Prestressed steel cable connector suitable for flat anchor
By designing a prestressed steel tendon connector suitable for flat anchors and utilizing the working clip and the clamping structure of the clip, the efficient disposal of negative bending moment prestressed steel tendons is achieved, which solves the problem of dealing with damaged steel tendons in the existing technology. solve difficult problems and achieve the safe utilization of the structure and the development of green, low-carbon cycle.
Patent Information
- Application Number
- CN202420415252.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-04
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-03-04
AI Technical Summary
When dealing with damaged negative bending moment prestressed steel tendons, the existing technology is difficult to achieve efficient dismantling and reconstruction, resulting in structural damage, heavy investment in human and financial resources, long construction period, and does not meet the requirements of green development.
A prestressed steel tendon connector suitable for flat anchors is designed. By placing retained and new prestressed steel bars in the connector, and using the working clip and the clamping structure of the clip, the tension of the steel tendon is achieved. and grouting, suitable for structural types such as integral box beams and cast-in-place slabs.
This technology effectively disposes of the severed negative bending moment prestressed steel tendons, ensuring a clear force transmission path and clear stress in the structure, which is in line with green development, reduces the scale of bridge structure grooving and new construction, and reduces project capital investment.
Smart Images

Figure CN221920336U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of prestressed steel bundle connectors, in particular to a prestressed steel bundle connector suitable for flat anchors. Background Art
[0002] With the rapid development of national economy, traffic planning and river planning, some bridge spans cannot meet the use requirements, or some bridge structures are seriously damaged due to traffic accidents, natural disasters and fires. In this case, the existing side spans or part of the bridge spans including the side spans will be demolished, and then new side spans that meet the planning requirements will be built. Or due to human factors, the negative moment prestressed steel strands of the continuous beam are cut off. In these cases, the negative moment prestressed steel strands will be handled.
[0003] Through patent search, it was found that the publication number of CN208396145U is a flat anchor plate that can be tensioned as a whole. The key points of its technical solution are that it includes an anchor plate body, which is a rectangular parallelepiped, and has at least two threading holes equidistantly opened along the length direction of the anchor plate body, and is fitted to the anchor plate body and provided with a wire bunker along the axial direction of the threading holes. This flat anchor plate adopts a rectangular anchor plate body structure, which makes it more convenient to process threading holes on mutually parallel planes, simplifying the manufacturing process of the utility model; on the other hand, the center lines of each threading hole are parallel to each other, and the tensioning can be completed at one time when the steel strand is tensioned, realizing the overall tensioning of the steel strand and avoiding the phenomenon of uneven stress distribution of the steel strand after tensioning.
[0004] At present, the main disposal method is to remove the damaged negative moment prestressed steel strands and then re-insert them. For the negative moment prestressed steel strands after grouting, it is difficult to dispose of them. Not only does it require grooving the beam body, but it also causes irreversible defects in the beam body. At the same time, it will also invest a lot of manpower and financial resources, and extend the construction period. At the same time, it is not in line with green development, conservation, intensiveness, low carbon and environmental protection. In order to promote the recycling and comprehensive utilization of construction materials and waste materials, a prestressed steel strand connector suitable for flat anchors is needed to solve the above technical problems. Utility Model Content
[0005] The utility model aims to make up for the deficiencies of the prior art and provides a prestressed steel bundle connector suitable for flat anchors.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a prestressed steel bundle connector suitable for flat anchors, including a connector, wherein a group of threading holes 1 and 2 are respectively opened at the top of the connector, a working clip 1 is provided in each threading hole 1, and the working clip 1 is composed of clip 1 and clip 2, a working clip 2 is provided in each threading hole 2, and the working clip 2 is composed of clip 3 and clip 4, a retained prestressed steel bar is provided in each working clip 1, and clip 1 and clip 2 both clamp the retained prestressed steel bar together and fill it in the threading hole 1, an additional prestressed steel bar is provided in each working clip 2, and clip 3 and clip 4 both clamp the additional prestressed steel bar together and fill it in the threading hole 2.
[0007] Preferably, one side of the threading hole one and the threading hole two are respectively provided with groove one and groove two, the top ends of the groove one and groove two are respectively rotatably connected with rotating steel sheets one and rotating steel sheets two, the side of the rotating steel sheet one away from the retained prestressed steel bar is fixedly connected with spring one, and the other end of the spring one is fixedly connected to the inner side wall of groove one, the side of the rotating steel sheet two away from the newly added prestressed steel bar is fixedly connected with spring two, and the other end of the spring two is fixedly connected to the inner side wall of groove two, the side of the retained prestressed steel bar close to groove one is provided with slot one, and the side of the newly added prestressed steel bar close to groove two is provided with slot two.
[0008] Preferably, a sliding groove is provided on a side of the threading hole away from the groove, and a positioning block is fixedly connected to the bottom end of the side of the working clamp away from the groove.
[0009] Preferably, a second slide groove is provided on a side of the second threading hole away from the second groove, and a second positioning block is fixedly connected to the top of the second working clamp on a side away from the second groove.
[0010] Preferably, the top end of the working clamp piece 1 away from the groove 1 is fixedly connected to the blocking piece 1, and the bottom end of the working clamp piece 2 away from the groove 2 is fixedly connected to the blocking piece 2.
[0011] Preferably, the inner sides of the clips 1 and 3 are provided with friction lines No. 1, the inner sides of the clips 2 and 4 are provided with friction lines No. 2, and the directions of the friction lines No. 1 and No. 2 are opposite.
[0012] Preferably, the diameter of the threading hole 1 gradually increases from the bottom end to the top end, and the diameter of the threading hole 2 gradually decreases from the bottom end to the top end.
[0013] Beneficial effects:
[0014] Compared with the prior art, the prestressed steel bundle connector suitable for flat anchors has the following beneficial effects:
[0015] 1. The utility model places the retained prestressed steel bars and the newly added prestressed steel bars in the original beam into the connector respectively, and fixes them with working clips 1 and 2 respectively, and then tensions the prestressed steel bundles. The prestressed steel bundles after connection are tensioned, and grouting is performed after tensioning. Therefore, the structure can be used for the disposal and utilization of the negative bending moment prestressed steel bundles after cutting. It is suitable for upper structure types such as integral box beams, cast-in-place slabs, T beams, small box beams, hollow slabs, and I-beams. It can effectively dispose of the cut negative bending moment prestressed steel bundles. The structure has a clear force transmission path, clear force, and safe structure. It conforms to green development, conservation, intensiveness, low carbon and environmental protection, and comprehensive utilization of the original structure, creating an economic system of green, low carbon and circular development, greatly reducing the scale of bridge structure grooving and new construction, and greatly reducing project capital investment.
[0016] 2. The utility model knocks the working clamp piece 1 and the working clamp piece 2 into the threading hole 1 and the threading hole 2, so that the rotating steel sheet 1 and the rotating steel sheet 2 are squeezed by the retained prestressed steel bars and the newly added prestressed steel bars and shrink into the groove 1 and the groove 2 respectively. When the rotating steel sheet 1 and the rotating steel sheet 2 pass through the clamping groove 1 and the clamping groove 2 respectively, under the action of the spring 1 and the spring 2, the ends of the rotating steel sheet 1 and the rotating steel sheet 2 are respectively bounced into the clamping groove 1 and the clamping groove 2, which is beneficial to enhance the stability of the working clamp piece 1 and the working clamp piece 2 after being knocked into the threading hole 1 and the threading hole 2, and the working clamp piece 1 and the working clamp piece 2 will not loosen. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a three-dimensional structural schematic diagram of the utility model;
[0018] Figure 2 It is a cross-sectional view of the utility model;
[0019] Figure 3 For this utility model Figure 2 A local enlarged schematic diagram of point A in FIG.
[0020] Figure 4 For this utility model Figure 2 A local enlarged schematic diagram of point B in the figure.
[0021] In the figure: 1. Connector; 2. Threading hole 1; 3. Threading hole 2; 4. Working clip 1; 41. Clip 1; 42. Clip 2; 5. Working clip 2; 51. Clip 3; 52. Clip 4; 6. Prestressed steel bars are retained; 7. Prestressed steel bars are added; 8. Groove 1; 9. Groove 2; 10. Rotating steel sheet 1; 11. Rotating steel sheet 2; 12. Spring 1; 13. Spring 2; 14. Slot 1; 15. Slot 2; 16. Slide 1; 17. Positioning block 1; 18. Slide 2; 19. Positioning block 2; 20. Block 1; 21. Block 2. DETAILED DESCRIPTION
[0022] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0023] like Figure 1 to Figure 4 As shown, a prestressed steel strand connector suitable for flat anchors includes a connector 1. A group of threading holes 1 and threading holes 2 3 are respectively opened at the top of the connector 1. Working clips 14 are arranged in the threading holes 12. The working clips 14 are composed of clips 1 41 and clips 2 42. A sliding groove 16 is opened on the side of the threading hole 12 away from the groove 18. A positioning block 17 is fixedly connected to the bottom end of the side of the working clip 4 away from the groove 8. The design of the positioning block 17 and the sliding groove 16 positions the rotating steel sheet 10 to align with the slot 14, and makes the top of each working clip 4 in a parallel state. A baffle 20 is fixedly connected to the top of the side of the working clip 4 away from the groove 18, and a baffle 21 is fixedly connected to the bottom end of the side of the working clip 2 5 away from the groove 29. The baffle 10 and the baffle 21 play a closing role on the sliding groove 16 and the sliding groove 2 18. The threading holes 23 are each provided with working clips 25, and the working clips 25 are each composed of clips 3 51 and clips 4 52. The diameter of the threading hole 12 gradually increases from the bottom to the top, and the diameter of the threading hole 23 gradually decreases from the bottom to the top, which plays a role in fixing the working clips 14 and 25. The threading holes 23 are each provided with a slide groove 2 18 on the side away from the groove 2 9, and the top of the working clips 25 on the side away from the groove 2 9 is fixedly connected with a positioning block 2 19. The design of the positioning block 2 19 and the slide groove 2 18 positions the rotating steel sheet 2 11 to align with the card groove 2 15, and makes the bottom end of each working clip 2 5 in a parallel state. The working clamping piece 1 4 is provided with a retained prestressed steel bar 6, and the clamping piece 1 41 and the clamping piece 2 42 both clamp the retained prestressed steel bar 6 together and fill it in the threading hole 1 2, and the working clamping piece 2 5 is provided with a newly added prestressed steel bar 7, and the clamping piece 3 51 and the clamping piece 4 52 both clamp the newly added prestressed steel bar 7 together and fill it in the threading hole 2 3. The inner sides of the clamping piece 1 41 and the clamping piece 3 51 are provided with a No. 1 friction pattern, and the inner sides of the clamping piece 2 42 and the clamping piece 4 52 are provided with a No. 2 friction pattern, and the texture directions of the No. 1 friction pattern and the No. 2 friction pattern are opposite. The design of the No. 1 friction pattern and the No. 2 friction pattern, as well as the design of the opposite textures, greatly increases the stability of the retained prestressed steel bar 6 and the newly added prestressed steel bar 7 inside the working clamping piece 1 4 and the working clamping piece 2 5.
[0024] During work, static cutting equipment is used to cut along the outer side of the bridge span to be retained so that the retained bridge span structure is intact. The remaining diaphragms are removed by manual smashing. The negative moment prestressed steel bundle in the original beam is grouting-broken. The cement slurry around the prestressed steel bundle is broken by manual smashing to expose the prestressed steel strands. The exposed length should not be loose and meet the working length connected to the connector 1. When the negative moment prestressed steel bundle retained in the original beam is long, the retained prestressed steel bars 6 and the newly added prestressed steel bars 7 in the original beam are respectively placed in the connector 1, and are fixed by working clips 1 4 and working clips 2 5 respectively. Then the prestressed steel bundle is tensioned. The prestressed steel bundle after connection is tensioned, and grouting is performed after tensioning. Therefore, the structure can be used for disposal and utilization after the negative moment prestressed steel bundle is cut off. It is suitable for upper structure types such as integral box beams, cast-in-place slabs, T beams, small box beams, hollow slabs, and I-beams, and can effectively dispose of the cut negative moment prestressed steel bundles.
[0025] A groove 18 and a groove 29 are respectively provided on one side of the threading hole 2 and the threading hole 23, and the top ends of the grooves 18 and 29 are rotatably connected with a rotating steel sheet 10 and a rotating steel sheet 2 11 respectively. The side of the rotating steel sheet 10 away from the retained prestressed steel bar 6 is fixedly connected with a spring 12, and the other end of the spring 12 is fixedly connected to the inner side wall of the groove 18, and the side of the rotating steel sheet 2 11 away from the newly added prestressed steel bar 7 is fixedly connected with a spring 2 13, and the other end of the spring 2 13 is fixedly connected to the inner side wall of the groove 2 9. A slot 14 is provided on the side of the retained prestressed steel bar 6 close to the groove 18, and a slot 2 15 is provided on the side of the newly added prestressed steel bar 7 close to the groove 2 9. The rotating steel sheet 10 and the rotating steel sheet 2 11 are stuck in the slot 14 and the slot 2 15, thereby limiting the movement of the working clamp 1 4 and the working clamp 2 5.
[0026] During operation, the working clamp 1 4 and the working clamp 2 5 are knocked into the threading hole 1 2 and the threading hole 2 3, and the rotating steel sheet 10 and the rotating steel sheet 2 11 are squeezed by the retained prestressed steel bars 6 and the newly added prestressed steel bars 7, and shrink into the groove 1 8 and the groove 2 9 respectively. When the rotating steel sheet 10 and the rotating steel sheet 2 11 pass through the slot 1 14 and the slot 2 15 respectively, under the action of the spring 12 and the spring 2 13, the ends of the rotating steel sheet 10 and the rotating steel sheet 2 11 are respectively bounced into the slot 1 14 and the slot 2 15, which is beneficial to enhance the stability of the working clamp 1 4 and the working clamp 2 5 after being knocked into the threading hole 1 2 and the threading hole 2 3, and the working clamp 1 4 and the working clamp 2 5 will not loosen.
[0027] Working principle: Use static cutting equipment to cut along the outer side of the bridge span to be retained, so that the retained bridge span structure is intact, and the remaining diaphragms are removed by manual smashing. The negative bending moment prestressed steel strands in the original beam are grout-grouted and broken. The cement slurry around the prestressed steel strands is broken by manual smashing to expose the prestressed steel strands. The exposed length should not be loose and meet the working length connected to the connector 1. When the negative bending moment prestressed steel strands retained in the original beam are long, the retained prestressed steel bars 6 and the newly added prestressed steel bars 7 in the original beam are placed in the connector 1 respectively, and the working clips 1 4 and 2 5 are knocked into the threading holes 1 2 and 2 3. The rotating steel sheets 10 and 11 are squeezed by the retained prestressed steel bars 6 and the newly added prestressed steel bars 7, and shrink to the grooves 1 8 and 2 9 respectively. When the rotating steel sheets 10 and 11 pass through the slots 14 and 2 15 respectively, under the action of the springs 12 and 2 13 The ends of the rotating steel sheet 10 and the rotating steel sheet 2 11 are respectively ejected into the card slot 14 and the card slot 2 15, which is conducive to strengthening the stability of the working clamp 1 4 and the working clamp 2 5 after being knocked into the threading hole 1 2 and the threading hole 2 3, and there will be no loosening of the working clamp 1 4 and the working clamp 2 5, and then the prestressed steel bundle is tensioned, and the prestressed steel bundle after the connection is completed is tensioned, and grouting is performed after tensioning, so that the structure can be suitable for the disposal and utilization of the negative bending moment prestressed steel bundle after cutting, and is suitable for upper structure types such as integral box girders, cast-in-place slabs, T-beams, small box girders, hollow slabs, and I-beams. It can effectively dispose of the cut negative bending moment prestressed steel bundles, which is in line with green development, conservation, intensiveness, low-carbon environmental protection, and comprehensive utilization of the original structure, creating an economic system of green, low-carbon and circular development, greatly reducing the scale of bridge structure grooving and new construction, and greatly reducing project capital investment.
[0028] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A prestressed steel strand connector suitable for flat anchors, comprising a connector (1), characterized in that: The top of the connector (1) is respectively provided with a group of threading holes one (2) and threading holes two (3), each of the threading holes one (2) is provided with a working clip one (4), each of the working clip one (4) is composed of a clip one (41) and a clip two (42), each of the threading holes two (3) is provided with a working clip two (5), each of the working clip two (5) is composed of a clip three (51) and a clip four (52), each of the working clip one (4) is provided with a retained prestressed steel bar (6), and the clip one (41) and the clip two (42) both clamp the retained prestressed steel bar (6) together and fill the retained prestressed steel bar (6) in the threading hole one (2), and each of the working clip two (5) is provided with a newly added prestressed steel bar (7), and the clip three (51) and the clip four (52) both clamp the newly added prestressed steel bar (7) together and fill the retained prestressed steel bar (7) in the threading hole two (3).
2. A prestressed steel strand connector suitable for flat anchors according to claim 1, characterized in that: A groove 1 (8) and a groove 2 (9) are respectively provided on one side of the threading hole 1 (2) and the threading hole 2 (3); the top ends of the groove 1 (8) and the groove 2 (9) are respectively rotatably connected with a rotating steel sheet 1 (10) and a rotating steel sheet 2 (11); a spring 1 (12) is fixedly connected to the side of the rotating steel sheet 1 (10) away from the retained prestressed steel bar (6), and the other end of the spring 1 (12) is fixedly connected to the inner side wall of the groove 1 (8); a spring 2 (13) is fixedly connected to the side of the rotating steel sheet 2 (11) away from the newly added prestressed steel bar (7), and the other end of the spring 2 (13) is fixedly connected to the inner side wall of the groove 2 (9); a clamping groove 1 (14) is provided on the side of the retained prestressed steel bar (6) close to the groove 1 (8), and a clamping groove 2 (15) is provided on the side of the newly added prestressed steel bar (7) close to the groove 2 (9).
3. A prestressed steel strand connector suitable for flat anchors according to claim 2, characterized in that: A sliding groove (16) is provided on the side of the threading hole (2) away from the groove (8), and a positioning block (17) is fixedly connected to the bottom end of the working clamp (4) on the side away from the groove (8).
4. A prestressed steel strand connector suitable for flat anchors according to claim 2, characterized in that: The second threading hole (3) is provided with a second slide groove (18) on the side away from the second groove (9), and the top of the second working clamp (5) is fixedly connected with a second positioning block (19) on the side away from the second groove (9).
5. A prestressed steel strand connector suitable for flat anchors according to claim 2, characterized in that: The top end of the working clamping piece 1 (4) away from the groove 1 (8) is fixedly connected with a blocking piece 1 (20), and the bottom end of the working clamping piece 2 (5) away from the groove 2 (9) is fixedly connected with a blocking piece 2 (21).
6. A prestressed steel strand connector suitable for flat anchors according to claim 1, characterized in that: The inner sides of the clamping piece 1 (41) and the clamping piece 3 (51) are both provided with a No. 1 friction pattern, and the inner sides of the clamping piece 2 (42) and the clamping piece 4 (52) are both provided with a No. 2 friction pattern.
7. A prestressed steel strand connector suitable for flat anchors according to claim 1, characterized in that: The diameter of the threading hole 1 (2) increases from the bottom to the top, and the diameter of the threading hole 2 (3) decreases from the bottom to the top.