Building structure of arch type transfer layer of high-rise building

By using specific angle steel and arch plate components in the arch transfer layer structure of high-rise buildings, a stable support and limit structure is formed, which solves the problem of insufficient pipe support stability in the existing technology and improves the overall stability of the building structure. and ceiling security.

CN221895930UActive Publication Date: 2024-10-25ZHEJIANG XINZHONGYUAN CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420209656.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-29
Publication Date
2024-10-25
Estimated Expiration
2034-01-29

AI Technical Summary

Technical Problem

The existing arch-type transfer layer structure of high-rise buildings lacks stability when supporting and limiting pipes, which affects the stability of the overall building structure.

Method used

Angle steel three, angle steel one, angle steel two, angle steel four, arch plate, limit block and suspender are used to form a stable triangular structure through equidistant distribution and tilted installation. Combined with the force of the arch plate and angle steel, the pipeline is realized Uniform support and limitation.

Benefits of technology

It improves the installation stability of pipelines and the stability of the overall building structure, ensures the safe positioning of pipelines and ceiling installation in high-rise buildings, and prevents the ceiling from falling under the action of air pressure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221895930U_ABST
    Figure CN221895930U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of buildings, in particular to a building structure of an arch type transfer layer of a high-rise building, which comprises third angle steel, a secondary keel is arranged below the third angle steel, the third angle steel is T-shaped, a building structure top is arranged above the third angle steel, and a plurality of first angle steel and fourth angle steel which are distributed at equal intervals are connected between the building structure top and the third angle steel. A plurality of sets of second angle steel are installed between the building structure top and the third angle steel, each set of second angle steel comprises two second angle steel bodies located on the left side and the right side of the adjacent first angle steel body respectively, a pipeline is arranged between the two adjacent sets of second angle steel bodies, and the upper face of the third angle steel body is connected with an arch plate attached to the lower face of the pipeline. Limiting blocks attached to the outer wall of the pipeline are connected to the left end and the right end of the upper face of the arch plate, second hanging rods are connected between the left side and the right side of the arch plate and the adjacent second angle steel, and a plurality of bearing keels are installed above the secondary keels. According to the utility model, the pipeline is well supported and limited, and the overall stability of the building structure of the arch-type transfer floor of the high-rise building is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction and discloses a building structure of an arch-type transfer layer of a high-rise building. Background Art

[0002] High-rise buildings usually require the use of transfer layers during construction. The architectural structure of the arched transfer layer of a high-rise building is used to perform structural conversion of floors. Since high-rise buildings are mostly commercial in the lower floors and accommodation in the upper floors, the transfer layer usually needs to convert between the large commercial space in the lower floors and the small space with multiple walls and columns in the upper accommodation. The architectural structure of the arched transfer layer of a high-rise building can locate and store the pipelines at the upper end of the floor, and at the same time facilitate the installation of the suspended ceiling to prevent the suspended ceiling from falling under the action of air pressure, thereby improving the safety of the building;

[0003] The existing architectural structure of the arched transfer layer of a high-rise building usually needs to accommodate large pipelines such as air ducts. At this time, the commonly used structure is a structure of a hanger plus an arched steel frame transfer layer. Hangers connected to the top of the upper building structure are arranged on the left and right sides of the pipeline, and the lower end of the hanger located on the outside of the pipeline is connected to the arched steel frame transfer layer. The stability is limited, and it is difficult to better support and limit the pipeline, thereby affecting the overall stability of the architectural structure of the arched transfer layer of the high-rise building. Utility Model Content

[0004] The purpose of the utility model is to provide a building structure of an arched transfer layer of a high-rise building in view of the above-mentioned problems and shortcomings, so as to better support and limit the pipeline and ensure the overall stability of the building structure of the arched transfer layer of the high-rise building.

[0005] A building structure of an arched transfer layer of a high-rise building, comprising angle steel three, with a secondary keel provided below the angle steel three;

[0006] The angle steel 3 is T-shaped, a building structure top is arranged above the angle steel 3, and a plurality of angle steels 1 and 4 distributed at equal distances are connected between the building structure top and the angle steel 3;

[0007] Several groups of angle steels 2 are installed between the top of the building structure and angle steel 3, each group of angle steels 2 includes two angle steels 2 respectively located on the left and right sides of the adjacent angle steels 1, and pipes are provided between two adjacent groups of angle steels 2. An arch plate that fits with the bottom of the pipe is connected to the top of the angle steel 3, and limit blocks that fit with the outer wall of the pipe are connected to the left and right ends of the arch plate, and suspension rods 2 are connected between the left and right sides of the arch plate and the adjacent angle steels 2.

[0008] Furthermore, a plurality of load-bearing keels are installed above the secondary keel, and a suspension rod one is connected between the load-bearing keel and the angle steel three.

[0009] Furthermore, the angle steel four is inclined, the cross-section of the arch plate is arched, and the left and right sides of the pipeline are connected to the suspension rod three connected to the top of the building structure.

[0010] Beneficial effects:

[0011] When the building structure of the arched transfer layer of the high-rise building is constructed, several angle steels 3 are evenly arranged from front to back on the top of the building structure to ensure that a whole layer of structure is formed under the top of the entire building structure. The angle steel 3 is first connected to the top of the building structure through several angle steels 1 that are evenly distributed. The angle steel 4 is obliquely installed between the top of the building structure and the angle steel 3, so that the angle steel 4, the top of the building structure and the angle steel 1 are in a triangular shape, thereby ensuring the stability of the installation of the angle steel 3.

[0012] Install the arch plate on top of angle steel three, and then connect the left and right sides of the arch plate to the adjacent angle steel two through hanger rod two. At this time, place the pipe on top of the arch plate, and the arch plate can support the lower end of the pipe. Connect the left and right ends of the pipe to the top of the building structure through hanger rod three. At this time, the pipe can be better lifted, thereby further supporting the pipe. The user can weld limit blocks on the left and right sides of the pipe above the arch plate according to the diameter of the pipe. The limit blocks on the left and right sides can limit the pipe to ensure the stability of the pipe installation, and the pressure of the pipe on the arch plate can be better dispersed on angle steel three and angle steel two, so that the force on the arch plate is more uniform, and the pipe is better supported and limited to ensure the overall stability of the building structure of the arch transfer layer of the high-rise building. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic diagram of the overall main cross-sectional structure of the utility model;

[0014] Figure 2 This is a schematic diagram of the right side cross-sectional structure of the angle steel of the utility model;

[0015] Figure 3 For this utility model Figure 1 A is a schematic diagram of a local enlarged structure.

[0016] Markings in the figure: top of building structure 1, pipe 2, angle steel one 3, angle steel two 4, angle steel three 5, hanger one 6, secondary keel 7, arch plate 8, hanger two 9, angle steel four 10, limit block 11, load-bearing keel 12, hanger three 13. DETAILED DESCRIPTION

[0017] like Figures 1 to 3As shown, the present application is a building structure of an arched transfer layer of a high-rise building, including angle steel three 5, a secondary keel 7 is arranged below the angle steel three 5, the angle steel three 5 is T-shaped, a building structure top 1 is arranged above the angle steel three 5, and a plurality of equally distributed angle steels 1 3 and angle steels 4 10 are connected between the building structure top 1 and the angle steel three 5, and the angle steel four 10 is inclined;

[0018] When the building structure of the arched transfer layer of the high-rise building is constructed, a plurality of angle steels 3 5 are evenly arranged in sequence from the front to the back on the top 1 of the building structure to ensure that a whole layer of structure is formed under the top 1 of the entire building structure. The angle steel 3 5 is first connected to the top 1 of the building structure through a plurality of angle steels 1 3 that are evenly distributed, thereby determining the installation position of the angle steel 3 5. After the angle steel 1 3 is connected, a plurality of angle steels 4 10 are taken out, and the angle steel 4 10 is obliquely installed between the top 1 of the building structure and the angle steel 3 5, so that the angle steel 4 10, the top 1 of the building structure and the angle steel 1 3 are in a triangular shape, thereby ensuring the stability of the installation of the angle steel 3 5.

[0019] Several groups of angle steels 2 4 are installed between the building structure top 1 and the angle steel 3 5, each group of angle steels 2 4 includes two angle steels 2 4 respectively located on the left and right sides of the adjacent angle steels 1 3, and a pipeline 2 is arranged between two adjacent groups of angle steels 2 4, and an arch plate 8 is connected to the top of the angle steel 3 5 and fits with the bottom of the pipeline 2, and the left and right ends of the arch plate 8 are connected to limit blocks 11 that fit with the outer wall of the pipeline 2, and the left and right sides of the arch plate 8 are connected to the adjacent angle steels 2 4 with a suspension rod 2 9;

[0020] The cross section of the arch plate 8 is arched, and the left and right sides of the pipe 2 are connected to the suspension rod 3 13 connected to the top 1 of the building structure;

[0021] like Figure 1 As shown, the arrangement of several groups of angle steels 2 4 can make several triangles appear between the several groups of angle steels 2 4 and the building structure top 1, thereby further ensuring the stability of the installation of angle steels 3 5, and placing an arch plate 8 between two adjacent groups of angle steels 2 4, installing the arch plate 8 above the angle steels 3 5, and then connecting the left and right sides of the arch plate 8 to the adjacent angle steels 2 4 through the suspension rod 2 9. At this time, the pipeline 2 is placed above the arch plate 8, and the arch plate 8 can support the lower end of the pipeline 2. The left and right ends of the pipeline 2 are connected to the building structure top 1 through the suspension rod 3 13. At this time, the pipeline 2 can be better lifted, thereby further supporting the pipeline 2;

[0022] The user can weld the limit blocks 11 on the left and right sides of the pipe 2 above the arch plate 8 according to the diameter of the pipe 2. The limit blocks 11 on the left and right sides can limit the pipe 2 to ensure the stability of the installation of the pipe 2, and the pressure of the pipe 2 on the arch plate 8 can be better dispersed on the angle steel 3 5 and the angle steel 2 4, so that the force of the arch plate 8 is more uniform, the pipe 2 is better supported and limited, and the overall stability of the architectural structure of the arch transfer layer of the high-rise building is ensured;

[0023] A plurality of load-bearing keels 12 are installed above the secondary keel 7, and a suspension rod 1 6 is connected between the load-bearing keel 12 and the angle steel 3 5;

[0024] Several secondary purlins 7 and several load-bearing purlins 12 under several angle steels 3 5 form a relatively complete surface. The load-bearing purlin 12 and the angle steel 3 5 are connected by a hanger 6. After the connection is completed, a ceiling decorative panel is arranged under the load-bearing purlin 12 and the secondary purlin 7. The ceiling decorative panel can shield the architectural structure of the entire arched transition layer of the high-rise building, facilitate the installation of the ceiling, effectively shorten the length of the hanger 6, prevent the ceiling from falling under the action of air pressure, and improve the safety of the building.

Claims

1. A building structure of an arched transfer layer of a high-rise building, comprising angle steel three (5), wherein a secondary keel (7) is arranged below the angle steel three (5), characterized in that: The angle steel three (5) is T-shaped, a building structure top (1) is provided above the angle steel three (5), and a plurality of angle steels one (3) and angle steel four (10) which are evenly distributed are connected between the building structure top (1) and the angle steel three (5); A plurality of groups of angle steels 2 (4) are installed between the building structure top (1) and the angle steel 3 (5), each group of the angle steels 2 (4) comprises two angle steels 2 (4) respectively located on the left and right sides of the adjacent angle steels 1 (3), a pipe (2) is provided between two adjacent groups of the angle steels 2 (4), an arch plate (8) is connected to the top of the angle steel 3 (5) and is fitted with the bottom of the pipe (2), the left and right ends of the top of the arch plate (8) are connected to limit blocks (11) fitted with the outer wall of the pipe (2), and the left and right sides of the arch plate (8) are connected to the adjacent angle steels 2 (4) with suspension rods 2 (9).

2. The architectural structure of the arched transfer layer of a high-rise building according to claim 1, characterized in that: A plurality of load-bearing keels (12) are installed above the secondary keel (7), and a suspension rod (6) is connected between the load-bearing keel (12) and the angle steel (5).

3. The architectural structure of the arched transfer layer of a high-rise building according to claim 1, characterized in that: The angle steel four (10) is inclined, the cross section of the arch plate (8) is arched, and the left and right sides of the pipeline (2) are both connected to the suspension rod three (13) connected to the top (1) of the building structure.