Movable PCCP (prestressed concrete cylinder pipe) installation joint grouting working platform

By designing a mobile working platform on the large-diameter PCCP pipeline, the problem of insufficient working space on the top and safety belt hanging is solved, safe and efficient grouting work is achieved, and construction safety is improved.

CN221878756UActive Publication Date: 2024-10-22SINOHYRDO ENG BUREAU 3 CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420253274.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-01
Publication Date
2024-10-22
Estimated Expiration
2034-02-01

AI Technical Summary

Technical Problem

The large-diameter PCCP pipe joint grouting work has safety risks due to the limited top working space and the lack of fixed safety belt connections, making it difficult to meet construction safety requirements.

Method used

Design a mobile PCCP pipe installation joint grouting working platform, which includes a mobile frame installed on the pipeline and a fixed working platform with guardrails. One side of the fixed working platform is hinged and foldable, and is mounted on an arc-shaped support frame. Rollers and telescopic ladders are installed underneath to ensure flexible movement and safe mounting of the platform.

Benefits of technology

It effectively solves the problem of insufficient working space at the top of large-diameter PCCP pipelines, provides a safe working environment, facilitates the installation of safety belts, and improves construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221878756U_ABST
    Figure CN221878756U_ABST
Patent Text Reader

Abstract

The utility model discloses a movable PCCP (prestressed concrete cylinder pipe) installation joint grouting working platform which comprises a movable frame body arranged on the upper portion of a pipe, a fixed working platform is arranged on the top of the movable frame body, a guardrail is arranged on the fixed working platform, a folding working platform is hinged to one side of the fixed working platform, and the folding working platform is hinged to the other side of the fixed working platform. The lower portions of the two sides of the movable frame body are each hinged to a telescopic ladder stand, the movable frame body comprises an arc-shaped supporting frame and a plurality of idler wheels arranged on the concave arc side of the arc-shaped supporting frame, and the bottom of the fixed working platform and the bottom of the folding working platform are each provided with four telescopic supporting legs. The working platform is reasonable in structural design, the fixed working platform with the guardrails is installed on the pipeline through the movable frame body, the folding type working platform is hinged to one side of the fixed working platform, the folding type working platform can be flexibly folded and unfolded according to construction requirements, the problem that the working space of the top of the large-diameter PCCP is limited is solved, and the working efficiency of the large-diameter PCCP is improved. Meanwhile, the safety belt can be hung conveniently, and construction safety is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of pipeline installation, and in particular relates to a mobile PCCP pipeline installation joint grouting work platform. Background Art

[0002] PCCP pipeline installation joint grouting is an important step in pipeline installation. Joint grouting work is required after every two sections of pipeline are butt-jointed and installed. It is mainly to maintain the airtightness of the water pipeline and prevent the steel socket from directly contacting the soil environment and causing corrosion.

[0003] At present, the construction projects of large-diameter PCCP water pipelines are increasing. The grouting of large-diameter PCCP pipeline joints is a high-altitude operation project with certain risks. It is also a key project for pipeline installation. It is of great significance for pressure testing and pipeline corrosion protection before the completion of the pipeline. At present, most people carry out grouting work on the premise of taking good safety protection on the top of the pipeline. However, the working space on the top of the large-diameter PCCP pipeline is limited, and unlike other high-altitude operation projects, there is no fixed safety belt connection on the top of the pipeline, which cannot meet the safety requirements of the safety belt hanging high and using low. Therefore, the safety protection on the top of the PCCP pipeline often requires the use of other auxiliary facilities. Therefore, a mobile PCCP pipeline installation joint grouting work platform is needed to solve the problem of insufficient working space on the top of the pipeline. Utility Model Content

[0004] The technical problem to be solved by the utility model is to provide a mobile PCCP pipeline installation joint grouting work platform in view of the deficiencies in the above-mentioned prior art. The structure is reasonably designed. A fixed work platform with a guardrail is installed on the pipeline through a mobile frame, and a foldable work platform is hinged on one side of the fixed work platform. The foldable work platform can be flexibly retracted and deployed according to construction requirements, which solves the problem of limited working space on the top of large-diameter PCCP pipelines. At the same time, it is convenient to hang a safety belt to ensure construction safety.

[0005] In order to solve the above technical problems, the technical solution adopted by the utility model is: a mobile PCCP pipeline installation joint grouting work platform, characterized in that: it includes a mobile frame arranged on the upper part of the pipeline and capable of moving along the longitudinal direction of the pipeline, a fixed working platform is arranged on the top of the mobile frame, a guardrail is arranged on the fixed working platform, a foldable working platform that can be folded upward is hinged on one side of the fixed working platform, and a telescopic ladder that can be folded upward is respectively hinged on the lower part of both sides of the mobile frame, the mobile frame includes an arc-shaped support frame and a plurality of rollers arranged on the concave arc side of the arc-shaped support frame, and four telescopic legs are respectively arranged at the bottom of the fixed working platform and the bottom of the foldable working platform.

[0006] The above-mentioned mobile PCCP pipeline installation joint grouting work platform is characterized in that: the arc-shaped support frame includes two arc-shaped supports arranged in sequence along the longitudinal direction of the pipeline, and a plurality of longitudinal connecting rods are connected between the two arc-shaped supports.

[0007] The above-mentioned mobile PCCP pipeline installation joint grouting work platform is characterized in that the arc-shaped support frame is coaxially arranged with the pipeline.

[0008] The above-mentioned mobile PCCP pipeline installation joint grouting work platform is characterized in that: the fixed work platform is welded to the top of the arc-shaped support frame, and the four telescopic legs at the bottom of the fixed work platform pass through the arc-shaped support frame and are supported on the pipeline.

[0009] The above-mentioned mobile PCCP pipeline installation joint grouting work platform is characterized in that the roller is a rubber wheel.

[0010] The above-mentioned mobile PCCP pipeline installation joint grouting work platform is characterized in that: the telescopic ladder includes an upper ladder and a lower ladder arranged at the lower part of one side of the upper ladder, the upper ladder includes two upper side railings and a plurality of upper cross bars connected between the two upper side railings, the lower ladder includes two lower side railings and a plurality of lower cross bars connected between the two lower side railings, and the upper ends of the two lower side railings are respectively arranged close to the lower ends of one side of the two upper side railings.

[0011] The above-mentioned mobile PCCP pipeline installation joint grouting work platform is characterized in that the upper side railing and the lower side railing connected thereto are fixedly connected by bolts, a plurality of bolt through holes are opened on the upper side railing, and a bolt through hole is opened on the lower side railing.

[0012] The above-mentioned mobile PCCP pipeline installation joint grouting work platform is characterized in that: a fastener is arranged between the lower part of the arc-shaped support frame and the upper part of the telescopic ladder, and the fastener includes a first sleeve fixed to the bottom of the concave arc side of the arc-shaped support frame, a second sleeve fixed to the upper inner side of the telescopic ladder, and a positioning pin connecting the first sleeve and the second sleeve together.

[0013] Compared with the prior art, the utility model has the following advantages:

[0014] 1. The utility model installs a fixed working platform on the pipeline through a mobile frame, which is convenient for construction personnel to flexibly adjust the fixed working platform to a position according to the pipeline construction position, and then perform grouting work on the pipeline joints. At the same time, a foldable working platform is hinged on one side of the fixed working platform. The foldable working platform can be flexibly retracted and deployed according to construction requirements, which has solved the problem of limited working space on the top of large-diameter PCCP pipelines.

[0015] 2. The utility model can effectively ensure the safety of construction workers by arranging guardrails on the fixed working platform. At the same time, the safety belt can be hung on the guardrails during construction work.

[0016] To sum up, the utility model has a reasonable structural design. A fixed working platform with a guardrail is installed on the pipeline through a mobile frame, and a folding working platform is hinged on one side of the fixed working platform. The folding working platform can be flexibly retracted and deployed according to construction requirements, which solves the problem of limited working space on the top of large-diameter PCCP pipelines. At the same time, it is convenient to hang a safety belt to ensure construction safety.

[0017] The technical solution of the utility model is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a structural schematic diagram of the utility model.

[0019] Figure 2 for Figure 1 Enlarged view of point A.

[0020] Figure 3 for Figure 1 Left view of .

[0021] Figure 4 for Figure 1 Top view of the .

[0022] Description of reference numerals:

[0023] 1—Pipeline; 2—Fixed working platform; 3—Foldable working platform;

[0024] 4—telescopic legs; 5—arc-shaped support frame; 5-1—arc-shaped bracket;

[0025] 5-2—longitudinal connecting rod; 6—roller; 7—guardrail;

[0026] 8—telescopic ladder; 8-1-1—upper side rails; 8-1-2—upper crossbars;

[0027] 8-2-1—lower side rail; 8-2-2—lower crossbar; 8-3—bolts;

[0028] 8-4—bolt hole; 9—first sleeve; 10—second sleeve;

[0029] 11—Location pin. DETAILED DESCRIPTION

[0030] like Figures 1 to 4 As shown, the utility model includes a mobile frame which is arranged on the upper part of the pipeline 1 and can move along the longitudinal direction of the pipeline 1, a fixed working platform 2 is arranged on the top of the mobile frame, a guardrail 7 is arranged on the fixed working platform 2, a foldable working platform 3 which can be folded upwards is hinged on one side of the fixed working platform 2, and a telescopic ladder 8 which can be folded upwards is hinged on the lower part of both sides of the mobile frame respectively, the mobile frame includes an arc-shaped support frame 5 and a plurality of rollers 6 arranged on the concave arc side of the arc-shaped support frame 5, and four telescopic legs 4 are respectively arranged at the bottom of the fixed working platform 2 and the bottom of the foldable working platform 3.

[0031] During actual use, a fixed working platform 2 is installed on the pipeline 1 through a mobile frame, so that construction personnel can flexibly adjust the position of the fixed working platform 2 according to the pipeline construction position, and then carry out grouting work on the pipeline joints. At the same time, a foldable working platform 3 is hinged on one side of the fixed working platform 2. The foldable working platform 3 can be flexibly retracted and deployed according to construction requirements, which has solved the problem of limited working space on the top of large-diameter PCCP pipelines.

[0032] It should be noted that by providing the guardrail 7 on the fixed working platform 2 , the safety of the construction workers can be effectively guaranteed. Meanwhile, the safety belt can be hung on the guardrail 7 during the construction work.

[0033] In specific implementation, by arranging a plurality of rollers 6 on the concave arc side of the arc-shaped support frame 5, the working platform can be moved to a desired position along the pipeline 1 as a whole, thereby preventing the working platform from directly contacting the pipeline and scratching the pipeline.

[0034] It should be noted that by hingedly connecting a telescopic ladder 8 to the lower part of both sides of the arc-shaped support frame 5, it is convenient for workers to go up and down. During construction, the telescopic length of the telescopic ladder 8 can be adjusted so that the bottom of the telescopic ladder 8 is in contact with the concrete base to increase the stability of the platform. When the working platform needs to be moved, the telescopic ladder 8 can be folded and fixed in a position above the tube, so as to facilitate crossing higher obstacles when moving the working platform.

[0035] During specific implementation, the arc-shaped support frame 5 is located directly above the pipeline 1 , and the two telescopic ladders 8 are symmetrically arranged on both sides of the pipeline 1 .

[0036] During specific implementation, the arc-shaped support frame 5, the guardrail 7, the fixed working platform 2, the foldable working platform 3 and the telescopic ladder 8 are all made of galvanized square tubes.

[0037] During specific implementation, the fixed working platform 2 and the foldable working platform 3 have the same structure and size. Both the fixed working platform 2 and the foldable working platform 3 are composed of a rectangular frame and a plurality of longitudinal supports arranged in the rectangular frame. When not in use, the foldable working platform 3 can be folded and hung on one side of the guardrail 7. If it is necessary to perform coordinated operations on both sides of the pipeline joint, the foldable working platform 3 can be put down.

[0038] like Figure 1 and Figure 4 As shown, in this embodiment, the arc-shaped support frame 5 includes two arc-shaped supports 5 - 1 arranged in sequence along the longitudinal direction of the pipeline 1 , and a plurality of longitudinal connecting rods 5 - 2 are connected between the two arc-shaped supports 5 - 1 .

[0039] In actual use, the arc support 5-1 is a semicircle welded with a galvanized square tube with a cross section of 40mm×40mm, and the overall width of the arc support frame 5 is 1000mm. The longitudinal connecting rod 5-2 is a galvanized square tube with a cross section of 40mm×40mm. Since the galvanized square tube can be elastically deformed within a certain range, it can be applied to working conditions with different pipe wall thicknesses when the inner diameter of the pipe is determined.

[0040] During specific implementation, the arc-shaped bracket 5-1 is welded to the longitudinal connecting rod 5-2.

[0041] In this embodiment, the arc-shaped support frame 5 and the pipeline 1 are coaxially arranged.

[0042] like Figure 1 and Figure 3 As shown, in this embodiment, the fixed working platform 2 is welded to the top of the arc-shaped support frame 5 , and the four telescopic legs 4 at the bottom of the fixed working platform 2 pass through the arc-shaped support frame 5 and are supported on the pipeline 1 .

[0043] In actual use, the bottom of the telescopic leg 4 is arc-shaped to avoid scratching the pipeline 1.

[0044] In this embodiment, the roller 6 is a rubber wheel.

[0045] like Figure 1 and Figure 3As shown, in this embodiment, the telescopic ladder 8 includes an upper ladder and a lower ladder arranged at the lower part of one side of the upper ladder, the upper ladder includes two upper side railings 8-1-1 and a plurality of upper cross bars 8-1-2 connected between the two upper side railings 8-1-1, the lower ladder includes two lower side railings 8-2-1 and a plurality of lower cross bars 8-2-2 connected between the two lower side railings 8-2-1, and the upper ends of the two lower side railings 8-2-1 are respectively arranged close to the lower ends of one side of the two upper side railings 8-1-1.

[0046] In actual use, the width of the upper ladder is smaller than the width of the arc-shaped support frame 5, and the upper outer side of the upper ladder is hingedly connected to the bottom outer side of the arc-shaped support frame 5 through a hinge.

[0047] like Figure 2 As shown, in this embodiment, the upper side rail 8-1-1 and the lower side rail 8-2-1 connected thereto are fixedly connected by bolts 8-3, a plurality of bolt through holes 8-4 are provided on the upper side rail 8-1-1, and a bolt through hole is provided on the lower side rail 8-2-1.

[0048] In actual use, the working length of the telescopic ladder 8 is adjusted and locked by adjusting the installation position of the bolt 8-3 on the upper side rail 8-1-1.

[0049] like Figure 3 As shown, in this embodiment, a fastener is provided between the lower part of the arc-shaped support frame 5 and the upper part of the telescopic ladder 8, and the fastener includes a first sleeve 9 fixed to the bottom of the concave arc side of the arc-shaped support frame 5, a second sleeve 10 fixed to the upper inner part of the telescopic ladder 8, and a positioning pin 11 connecting the first sleeve 9 and the second sleeve 10 together.

[0050] In actual use, the setting of the fasteners can effectively ensure the safe use of the telescopic ladder 8. When the telescopic ladder 8 is lowered, the first sleeve 9 and the second sleeve 10 are coaxially arranged, so that the lower end of the positioning pin 11 passes through the first sleeve 9 and the second sleeve 10 from top to bottom in sequence, so that the telescopic ladder 8 will not be folded upward during use. When the telescopic ladder 8 needs to be folded, the positioning pin 11 is removed to fold the telescopic ladder 8 upward.

[0051] In this embodiment, the telescopic leg 4 is a screw rod, and the fixed working platform 2 and the folding working platform 3 are both provided with internal threaded holes for installing the telescopic leg 4. By screwing the telescopic leg 4, the effective length of the telescopic leg 4 located at the lower part of the fixed working platform 2 or the folding working platform 3 can be adjusted.

[0052] When the utility model is actually used, firstly, the effective length of the telescopic legs 4 is adjusted so that the rollers 6 on the arc-shaped support frame 5 are in contact with the pipe 1, and the bottom of the telescopic legs 4 is suspended in the air. Then, the entire working platform is pushed to move it to a specified position along the longitudinal direction of the pipe 1. Then, the effective length of the telescopic legs 4 is adjusted so that the rollers 6 on the arc-shaped support frame 5 are suspended in the air. The telescopic legs 4 are forced to support the entire working platform. Then, the two telescopic ladders 8 are lowered, and the length of the telescopic ladders 8 is adjusted so that the bottom of the telescopic ladders 8 is in contact with the concrete base. According to construction needs, the foldable working platform 3 can be flexibly retracted and released.

[0053] The above is only a preferred embodiment of the present invention and does not constitute any limitation to the present invention. Any simple modification, change and equivalent structural change made to the above embodiments according to the technical essence of the present invention shall still fall within the protection scope of the technical solution of the present invention.

Claims

1. A mobile PCCP pipeline installation joint grouting work platform, characterized by: The invention comprises a movable frame which is arranged on the upper part of a pipeline (1) and can move in the longitudinal direction of the pipeline (1), a fixed working platform (2) is arranged on the top of the movable frame, a guardrail (7) is arranged on the fixed working platform (2), a foldable working platform (3) which can be folded upwards is hinged on one side of the fixed working platform (2), and a telescopic ladder (8) which can be folded upwards is hinged on the lower part of both sides of the movable frame, the movable frame comprises an arc-shaped support frame (5) and a plurality of rollers (6) arranged on the concave arc side of the arc-shaped support frame (5), and four telescopic legs (4) are respectively arranged on the bottom of the fixed working platform (2) and the bottom of the foldable working platform (3).

2. A mobile PCCP pipeline installation joint grouting work platform according to claim 1, characterized in that: The arc-shaped support frame (5) comprises two arc-shaped supports (5-1) arranged in sequence along the longitudinal direction of the pipeline (1), and a plurality of longitudinal connecting rods (5-2) are connected between the two arc-shaped supports (5-1).

3. A mobile PCCP pipeline installation joint grouting work platform according to claim 1, characterized in that: The arc-shaped support frame (5) and the pipeline (1) are arranged coaxially.

4. A mobile PCCP pipeline installation joint grouting work platform according to claim 1, characterized in that: The fixed working platform (2) is welded to the top of the arc-shaped support frame (5), and the four telescopic legs (4) at the bottom of the fixed working platform (2) pass through the arc-shaped support frame (5) and are supported on the pipeline (1).

5. A mobile PCCP pipeline installation joint grouting work platform according to claim 1, characterized in that: The roller (6) is a rubber wheel.

6. A mobile PCCP pipeline installation joint grouting work platform according to claim 1, characterized in that: The telescopic ladder (8) comprises an upper ladder and a lower ladder arranged at the lower part of one side of the upper ladder, the upper ladder comprises two upper side railings (8-1-1) and a plurality of upper crosspieces (8-1-2) connected between the two upper side railings (8-1-1), the lower ladder comprises two lower side railings (8-2-1) and a plurality of lower crosspieces (8-2-2) connected between the two lower side railings (8-2-1), and the upper ends of the two lower side railings (8-2-1) are respectively arranged in close contact with the lower ends of one side of the two upper side railings (8-1-1).

7. A mobile PCCP pipeline installation joint grouting work platform according to claim 6, characterized in that: The upper side rail (8-1-1) and the lower side rail (8-2-1) connected thereto are fixedly connected via bolts (8-3); a plurality of bolt through holes (8-4) are provided on the upper side rail (8-1-1), and a bolt through hole is provided on the lower side rail (8-2-1).

8. A mobile PCCP pipeline installation joint grouting work platform according to claim 1, characterized in that: A fastener is provided between the lower part of the arc-shaped support frame (5) and the upper part of the telescopic ladder (8), and the fastener comprises a first sleeve (9) fixed to the bottom of the concave arc side of the arc-shaped support frame (5), a second sleeve (10) fixed to the upper inner part of the telescopic ladder (8), and a positioning pin (11) connecting the first sleeve (9) and the second sleeve (10) together.