Concrete pouring and vibrating integrated equipment

By designing integrated equipment for concrete pouring and vibration, using installation sleeves and reinforcement components to achieve simultaneous pouring and vibration, we solve the problems of low efficiency and high cost caused by the existing equipment design, and provide a solution that facilitates integrated operation. .

CN221878868UActive Publication Date: 2024-10-22QINGDAO DESHENG ENGINEERING TECHNOLOGY CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420439742.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-07
Publication Date
2024-10-22
Estimated Expiration
2034-03-07

AI Technical Summary

Technical Problem

Existing concrete pouring and vibrating equipment are usually not designed in an integrated manner, resulting in users having to vibrate separately after completing concrete pouring, which reduces work efficiency, and some integrated equipment is costly and inconvenient to use.

Method used

An integrated equipment for concrete pouring and vibration is designed, including a vibrator rod and a pouring hose. By setting up the installation sleeve, reinforcement component and limiting component, pouring and vibration can be performed simultaneously, and the equipment can be operated separately.

Benefits of technology

It realizes the synchronous operation of pouring and vibrating, improves work efficiency, solves the problems of high equipment cost and inconvenient use, and provides the convenience of easy integration and separate operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221878868U_ABST
    Figure CN221878868U_ABST
Patent Text Reader

Abstract

The utility model discloses concrete pouring and vibrating integrated equipment which comprises a vibrating rod and a pouring hose, the top of the vibrating rod is sleeved with a mounting sleeve, the inner wall of the mounting sleeve is provided with a mounting mechanism, the top of the mounting sleeve is fixedly connected with a reinforcing assembly, and the two sides of the mounting sleeve are fixedly connected with connecting frames. The pouring head is arranged, the mounting sleeve is mounted at the top of the vibrating rod, and the pouring hose, the corresponding concrete pouring machine and the vibrating rod are started at the same time, so that pouring and vibrating are performed synchronously, when a user needs to use the vibrating rod independently, the mounting sleeve can be directly taken down, and the vibrating rod can be used independently; the problems that due to the fact that concrete pouring equipment and vibrating equipment are generally not integrally designed, a user can conduct vibrating after concrete pouring is completed, the working efficiency is greatly reduced, and part of concrete pouring and vibrating integrated equipment is high in manufacturing cost and inconvenient to use are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction tools, in particular to a concrete pouring and vibrating integrated device. Background Art

[0002] During concrete construction, the concrete in the beam and column parts cannot be filled densely by itself due to the excessive fine aggregate and the friction between the aggregates and the bonding force of the cement slurry. The interior of the concrete is loose, with a certain volume of voids and bubbles, and cannot reach the required density, thus affecting its strength, frost resistance, impermeability and durability. Therefore, vibration treatment is required to expel the bubbles in the concrete, make the concrete densely combined, eliminate the honeycombed surface of the concrete and other phenomena, so as to improve its strength and ensure the quality of concrete components.

[0003] For example, the application number is CN202321958562.8. The utility model discloses a vibrator for concrete pouring, including a vibrating rod, a motor, and a cable for connecting the motor and the vibrating rod. A damping button is provided on the outside of the cable. The damping button is used for the vibration timing of a single vibration position. The damping button is pressed and reset after at least 10 seconds. The utility model sets a damping button, and its pressing shell can be quickly pressed into place, and slowly reset automatically to achieve timing when the pressing shell is reset. It can remind the vibration duration and ensure that each vibration duration exceeds the minimum vibration duration of the vibration position before the transfer is performed, which can avoid the situation where the concrete is not dense due to insufficient vibration duration.

[0004] Based on the search of the above patents and in combination with the equipment in the prior art, it is found that when the above equipment is used, although it can solve the problem of the vibration time of the concrete vibrator at each vibration position being judged and controlled by manual experience, due to the uncertainty of manual experience and the inability to quantify the vibration time, the vibration effects at different vibration positions are different, and in order to avoid segregation of concrete, the previous vibration position is often left in advance, which easily leads to the problem of loose vibration of concrete. However, during use, since the concrete pouring equipment and the vibration equipment are usually not integrated in design, the user can only vibrate after the concrete pouring is completed, thereby greatly reducing the work efficiency, and some equipment that integrates concrete pouring and vibration is relatively expensive and inconvenient during use. Utility Model Content

[0005] In order to solve the problems raised in the above-mentioned background technology, the purpose of the utility model is to provide an integrated concrete pouring and vibrating equipment, which has the advantages of being easy to integrate and can be operated separately, and solves the problem that the concrete pouring equipment and the vibrating equipment are usually not designed as an integrated whole, resulting in the user being able to vibrate only after the concrete pouring is completed, thereby greatly reducing the work efficiency, and the cost of some integrated concrete pouring and vibrating equipment is high and inconvenient during use.

[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a concrete pouring and vibrating integrated equipment, comprising a vibrating rod and a pouring hose, the top of the vibrating rod is provided with a mounting sleeve, the inner wall of the mounting sleeve is provided with a mounting mechanism, the top of the mounting sleeve is fixedly connected with a reinforcement component, both sides of the mounting sleeve are fixedly connected with a connecting frame, the bottom of the connecting frame is movably connected with a screw rod through an axle pin, the surface of the screw rod is threadedly connected with a screw sleeve, a pouring head is provided on the outside of the screw sleeve, the top of the pouring head is connected to the pouring hose, and a limiting component is provided on the outside of the top of the screw sleeve.

[0007] As a preferred embodiment of the utility model, the mounting mechanism includes an anti-rotation groove, the anti-rotation groove is opened on the surface of the inner wall of the mounting sleeve, six anti-rotation grooves are opened and distributed in a ring shape with equal distances, the inside of the anti-rotation groove is slidably connected with an anti-rotation rod, and a first limiting ring is provided at the bottom of the mounting sleeve, and the first limiting ring fixing sleeve is arranged on the top of the surface of the vibrating rod.

[0008] As a preferred embodiment of the utility model, the reinforcement assembly includes a connecting plate, six of which are arranged and distributed equidistantly in a ring shape, the outer side of the bottom of the connecting plate is fixedly connected to the top of the vibrating rod, the inner side of the top of the connecting plate is threadedly connected with bolts, and the connecting plate is fixedly connected to the anti-rotation rod by the bolts.

[0009] As a preferred embodiment of the utility model, the limit assembly includes a limit groove, which is opened on the outer side of the top of the screw sleeve, and the outer side of the bottom of the connecting frame is fixedly connected to a limit rod, and the surface of the limit rod is slidably connected to the inner wall of the limit groove.

[0010] As a preferred embodiment of the present invention, a knob is fixedly connected to the bottom of the screw rod, and the knob is arranged in a cross shape.

[0011] As a preferred embodiment of the utility model, an elastic clamp ring is fixedly connected to the outer side of the screw sleeve, and the elastic clamp ring is sleeved on the surface of the casting head.

[0012] As a preferred embodiment of the utility model, the top of the casting head is fixedly connected to a limiting plate, and the surface fixing sleeve of the casting head is provided with a second limiting ring.

[0013] Compared with the prior art, the beneficial effects of the utility model are as follows:

[0014] 1. The utility model provides a pouring head, installs the installation sleeve on the top of the vibrating rod and opens the pouring hose and the corresponding concrete pouring machine and vibrating rod at the same time, so that pouring and vibrating are carried out simultaneously. When the user needs to use the vibrating rod separately, the installation sleeve can be directly removed to use the vibrating rod separately. The problem that the concrete pouring equipment and the vibrating equipment are usually not integrated in design, resulting in the user being able to vibrate only after the concrete pouring is completed, thereby greatly reducing the work efficiency, and the problem that some equipment integrating concrete pouring and vibration is relatively expensive and inconvenient in use, is achieved. The effect of being easy to integrate and can be operated separately is achieved.

[0015] 2. The utility model provides an installation mechanism, which makes it easy for the user to place the installation sleeve on the top of the vibrating rod, so that the anti-rotation rod on the vibrating rod is inserted into the anti-rotation groove in the installation sleeve, thereby limiting the rotation of the installation sleeve, and then using the first limiting ring to limit the installation sleeve downward, so as to quickly connect the connecting frame and the vibrating rod.

[0016] 3. The utility model provides a reinforcement component, so that after the user inserts the anti-rotation rod into the anti-rotation groove, the connecting plate on the mounting sleeve contacts the corresponding anti-rotation rod, and then the user can use bolts to thread the connecting plate and the corresponding anti-rotation rod, thereby reinforcing the installation of the mounting sleeve. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the three-dimensional structure of the utility model;

[0018] Figure 2 For this utility model Figure 1 The enlarged structural diagram at A in the middle;

[0019] Figure 3 For this utility model Figure 2 Enlarged structural diagram at B in the middle.

[0020] In the figure: 1. vibrating rod; 2. pouring hose; 3. mounting sleeve; 4. mounting mechanism; 41. anti-rotation groove; 42. anti-rotation rod; 43. first limiting ring; 5. reinforcement assembly; 51. connecting plate; 52. bolt; 6. connecting frame; 7. screw rod; 8. screw sleeve; 9. pouring head; 10. limiting assembly; 101. limiting groove; 102. limiting rod; 11. knob; 12. elastic clamp ring; 13. limiting disk; 14. second limiting ring. DETAILED DESCRIPTION

[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0022] like Figures 1 to 3 As shown, the utility model provides an integrated concrete pouring and vibrating device, including a vibrating rod 1 and a pouring hose 2, the top of the vibrating rod 1 is sleeved with a mounting sleeve 3, the inner wall of the mounting sleeve 3 is provided with a mounting mechanism 4, the top of the mounting sleeve 3 is fixedly connected with a reinforcement component 5, both sides of the mounting sleeve 3 are fixedly connected with a connecting frame 6, the bottom of the connecting frame 6 is movably connected with a screw rod 7 through an axle pin, the surface of the screw rod 7 is threadedly connected with a screw sleeve 8, a pouring head 9 is arranged on the outside of the screw sleeve 8, the top of the pouring head 9 is connected to the pouring hose 2, and a limiting component 10 is provided on the outside of the top of the screw sleeve 8.

[0023] refer to Figure 1 and Figure 2 The mounting mechanism 4 includes an anti-rotation groove 41, which is opened on the surface of the inner wall of the mounting sleeve 3. There are six anti-rotation grooves 41 and they are distributed in a ring shape with equal distances. An anti-rotation rod 42 is slidably connected inside the anti-rotation groove 41. A first limiting ring 43 is provided at the bottom of the mounting sleeve 3. The first limiting ring 43 is fixedly sleeved on the top of the surface of the vibrating rod 1.

[0024] As a technical optimization solution of the utility model, the user is provided with the convenience of mounting the mounting sleeve 3 on the top of the vibrating rod 1, so that the anti-rotation rod 42 on the vibrating rod 1 is inserted into the anti-rotation groove 41 in the mounting sleeve 3, thereby enabling the mounting sleeve 3 to be rotationally limited, and then the first limiting ring 43 is used to limit the mounting sleeve 3 downward, thereby quickly connecting the connecting frame 6 to the vibrating rod 1.

[0025] refer to Figure 2 The reinforcement component 5 includes a connecting plate 51, six connecting plates 51 are arranged and distributed in a circular shape with equal distances, the outer side of the bottom of the connecting plate 51 is fixedly connected to the top of the vibrating rod 1, the inner side of the top of the connecting plate 51 is threadedly connected with a bolt 52, and the connecting plate 51 is fixedly connected to the anti-rotation rod 42 through the bolt 52.

[0026] As a technical optimization scheme of the utility model, by setting a reinforcement component 5, the user can insert the anti-rotation rod 42 into the anti-rotation groove 41, and then the connecting plate 51 on the mounting sleeve 3 will contact the corresponding anti-rotation rod 42. Then the user can use the bolt 52 to threadably connect the connecting plate 51 with the corresponding anti-rotation rod 42, thereby reinforcing the installation of the mounting sleeve 3.

[0027] refer to Figure 3 The limiting assembly 10 includes a limiting groove 101, which is opened on the outer side of the top of the screw sleeve 8, and a limiting rod 102 is fixedly connected to the outer side of the bottom of the connecting frame 6, and the surface of the limiting rod 102 is slidably connected to the inner wall of the limiting groove 101.

[0028] As a technical optimization scheme of the utility model, by setting a limit assembly 10, during the rotation of the screw rod 7, the sliding connection between the limit rod 102 and the limit groove 101 is utilized to limit the rotation of the screw sleeve 8, thereby preventing the screw rod 7 from directly driving the screw sleeve 8 to rotate during the rotation, resulting in the screw sleeve 8 being unable to be adjusted up and down.

[0029] refer to Figure 1 The bottom of the screw rod 7 is fixedly connected with a knob 11, which is arranged in a cross shape.

[0030] As a technical optimization solution of the utility model, by setting the knob 11, when the user needs to rotate the screw 7, the user can drive the screw 7 to rotate by rotating the knob 11, thereby providing the user with a fulcrum for applying force to the screw 7. The knob 11 is then arranged in a cross shape, so that the user can hold the knob 11 with his hand to apply force and avoid slipping.

[0031] refer to Figure 3 The outer side of the screw sleeve 8 is fixedly connected with an elastic clamp ring 12 , and the elastic clamp ring 12 is sleeved on the surface of the pouring head 9 .

[0032] As a technical optimization solution of the utility model, by providing an elastic clamp ring 12, when the user needs to use the pouring head 9, the user can directly insert the pouring head 9 horizontally into the interior of the elastic clamp ring 12, and then use the resilience of the elastic clamp ring 12 to tighten and fix the pouring head 9, while making it convenient for the user to take out the pouring head 9 for other uses.

[0033] refer to Figure 3 The top of the pouring head 9 is fixedly connected with a limiting plate 13, and the surface of the pouring head 9 is fixedly sleeved with a second limiting ring 14.

[0034] As a technical optimization scheme of the utility model, by setting a limit plate 13, when the pouring head 9 is clamped by the elastic clamp ring 12, the limit plate 13 can be used to limit the pouring head 9 downward, and then by setting a second limit ring 14, the pouring head 9 can be limited upward, thereby preventing the pouring head 9 from sliding up and down unsteadily during use.

[0035] The working principle and use process of the utility model are as follows: when the user needs to cast and vibrate, the user first sets the installation sleeve 3 on the top of the vibrating rod 1, so that the anti-rotation rod 42 on the vibrating rod 1 is inserted into the anti-rotation groove 41 in the installation sleeve 3, so that the installation sleeve 3 can be rotationally limited, and then the first limiting ring 43 can be used to limit the installation sleeve 3 downward, so as to quickly connect the connecting frame 6 with the vibrating rod 1. After the anti-rotation rod 42 is inserted into the anti-rotation groove 41, the connecting plate 51 on the installation sleeve 3 contacts the corresponding anti-rotation rod 42, and then the user can use the bolt 52 to thread the connecting plate 51 with the corresponding anti-rotation rod 42, so as to reinforce the installation of the installation sleeve 3, and then connect the pouring hose 2 on the pouring head 9 with the corresponding concrete pouring machine, and then The concrete pouring machine in which the vibrating rod 1 is connected to the pouring hose 2 is started synchronously, so that the concrete pouring and vibration are carried out synchronously, which improves the work efficiency. At the same time, when the user needs to use the vibrating rod 1 separately, the mounting sleeve 3 can be directly removed to use the vibrating rod 1 separately. When the height needs to be adjusted during the use of the pouring head 9, the user can directly drive the screw sleeve 8 to adjust up and down by rotating the screw rod 7, and then the screw sleeve 8 will drive the pouring head 9 to adjust up and down. In the process of rotation of the screw rod 7, the sliding connection between the limit rod 102 and the limit groove 101 is utilized to limit the rotation of the screw sleeve 8, so as to prevent the screw rod 7 from directly driving the screw sleeve 8 to rotate during the rotation, resulting in the screw sleeve 8 being unable to be adjusted up and down. The screw sleeve 8 has the ability to be easy to integrate and can be operated separately.

[0036] To sum up: the integrated concrete pouring and vibrating equipment, by setting a pouring head 9, installs the mounting sleeve 3 on the top of the vibrating rod 1 and simultaneously opens the pouring hose 2 and the corresponding concrete pouring machine and vibrating rod 1, so that pouring and vibrating are carried out simultaneously. When the user needs to use the vibrating rod 1 separately, the mounting sleeve 3 can be directly removed and the vibrating rod 1 can be used separately. This solves the problem that the concrete pouring equipment and the vibrating equipment are usually not integrated in design, resulting in the user having to vibrate after the concrete pouring is completed, thereby greatly reducing the work efficiency. The cost of some integrated concrete pouring and vibrating equipment is high and it is inconvenient to use.

[0037] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0038] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A concrete pouring and vibrating integrated device, comprising a vibrating rod (1) and a pouring hose (2), characterized in that: The top of the vibrating rod (1) is provided with a mounting sleeve (3), the inner wall of the mounting sleeve (3) is provided with a mounting mechanism (4), the top of the mounting sleeve (3) is fixedly connected with a reinforcement component (5), both sides of the mounting sleeve (3) are fixedly connected with a connecting frame (6), the bottom of the connecting frame (6) is movably connected with a screw rod (7) through an axle pin, the surface of the screw rod (7) is threadedly connected with a screw sleeve (8), a pouring head (9) is provided on the outside of the screw sleeve (8), the top of the pouring head (9) is connected with a pouring hose (2), and a limit position component (10) is provided on the outside of the top of the screw sleeve (8).

2. The integrated concrete pouring and vibrating equipment according to claim 1, characterized in that: The mounting mechanism (4) comprises an anti-rotation groove (41), wherein the anti-rotation groove (41) is formed on the surface of the inner wall of the mounting sleeve (3), six anti-rotation grooves (41) are formed and are distributed in a circular shape with equal distances, an anti-rotation rod (42) is slidably connected inside the anti-rotation groove (41), and a first limiting ring (43) is provided at the bottom of the mounting sleeve (3), and the first limiting ring (43) is fixedly sleeved on the top of the surface of the vibrating rod (1).

3. The integrated concrete pouring and vibrating equipment according to claim 2, characterized in that: The reinforcement assembly (5) comprises a connecting plate (51), six connecting plates (51) are provided and are distributed in a circular shape at equal distances, the outer side of the bottom of the connecting plate (51) is fixedly connected to the top of the vibrating rod (1), the inner side of the top of the connecting plate (51) is threadedly connected with a bolt (52), and the connecting plate (51) is fixedly connected to the anti-rotation rod (42) via the bolt (52).

4. The integrated concrete pouring and vibrating equipment according to claim 1, characterized in that: The limiting assembly (10) comprises a limiting groove (101), wherein the limiting groove (101) is arranged on the outer side of the top of the screw sleeve (8), and a limiting rod (102) is fixedly connected to the outer side of the bottom of the connecting frame (6), and the surface of the limiting rod (102) is slidably connected to the inner wall of the limiting groove (101).

5. The integrated concrete pouring and vibrating equipment according to claim 1, characterized in that: A knob (11) is fixedly connected to the bottom of the screw rod (7), and the knob (11) is arranged in a cross shape.

6. The integrated concrete pouring and vibrating equipment according to claim 1, characterized in that: An elastic clamp ring (12) is fixedly connected to the outer side of the screw sleeve (8), and the elastic clamp ring (12) is sleeved on the surface of the pouring head (9).

7. The integrated concrete pouring and vibrating equipment according to claim 1, characterized in that: The top of the pouring head (9) is fixedly connected to a limiting plate (13), and the surface of the pouring head (9) is fixedly sleeved with a second limiting ring (14).

Citation Information

Cited By

  • Mass concrete pouring equipment

    CN119737054A