River channel slope protection structure based on water conservancy and hydropower engineering design
By using fixed columns, studs, cone columns and screws in the river slope protection structure, the concrete layer is fixed in the soil, which solves the problem of offset and collapse of the concrete layer under the impact of water flow, and improves the stability of the river slope protection. and security.
Patent Information
- Application Number
- CN202420587306.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-26
- Publication Date
- 2024-11-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The concrete layer of the river slope protection in the existing hydropower engineering section is prone to deviation and collapse under long-term impact of water flow, and lacks effective fixing measures.
A river slope protection structure including concrete layer, fixed column, stud, conical column, screw, slider and support rod was designed. The conical column drilled into the soil layer, and the screw drove the slider to move, and the support rod was propped open and fixed to In the soil, strengthen the fixity of the concrete layer.
It effectively avoids the deviation and landslide of the concrete layer, improves the stability of the river slope protection, and ensures the safety of the slope.
Smart Images

Figure CN221941238U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of river channel slope protection, in particular to a river channel slope protection structure designed based on water conservancy and hydropower engineering. Background Art
[0002] River slope protection refers to slope protection projects on both sides of the river to prevent river bank erosion and maintain the stability and safety of the river. Slope protection projects generally include selecting appropriate slopes and materials, and reinforcing and protecting the slopes. In river slope protection projects in hydropower project sections, concrete will be used to reinforce and protect the slopes on both sides of the river. The concrete layer can effectively prevent river bank erosion and slope collapse, and improve the stability and safety of the river in the hydropower project section.
[0003] The above-mentioned and existing related technologies often have the following defects: when protecting the slopes on both sides of the river in the hydropower project section, concrete is usually used to pour on both sides. After the concrete solidifies, the concrete will protect the slopes on both sides to prevent landslides on the slopes on both sides. After the concrete layer is poured on the slope, the concrete layer has no grip on the slope, and the concrete layer is impacted by the water flow for a long time, which makes the concrete layer easily deviate.
[0004] Therefore, we propose a river slope protection structure based on the design of water conservancy and hydropower engineering. Utility Model Content
[0005] The utility model aims to provide a river slope protection structure designed based on water conservancy and hydropower engineering to solve the problems raised in the above-mentioned background technology.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a river slope protection structure designed based on water conservancy and hydropower engineering, comprising a concrete layer, a fixed column is fixedly connected to the surface of the concrete layer, a stud is detachably installed on the inner wall of the fixed column, a conical column is fixedly connected to one end of the stud, a first support rod is rotatably connected to the inner wall of the conical column, a screw is rotatably connected to the inner wall of the conical column, a slider is threadedly connected to the arc surface of the screw, and a second support rod is rotatably connected to the surface of the slider.
[0007] The effects achieved by the above components are as follows: when protecting the slope surface of the hydropower project section, the fixed column is fixed on the soil of the slope surface, and then concrete is poured on the slope surface. After the concrete solidifies, a concrete layer is formed, and the fixed column is fixed in the concrete layer. Then the cone column is inserted into the fixed column along the guide ring, and the first handle is installed on the stud. The stud is rotated, and the cone column will rotate in the fixed column and drill into the soil layer. When the stud completely enters the fixed column, the first handle is removed, the guide ring is removed, and then the second handle is engaged on the screw rod. The screw rod is rotated to drive the slider to move along the screw rod. The first support rod and the second support rod will rotate along the limit block, and the cone thorns will penetrate into the soil layer. The expanded first support rod and the second support rod will be buckled in the soil to fix the fixed column, thereby fixing the concrete layer on the slope surface to prevent the concrete layer from collapsing and shifting. After the installation is completed, the second handle is removed.
[0008] Preferably, a surface of the first support rod is rotatably connected to a limiting block, and the limiting block is rotatably connected to the second support rod.
[0009] The effect achieved by the above components is that the limiting block limits the moving paths of the first support rod and the second support rod, so that the first support rod and the second support rod are stably embedded in the soil.
[0010] Preferably, a cone thorn is fixedly connected to the surface of the limit block.
[0011] The effect achieved by the above components is that the cone thorns reduce the resistance of the limit block penetrating into the soil, making it easier for the first support rod and the second support rod to penetrate into the soil.
[0012] Preferably, a first handle is snap-connected to the surface of the stud, and a second handle is snap-connected to one end of the screw rod.
[0013] The effects achieved by the above components are: the first handle and the second handle facilitate the staff to rotate the stud and the screw.
[0014] Preferably, the surface of the first handle is covered with a first rubber cover, and the surface of the second handle is covered with a second rubber cover.
[0015] The effects achieved by the above components are: the first rubber pad on the first handle and the second rubber pad on the second handle make it difficult for the staff to slip when turning the first handle and the second handle.
[0016] Preferably, a pebble layer is fixedly connected to the surface of the concrete layer.
[0017] The effects achieved by the above components are: the pebble layer on the concrete layer can help slow down the water flow speed, reduce the erosion of the water flow on the concrete layer, and protect the stability of the concrete layer.
[0018] Preferably, a guide ring is detachably mounted on the surface of the fixing column.
[0019] The effect achieved by the above components is: the guide ring is installed on the fixed column, and the guide ring makes it convenient for the staff to install the cone column in the fixed column.
[0020] Compared with the prior art, the beneficial effects of the utility model are:
[0021] The utility model provides a concrete layer, a stud, a cone column, a fixed column, a screw rod, a slider, a first support rod and a second support rod, and drills the cone column into the soil layer. The screw rod drives the slider to move, and the slider spreads the first support rod and the second support rod and buckles them in the soil layer, thereby fixing and limiting the concrete layer, thereby improving the stability of the concrete layer laid on the slope to a certain extent, making the slope less likely to collapse. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0023] Figure 2 For the utility model Figure 1 Schematic diagram of the local structure;
[0024] Figure 3 It is a structural schematic diagram of the stud in the utility model;
[0025] Figure 4 For the utility model Figure 3 Schematic diagram of the split structure;
[0026] Figure 5 For the utility model Figure 4 Schematic diagram of the local structure;
[0027] Figure 6 It is a schematic diagram of the local structure of the cone column in the utility model;
[0028] Figure 7 It is a structural schematic diagram of the screw in the utility model.
[0029] In the figure: 1, concrete layer; 2, pebble layer; 3, fixed column; 4, stud; 5, cone column; 6, guide ring; 7, first handle; 8, second handle; 9, first support rod; 10, second support rod; 11, screw rod; 12, slider; 13, limit block; 14, cone thorn; 15, first rubber sleeve; 16, second rubber sleeve. DETAILED DESCRIPTION
[0030] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0031] See also Figure 1-Figure 7The utility model provides a technical solution: a river slope protection structure designed based on water conservancy and hydropower engineering, including a concrete layer 1, a fixed column 3 is fixedly connected to the surface of the concrete layer 1, a stud 4 is detachably installed on the inner wall of the fixed column 3, a cone column 5 is fixedly connected to one end of the stud 4, a first support rod 9 is rotatably connected to the inner wall of the cone column 5, a screw 11 is rotatably connected to the inner wall of the cone column 5, a slider 12 is threadedly connected to the arc surface of the screw 11, and a second support rod 10 is rotatably connected to the surface of the slider 12. When protecting the slope surface of the hydropower engineering section, the fixed column 3 is fixed on the soil of the slope surface, and then concrete is poured on the slope surface. After the concrete solidifies, a concrete layer 1 is formed, and the solidified The fixed column 3 is fixed in the concrete layer 1, and then the cone column 5 is inserted into the fixed column 3 along the guide ring 6, and the first handle 7 is installed on the stud 4. The stud 4 is rotated, and the cone column 5 will rotate in the fixed column 3 and drill into the soil layer. When the stud 4 completely enters the fixed column 3, the first handle 7 is removed, the guide ring 6 is removed, and then the second handle 8 is engaged with the screw rod 11. The screw rod 11 is rotated to drive the slider 12 to move along the screw rod 11, and the first support rod 9 and the second support rod 10 will rotate along the limit block 13, and the cone thorn 14 will penetrate into the soil layer. The first support rod 9 and the second support rod 10 that are stretched out will be buckled in the soil to fix the fixed column 3, thereby fixing the concrete layer 1 on the slope surface to avoid The concrete layer 1 collapses and deviates. After the installation is completed, the second handle 8 is removed. The surface of the first support rod 9 is rotatably connected to the limiting block 13. The limiting block 13 is rotatably connected to the second support rod 10. The limiting block 13 limits the moving paths of the first support rod 9 and the second support rod 10, so that the first support rod 9 and the second support rod 10 are stably inserted into the soil. The surface of the limiting block 13 is fixedly connected with a cone thorn 14. The cone thorn 14 will reduce the resistance of the limiting block 13 inserted into the soil, making it easier for the first support rod 9 and the second support rod 10 to penetrate into the soil. The surface of the stud 4 is snap-connected with the first handle 7, and one end of the screw rod 11 is snap-connected with the second handle 8. The first handle 7 and the second handle 8 are convenient for workers. The staff rotates the stud 4 and the screw 11, the surface of the first handle 7 is covered with a first rubber sleeve 15, the surface of the second handle 8 is covered with a second rubber sleeve 16, the first rubber pad on the first handle 7 and the second rubber pad on the second handle 8 make it difficult for the staff to slip when rotating the first handle 7 and the second handle 8, the surface of the concrete layer 1 is fixedly connected with a pebble layer 2, the pebble layer 2 on the concrete layer 1 can help slow down the water flow speed, reduce the erosion of the water flow on the concrete layer 1, and protect the stability of the concrete layer 1, the surface of the fixed column 3 is detachably installed with a guide ring 6, the guide ring 6 is installed on the fixed column 3, the guide ring 6 is convenient for the staff to install the cone column 5 in the fixed column 3.
[0032] Working principle: When protecting the slope of the hydropower project section, fix the fixed column 3 on the soil of the slope, then pour concrete on the slope, and after the concrete solidifies, a concrete layer 1 is formed. The fixed column 3 is fixed in the concrete layer 1, and the guide ring 6 is installed on the fixed column 3. The guide ring 6 facilitates the staff to install the cone column 5 in the fixed column 3, and then insert the cone column 5 into the fixed column 3 along the guide ring 6. Install the first handle 7 on the stud 4, turn the stud 4, and the cone column 5 will rotate in the fixed column 3 and drill into the soil layer. When the stud 4 is turned, the cone column 5 will rotate in the fixed column 3 and drill into the soil layer. The column 4 is completely inserted into the fixed column 3, the first handle 7 is removed, the guide ring 6 is removed, and then the second handle 8 is engaged with the screw 11. The screw 11 is rotated to drive the slider 12 to move along the screw 11. The first handle 7 and the second handle 8 are convenient for the staff to rotate the stud 4 and the screw 11. The first rubber pad on the first handle 7 and the second rubber pad on the second handle 8 make it difficult for the staff to slip when rotating the first handle 7 and the second handle 8. The first support rod 9 and the second support rod 10 will rotate along the limit block 13, and the limit block 13 is on the first support rod 9. The moving path of the second support rod 10 is limited, so that the first support rod 9 and the second support rod 10 are stably inserted into the soil, the cone thorn 14 will penetrate into the soil layer, and the cone thorn 14 will reduce the resistance of the limit block 13 penetrating into the soil, making it easier for the first support rod 9 and the second support rod 10 to penetrate into the soil. The spread first support rod 9 and the second support rod 10 will buckle in the soil to fix the fixing column 3, thereby fixing the concrete layer 1 on the slope to prevent the concrete layer 1 from collapsing and deviating. After the installation is completed, the second handle 8 is removed, and the pebble layer 2 on the concrete layer 1 can be In order to help slow down the speed of water flow, reduce the erosion of water flow on the concrete layer 1, and protect the stability of the concrete layer 1, by setting the concrete layer 1, the stud 4, the cone column 5, the fixed column 3, the screw 11, the slider 12, the first support rod 9 and the second support rod 10, the cone column 5 is drilled into the soil layer, and the slider 12 is driven to move by the screw 11. The slider 12 opens the first support rod 9 and the second support rod 10 and buckles them in the soil layer, thereby fixing and limiting the concrete layer 1. To a certain extent, the stability of the concrete layer 1 laid on the slope is improved, making the slope less likely to collapse.
[0033] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0034] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A river slope protection structure designed for water conservancy and hydropower engineering, comprising a concrete layer (1), characterized in that: A fixing column (3) is fixedly connected to the surface of the concrete layer (1); a stud (4) is detachably mounted on the inner wall of the fixing column (3); a conical column (5) is fixedly connected to one end of the stud (4); a first support rod (9) is rotatably connected to the inner wall of the conical column (5); a screw rod (11) is rotatably connected to the inner wall of the conical column (5); a slider (12) is threadedly connected to the arc surface of the screw rod (11); and a second support rod (10) is rotatably connected to the surface of the slider (12).
2. A river slope protection structure designed for water conservancy and hydropower engineering according to claim 1, characterized in that: The surface of the first support rod (9) is rotatably connected to a limiting block (13), and the limiting block (13) is rotatably connected to the second support rod (10).
3. The river slope protection structure designed for water conservancy and hydropower engineering according to claim 2 is characterized by: A cone thorn (14) is fixedly connected to the surface of the limiting block (13).
4. The river slope protection structure designed for water conservancy and hydropower engineering according to claim 1 is characterized by: A first handle (7) is snap-fitted to the surface of the stud (4), and a second handle (8) is snap-fitted to one end of the screw rod (11).
5. The river slope protection structure designed based on water conservancy and hydropower engineering according to claim 4 is characterized by: The surface of the first handle (7) is covered with a first rubber sleeve (15), and the surface of the second handle (8) is covered with a second rubber sleeve (16).
6. The river slope protection structure designed for water conservancy and hydropower engineering according to claim 1 is characterized by: A pebble layer (2) is fixedly connected to the surface of the concrete layer (1).