Automatic temperature control system for mass concrete construction
By installing temperature sensors and cooling water pipes on the concrete facade, combined with a PLC controller and audible and visual alarms, automated temperature control was achieved during the construction of large-volume concrete, solving the problems of temperature difference and cracking, and improving construction quality.
Patent Information
- Application Number
- CN202420394844.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-01
- Publication Date
- 2024-11-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The problems of temperature difference and cracking caused by improper temperature control in existing concrete construction are due to incomplete data collection, reliance on manual data collection, and untimely response of existing technologies.
Design an automated temperature control system for large-volume concrete construction. The system uses temperature sensors and cooling water pipes combined with a PLC controller to achieve real-time temperature monitoring and automated control. The system adjusts the opening and closing of the cooling water pipes through an electrically controlled valve and uses an audible and visual alarm to alert workers.
It enables real-time monitoring and automated control of the internal temperature of concrete, reducing cracks caused by temperature stress and improving concrete quality.
Smart Images

Figure CN221941346U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of temperature control in concrete construction, in particular to an automatic temperature control system for large-volume concrete construction. Background Art
[0002] In large-volume concrete construction, if the temperature is not properly controlled, temperature stress and uneven shrinkage caused by temperature difference may lead to cracks, seriously affecting the quality and safety of the building.
[0003] The principles of concrete temperature control are:
[0004] ①Try to reduce the temperature rise of concrete and delay the occurrence of the highest temperature;
[0005] ② Reduce the cooling rate;
[0006] ③ Reduce the temperature difference between the center and surface of concrete, between new and old concrete, and control the difference between the concrete surface and air temperature.
[0007] However, the existing concrete pouring temperature monitoring technology has the following defects: incomplete data collection, reliance on manual collection, untimely response, etc. Therefore, the utility model provides an automated temperature control system for large-volume concrete construction, which is of great significance for effectively managing the construction temperature of large-volume concrete and ensuring the quality of the project. Utility Model Content
[0008] In view of the deficiencies in the prior art, the utility model provides an automated temperature control system for large-volume concrete construction, which solves the problems raised by the above-mentioned background technology.
[0009] To achieve the above objectives, the utility model is implemented through the following technical solutions: an automated temperature control system for mass concrete construction, comprising a concrete facade and an insulation layer arranged on the surface of the concrete facade, wherein the upper, middle and lower parts of the concrete facade are each provided with a temperature control cross-sectional layer;
[0010] A layer of interconnected cooling water pipes and a temperature sensor are provided inside the concrete facade corresponding to each temperature control cross-sectional layer;
[0011] One end of each cooling water pipe is connected to a water inlet pipe, and the other end is connected to a water outlet pipe, and the water outlet pipe and the water inlet pipe are both provided with an electric control valve;
[0012] Temperature sensor three and temperature sensor two are respectively arranged inside the thermal insulation layer and outside the thermal insulation layer.
[0013] As a further technical solution of the utility model, it also includes a PLC controller and an audible and visual alarm connected to the PLC controller. The temperature sensor 1, the temperature sensor 2 and the temperature sensor 3 are all connected to the PLC controller through wires, and the PLC controller is connected to the electric control valve through wires.
[0014] As a further technical solution of the utility model, the cooling water pipe is a "bow" shaped structure, and the diameter of the cooling water pipe is 20-30 mm. The cooling water pipe is made of steel pipe or wire mesh plastic composite pipe or HDPE plastic pipe.
[0015] As a further technical solution of the utility model, there are three temperature sensors one and they correspond to three temperature control cross-sectional layers respectively. The detection probe of the temperature sensor two is located in the air outside the insulation layer for detecting the external temperature. The detection probe of the temperature sensor three extends to the interior of the insulation layer for detecting the temperature inside the insulation layer.
[0016] As a further technical solution of the present invention, the distances between the positions of the two temperature sensors corresponding to the lower and upper parts of the concrete facade and the bottom and top parts of the concrete facade are both 10 cm.
[0017] The utility model provides an automatic temperature control system for large-volume concrete construction, which has the following beneficial effects compared with the prior art:
[0018] This design of an automated temperature control system for large-volume concrete construction can realize real-time monitoring of the internal temperature of concrete during large-volume concrete construction. The temperature control indicators of the temperature difference between the interior and surface of the concrete and the temperature change rate every 4 hours can be used to control the opening and closing positions of the electric control valves on each layer of cooling water pipes in real time. When the temperature is abnormal, an alarm will be issued to remind the staff to deal with it and strengthen insulation measures. This effectively realizes automated temperature control during large-volume concrete construction, reduces the occurrence of cracks caused by temperature stress, and improves the quality of concrete. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a structural schematic diagram of an automated temperature control system for large-volume concrete construction.
[0020] In the figure: 1. Concrete facade; 2. Insulation layer; 3. Water outlet pipe; 4. Water inlet pipe; 5. Electric control valve; 6. Cooling water pipe; 7. Temperature sensor 1; 71. Temperature sensor 2; 72. Temperature sensor 3; 8. PLC controller; 9. Sound and light alarm. DETAILED DESCRIPTION
[0021] The technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0022] See also Figure 1 The utility model provides a technical solution for an automated temperature control system for large-volume concrete construction: an automated temperature control system for large-volume concrete construction, comprising a concrete facade 1 and an insulation layer 2 arranged on the surface of the concrete facade 1, wherein a temperature control cross-sectional layer is arranged at the upper, middle and lower parts of the concrete facade 1; a layer of interconnected cooling water pipes 6 (that is, the cooling water pipes 6 of this layer are laid in series in the concrete in a "bow" shape) and a temperature sensor 7 are arranged at each temperature control cross-sectional layer inside the concrete facade 1; one end of each cooling water pipe 6 is connected to a water inlet pipe 4, and the other end is connected to a water inlet pipe 4. One end is connected with a water outlet pipe 3, and an electric control valve 5 is provided on the water outlet pipe 3 and the water inlet pipe 4. The cooling water pipe 6 is a "bow"-shaped structure, and the diameter of the cooling water pipe 6 is 20-30 mm. The cooling water pipe 6 is made of a steel pipe or a steel wire mesh plastic composite pipe or a HDPE plastic pipe. The PLC controller 8 is connected to the electric control valve 5 through a wire. The three cooling water pipes 6 are distributed at three temperature control section layers respectively. The water inlet of each cooling water pipe 6 is independently controlled by the electric control valve 5 on the water inlet pipe 4 at one end thereof. The opening and closing gear of the electric control valve 5 on each layer of the cooling water pipe 6 can be controlled in real time through the PLC controller 8;
[0023] A temperature sensor 3 72 and a temperature sensor 2 71 are respectively arranged inside the insulation layer 2 and outside the insulation layer 2, and also include a PLC controller 8 and an audible and visual alarm 9 connected to the PLC controller 8. The temperature sensor 1 7, the temperature sensor 2 71 and the temperature sensor 3 72 are all connected to the PLC controller 8 through wires. It should be added that when each temperature sensor is installed, its detection probe (i.e., temperature sensor probe) shall not contact the steel bar. The detection probe of the temperature sensor 2 71 is located in the air outside the insulation layer 2 for detecting the external temperature (i.e., the ambient temperature). The detection probe of the temperature sensor 3 72 extends to the inside of the insulation layer 2 for detecting the temperature inside the insulation layer 2. The temperature sensor 1 7 and the temperature sensor 3 72 and the temperature sensor 3 72 have the same structural parameters, and are all conventional temperature sensors for detecting concrete temperature sold in the existing market. The PLC controller 8 is also a device sold in the market, which is a programmable memory, which stores instructions for performing operations such as logical operations, sequential control, timing, counting and arithmetic operations, controls the process through digital input and output, and integrates data acquisition, data processing and data output into one PLC controller;
[0024] Among them, the input of the PLC controller 8 is the temperature difference between each temperature measuring point inside the concrete (i.e., the temperature at each temperature control cross-sectional layer) and the surface, and the temperature change rate at the temperature measuring point every 4 hours. The output of the PLC controller 8 is the opening and closing gear of the electric control valve 5 on the water inlet pipe 4 of the cooling water pipe 6 at each temperature control cross-sectional layer, and the sound and light alarm 9. It should be noted that the electric control valve 5 of this design uses a solenoid valve with 6 gears sold on the market, and each gear can be opened at an angle of 60°; the input and output relationship table of the PLC controller 8 is as follows:
[0025]
[0026] It should be noted that during the process of burying and pouring the cooling water pipe 6 in the concrete, the water inlet pipe 4 and the water outlet pipe 3 both extend out of the concrete foundation surface by about 40 cm to facilitate water supply operations.
[0027] There are three temperature sensors 7, which correspond to three temperature control section layers respectively. The positions of the two temperature sensors 7 corresponding to the lower and upper parts of the concrete facade 1 are 10 cm away from the bottom and top of the concrete facade 1. That is to say, the three temperature sensors 7 laid at the three temperature control section layers corresponding to the inside of the concrete facade 1 are for measuring the temperature of the upper, middle and lower parts of the concrete facade 1 respectively, and the upper and lower temperature sensors 7 are both located 10 cm from the top and bottom of the concrete facade 1 to ensure the uniformity of temperature measurement and detection at the three temperature control section layers inside the concrete facade 1.
[0028] The working principle of the utility model is: in the three temperature control section layers of the large volume concrete facade 1, such as Figure 1 As shown, a, b, and c are respectively provided with a temperature sensor 7 and a layer of cooling water pipe 6, and the cooling water pipe 6 is laid in the concrete in a "bow" shape, that is, on the corresponding temperature control section layer by layer;
[0029] When in use, three temperature sensors 1 7 are used to monitor the temperature of each layer of the corresponding temperature-controlled section, that is, the temperature monitoring of the upper, middle and lower parts of the concrete (concrete facade 1), and the temperature sensor 2 71 is used to detect the external environmental temperature, and the temperature sensor 3 72 is used to detect the temperature inside the insulation layer 2. The temperature data detected by each temperature sensor will be synchronously transmitted to the PLC controller 8, which controls the opening of the electric control valve 5 on each layer of the cooling water pipe 6 according to the temperature change data;
[0030] When the maximum temperature of large-volume concrete after pouring exceeds 75°C, or the difference between the internal center temperature of the concrete structure and the surface temperature of the concrete exceeds 25°C, or the temperature of each measuring point in the temperature-controlled section layer drops by more than 10°C, the PLC controller 8 will control the sound and light alarm 9 to alarm, reminding the staff to take measures and strengthen insulation measures, effectively realizing the automated temperature control during the construction of large-volume concrete, reducing the occurrence of cracks caused by temperature stress, and improving the quality of concrete.
[0031] The above is only a preferred embodiment of the present invention. It should be noted that, for ordinary technicians in the technical field, several improvements and modifications can be made without departing from the principle of the present invention, and these improvements and modifications should also be regarded as the protection scope of the present invention. The structures, devices and operating methods not specifically described and explained in the present invention shall be implemented according to the conventional means in the field unless otherwise specified and limited.
Claims
1. An automated temperature control system for mass concrete construction, comprising a concrete facade (1) and an insulation layer (2) arranged on the surface of the concrete facade (1), characterized in that: The upper, middle and lower parts of the concrete facade (1) are each provided with a temperature control cross-sectional layer; A layer of interconnected cooling water pipes (6) and a temperature sensor (7) are provided inside the concrete facade (1) corresponding to each temperature control cross-sectional layer; One end of each cooling water pipe (6) is connected to a water inlet pipe (4), and the other end is connected to a water outlet pipe (3), and an electric control valve (5) is provided on each of the water outlet pipe (3) and the water inlet pipe (4); A third temperature sensor (72) and a second temperature sensor (71) are respectively arranged inside the thermal insulation layer (2) and outside the thermal insulation layer (2).
2. The automatic temperature control system for mass concrete construction according to claim 1 is characterized in that: It also includes a PLC controller (8) and an audible and visual alarm (9) connected to the PLC controller (8), wherein the temperature sensor 1 (7), the temperature sensor 2 (71) and the temperature sensor 3 (72) are all connected to the PLC controller (8) via wires, and the PLC controller (8) is connected to the electric control valve (5) via wires.
3. The automatic temperature control system for mass concrete construction according to claim 1 is characterized in that: The cooling water pipe (6) is a "bow"-shaped structure, and the diameter of the cooling water pipe (6) is 20-30 mm. The cooling water pipe (6) is made of a steel pipe, a steel wire mesh plastic composite pipe, or a HDPE plastic pipe.
4. The automatic temperature control system for mass concrete construction according to claim 1 is characterized in that: The number of the temperature sensors 1 (7) is three and they correspond to three temperature control cross-sectional layers respectively; the detection probe of the temperature sensor 2 (71) is located in the air outside the thermal insulation layer (2) for detecting the external temperature; the detection probe of the temperature sensor 3 (72) extends into the interior of the thermal insulation layer (2) for detecting the temperature inside the thermal insulation layer (2).
5. The automatic temperature control system for mass concrete construction according to claim 1 is characterized in that: The positions of the two temperature sensors 1 (7) corresponding to the lower and upper parts of the concrete facade (1) are both 10 cm away from the bottom and top of the concrete facade (1).