Offshore deeply-buried steel pipe branch pile

By designing offshore deep-buried steel pipe support plate piles and using deep-buried support plates to improve the compressive bearing capacity, the problem of slow construction speed and high cost of offshore engineering has been solved, and rapid construction and low cost have been achieved.

CN221895816UActive Publication Date: 2024-10-25SHANGHAI DIGU GEOTECHNICAL ENGINEER CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202320627062.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-03-22
Publication Date
2024-10-25
Estimated Expiration
2033-03-22

Smart Images

  • Figure CN221895816U_ABST
    Figure CN221895816U_ABST
Patent Text Reader

Abstract

The utility model relates to an offshore deeply-buried steel pipe branch pile which comprises a steel pipe pile, a branch bottom plate, a stiffening plate, a foundation connector, an annular stiffening plate and a leveling filling layer, and the steel pipe pile is in a pile foundation form which is inserted into foundation soil below a seabed to provide foundation support for ocean engineering. The supporting plate bottom plate is a plate-shaped component which is connected to the outer side of the steel pipe pile and is embedded in foundation soil below a seabed, the stiffening plate is a plate-shaped component which is connected between the supporting plate bottom plate and the steel pipe pile, and the leveling filling layer is a component which compactly fills a gap between the supporting plate bottom plate and the foundation soil and has compressive bearing capacity. The combined action of the supporting plate bottom plate and the steel pipe pile is utilized to provide pressure-resistant, anti-sliding and anti-overturning bearing capacity, the bearing capacity of a single pile is greatly improved, the length of the steel pipe pile is reduced, the construction speed is high, the cost is low, and the quality is reliable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to an offshore deep-buried steel pipe branch pile in the field of marine engineering. Background Art

[0002] Marine engineering needs to be constructed in the vast ocean, which is greatly affected by weather, tides, and waves, and has significantly different construction conditions compared to land engineering. Marine engineering construction generally requires ships as construction platforms, and the construction equipment is large and expensive. The construction cost of marine foundation engineering mainly depends on the construction speed and the cost of using the construction equipment. Marine foundation engineering construction requires the components to be inserted into the soil below the seabed. The seawater depth varies, and the geological conditions of the seabed vary. Therefore, the construction is difficult and the cost is high. At present, the main forms of marine engineering foundations include large-diameter steel pipe piles, large-diameter bored piles, floating foundations, suction tube foundations and other foundation forms. The pile foundations such as steel pipe piles and bored piles have a large diameter and a deep burial depth, generally with a diameter of 3 to 7 meters and a burial depth of 50 to 80 meters. The existing large-diameter steel pipe piles have the advantages of fast construction speed, long length, large construction equipment, high material costs and construction costs; the construction period of offshore bored piles is long, and the construction time of a single pile often takes one month or even longer, and there is also a problem of high cost. Due to the scouring effect of the seabed, the shallow foundation commonly used on land is difficult to apply. It is urgent to develop a marine engineering foundation form with fast construction speed, low construction cost, safety and reliability. Summary of the invention

[0003] The utility model aims to provide an offshore deeply buried steel pipe branch plate pile, which can greatly improve the compression, overturning and sliding resistance of the steel pipe pile by using the deeply buried branch plate, has fast construction speed and low cost.

[0004] The deep-buried offshore steel pipe branch plate piles include six parts: steel pipe piles, branch plate bottom plates, stiffening plates, foundation connections, annular stiffening plates, and leveling filling layers. The steel pipe piles are a type of pile foundation that is inserted into the foundation soil below the seabed to provide basic support for marine engineering. The branch plate bottom plates are plate-like components connected to the outside of the steel pipe piles and buried in the foundation soil below the seabed. The stiffening plates are plate-like components connected between the branch plate bottom plates and the steel pipe piles. The foundation connection is a connecting component between the steel pipe piles and the upper structure of the marine engineering. The annular stiffening plates are plate-like components connected between the branch plate bottom plates and the stiffening plates. The leveling filling layer is a component that densely fills the gap between the branch plate bottom plates and the foundation soil and has a compressive bearing function.

[0005] In the above-mentioned offshore deep-buried steel pipe branch plate pile, a reinforcing hoop can be welded on the periphery of the above-mentioned branch plate bottom plate, and the reinforcing hoop can be an annular component with the same shape as the branch plate bottom plate.

[0006] The deep-buried offshore steel pipe branch plate piles of the utility model can meet the requirements for controlling the depth of seabed scouring, can utilize the bearing capacity of deep seabed foundation soil, and combine the branch plate bottom plate with the steel pipe piles. They have high bearing capacity and fast construction speed. Compared with existing offshore steel pipe piles, they can save a large amount of steel pipe materials and have low requirements for piling equipment. Compared with other offshore foundation construction processes, they can also greatly save construction costs and save construction time. BRIEF DESCRIPTION OF THE DRAWINGS

[0007] Figure 1 A schematic cross-sectional view of a pile body structure of a deep-buried offshore steel pipe branch pile used in one embodiment of the utility model;

[0008] Figure 2 A schematic cross-sectional view of a soil pit formed after the fourth step of construction of a method for constructing deep-buried steel pipe branch piles at sea used in one embodiment of the utility model is completed;

[0009] Figure 3 A schematic diagram of the working condition after the fifth step of the construction of a method for constructing deep-buried steel pipe branch piles at sea used in one embodiment of the utility model is completed;

[0010] Figure 4 A cross-sectional schematic diagram of a deep-buried steel pipe pile branch plate formed after the seventh step of construction of a method for constructing deep-buried steel pipe pile branches and plates used in an embodiment of the utility model is completed;

[0011] Figure 5 The present invention is a schematic plan view of a bottom plate structure of a deep-buried offshore steel pipe branch pile used in one embodiment of the present invention. DETAILED DESCRIPTION

[0012] Explanation of the reference numerals: 1- steel pipe pile; 2- support plate bottom plate; 3- stiffening plate; 4- foundation connection; 5- annular stiffening plate; 6- leveling filling layer; 7- stiffening hoop; 8- sea level; 9- seabed; 10- soil pit.

[0013] As an embodiment of the present utility model, the following Figure 1 to Figure 5 The utility model introduces the structure and construction method of a deep-buried offshore steel pipe branch pile. Figure 4 and Figure 5 , introduces the structural construction of deep-buried steel pipe branch piles at sea. Figure 4 and Figure 5As shown, the offshore deeply buried steel pipe branch plate piles include six parts: steel pipe piles, branch plate bottom plate, stiffening plate, foundation connection, annular stiffening plate, and leveling filling layer. The steel pipe piles are a type of pile foundation inserted into the foundation soil below the seabed to provide basic support for marine engineering. The branch plate bottom plate is a plate-like component connected to the outside of the steel pipe piles and buried in the foundation soil below the seabed. The stiffening plate is a plate-like component connected between the branch plate bottom plate and the steel pipe piles. The foundation connection is a connecting component between the steel pipe piles and the upper structure of the marine engineering. The annular stiffening plate is a plate-like component connected between the branch plate bottom plate and the stiffening plate. The leveling filling layer is a component that densely fills the gap between the branch plate bottom plate and the foundation soil and has compressive bearing capacity. In this embodiment, a stiffening hoop can be welded on the periphery of the support plate bottom plate. The stiffening hoop can be an annular component with the same shape as the support plate bottom plate. The stiffening hoop can improve the bearing capacity of the support plate bottom plate on the one hand, and strengthen the interaction between the support plate bottom plate and the foundation soil on the other hand. The stiffening hoop can be welded to the lower edge of the support plate bottom plate. In this embodiment, the steel pipe piles, the support plate bottom plate, the stiffening plate, the foundation connection, the annular stiffening plate, and the stiffening hoop can all be steel structures, and adjacent components are connected by welding. In this embodiment, the leveling filling layer can be one or a combination of cement slurry, mortar, and concrete. The following part of this embodiment is mainly combined with Figures 1 to 4 , introduces the specific implementation steps of the offshore deep buried steel pipe branch pile construction method of the utility model. The first step, refer to Figure 1, use large diameter steel pipes to make steel pipe piles, connect the support plate bottom plate in the middle of the steel pipe piles, connect the stiffening plate between the support plate bottom plate and the steel pipe piles, complete the production of the steel pipe support plate pile body, and determine the buried depth of the support plate bottom plate. In this step, welding can be used to connect the steel pipe piles to the support plate bottom plate, stiffening plate, annular stiffening plate, and foundation connection, and meet the requirements of steel structure design and specifications. The support plate bottom plate can be set to a circular or polygonal shape as needed, and the diameter, wall thickness, pile length and position of the steel pipe pile in the steel sheet pile are designed according to the bearing capacity. In general, a certain length of steel pipe piles should be designed at the bottom of the support plate, so that the support plate bottom plate can be used as a pile cap deeply buried in the soil, and work together with the steel pipe piles to provide bearing capacity. In this embodiment, the diameter of the steel pipe pile can be designed to be 3 to 10m, the wall thickness of the steel pipe pile can be designed to be 30 to 100mm, and the length of the steel pipe pile is closely related to the geological conditions. In this embodiment, the buried depth of the support plate bottom plate can be 10 to 20 meters, which must be deeper than a certain depth below the scour line. The depth of the steel pipe pile deeper than the support plate bottom plate can be designed to be 10 to 30 meters. The size of the support plate bottom plate is mainly determined according to the foundation design compressive bearing capacity and the bending moment required for anti-overturning. The diameter of the support plate bottom plate can be designed to be 10 to 30 meters. The thickness of the steel plate of the support plate bottom plate can be selected between 30 and 100 mm. The arrangement and size of the stiffening plate and the annular stiffening plate can be determined according to the steel structure calculation and construction requirements. Complete the first step and enter the second step. According to the design drawings, determine the position of the deeply buried steel pipe support plate piles, cut the foundation soil at the pile position, and mix the foundation soil with water to form a mixture. In this step, a rotating drill bit can be used to cut the foundation soil, or high-pressure jetting piles, MJS, etc. can be used to cut the soil using high-pressure jet water. A cutter head can also be placed on a rotating device to cut the rock and soil, and enough water is added to the cut soil to form a mixture. When the amount of water is sufficient and under the condition of continuous stirring, the cut rock and soil fragments can flow under the action of hydraulic force. Complete the second step and enter the third step. In this step, the mixture formed in the second step is sucked into the conveying pipeline, and the mixture in the pipeline is pressurized by rotating blades to transport the mixture to a place outside the influence range of the pile foundation construction. In this step, a suction pump can be set near the pipeline inlet to suck the rock and soil debris generated by the second step of construction together with the mixed water into the pipeline, and then the mixture is pumped outward by pressurizing the rotating blades set in the pipeline, and the pumped mixture is kept at a sufficient flow rate to avoid the accumulation of sand and gravel during the pumping process. Complete the third step and enter the fourth step. This step is a repetitive step. Repeat the second and third steps, continuously excavate the rock and soil at the pile position and transport it to a place outside the influence range of the pile foundation construction, until a pit is formed in the seabed foundation soil, and the depth of the pit meets the burial depth requirements of the support plate bottom plate, and the shape and size of the pit meet the requirements for placing the support plate bottom plate. Complete the fourth step and enter the fifth step.In this step, the steel pipe branch plate piles manufactured in the first step are hoisted to the position of the earth pit formed in the fourth step, and the steel pipe branch plate piles are driven into a predetermined depth. In this step, a vibration hammer or a hammer method can be used for pile driving. Because the branch plate bottom plate can be used to provide a huge bearing capacity, the length of the steel pipe piles required by the design is much shorter than that of the steel pipe piles without a branch plate bottom plate. For deeply buried steel pipe branch plate piles, the branch plate bottom plate only needs to be driven to the bottom of the earth pit and does not need to be driven into the soil. The length of the deeply buried steel pipe branch plate piles is much shorter than that of the steel pipe piles with the same bearing capacity. Accordingly, the pile driving resistance will be greatly reduced, the requirements for pile driving equipment will be greatly reduced, the pile driving efficiency will be improved, and the construction cost will be greatly reduced. In this step, the support plate bottom plate cannot be driven into the soil. Considering that the flatness of the bottom of the pit formed in the fourth step is often difficult to ensure close contact with the entire area of ​​the support plate bottom plate, in this step, the problem of separation of the support plate bottom plate from the soil can be solved by one of the following two methods: the first method is that before the pile driving construction, one or more combinations of cement slurry, grouting mortar or concrete are injected into the pit formed in the fourth step to level the bottom of the pit, and the steel pipe piles are driven into the soil before these materials solidify, and the bottom of the support plate bottom plate is closely contacted with the poured materials, and a flat surface can be formed before the poured materials solidify, and the support plate bottom plate is supported after the poured materials solidify; the second method is that in this step, the deep-buried steel pipe support plate piles are driven into the soil, and after the support plate bottom plate contacts the bottom of the pit, a grouting pipe is reserved between the support plate bottom plate and the bottom of the pit, and after the pit is backfilled, grouting construction is carried out at the bottom of the support plate bottom plate to fill the gap between the foundation soil and the support plate bottom plate. Complete the fifth step and proceed to the sixth step. In this step, the foundation soil is cut at a position outside the influence range of the pile foundation, and the foundation soil is mixed with water to form a mixture. The construction process of this step is similar to that of the second step, and the difference from the second step is that the construction location is different. Complete the sixth step and proceed to the seventh step. In this step, the mixture formed in the construction of the sixth step is sucked into the conveying pipeline, and the mixture in the pipeline is pressurized by rotating blades, and the mixture is transported to the soil pit formed in the construction of the fourth step, and the soil pit is backfilled to a predetermined height. This step is similar to the construction process of the third step, and the difference is that the construction purpose is to backfill the soil pit. Thereby completing the construction of the deep-buried offshore steel pipe branch pile of the utility model.

[0014] This patent includes but is not limited to other basic forms that can be used alternatively by professionals in this field.

Claims

1. A deep-buried steel pipe branch pile at sea, characterized in that The invention comprises six parts, namely, a steel pipe pile (1), a support plate bottom plate (2), a stiffening plate (3), a foundation connection (4), an annular stiffening plate (5), and a leveling filling layer (6). The steel pipe pile (1) is a pile foundation form inserted into the foundation soil below the seabed to provide foundation support for marine engineering. The support plate bottom plate (2) is a plate-shaped component connected to the outside of the steel pipe pile (1) and buried in the foundation soil below the seabed. The stiffening plate (3) is a plate-shaped component connected between the support plate bottom plate (2) and the steel pipe pile (1). The foundation connection (4) is a connecting component between the steel pipe pile (1) and the upper structure of the marine engineering. The annular stiffening plate (5) is a plate-shaped component connected between the support plate bottom plate (2) and the stiffening plate (3). The leveling filling layer (6) is a component that densely fills the gap between the support plate bottom plate and the foundation soil and has a compressive bearing function.

2. The offshore deep buried steel pipe branch pile according to claim 1 is characterized in that A reinforcing hoop (7) is welded to the periphery of the support plate bottom plate (2), and the reinforcing hoop (7) is an annular component having the same shape as the support plate bottom plate (2).

Citation Information

Cited By

  • Construction method for offshore deeply-buried steel pipe branch pile

    CN116289924A