Air-cooled temperature control system capable of reducing temperature difference between inside and outside of prefabricated T-beam in curing period
By using an air-cooled temperature control system to monitor and adjust the temperature difference between the inside and outside of the T-beam in real time, the problem of temperature difference during the curing period of the T-beam was solved, the risk of cracking was reduced, and the load-bearing capacity and durability of the structure were improved.
Patent Information
- Application Number
- CN202420248809.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-01
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2034-02-01
AI Technical Summary
Excessive temperature difference between the inside and outside of the T-beam during curing causes the tensile stress in the concrete to increase faster than its tensile strength, making it prone to vertical cracks and affecting its load-bearing capacity and durability.
An air-cooled temperature control system is adopted, which delivers air into the prestressed ducts through a blower. Combined with a temperature sensor to monitor the temperature difference between the inside and outside in real time, the system uses a temperature control device to intelligently adjust the air volume and the blower's output air volume to keep the temperature difference between the inside and outside within a reasonable range.
This effectively reduced the temperature difference between the inside and outside of the T-beam, decreased the risk of concrete cracking, and improved load-bearing capacity and durability.
Smart Images

Figure CN221937109U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of highway bridge engineering construction, in particular to an air-cooling temperature control system capable of reducing the temperature difference between inside and outside of a prefabricated T-beam during curing. Background Art
[0002] The T-beam structure is simple, easy to prefabricate and install, and has a large spanning capacity. It is widely used in the field of highway bridges. The T-beam concrete has high strength and a large amount of cement, which leads to excessive hydration heat during the curing period of the T-beam, which can easily cause the temperature inside the concrete to rise rapidly. When the growth rate of concrete tensile strength is lower than the growth rate of concrete tensile stress caused by the temperature difference between the inside and outside of the concrete, vertical cracks are prone to appear in the web of the T-beam and extend to the flange, affecting the bearing capacity and durability of the T-beam. Utility Model Content
[0003] In order to overcome the shortcomings of the prior art, the purpose of the utility model is to provide an air-cooled temperature control system that can reduce the temperature difference between the inside and outside of a prefabricated T-beam during curing. The utility model solves the problem that when the growth rate of the tensile strength of concrete is lower than the growth rate of the tensile stress of concrete caused by the temperature difference between the inside and outside of the concrete, vertical cracks are prone to appear in the web of the T-beam and extend to the flange, affecting the bearing capacity and durability of the T-beam.
[0004] To achieve the above purpose, the utility model provides the following solutions:
[0005] An air cooling temperature control system capable of reducing the temperature difference between inside and outside of a prefabricated T-beam during curing, comprising:
[0006] A blower, a base, a connecting device, an air volume regulating valve, a first temperature sensor, a second temperature sensor and a temperature control device;
[0007] The air volume regulating valve is installed on the branch pipe of the prefabricated T-beam to be tested, the blower is installed on the base and connected to the longitudinal prestressed channel of the T-beam to be tested through the connecting device, the first temperature sensor is installed at the outlet of the longitudinal prestressed channel of the T-beam to be tested, the second temperature sensor is installed on the surface of the T-beam to be tested, and the temperature control device is respectively connected to the first temperature sensor, the second temperature sensor, the blower and the air volume regulating valve;
[0008] The blower is used to cool down the T-beam to be tested, the base is used to fix the blower, the air volume regulating valve is used to adjust the air supply volume of each prestressed channel, the first temperature sensor is used to obtain temperature data of each longitudinal prestressed channel of the T-beam to be tested, the second temperature sensor is used to obtain temperature data of the surface of the T-beam to be tested, and the temperature control device is used to obtain data from the first temperature sensor and data from the second temperature sensor and adjust the blower according to the data from the first temperature sensor and adjust the air volume regulating valve according to the data from the second temperature sensor.
[0009] Preferably, the connecting device comprises:
[0010] Multiple branch pipes and main pipes connected to each other in a corresponding manner;
[0011] Each main pipe is connected to the blower, and each branch pipe is correspondingly connected to the longitudinal prestressed channel of the T-beam to be tested.
[0012] Preferably, each branch pipe is installed with an air volume regulating valve.
[0013] Preferably, the first temperature sensor is installed at a position 30 cm inward from the outlet of each longitudinal prestressed channel of the T-beam to be tested.
[0014] Preferably, the second temperature sensor is installed at a mid-span position on the surface of the T-beam to be measured.
[0015] According to the specific embodiments provided by the utility model, the utility model discloses the following technical effects:
[0016] The utility model provides an air-cooled temperature control system that can reduce the temperature difference between the inside and outside of the prefabricated T-beam during curing. The blower supplies air in the T prestressed channel in one direction to reduce the internal temperature of the T-beam. Temperature sensors are set at the channel outlet and the surface of the T-beam to monitor the temperature difference of each channel outlet and the temperature difference between the inside and outside of the concrete in real time. When the temperature difference of each channel outlet exceeds the temperature control threshold, the temperature control device sends a command to intelligently adjust the air volume regulating valve until the temperature of each channel outlet is uniform. When the temperature difference between the inside and outside exceeds the temperature control threshold, the temperature control device sends a warning command and intelligently adjusts the air volume of the blower to effectively control the maximum temperature difference between the inside and outside of the T-beam within a reasonable range, reducing the risk of concrete cracking due to excessive temperature difference between the inside and outside. The operation is simple and the effect is significant. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0018] Figure 1 A schematic diagram of the structure of an air-cooling temperature control system for reducing the temperature difference between the inside and outside of a prefabricated T-beam during curing is provided in an embodiment of the utility model.
[0019] Description of reference numerals:
[0020] 1-blower, 2-base, 3-connecting device, 4-air volume regulating valve, 5-1-first temperature sensor, 5-2-second temperature sensor, 6-temperature control device, 7-prefabricated T-beam, 8-prestressed channel, 9-T-beam prefabricated pedestal, 10-wire. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0022] The purpose of the utility model is to provide an air-cooled temperature control system that can reduce the temperature difference between the inside and outside of a prefabricated T-beam during curing. The utility model solves the problem that when the growth rate of the tensile strength of concrete is lower than the growth rate of the tensile stress of concrete caused by the temperature difference between the inside and outside of the concrete, vertical cracks are prone to appear on the web of the T-beam and extend to the flange, thereby affecting the bearing capacity and durability of the T-beam.
[0023] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0024] like Figure 1 As shown, the utility model provides an air cooling temperature control system capable of reducing the temperature difference between the inside and outside of a prefabricated T-beam during curing, comprising:
[0025] Blower 1, base 2, connecting device 3, air volume regulating valve 4, first temperature sensor 5-1, second temperature sensor 5-2 and temperature control device 6;
[0026] The air volume regulating valve 4 is installed on the branch pipe of the prefabricated T-beam 7 to be tested, the blower 1 is installed on the base 2, and is connected to the longitudinal prestressed channel 8 of the T-beam to be tested through the connecting device 3, the first temperature sensor 5-1 is installed at the outlet of the longitudinal prestressed channel 8 of the T-beam to be tested, the second temperature sensor 5-2 is installed on the surface of the T-beam to be tested, and the temperature control device 6 is respectively connected to the first temperature sensor 5-1, the second temperature sensor 5-2, the blower 1 and the air volume regulating valve 4;
[0027] The blower 1 is used to cool down the T-beam to be tested, the base 2 is used to fix the blower 1, the air volume regulating valve 4 is used to adjust the air supply volume of each prestressed channel 8, the first temperature sensor 5-1 is used to obtain the temperature data of each longitudinal prestressed channel 8 of the T-beam to be tested, the second temperature sensor 5-2 is used to obtain the temperature data of the surface of the T-beam to be tested, and the temperature control device 6 is used to obtain the data of the first temperature sensor 5-1 and the data of the second temperature sensor 5-2 and adjust the blower 1 according to the data of the first temperature sensor 5-1 and adjust the air volume regulating valve 4 according to the data of the second temperature sensor 5-2.
[0028] Specifically, using temperature sensor data to adjust the blower belongs to the prior art. The principle is similar to the principle that the air conditioner automatically adjusts the air volume according to the data changes detected by the temperature sensor. It is called a "feedback control system" and is an automated control system. Most existing systems use PLC systems. This system monitors environmental parameters (such as temperature, humidity, air quality, etc.) through sensors and converts these parameters into electrical signals or digital signals. Then, the control system compares these signals with the set values and adjusts the output of the actuator (such as wind speed, temperature, etc.) to maintain the environmental parameters within the set range. This patent is mainly based on the temperature sensor to monitor the temperature on the surface of the T-beam and the prestressed duct in real time and compare it with the standard internal and external temperature difference set by the system, and automatically adjusts the wind speed to maintain the constant temperature difference between the inside and outside of the T-beam.
[0029] Specifically, the temperature control device 6 is connected to the blower 1, the first temperature sensor 5-1, the second temperature sensor 5-2 and the air volume regulating valve 4 respectively through the wire 10, and the wire 10 here can also be a signal line.
[0030] Specifically, the prefabricated T-beam 7 is placed on the T-beam prefabricated pedestal 9 .
[0031] Specifically, the base 2 is installed after the prefabricated T-beam 7 is cast and is located near one end of the T-beam.
[0032] Furthermore, the connecting device 3 comprises:
[0033] Multiple branch pipes and main pipes connected to each other in a corresponding manner;
[0034] Each main pipe is connected to the blower 1, and each branch pipe is correspondingly connected to the longitudinal prestressed channel 8 of the T-beam to be tested.
[0035] Furthermore, each branch pipe is installed with an air volume regulating valve 4 for adjusting the air supply volume of each prestressed channel 8 .
[0036] Furthermore, the first temperature sensor 5 - 1 is installed at a position 30 cm inward from the exit of each longitudinal prestressed channel 8 of the T-beam to be tested, including but not limited to 30 cm.
[0037] Furthermore, the second temperature sensor 5-2 is installed at a mid-span position on the surface of the T-beam to be measured, including but not limited to the mid-span position.
[0038] Specifically, the temperature control device 6 reasonably sets the temperature difference threshold of the channel outlet and the temperature difference threshold of the inside and outside of the T-beam according to the environment in which the T-beam is prefabricated.
[0039] Specifically, the temperature difference at the outlet of each channel is monitored in real time by the temperature control device 6. When the temperature difference at the outlet of each channel exceeds the temperature control threshold, the temperature control device 6 issues a command to intelligently adjust the air volume regulating valve 4 until the outlet temperature of each channel is uniform.
[0040] Specifically, the temperature difference between the inside and outside of the concrete is monitored in real time by the temperature control device 6. When the temperature difference between the inside and outside exceeds the temperature control threshold, the temperature control device 6 issues a warning instruction and intelligently adjusts the air volume of the blower 1.
[0041] Specifically, the existing technology mostly uses PLC system. The full name of PLC control system is Programmable Logic Controller. It uses digital electrical signals for control. Its components include PLC controller, central control equipment, communication network, sensor, actuator and regulating valve. In the input conversion process, the controller receives the signal from the temperature sensor and humidity sensor and converts it into a digital signal; then, through the output conversion process, the digital signal is converted into a control signal and output, so as to achieve the purpose of controlling the operation of the system. The control operation function can be subdivided into multiple modules such as PID control, timer, signal reversal and signal selection. The specific operation is mainly controlled by the input signal. The calculation result is output to each regulating valve by the output conversion function to control the operation of each valve.
[0042] The utility model also provides a specific embodiment:
[0043] A 40m prefabricated T-beam 7 has a beam height of 2.5m and 6 longitudinal prestressed channels 8 are arranged inside the T-beam. The T-beams are centrally prefabricated at the beam yard. After the T-beam is demolded, the film coating and curing work is immediately carried out. At the same time, the base 2 is installed at the end of the beam and adjusted to a suitable angle and height. After the blower 1 is installed in place on the base 2, the blower 1 is connected to the prestressed channel 8 through the main branch pipe connection device 3, and a trial run is carried out to ensure that the pipeline is unobstructed and the connection parts are sealed and leak-proof. An air volume regulating valve 4 is installed on each branch pipe to adjust the conveying air volume of each branch pipe. Temperature sensors are set at the channel outlet and the surface of the T-beam, and the temperature difference of each channel outlet and the temperature difference between the inside and outside of the concrete are monitored in real time through the temperature control device 6. When the temperature difference at the outlet of each channel exceeds the temperature control threshold, the temperature control device 6 issues a command to intelligently adjust the air volume control valve 4 until the temperature at the outlet of each channel is uniform. When the temperature difference between the inside and outside exceeds the temperature control threshold, the temperature control device 6 issues a warning command and intelligently adjusts the air volume of the blower 1 to always control the temperature difference between the inside and outside of the T-beam within a reasonable range, thereby reducing the risk of cracking of concrete due to excessive temperature difference between the inside and outside.
[0044] The beneficial effects of the utility model are as follows:
[0045] The temperature difference between the inside and outside of the T-beam is always controlled within a reasonable range, reducing the risk of concrete cracking due to excessive temperature difference between the inside and outside. The system is simple, easy to install, simple to operate, and has significant effects.
[0046] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0047] This article uses specific examples to illustrate the principles and implementation methods of the utility model. The above examples are only used to help understand the method and core ideas of the utility model. At the same time, for those skilled in the art, according to the ideas of the utility model, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the utility model.
Claims
1. A wind-cooled temperature control system that can reduce the temperature difference between inside and outside of prefabricated T-beams during curing. It is characterized in that include: A blower, a base, a connecting device, an air volume regulating valve, a first temperature sensor, a second temperature sensor and a temperature control device; The air volume regulating valve is installed on the branch pipe of the prefabricated T-beam to be tested, the blower is installed on the base and connected to the longitudinal prestressed channel of the T-beam to be tested through the connecting device, the first temperature sensor is installed at the outlet of the longitudinal prestressed channel of the T-beam to be tested, the second temperature sensor is installed on the surface of the T-beam to be tested, and the temperature control device is respectively connected to the first temperature sensor, the second temperature sensor, the blower and the air volume regulating valve; The blower is used to cool down the T-beam to be tested, the base is used to fix the blower, the air volume regulating valve is used to adjust the air supply volume of each prestressed channel, the first temperature sensor is used to obtain temperature data of each longitudinal prestressed channel of the T-beam to be tested, the second temperature sensor is used to obtain temperature data of the surface of the T-beam to be tested, and the temperature control device is used to obtain data from the first temperature sensor and data from the second temperature sensor and adjust the blower according to the data from the first temperature sensor and adjust the air volume regulating valve according to the data from the second temperature sensor.
2. According to claim 1, a wind-cooled temperature control system capable of reducing the temperature difference between inside and outside of a prefabricated T-beam during curing, It is characterized in that The connecting device comprises: Multiple branch pipes and main pipes connected to each other in a corresponding manner; Each main pipe is connected to the blower, and each branch pipe is correspondingly connected to the longitudinal prestressed channel of the T-beam to be tested.
3. The air-cooling temperature control system according to claim 2 that can reduce the temperature difference between the inside and outside of the prefabricated T-beam during curing, It is characterized in that An air volume regulating valve is installed on each branch pipe.
4. The air-cooling temperature control system according to claim 1 that can reduce the temperature difference between inside and outside of the prefabricated T-beam during curing, It is characterized in that The first temperature sensor is installed at a position 30 cm inward from the outlet of each longitudinal prestressed channel of the T-beam to be tested.
5. The air-cooling temperature control system according to claim 1 that can reduce the temperature difference between the inside and outside of the prefabricated T-beam during curing, It is characterized in that The second temperature sensor is installed at the mid-span of the surface of the T-beam to be measured.