Matched construction joint of underground excavated vertical shaft and retaining pile
By cooperating with the construction nodes of underground shafts and retaining piles, and using tunnel transportation and electric hoist lifting technology, the impact of shaft construction on traffic and cost issues were solved, and an efficient and safe construction process was achieved.
Patent Information
- Application Number
- CN202420607069.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-27
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-03-27
AI Technical Summary
During the construction process of shafts on urban main lines, existing technology has caused the construction to have a great impact on ground traffic, increased construction costs and construction time, and has safety hazards. It cannot meet the land requirements for mechanical equipment, seriously affecting traffic and disturbing residents.
Use underground excavation shafts and wall protection piles to coordinate construction nodes. By setting up the first and second shafts, transportation channels, gantry frames, concrete foundations, main beams, steel bridge decks and wall protection piles, tunnels are used to transport earthwork and equipment pipelines, and electric hoists. Lift equipment to reduce impact on roads.
It effectively reduces the impact of construction on traffic, reduces construction costs and time, improves construction efficiency, reduces road occupation, and ensures construction safety and efficiency.
Smart Images

Figure CN221879387U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of shaft construction, in particular to a construction node for matching a dark-dug shaft with a retaining wall pile. Background Art
[0002] At present, in the process of shaft construction of urban main roads, in order to ensure construction safety and civilized construction requirements, construction progress and respond to various construction node requirements, the construction needs to consider the impact of surrounding buildings and structures and traffic guidance, disturbance to the public, the site is limited, the construction process is cumbersome, and the land occupation requirements of the construction shaft and mechanical equipment cannot be met. The construction time is limited. Generally, during the construction of the road shaft, the road will be fenced and then excavated. This construction method seriously affects traffic and poses a safety hazard. Vehicles need to pass in the one-way lane on one side of the construction site, which increases the risk factor. Therefore, the utility model is born to effectively reduce construction costs (labor, machinery, equipment) and construction progress, and avoid the above-mentioned fundamental problems of construction traffic guidance, disturbance to the public, site restrictions, and construction procedures. Utility Model Content
[0003] The present application provides a construction node that cooperates with a concealed shaft and retaining wall piles to solve the impact of the existing road shaft construction structure on ground traffic, construction costs (labor, machinery, equipment), and construction progress, and avoid the above-mentioned fundamental problems of construction traffic guidance, disturbance to residents, site restrictions, and construction procedures.
[0004] In order to solve the above technical problems, the present application provides a construction node of a concealed vertical shaft and a retaining wall pile, comprising: a first vertical shaft, a second vertical shaft arranged on one side of the first vertical shaft, and a locking ring beam arranged at the top of the first vertical shaft and the second vertical shaft; a transportation channel is arranged between the bottoms of the first vertical shaft and the second vertical shaft, a gantry is arranged at the top of the first vertical shaft, a concrete foundation is arranged on the outer side of the locking ring beam at the top of the second vertical shaft, a main beam is arranged on the top of the concrete foundation, a steel temporary bridge panel is arranged on the top surface of the main beam, and retaining wall piles are opened inside the second vertical shaft, the retaining wall piles extend to the bottom of the second vertical shaft, and the retaining wall piles are connected to the transportation channel.
[0005] The earthwork of the second shaft is transported to the first shaft through the tunnel, and is supplied to the second shaft through the equipment pipeline of the first shaft through the tunnel.
[0006] In some embodiments of the present application, the gantry includes a plurality of beams overlapped at the mouth of the first vertical shaft, columns arranged on the top of the plurality of beams, connecting beams arranged on the top of the columns, and running beams arranged on the top of the connecting beams, a first angle brace is arranged between the columns and the connecting beams, an electric hoist is arranged on the running beam, the electric hoist is slidably connected to the running beam, and an X-shaped support is arranged between adjacent columns.
[0007] In some embodiments of the present application, the diameter of the wall retaining pile is 1000 mm.
[0008] In some embodiments of the present application, the spacing between adjacent columns is 8000 mm, and the length of the columns is 7000 mm.
[0009] In some embodiments of the present application, a second angle brace is provided between the shoulder beam and the inner side wall of the first vertical shaft, and the distance between the top of the second angle brace and the edge of the first vertical shaft is 2000 mm.
[0010] In some embodiments of the present application, the height of the locking ring beam is 1200 mm.
[0011] In some embodiments of the present application, the shoulder beam is formed by two I-beams connected by welding.
[0012] Compared with the prior art, the utility model has the following characteristics and beneficial effects:
[0013] The utility model is arranged on a driving road, and the first vertical shaft and the second vertical shaft are arranged at adjacent positions on the inner side of the driving road respectively. During the construction process, the outer lane of the driving road can be passed, and the impact on the road traffic is reduced while separating the oncoming vehicles, so that the oncoming vehicles do not interfere with each other. The first vertical shaft and the second vertical shaft are connected by setting a transportation channel, and the earthwork of the second vertical shaft is transported to the first vertical shaft through a tunnel, and the earthwork of the first vertical shaft is transported to the first vertical shaft through the equipment pipeline of the first vertical shaft through the tunnel for use by the second vertical shaft. Some small construction materials that can be carried by hand are transported to the first vertical shaft through the second vertical shaft, and some large construction equipment are hoisted by an electric hoist. During the construction period, the main beam and the steel temporary bridge panel are hoisted by the electric hoist, which is equivalent to opening the top surface of the second vertical shaft. During the non-construction period, the main beam and the steel temporary bridge panel are put back to expand the traffic area. This construction node saves road construction space, reduces construction costs, and speeds up construction progress. Popularization and use can produce better results. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This is a schematic diagram of the second vertical shaft structure of the utility model embodiment;
[0015] Figure 2 This is a schematic diagram of the main view of the transport channel of the embodiment of the utility model;
[0016] Figure 3 It is a schematic top view of the second vertical shaft of the embodiment of the utility model;
[0017] Figure 4 It is a side view schematic diagram of the first vertical shaft of the embodiment of the utility model;
[0018] Figure 5 It is a schematic front view of the gantry frame of the utility model embodiment.
[0019] In the figure, 100, the first vertical shaft; 110, the second angle brace; 200, the second vertical shaft; 210, the concrete foundation; 220, the main beam; 230, the steel temporary bridge panel; 240, the retaining wall piles; 300, the locking ring beam; 400, the transport channel; 500, the gantry; 510, the carrying beam; 520, the column; 530, the connecting beam; 540, the running beam; 550, the first angle brace; 560, the electric hoist; 570, the X-shaped support. DETAILED DESCRIPTION
[0020] The following is a further detailed description of the specific implementation of the present invention in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0021] In the description of the present application, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0022] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.
[0023] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0024] like Figure 1-5As shown, according to some embodiments of the present application, a construction node of a dark-excavated vertical shaft and a retaining wall pile includes: a first vertical shaft 100, a second vertical shaft 200 arranged on one side of the first vertical shaft 100, and a locking ring beam 300 arranged at the top of the first vertical shaft 100 and the second vertical shaft 200; the first vertical shaft 100 and the second vertical shaft 200 are located on both sides of a road, close to the center line of the road, a transportation channel 400 is arranged between the bottoms of the first vertical shaft 100 and the second vertical shaft 200, a gantry 500 is arranged at the top of the first vertical shaft 100, and a locking ring beam 300 is arranged at the top of the second vertical shaft 200. A concrete foundation 210 is arranged on the outer side of the ring beam 300, a main beam 220 is arranged on the top of the concrete foundation 210, a steel temporary bridge panel 230 is arranged on the top surface of the main beam 220, and a retaining wall pile 240 is opened inside the second vertical shaft 200. The retaining wall pile 240 is an artificial retaining wall pile 240 with a diameter of 1 meter. Except for the steel grille and large materials at the top of the vertical shaft, all others can be sent to the first vertical shaft 100 through the retaining wall pile 240 and the transportation channel 400. The retaining wall pile 240 extends to the bottom of the second vertical shaft 200, and the retaining wall pile 240 is connected to the transportation channel 400.
[0025] It should be noted here that both the first vertical shaft 100 and the second vertical shaft 200 can be used as channels for transporting construction materials. Equipment pipelines can be transported to the second vertical shaft 200 through the first vertical shaft 100 for use in the second vertical shaft 200, and earthwork can be transported to the first vertical shaft 100 through the second vertical shaft 200, so that the two processes do not affect each other. Compared with construction in a single vertical shaft, the construction efficiency is high, less manpower is used, the machinery cost is low, and the impact on traffic is small.
[0026] According to some embodiments of the present application, the gantry 500 includes a plurality of beams 510 overlapped at the wellhead of the first vertical shaft 100, columns 520 arranged on the top of the plurality of beams 510, connecting beams 530 arranged on the top of the columns 520, and running beams 540 arranged on the top of the connecting beams 530. The plurality of beams 510 are fixed to the top of the locking ring beam 300, the bottom of the column 520 is fixedly connected to the beams 510, a first angle brace 550 is arranged between the column 520 and the connecting beam 530, an electric hoist 560 is arranged on the running beam 540, the electric hoist 560 is slidably connected to the running beam 540, and an X-shaped support 570 is arranged between adjacent columns 520.
[0027] It should be noted that a portion of the gantry 500 is disposed on the road surface between the first vertical shaft 100 and the second vertical shaft 200 , leaving a construction space for the top surface of the first vertical shaft 100 .
[0028] According to some embodiments of the present application, the diameter of the wall retaining pile 240 is 1000 mm.
[0029] According to some embodiments of the present application, the distance between adjacent columns 520 is 8000 mm, and the length of the column 520 is 7000 mm.
[0030] According to some embodiments of the present application, a second angle brace 110 is provided between the shoulder beam 510 and the inner side wall of the first vertical shaft 100 , and the distance between the top of the second angle brace 110 and the edge of the first vertical shaft 100 is 2000 mm.
[0031] According to some embodiments of the present application, the height of the locking ring beam 300 is 1200 mm.
[0032] According to some embodiments of the present application, the shoulder beam 510 is formed by two I-beams connected by welding.
[0033] In summary, the utility model relates to the technical field of shaft construction, and discloses a construction node of a concealed shaft and retaining wall piles, comprising: a first shaft, a second shaft arranged on one side of the first shaft, and a locking ring beam arranged at the top of the first shaft and the second shaft; a transportation channel is arranged between the bottoms of the first shaft and the second shaft, a gantry is arranged at the top of the first shaft, a concrete foundation is arranged on the outer side of the locking ring beam at the top of the second shaft, a main beam is arranged on the top of the concrete foundation, a steel temporary bridge panel is arranged on the top surface of the main beam, retaining wall piles are opened inside the second shaft, the retaining wall piles extend to the bottom of the second shaft, and the retaining wall piles are connected to the transportation channel. This construction node takes into account both driving safety and construction efficiency, and uses the transportation channel to complete material transportation underground to ensure construction safety.
[0034] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principle of the present invention. These improvements and substitutions should also be regarded as the protection scope of the present invention.
Claims
1. A construction node for a concealed vertical shaft and a retaining wall pile, comprising: A first vertical shaft (100), a second vertical shaft (200) arranged on one side of the first vertical shaft (100), and a locking ring beam (300) arranged at the top of the first vertical shaft (100) and the second vertical shaft (200); characterized in that a transportation channel (400) is arranged between the bottoms of the first vertical shaft (100) and the second vertical shaft (200), a gantry (500) is arranged at the top of the first vertical shaft (100), a concrete foundation (210) is arranged on the outer side of the locking ring beam (300) at the top of the second vertical shaft (200), a main beam (220) is arranged at the top of the concrete foundation (210), a steel temporary bridge panel (230) is arranged on the top surface of the main beam (220), and a retaining wall pile (240) is opened inside the second vertical shaft (200), the retaining wall pile (240) extends to the bottom of the second vertical shaft (200), and the retaining wall pile (240) is connected to the transportation channel (400).
2. A construction node of a concealed vertical shaft and a retaining wall pile according to claim 1, characterized in that: The gantry (500) comprises a plurality of beams (510) overlapped at the wellhead of the first shaft (100), columns (520) arranged on the top of the plurality of beams (510), connecting beams (530) arranged on the top of the columns (520), and a traveling beam (540) arranged on the top of the connecting beam (530), a first angle brace (550) is arranged between the columns (520) and the connecting beam (530), an electric hoist (560) is arranged on the traveling beam (540), the electric hoist (560) is slidably connected to the traveling beam (540), and an X-shaped support (570) is arranged between adjacent columns (520).
3. A construction node of a concealed vertical shaft and a retaining wall pile according to claim 1, characterized in that: The diameter of the wall protection pile (240) is 1000 mm.
4. A construction node of a concealed vertical shaft and a retaining wall pile according to claim 2, characterized in that: The distance between adjacent columns (520) is 8000 mm, and the length of the column (520) is 7000 mm.
5. A construction node of a concealed vertical shaft and a retaining wall pile according to claim 2, characterized in that: A second angle brace (110) is provided between the shoulder beam (510) and the inner side wall of the first vertical shaft (100), and the distance between the top of the second angle brace (110) and the edge of the first vertical shaft (100) is 2000 mm.
6. A construction node of a concealed vertical shaft and a retaining wall pile according to claim 1, characterized in that: The height of the locking ring beam (300) is 1200 mm.
7. A construction node of a concealed vertical shaft and a retaining wall pile according to claim 2, characterized in that: The supporting beam (510) is formed by welding two I-beams.