Road concrete side formwork
By setting up synchronous supporting components on the road concrete side formwork, the problems of unstable support of the side formwork and concrete leakage are solved, the precise positioning of the dowel rods and the clean state of the side formwork are achieved, and the construction and transportation process is simplified.
Patent Information
- Application Number
- CN202420180838.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-01-25
AI Technical Summary
In road concrete construction, the side formwork is easily deformed when supporting the dowel rod, and the gap at the hole where the dowel rod passes causes concrete to seep out, which increases the quality of the side formwork and affects handling.
A road concrete side formwork was designed, using synchronous support components, including support frames, positioning sleeves, threaded pipes and sponge layers, to ensure the precise positioning and sealing of the dowel rods and prevent concrete seepage.
It achieves stable support of the side formwork and precise positioning of the dowel rod, avoids concrete leakage, and simplifies the installation and subsequent transportation process.
Smart Images

Figure CN221877633U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of road concrete construction, in particular to a road concrete side formwork. Background Art
[0002] In the road pouring concrete construction, it is necessary to use side formwork to limit the poured concrete. At the same time, it is necessary to penetrate a plurality of force transfer rods through the side formwork. The force transfer rods are located in the center of the transverse joints of the cement concrete road slab to strengthen the road surface and ensure that the vehicle load can be smoothly transmitted.
[0003] When in use, the side formwork needs to be supported by diagonal rods to prevent it from being deformed by force. At the same time, multiple force transfer rods need to be passed through the side formwork. In order to ensure the neatness of the multiple force transfer rods, additional support is required for the force transfer rods, which is time-consuming and labor-intensive. In addition, there will be gaps when the force transfer rods pass through the through holes of the side formwork. The poured concrete will seep out from the gaps to the outside of the side formwork for solidification, increasing the mass of the side formwork and affecting subsequent handling. Utility Model Content
[0004] In order to solve the above-mentioned problems, the utility model provides a road concrete side formwork.
[0005] The utility model is realized through the following technical solutions:
[0006] A road concrete side formwork comprises a side formwork on a concrete side, wherein a plurality of through holes are opened on the side formwork, force transmission rods are passed through the through holes, and a support assembly for synchronously positioning the force transmission rod and the side formwork is arranged on the outer side of the force transmission rod.
[0007] Further optionally, the support assembly includes a support frame facing the through hole, a vertical positioning sleeve is provided on the outer side of the support frame, and a positioning rod is provided in the positioning sleeve.
[0008] Further optionally, a threaded tube is transversely arranged in the middle of the support frame, a limit sleeve is connected to the inner thread of the threaded tube, and a force transmission rod is passed through the inner thread of the limit sleeve.
[0009] Further optionally, one end of the limiting sleeve extends into the step groove outside the through hole.
[0010] Further optionally, an annular groove is formed inside one side of the limiting sleeve facing the through hole, and a sealed sponge layer is arranged in the annular groove.
[0011] Further optionally, the top of the positioning rod is located on the upper part of the limiting sleeve to limit the force transmission rod.
[0012] Compared with the existing technology, the beneficial effect of the utility model is that: by arranging a support component on the outer side of the road concrete side formwork to synchronously position it and the force transfer rod, the utility model not only realizes the stable support of the side formwork, but also enables the precise positioning of multiple force transfer rods, thereby ensuring the neatness of the installation of multiple force transfer rods. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a three-dimensional schematic diagram of the structure of the utility model;
[0014] Figure 2 yes Figure 1 A schematic enlarged view of the local structure in FIG.
[0015] Figure 3 It is a cross-sectional schematic diagram of the practical limit sleeve;
[0016] In the figure: side template 1, through hole 2, support frame 3, threaded pipe 4, limit sleeve 5, annular groove 51, sponge layer 52, force transmission rod 6, positioning sleeve 7, positioning plug rod 8. DETAILED DESCRIPTION
[0017] The present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods:
[0018] like Figure 1 As shown, a road concrete side formwork includes a side formwork 1 on the concrete side, a plurality of through holes 2 are opened on the side formwork 1, force transmission rods 6 are passed through the through holes 2, and a supporting component for synchronously positioning the force transmission rods 6 and the side formwork 1 is arranged on the outer side of the force transmission rods 6.
[0019] like Figure 2 As shown, the support assembly includes a support frame 3 facing the through hole 2, a vertical positioning sleeve 7 is arranged on the outer side of the support frame 3, and a positioning rod 8 is arranged inside the positioning sleeve 7. The positioning rod 8 is positioned and fixed to achieve stable support of the side template 1.
[0020] like Figure 2 As shown, a threaded tube 4 is horizontally arranged in the middle of the support frame 3, and the inner thread of the threaded tube 4 is connected to a limiting sleeve 5. The force transmission rod 6 is positioned by the limiting sleeve 5, and the force transmission rod 6 is inserted into the limiting sleeve 5. When the sponge layer 52 in the limiting sleeve 5 is damaged and the sealing performance is poor, the limiting sleeve 5 in the threaded tube 4 can be rotated to disengage it from the through hole 2, so that the sponge layer 52 in the limiting sleeve 5 can be replaced conveniently.
[0021] like Figure 2 As shown, one end of the limiting sleeve 5 extends into the step groove outside the through hole 2, and the closure of the limiting sleeve 5 and the through hole 2 is achieved through the step groove.
[0022] like Figure 3As shown, an annular groove 51 is opened inside the side of the limit sleeve 5 facing the through hole 2, and a sealed sponge layer 52 is arranged in the annular groove 51. The arranged sponge layer 52 can prevent concrete from seeping from the limit sleeve 5, thereby ensuring the cleanliness of the limit sleeve 5. When the side formwork 1 is disassembled later, it is more convenient for the limit sleeve 5 to be separated from the force transmission rod 6.
[0023] like Figure 2 As shown, the top of the positioning rod 8 is located on the upper part of the limiting sleeve 5 to limit the force transmission rod 6.
[0024] The implementation principle of a road concrete side formwork in the embodiment of the present application is:
[0025] When the side formwork 1 is fixed, place it vertically (such as Figure 1 As shown), insert a plurality of positioning rods 8 into the positioning sleeves 7 of the corresponding support components, and insert the positioning rods 8 into the lower base for fixing, and support and fix the side template 1 through the support frame 3;
[0026] After the side formwork 1 is fixed, multiple force transfer rods 6 are passed through the through hole 2 of the side formwork 1, so that one section of the force transfer rod 6 remains on the inner side of the side formwork 1, and the other section of the force transfer rod 6 passes through the limiting sleeve 5 and its end is in contact with the positioning plug rod 8. In this way, the positioning of multiple force transfer rods 6 is achieved and the neatness of the installation of multiple force transfer rods 6 is ensured. At the same time, the sponge layer 52 in the limiting sleeve 5 can prevent the concrete from seeping from the gap between the through hole 2 and the force transfer rod 6 when it is delivered, thereby ensuring the cleanliness of the side formwork 1 and making subsequent transportation more convenient.
[0027] The above shows and describes the basic principles, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principles of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.
Claims
1. A road concrete side formwork, comprising a side formwork (1) for a concrete side portion, characterized in that: The side formwork (1) is provided with a plurality of through holes (2), a force transmission rod (6) is passed through the through holes (2), and a support assembly for synchronously positioning the force transmission rod (6) and the side formwork (1) is provided on the outer side of the force transmission rod (6); The support assembly comprises a support frame (3) facing the through hole (2), a vertical positioning sleeve (7) is arranged on the outer side of the support frame (3), and a positioning rod (8) is arranged inside the positioning sleeve (7); A threaded tube (4) is transversely arranged in the middle of the support frame (3); the threaded tube (4) is internally threadedly connected to a limiting sleeve (5); and a force transmission rod (6) is inserted into the limiting sleeve (5); One end of the limiting sleeve (5) extends into the step groove outside the through hole (2), and an annular groove (51) is formed inside the side of the limiting sleeve (5) facing the through hole (2), and a sealing sponge layer (52) is arranged in the annular groove (51); The top of the positioning rod (8) is located on the upper part of the limiting sleeve (5) and can limit the force transmission rod (6).