Connecting structure of station facing concrete side wall and arch crown plate

By using diagonal wooden formwork and variable cross-section structures at the connection between the station's facing concrete side walls and the vault plate, the problem of insufficient strength of the connection nodes is solved, more reliable force transmission and water resistance are achieved, and the overall appearance of the subway station is improved. Safety and durability.

CN221895963UActive Publication Date: 2024-10-25SINOHYDRO BUREAU 5 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420421369.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-05
Publication Date
2024-10-25
Estimated Expiration
2034-03-05

AI Technical Summary

Technical Problem

The strength of the joints connecting the station's facing concrete side walls and the vault slab is insufficient, and the joint quality is poor, resulting in insufficient safety and impermeability durability.

Method used

The diagonal wooden formwork is used for pouring, combined with the arc arch foot transition between the side wall and the vault plate, to form a variable cross-section structure, which improves the strength of the connection nodes and optimizes the stress. The full cast-in-place mode is used to solve the problem of prefabricated complex stress-bearing curved surface vaults and The problem of unreliable side wall connection.

Benefits of technology

It effectively improves the strength of the connection nodes, ensures the reliability of force transmission and water penetration resistance, and improves the overall safety and anti-seepage durability of the subway station.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221895963U_ABST
    Figure CN221895963U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of station side wall structures, and particularly discloses a station facing concrete side wall and vault plate connecting structure which comprises a side wall and a vault plate. The two side walls are respectively arranged on the left side and the right side by adopting a straight wall structure; a pouring opening is formed in the upper portion of the side wall, and an inclined wood formwork is arranged in the pouring opening. The left end of the vault plate is connected to the left side wall, and the right end is connected to the right side wall. A full cast-in-place mode is formed through inclined wood formwork pouring, transition of the side walls and the arc arch feet of the arch crown plate is matched, the problems that connection between the prefabricated complex stress curved surface arch crown and the side walls is not reliable, and a force transmission route is complex are effectively solved, and the strength of a connecting joint is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of station side wall structures, in particular to a station facing concrete side wall and arch top plate connection structure. Background Art

[0002] The cast-in-place integral concrete structure adopts on-site support formwork, on-site pouring, and on-site maintenance. It has strong adaptability to irregular planes, changeable shapes, easy hole opening, and good overall performance and anti-seepage and waterproofing properties. It is particularly suitable for large-volume underground infrastructure with integrity requirements.

[0003] Facing concrete, also known as decoration-free concrete, is cast in one go without any external decoration. After the formwork is removed, the natural surface of the cast-in-place concrete is used directly as the facing. The facing concrete needs to use a formwork when casting. The high-performance concrete area for facing the subway station is the side wall and top plate of the station hall. For example, the arch of the underground station is generally cast in place; if the station arch also uses prefabricated parts, the strength of the connection node between it and the station side wall, the quality of the joint and the water permeability are difficult to guarantee. Node design is the difficulty and focus of the design of large and complex building structures, and it is an important factor affecting the safety of engineering building structures. As a curved station arch, the arch load is easily transmitted to the connection node where the strength of the variable section side wall structure is relatively weak. Obviously, the connection structure between the facing concrete side wall and the arch plate, especially the tight and reliable connection of the connection node, will directly affect the overall safety and water resistance and durability of the subway station.

[0004] Therefore, it is necessary to propose a connection structure between the station facing concrete side wall and the vault slab. Utility Model Content

[0005] The technical problem to be solved by the utility model is to provide a station facing concrete side wall and arch top plate connection structure to solve the problems of insufficient connection node strength and poor quality of joints leading to poor safety and impermeability durability.

[0006] In order to solve the above technical problems, the technical solution adopted by the utility model is: a station facing concrete side wall and arch plate connection structure, including a side wall and an arch plate;

[0007] There are two side walls, which are arranged on the left and right sides respectively with a straight wall structure; a pouring port is arranged at the upper part of the side wall, and an inclined wooden formwork is arranged inside the pouring port;

[0008] The left end of the vault plate is connected to the left side wall, and the right end is connected to the right side wall.

[0009] As a further technical solution of the above solution, a variable cross-section structure is adopted at the connection between the arch plate and the side wall.

[0010] As a further technical solution of the above solution, the oblique wooden formwork is placed obliquely downward at an angle of 25° to 30°.

[0011] Compared with the prior art, the utility model has the following advantages and beneficial effects: the utility model forms a fully cast-in-place mode through oblique wooden formwork casting, and cooperates with the arc arch foot transition between the side wall and the arch top plate, effectively solving the problems of unreliable connection between the prefabricated complex load-bearing curved surface arch top and the side wall, and complex force transmission route, thereby improving the strength of the connection node. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a front structural schematic diagram of the utility model.

[0013] Figure 2 Schematic diagram of the arch slab formwork.

[0014] Figure 3 Schematic diagram of the side wall casting structure.

[0015] Figure 4 This is a schematic diagram of the inclined wooden formwork at the joint of the side wall and the arch plate.

[0016] The meanings of the numbers in the figure are: side wall-1; arch plate-2; pouring port-3; inclined wooden formwork-4. DETAILED DESCRIPTION

[0017] The following will clearly and completely describe the technical solutions in the embodiments of the utility model in conjunction with the accompanying drawings in the embodiments of the utility model, so as to have a further understanding of the concept of the utility model, the technical problems solved, the technical features constituting the technical solutions and the technical effects brought about.

[0018] like Figure 1 to Figure 4 As shown, the utility model is a station facing concrete side wall and arch plate connection structure, including a side wall 1 and an arch plate 2;

[0019] There are two side walls 1, which are arranged on the left and right sides respectively with a straight wall structure; a pouring port 3 is arranged at the upper part of the side wall 1, and an oblique wooden formwork 4 is arranged in the pouring port 3;

[0020] The left end of the arch plate 2 is connected to the left side wall 1, and the right end is connected to the right side wall 1.

[0021] During construction, the device adopts an arch structure. The side walls 1 on both sides adopt a straight wall structure. The connection between the arch plate 2 and the side wall 1 adopts an arc transition to form the arch foot. The full cast-in-place concrete mode and the arch foot transition are adopted to effectively solve the defects of unreliable connection between the prefabricated complex force-bearing curved surface arch and the side wall and complex force transmission route. The arch plate 2 structure effectively optimizes the stress of the top and bottom plate structures, realizes the large span of the top and bottom plates, and at the same time, the arch plate 2 is conducive to the layout of pipelines, and the spatial effect and decoration effect are good. During the specific construction, formwork is set on the side wall 1 and the arch slab 2 to form a concrete pouring cavity, and the concrete is poured into the concrete pouring cavity in layers and vibrated layer by layer; after the poured concrete solidifies, the formwork is removed, the curing agent is applied to the newly poured concrete, and the solidified concrete is sprayed for curing; wherein, when pouring the side wall concrete, the side wall concrete is poured from 20cm above the steel formwork, and when it is poured to 50cm below the steel formwork, the inclined wooden formwork 4 is installed and fixed, and the concrete pouring continues. When pouring to the joint of the steel formwork, the inclined wooden formwork is placed obliquely and serves as a pouring window and vibration port for concrete, and the remaining concrete is poured. 5-6 hours after the concrete pouring is completed, the inclined wooden formwork 4 at the dustpan mouth is removed, and then the excess concrete is shaved off, the exposed part is smoothed with cement slurry, and it is promptly watered for curing, and then the arch slab concrete is poured. During pouring, if Figure 1 As shown, cup-hook brackets and scaffolding will be used with square timber, steel, etc. as supporting connectors. Putty is used to fill the joints of the template to prevent leakage.

[0022] like Figure 2 As shown, as a preferred embodiment, the connection between the arch plate 2 and the side wall 1 adopts a variable cross-section structure. The variable cross-section structure is adopted at the connection between the arch plate 2 and the side wall 1. The variable cross-section can change its shape according to the changes in external conditions and material response. Different cross-sectional shapes can be used to adapt to different structural stresses and deformations, and the structure can reduce material loss while meeting strength and stability.

[0023] like Figure 4 As shown, as a preferred embodiment, the oblique wooden formwork 4 is placed obliquely downward at 25° to 30°. According to the arrangement of the side wall 1 and the arch top plate 2, the oblique wooden formwork 4 is set to 25° to 30°, which is more convenient for adding materials as a pouring window.

[0024] The words “connection” and “fixation” appearing in the description of the present invention may refer to fixed connection, processing and forming, welding, or mechanical connection. The specific meanings of the above terms in the present invention shall be understood according to the specific circumstances.

[0025] In the description of the present invention, the terms "center", "upper", "lower", "horizontal", "inner", "outer", etc., which indicate the orientation or position relationship, are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying a specific orientation that the device or element referred to must have, and therefore cannot be understood as a limitation on the present invention.

[0026] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, ordinary technicians in the field should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the utility model.

Claims

1. A station facing concrete side wall and arch slab connection structure, characterized by: It comprises a side wall (1) and a vault plate (2); Two side walls (1) are provided, and are respectively arranged on the left and right sides using a straight wall structure; a pouring port (3) is provided at the upper part of the side wall (1), and an oblique wooden formwork (4) is provided in the pouring port (3); The left end of the arch plate (2) is connected to the left side wall (1), and the right end is connected to the right side wall (1).

2. A station facing concrete side wall and vault slab connection structure as claimed in claim 1, characterized in that: The connection between the arch top plate (2) and the side wall (1) adopts a variable cross-section structure.

3. A station facing concrete side wall and vault slab connection structure as claimed in claim 1, characterized in that: The oblique wooden template (4) is placed obliquely downward at an angle of 25° to 30°.