Formwork trolley for partition wall in tunnel

By using the combination of lateral supports, vertical supports and self-aligning screws on the partition wall construction formwork trolley in the tunnel, combined with the traveling motor and hydraulic cylinder, the problem of the existing formwork installation and adjustment process being cumbersome has been solved, and the tunnel construction has been improved. efficiency and quality.

CN221896598UActive Publication Date: 2024-10-25CHINA CONSTR FIRST BUILDING (GRP) CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323596872.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-28
Publication Date
2024-10-25
Estimated Expiration
2033-12-28

AI Technical Summary

Technical Problem

The installation and adjustment process of partition wall construction formwork in existing tunnels is cumbersome, especially adjusting the centerline position of the formwork is complicated, which affects construction efficiency and quality.

Method used

A tunnel partition wall formwork trolley is designed. Through the cooperation of lateral supports, vertical supports and self-aligning screws, the position of the steel formwork can be accurately adjusted, and the traveling motor and hydraulic cylinder are used to drive the formwork components to move in the tunnel. Simplifies the installation and adjustment process.

Benefits of technology

It achieves fast and precise installation and adjustment of formwork, improves construction efficiency and quality, and reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221896598U_ABST
    Figure CN221896598U_ABST
Patent Text Reader

Abstract

The utility model discloses a tunnel mid-partition formwork trolley which comprises a formwork assembly, a plurality of steel plates and a plurality of steel plates, the formwork assembly comprises a plurality of arc-shaped steel plates, every two arc-shaped steel plates can form a formwork unit, a mid-partition pouring space is formed between every two arc-shaped steel plates, and a plurality of formwork units can form a steel formwork; the supporting assembly comprises a transverse support and a vertical support, the transverse support is arranged on the concave face of the steel formwork, the branch end of the vertical support makes contact with the bottom of the transverse support, and a first aligning lead screw and a plurality of lead screw jacks are arranged on the vertical support; the walking assembly comprises a power device capable of driving the formwork assembly and the supporting assembly to move in the extending direction of the tunnel. The steel formwork can be installed and fixed at a preset position through the cooperation of the transverse support, the vertical support, the aligning lead screw and the lead screw jack, and the position of the steel formwork is accurately adjusted after the formwork is driven by the walking assembly to walk to the building position, so that the construction efficiency and the construction quality are improved, and the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field related to tunnel engineering construction, and more specifically, to a partition wall template trolley in a tunnel. Background Art

[0002] With the rapid development of my country's transportation infrastructure construction, tunnel engineering projects are often encountered in some mountainous areas. At present, the method of pouring the middle partition wall in the middle guide tunnel in advance and then excavating the tunnels on both sides of the middle partition wall is also more commonly used. In order to ensure the construction quality and progress of the tunnel project, advanced technical means need to be adopted during the construction process to improve the efficiency and quality of tunnel construction, reduce construction costs, and reduce interference on the construction site.

[0003] After searching, the tunnel partition wall construction template and its construction device with publication number CN107191201A are found. The device sets multiple cross brace structures between the partition wall templates and between the templates and the inner wall of the tunnel. The installation and disassembly are cumbersome, and the adjustment of the center line position of the template is complicated.

[0004] Therefore, the utility model designs a tunnel partition wall template trolley to solve the above problems. Utility Model Content

[0005] One purpose of the utility model is to provide a tunnel partition wall template trolley, which can install and fix the steel template at a preset position and accurately adjust the position of the steel template through the cooperation of lateral support, vertical support and self-aligning screw rod.

[0006] In order to achieve these purposes and other advantages of the utility model, the utility model provides a tunnel partition wall template trolley, including: a template assembly, which includes a plurality of arc-shaped steel plates, the convex surfaces of each two arc-shaped steel plates are arranged oppositely to form a template unit, and a middle partition wall casting space is formed between the convex surfaces of the two arc-shaped steel plates, and a plurality of the template units can form a steel template; a support assembly, which includes a transverse support and a vertical support, the transverse support is arranged on the concave surface of the steel template along the extension direction of the steel template, and the vertical support is arranged between the concave surface of the steel template along the extension direction of the steel template. A plurality of F-shaped support frames are distributed at intervals, the branch ends of the F-shaped support frames are in contact with the bottom of the lateral support, the F-shaped support frames are provided with a first self-aligning screw and a plurality of screw jacks, one end of the first self-aligning screw is connected to the top of the F-shaped support frame, and the other end is connected to the top of the steel formwork, the screw jack is arranged at the branch of the F-shaped support frame, one end of the first self-aligning screw is in contact with the inner wall of the tunnel, and the other end is in contact with the lateral support; a walking assembly, which includes a power device that can drive the formwork assembly and the support assembly to move along the extension direction of the tunnel.

[0007] Furthermore, the power device includes a travel motor and travel wheels, the travel motor is arranged at the bottom of the head end of each side of the steel template, and the travel wheel is arranged at the bottom of the tail end of each side of the steel template.

[0008] Furthermore, a hydraulic cylinder is provided on the travel motor and travel wheel on each side of the steel formwork, a full-length crossbeam is provided on the hydraulic cylinder in the extension direction of the steel formwork, and the bottom of the F-shaped support frame is connected to the crossbeam.

[0009] Furthermore, a second self-aligning screw is provided on the crossbeam, one end of the second self-aligning screw is connected to the crossbeam, and the other end is connected to the transverse support at the bottom of the steel formwork.

[0010] Furthermore, grouting holes are provided on the arc-shaped steel plate, and the grouting holes are staggered and equidistantly arranged up and down along the extension direction of the steel template, and the grouting holes on both sides of the steel template are symmetrical.

[0011] Furthermore, a track is provided in the extension direction of the tunnel, the travel assembly is arranged on the track, and a vehicle blocker is provided on the track.

[0012] Furthermore, the lateral support, F-shaped support frame and cross beam are all made of steel sections.

[0013] The utility model includes at least the following beneficial effects: the steel template is fixed on the traveling device through the horizontal support and the vertical support. After the traveling device transports the steel template into the tunnel, the center line position of the steel template is accurately adjusted by the self-aligning screw rod, so as to simplify the template splicing and installation, improve the construction efficiency and construction quality, and reduce the construction cost.

[0014] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through research and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is a structural schematic diagram of a partition wall template trolley in a tunnel according to the utility model;

[0016] Figure 2 It is a side view of the partition wall template trolley in the tunnel of the utility model. DETAILED DESCRIPTION

[0017] The present invention will be further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.

[0018] It should be understood that the terms such as “having”, “including” and “comprising” used herein do not exclude the existence or addition of one or more other elements or combinations thereof.

[0019] like Figures 1-2 As shown, an embodiment of the present application provides a tunnel partition wall template trolley, including: a template assembly, which includes a plurality of arc-shaped steel plates 1 with a width of 1.5m and a thickness of 8mm. Optionally, an arc-shaped plate or a flat plate can be selected according to the shape of the partition wall to be constructed; the convex surfaces of every two arc-shaped steel plates 1 are arranged opposite to each other to form a template unit, and a partition wall casting space is formed between the convex surfaces of the two arc-shaped steel plates 1, and a plurality of template units can form a steel template; a support assembly, which includes a plurality of transverse supports 2 and vertical supports, the number of the transverse supports 2 is six, and three are arranged on each side of the steel template. The transverse supports 2 are arranged on the concave surface of the steel template at intervals along the extension direction of the steel template, and the vertical supports are a plurality of F-shaped support frames 3 distributed at intervals along the extension direction of the steel template, and the number of the F-shaped support frames 3 is determined according to the extension length of the steel template, and the branches of the F-shaped support frames 3 are A triangular support frame, optionally, a square support frame or other support structure with good supporting effect can be selected; the branch end of the F-shaped support frame 3 contacts the bottom of the lateral support 2, and the F-shaped support frame 3 is provided with a first self-aligning screw 4 and a plurality of screw jacks 6, one end of the first self-aligning screw 4 is connected to the top of the F-shaped support frame 3, and the other end is connected to the top of the steel template, and the angle of the steel template can be adjusted by adjusting the self-aligning screw to convert the rotation into linear motion, and the body of the screw jack 6 is fixedly arranged at the branch of the F-shaped support frame 3, one end of which contacts the inner wall of the tunnel, and the other end contacts the lateral support 2. During installation, the jack can be adjusted first to adjust the position of the steel template, and then the position of the steel template can be fine-tuned by the screw; a walking assembly, which includes a power device that can drive the template assembly and the support assembly to move along the extension direction of the tunnel. During assembly, first lay a track 12 for the walking assembly to travel, and the direction of the track 12 is set along the extension direction of the tunnel. Then, the power device is installed on the track 12, and the supporting structure is installed on the power device. The F-shaped support frame 3 is installed and fixed, and the screw jack 6 is installed on the branch of the F-shaped support frame 3. The convex surfaces of the arc-shaped steel plates 1 are relatively spliced ​​to form a template unit, leaving space for pouring the partition wall in the tunnel according to the design requirements, and multiple template units are arranged by arranging three transverse supports 2 at intervals on the concave surface on each side of the steel template. The template units are combined into a steel template, and the end of the branch triangular support frame of the F-shaped support frame 3 is placed at the bottom of the transverse support 2. One end of the screw jack 6 on the branch of the F-shaped support frame 3 is against the inner wall of the tunnel, and the other end is connected to the transverse support 2. Through the joint action of the triangular support frame and the screw jack 6, the steel template can be lifted up, and the steel template is driven forward by the power device. Optionally, the connection method of each component can be screwed or welded. The steel template can be fixedly connected to the power device through the cooperation of the self-aligning screw and the screw jack 6, and the center line position of the steel template can be adjusted. Then the power device can drive the steel template forward along the construction direction to improve construction efficiency and construction quality and reduce construction costs.

[0020] In other embodiments, the power device includes two travel motors 7 and two travel wheels 8. The travel motor 7 is a turbine reducer with a 6kW motor. After the tracks 12 for the power device to travel are set on both sides in the tunnel extension direction, the two travel motors 7 are set at the head end of the tracks 12 on both sides of the construction direction, and the two travel wheels 8 are set at the tail end of the tracks 12 on both sides of the construction direction. Optionally, the spacing between the travel motors 7 and the travel wheels 8 is determined according to the number of template units; after the travel motors 7 and the travel wheels 8 are installed and fixed, the support frame, steel template and other components are assembled. By setting the travel motors 7 and the travel wheels 8 in the tunnel construction direction, the steel template can be driven to move forward in the tunnel construction direction, thereby improving construction efficiency, shortening construction period and reducing construction costs.

[0021] In other embodiments, the travel motor 7 and the travel wheel 8 on each side are fixedly connected with a hydraulic cylinder 11 by screws, and a full-length crossbeam 10 is arranged between the two hydraulic cylinders 11 on the same side in the extension direction of the steel formwork, and the length of the crossbeam 10 is not less than the distance between the two hydraulic cylinders 11. During assembly, the travel motor 7 and the travel wheel 8 are installed on the track 12, and the hydraulic cylinder 11 is fixedly connected to the travel motor 7 and the travel wheel 8, and then the crossbeam 10 is fixed between the two hydraulic cylinders 11 on the same side. Optionally, the crossbeam 10 and the hydraulic cylinder 11 can be connected by screwing or welding. After the crossbeam 10 is installed, other upper components are installed, and the bottom end of the F-shaped support frame 3 is fixedly connected to the crossbeam 10. Optionally, the F-shaped support frame 3 and the crossbeam 10 can be connected by screwing or welding. Then the steel formwork is fixedly connected to the F-shaped support frame 3. The setting of the crossbeam 10 can keep the travel motor 7 driving the entire steel template to be evenly close to the tunnel construction direction, so as to achieve the effect of improving the construction efficiency and improving the integrity of the entire device.

[0022] In other embodiments, a second self-aligning screw 5 is provided on the crossbeam 10, one end of the second self-aligning screw 5 is attached to the crossbeam 10, and the other end is connected to the lateral support 2 at the bottom of each side of the steel formwork, and can be optionally fixed by welding or screw connection. After the components are assembled, the first self-aligning screw 4 and the second self-aligning screw 5 are rotated to convert the rotation into linear motion, and the inclination angle of the steel formwork can be controlled to adjust the centerline position of the steel formwork so that the centerline position of the steel formwork coincides with the centerline position of the tunnel. The inclination angle of the steel formwork can be fine-tuned by the self-aligning screw, and the steel formwork can be accurately placed at a predetermined position, thereby improving construction efficiency and quality.

[0023] In other embodiments, the curved steel plates 1 are provided with grouting holes 9, which are square holes with a side length of 450 mm. Optionally, the grouting holes 9 are not limited to squares, and may be circular, triangular, rectangular or other shapes; wherein the grouting holes 9 of a curved steel plate 1 on each side of the steel formwork and the curved steel plate 1 adjacent to the curved steel plate 1 are arranged alternately up and down, wherein the lower grouting holes 9 are 2m away from the ground, the upper grouting holes 9 are 4.5m away from the ground, and the grouting holes 9 on both sides of the steel formwork are symmetrical. After the formwork is assembled, the head and tail ends of the formwork are closed with plugging plates, and the bottoms of both sides of the steel formwork are closed with wooden formworks, and the components are checked for firm connection. After the inspection is completed, pouring begins from the working window of the grouting hole 9. When pouring, start from the lower working window, and pay attention to replacing the pouring holes during pouring. The speed of pouring concrete is not more than 6 to 7m. 3 / h, during the pouring process, tamping rods are required to be used for tamping, the height difference of the concrete before and after the steel formwork is required not to exceed 600mm; the height difference of the concrete on both sides is required not to exceed 500mm, and the pouring must be done at a low speed when the pouring is capped at the end of the pouring port, and attention must be paid to the changes in the pouring port pressure at all times to avoid deformation of the formwork due to excessive pressure caused by forced injection of concrete after it is filled. A window for pouring concrete is reserved in advance on the curved steel plate 1 to facilitate subsequent construction and improve construction efficiency.

[0024] In other embodiments, a track 12 is arranged along the extension direction of the tunnel, wherein the sleepers and rails must meet the requirements, and the gauge error is controlled within ±30mm after laying; the track 12 and the sleepers must be fixed with spikes to prevent danger when the trolley is running; the sleeper spacing shall not be greater than 500mm to prevent the rails from being broken. A car blocker is arranged near the running wheel 8 on the track 12, and optionally, a wooden wedge or other components that can prevent the running wheel 8 from sliding can be used; when the slope of a certain section in the tunnel is too large, causing the running component to slip on the track 12, some dry fine sand can be sprinkled on the track surface to increase the adhesion. After the template is assembled, the running component travels to the predetermined masonry position to start grouting. After the pouring is completed, it is cured for a specified time and ready for demoulding. When demoulding, the plugging plates at the head and tail ends of the steel template are first removed, and then the wooden template at the bottom of the steel template is removed, the hydraulic oil pump is started, and the handle of the manual reversing valve of the steel template is operated to extend the oil cylinder slightly to loosen the lead screw. After removing all the screws of the side formwork, operate the jack to retract the steel formwork and detach it from the forming surface. When the jack retracts, it must be retracted in batches, and it is forbidden to force demolding at one time. The retraction stroke of the jack is 180mm-300mm. Then operate the lifting hydraulic cylinder 11 to rise slightly, and push the control handle of the hydraulic cylinder 11 in the reverse direction, so that the hydraulic cylinder 11 is lowered by the deadweight of the formwork, and the steel formwork is detached from the forming surface. Remove the wooden wedge or car blocker at the walking wheel 8, and operate the walking assembly to drive the formwork forward to the next lining position. By setting up the track 12 for the walking assembly to travel according to the construction position of the middle partition wall in the tunnel, the construction position of the middle partition wall can be controlled, and the construction efficiency can be improved and the cost can be saved.

[0025] In other embodiments, the transverse support 2, the F-shaped support frame 3 and the cross beam 10 are all made of steel sections, wherein the transverse support 2 is a channel steel support, and the F-shaped support frame 3 and the cross beam 10 are made of I-shaped steel. Optionally, the support member is not limited to channel steel and I-shaped steel, and angle steel, T-shaped steel or other cross-sectional steel that meets the strength requirements can be used. Using steel sections as support components, among steels of the same weight, steel sections can withstand greater external forces, making the template splicing more secure and improving the construction quality.

[0026] The number of devices and processing scales described here are used to simplify the description of the utility model. The application, modification and variation of the utility model tunnel partition wall template trolley are obvious to those skilled in the art.

[0027] Although the implementation scheme of the utility model has been disclosed as above, it is not limited to the applications listed in the specification and implementation modes. It can be fully applied to various fields suitable for the utility model. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the utility model is not limited to the specific details and the illustrations shown and described herein.

Claims

1. The tunnel partition wall formwork trolley is characterized by: include: A template assembly, comprising a plurality of arc-shaped steel plates, wherein the convex surfaces of each two arc-shaped steel plates are arranged opposite to each other to form a template unit, and a middle partition wall casting space is formed between the convex surfaces of the two arc-shaped steel plates, and a plurality of the template units can form a steel template; A support assembly, comprising a transverse support and a vertical support, wherein the transverse support is arranged on the concave surface of the steel template along the extension direction of the steel template, and the vertical support is a plurality of F-shaped support frames spaced apart along the extension direction of the steel template, wherein the branch ends of the F-shaped support frames are in contact with the bottom of the transverse support, and the F-shaped support frames are provided with a first self-aligning screw and a plurality of screw jacks, wherein one end of the first self-aligning screw is connected to the top of the F-shaped support frame, and the other end is connected to the top of the steel template, and the screw jack is arranged at the branch of the F-shaped support frame, wherein one end of the first self-aligning screw is in contact with the inner wall of the tunnel, and the other end is in contact with the transverse support; The walking assembly comprises a power device capable of driving the template assembly and the supporting assembly to move along the extension direction of the tunnel.

2. The tunnel partition wall formwork trolley according to claim 1, characterized in that: The power device comprises a travel motor and travel wheels. The travel motor is arranged at the bottom of the head end of each side of the steel template, and the travel wheel is arranged at the bottom of the tail end of each side of the steel template.

3. The tunnel partition wall formwork trolley according to claim 2, characterized in that: A hydraulic cylinder is provided on the travel motor and the travel wheel on each side of the steel formwork, a through-length crossbeam is provided on the hydraulic cylinder in the extension direction of the steel formwork, and the bottom of the F-shaped support frame is connected to the crossbeam.

4. The tunnel partition wall formwork trolley according to claim 3, characterized in that: A second self-aligning screw rod is arranged on the cross beam, one end of the second self-aligning screw rod is connected to the cross beam, and the other end is connected to the transverse support at the bottom of the steel template.

5. The tunnel partition wall formwork trolley according to claim 1, characterized in that: The arc-shaped steel plate is provided with grouting holes, which are staggered and equidistantly arranged up and down along the extension direction of the steel template, and the grouting holes on both sides of the steel template are symmetrical.

6. The tunnel partition wall formwork trolley according to claim 1, characterized in that: A track is arranged in the extending direction of the tunnel, the traveling assembly is arranged on the track, and a vehicle blocker is arranged on the track.

7. The tunnel partition wall formwork trolley according to claim 1, characterized in that: The transverse support, F-shaped support frame and cross beam are all made of section steel.