ring 2d with two ends passing through is welded and fixed on the outer wall of one of the U-shaped rods 2a, and the ring 2d can be sleeved on the slide bar 3 to slide up and down, so that the frame 2 formed by the three U-shaped rods 2a is located above the bottom plate 1 and close to one side edge so that the height can be adjusted, and a threaded hole 2d1 is provided on one side of the ring 2d, and a positioning pin is connected to the inner thread of the threaded hole 2d1. When the frame 2 needs to be positioned after the height adjustment is completed, the medical staff can turn the locking bolt 2d11 to make the locking bolt 2d11 press against the outer wall of the slide bar 3, so that the frame 2 is positioned.
[0027] like Figure 1-3 As shown, the frame 2 is fixed with a ring body 2b and a ring body 2c in a circular shape by welding near the top end. The ring body 2b and the ring body 2c are both made of stainless steel material, and the size of the ring body 2c is smaller than the size of the ring body 2b. In addition, the setting height of the ring body 2c is lower than the setting height of the ring body 2b. A gap 5 can be formed between the ring body 2b and the ring body 2c, and the circumferential width of the gap 5 is the same. When a garbage bag is placed in the frame 2, the circumferential inner wall of the garbage bag near the bag opening abuts against the inner walls of the ring bodies 1 2b and 2c, so that an inclined abutting surface can be formed between the outer wall of the garbage bag, the ring body 2b, and the ring body 2c (that is, the circumferential inner wall of the garbage bag corresponding to the position of the gap 5).
[0028] like Figure 1-3 As shown, both ends of each U-shaped rod 2a are welded and fixed to the outer wall of the ring body 2c, and a plurality of support rods 5a are arranged at intervals in the gap 5. One end of each support rod 5a is welded to the outer wall of the ring body 2a, and the other end is welded and fixed to the end of the U-shaped rod 2a, so that the abutment surface of the garbage bag is more firm.
[0029] Principle of use: Before the operation, the medical staff will put the garbage bag into the frame 2, and the circumferential outer wall of the garbage bag near the bag opening will abut against the ring body 1 2b and the ring body 2 2c, so that the circumferential inner wall of the garbage bag near the bag opening forms an abutment surface. During the operation, the medical staff will place the used gauze (already absorbed with blood and pus) evenly along the abutment surface. At this time, the blood and pus in the gauze can flow into the garbage bag along the abutment surface and the inner wall of the garbage bag due to gravity. After the postoperative inventory is completed, the inventory personnel can directly pull the bag opening of the garbage bag to close it, so that all the gauze placed on the abutment surface falls into the garbage bag.
[0030] The specific embodiments described herein are merely examples of the spirit of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in similar ways, but they will not deviate from the spirit of the present invention or exceed the scope defined by the appended claims.
[0031] Although this article uses more terms such as 1, bottom plate; 2, frame; 2a, U-shaped rod; 2b, ring body 1; 2c, ring body 2; 2d, collar; 2d1, threaded hole; 2d11, locking bolt; 3, slide bar; 4, universal wheel; 5, gap, etc., it does not exclude the possibility of using other terms. The use of these terms is only for more convenient description and explanation of the essence of the utility model; interpreting them as any additional restrictions is contrary to the spirit of the utility model.
Claims
1. A garbage truck, comprising a bottom plate (1) capable of supporting a garbage can, It is characterized in that The bottom plate (1) is connected to a frame (2) formed by a plurality of U-shaped rods (2a) and having an open top. A ring body (2b) and a ring body (2c) smaller in size than the ring body (2b) are disposed transversely at the open end of the frame (2). A gap (5) is provided between the ring body (2b) and the ring body (2c), and the height of the ring body (2c) is equal to or lower than the height of the ring body (2b).
2. The garbage truck according to claim 1, It is characterized in that The gap (5) has the same circumferential width.
3. The garbage truck according to claim 1 or 2, It is characterized in that Both ends of the U-shaped rods (2a) are fixedly connected to the outer wall of the second ring body (2c); a plurality of support rods (5a) are arranged at intervals in the gap (5); one end of the support rod (5a) is fixedly connected to the outer wall of the first ring body (2b), and the other end is fixedly connected to the end of the U-shaped rod (2a).
4. The garbage truck according to claim 3, It is characterized in that A sliding rod (3) is vertically arranged on one side of the base plate (1), and the frame (2) is located above the base plate (1) and close to one side edge of the base plate (1). A sleeve (2d) capable of being sleeved on and sliding on the sliding rod (3) is fixedly arranged on the outer side wall of one of the U-shaped rods (2a), and a threaded hole (2d1) is opened on one side of the sleeve (2d). The threaded hole (2d1) is internally threadedly connected with a locking bolt (2d11) capable of pressing against the outer side wall of the sliding rod (3) to position the frame (2).
5. The garbage truck according to claim 4, It is characterized in that Universal wheels (4) are provided at the circumferential corners of the bottom of the base plate (1).