Waterproof and drainage system for highway tunnel corrugated steel preliminary bracing structure
By designing a combined drainage prevention system of arch corrugated steel initial support layer, longitudinal drainage pipe group, transverse drainage pipe group and circumferential drainage pipe group in the corrugated steel initial support structure in the highway tunnel, the initial support structure of corrugated steel is solved. Preventing drainage problems has achieved the effect of effectively reducing groundwater seepage and induction, and extending the service life of the tunnel.
Patent Information
- Application Number
- CN202420407295.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-04
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2034-03-04
AI Technical Summary
The initial support structure of corrugated steel in highway tunnels lacks an effective drainage system, which leads to groundwater seepage into the tunnel, reducing the durability and service life of the structure.
A drainage system including the initial support layer of the arch corrugated steel, a longitudinal drainage pipe group, a transverse drainage pipe group and annular drainage pipe group were designed. The rubber water stop belt, waterproof mortar and multiple drainage pipe combinations were formed. Three waterproof lines block, drain and drain water layer by layer, effectively reducing groundwater seepage and outlet.
It effectively reduces the phenomenon of groundwater seeping out of the surrounding rock of the tunnel into the tunnel, ensures timely drainage of groundwater, prevents groundwater from harming the tunnel structure, and extends the service life of the tunnel.
Smart Images

Figure CN221942512U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of initial corrugated steel support for highway tunnels, in particular to a drainage system for initial corrugated steel support structures for highway tunnels. Background Art
[0002] As the preferred road construction scheme through mountainous areas, highway tunnels can shorten the operating distance and improve the transportation capacity, and are an important part of the transportation infrastructure construction. However, many highway tunnels in my country have a certain degree of groundwater damage problems, which will reduce the durability of the highway tunnel lining structure and shorten the service life of the highway tunnel. Therefore, in order to ensure the long-term operation of the highway tunnel, it is necessary to set up a drainage system for the initial support structure of the highway tunnel.
[0003] At present, the waterproofing and drainage system of the steel frame concrete initial support structure of highway tunnels has been developed to maturity, while the waterproofing and drainage system of the corrugated steel initial support structure of highway tunnels that has been newly adopted in recent years still needs to be improved. Based on this, it is necessary to invent a waterproofing and drainage system for the corrugated steel initial support structure of highway tunnels. Utility Model Content
[0004] The utility model provides a drainage prevention system for the initial corrugated steel supporting structure of a highway tunnel in order to solve the drainage prevention problem of the initial corrugated steel supporting structure.
[0005] The utility model is realized by adopting the following technical solutions:
[0006] A drainage and waterproofing system for a corrugated steel primary support structure of a highway tunnel, comprising an arched corrugated steel primary support layer, a longitudinal drainage pipe group, a transverse drainage pipe group and a circumferential drainage pipe group;
[0007] The arched corrugated steel initial support layer comprises a plurality of corrugated steels, which are paved into the arched corrugated steel initial support layer by means of longitudinal lap bolts and circumferential bolt splicing; a rubber water stop is arranged between two corrugated steels butted against each other by longitudinal lap bolts and circumferential bolt splicing; a waterproof mortar is filled between the arched corrugated steel initial support layer and the external tunnel surrounding rock;
[0008] The longitudinal drainage pipe group includes two longitudinal drainage pipes I and two longitudinal drainage pipes II; the transverse drainage pipe group includes two transverse drainage pipes I and two transverse drainage pipes II; the annular drainage pipe group includes multiple annular drainage pipes I and multiple annular drainage pipes II;
[0009] Two longitudinal drainage pipes I are respectively arranged at the two outer arch feet of the arched corrugated steel initial support layer, and a number of water-permeable holes are opened in the upper half arc of each longitudinal drainage pipe I; two transverse drainage pipes I are evenly distributed in the tunnel, and one end of each transverse drainage pipe I passes through the arched corrugated steel initial support layer and is connected to the longitudinal drainage pipe I on the corresponding side, and the other end of each transverse drainage pipe I extends to the central ditch of the tunnel; multiple annular drainage pipes I are evenly arranged on the outer surface of the arched corrugated steel initial support layer, and the two ends of each annular drainage pipe I extend above the longitudinal drainage pipe I on the corresponding side;
[0010] The two longitudinal drainage pipes II are respectively arranged at the two inner arch feet of the arched corrugated steel initial support layer; the two transverse drainage pipes II are evenly distributed in the tunnel, and one end of each transverse drainage pipe II is connected to the longitudinal drainage pipe II on the corresponding side, and the other end of each transverse drainage pipe II extends to the central ditch of the tunnel; multiple annular drainage pipes II are evenly arranged on the inner surface of the arched corrugated steel initial support layer, and the two ends of each annular drainage pipe II are respectively connected to the longitudinal drainage pipe II on the corresponding side.
[0011] Furthermore, a connecting steel plate is prefabricated and welded at the edge of each corrugated steel, and each connecting steel plate is provided with a connecting hole. When two adjacent corrugated steels are circumferentially bolted together, they are fixed together by bolts passing through the two connecting holes. A rubber waterstop is arranged between the two bolted connecting steel plates, and waterproof mortar is filled between the corrugated steel and the external tunnel surrounding rock.
[0012] Furthermore, the multiple annular drainage pipes I are all spring semicircular drainage pipes.
[0013] Furthermore, each transverse drainage pipe I is connected to the longitudinal drainage pipe I on the corresponding side through a tee, and each transverse drainage pipe I is installed with the aid of a 45° elbow when socketing the tee; the two ends of each annular drainage pipe II are respectively connected to the longitudinal drainage pipe II on the corresponding side through a tee.
[0014] The structural design of the utility model is reasonable and reliable. The drainage system is divided into three waterproof lines, including the outer waterproof line of the arched corrugated steel initial support layer, the waterproof line of the arched corrugated steel initial support layer itself and the inner waterproof line of the arched corrugated steel initial support layer; the three waterproof lines form a reliable drainage system of blocking, diverting and draining, which is arranged layer by layer, and can effectively reduce the occurrence of groundwater seeping from the tunnel surrounding rock infiltrating into the tunnel, and timely divert and discharge the groundwater that has infiltrated the tunnel to prevent groundwater from harming the tunnel structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a structural schematic diagram of the utility model.
[0016] Figure 2 It is a schematic diagram of the initial supporting layer of the arched corrugated steel in the utility model.
[0017] Figure 3 It is a schematic diagram of the corrugated steel annular bolt splicing in the utility model.
[0018] Figure 4 It is a schematic diagram of longitudinal bolt overlap of corrugated steel in the utility model.
[0019] Figure 5 It is a schematic diagram of the positional relationship between the arched corrugated steel initial support layer and the concrete layer in the utility model.
[0020] Figure 6 is along Figure 1 Sectional view along line BB.
[0021] Figure 7 yes Figure 1 A local enlarged schematic diagram of point A in the middle.
[0022] In the figure: 1-arched corrugated steel initial support layer, 11-corrugated steel, 12-rubber waterstop, 13-connecting steel plate, 14-waterproof mortar, 21-longitudinal drainage pipe I, 22-longitudinal drainage pipe II, 31-transverse drainage pipe I, 32-transverse drainage pipe II, 41-annular drainage pipe I, 42-annular drainage pipe II, 5-tunnel center ditch. DETAILED DESCRIPTION
[0023] A drainage and waterproofing system for a corrugated steel primary support structure of a highway tunnel, comprising an arched corrugated steel primary support layer 1, a longitudinal drainage pipe group, a transverse drainage pipe group and a circumferential drainage pipe group;
[0024] The arched corrugated steel initial support layer 1 comprises a plurality of corrugated steels 11, which are paved into the arched corrugated steel initial support layer 1 by means of longitudinal lap bolts and circumferential bolt splicing; a rubber water stop 12 is arranged between two corrugated steels 11 butted against each other by longitudinal lap bolts and circumferential bolt splicing; a waterproof mortar 14 is filled between the arched corrugated steel initial support layer 1 and the external tunnel surrounding rock;
[0025] The longitudinal drainage pipe group includes two longitudinal drainage pipes I21 and two longitudinal drainage pipes II22; the transverse drainage pipe group includes two transverse drainage pipes I31 and two transverse drainage pipes II32; the annular drainage pipe group includes multiple annular drainage pipes I41 and multiple annular drainage pipes II42;
[0026] Two longitudinal drainage pipes I21 are respectively arranged at the two outer arch feet of the arched corrugated steel initial support layer 1, and a plurality of water-permeable holes are opened in the upper half arc of each longitudinal drainage pipe I21; two transverse drainage pipes I31 are evenly distributed in the tunnel, and one end of each transverse drainage pipe I31 passes through the arched corrugated steel initial support layer 1 and is connected to the longitudinal drainage pipe I21 on the corresponding side, and the other end of each transverse drainage pipe I31 extends to the central ditch 5 of the tunnel; multiple annular drainage pipes I41 are evenly arranged on the outer surface of the arched corrugated steel initial support layer 1, and the two ends of each annular drainage pipe I41 extend above the longitudinal drainage pipe I21 on the corresponding side;
[0027] The two longitudinal drainage pipes II22 are respectively arranged at the two inner arch feet of the arched corrugated steel initial support layer 1, and the two transverse drainage pipes II32 are evenly distributed in the tunnel, and one end of each transverse drainage pipe II32 is connected to the longitudinal drainage pipe II22 on the corresponding side, and the other end of each transverse drainage pipe II32 extends to the central ditch 5 of the tunnel; multiple annular drainage pipes II42 are evenly arranged on the inner surface of the arched corrugated steel initial support layer 1, and the two ends of each annular drainage pipe II42 are respectively connected to the longitudinal drainage pipe II22 on the corresponding side.
[0028] As attached Figure 3 As shown, the edge of each corrugated steel 11 is prefabricated and welded with a connecting steel plate 13, and each connecting steel plate 13 is provided with a connecting hole. When two adjacent corrugated steels 11 are spliced with circumferential bolts, they are fixed by bolts passing through the two connecting holes. A rubber waterstop 12 is arranged between the two bolted connecting steel plates 13, and waterproof mortar 14 is filled between the corrugated steel 11 and the external tunnel surrounding rock.
[0029] The multiple annular drainage pipes I41 are all spring semicircular drainage pipes.
[0030] Each transverse drainage pipe I31 is connected to the longitudinal drainage pipe I21 on the corresponding side through a tee. When each transverse drainage pipe I31 is inserted into the tee, it is installed with the aid of a 45° elbow. The two ends of each annular drainage pipe II42 are respectively connected to the longitudinal drainage pipe II22 on the corresponding side through a tee.
[0031] When groundwater seeps out of the tunnel surrounding rock outside the arched corrugated steel initial support layer 1, the water first flows through the drainage of multiple annular drainage pipes I41 to the two longitudinal drainage pipes I21, and then flows through the two transverse drainage pipes I31, and flows to the tunnel center ditch 5 through each transverse drainage pipe I31. This is the first waterproof line. Under the action of the first waterproof line, most of the groundwater seeping out of the tunnel surrounding rock has been discharged; and a rubber water stop 12 is provided between each two mutually connected corrugated steels 11 in the arched corrugated steel initial support layer 1, and at the same time The corrugated steel plate itself is also waterproof, which can block the groundwater remaining on the outer surface of the arched corrugated steel initial support layer 1 to a certain extent. This is the second waterproof line; if the groundwater remaining on the outer surface of the arched corrugated steel initial support layer 1 penetrates into the inner surface of the arched corrugated steel initial support layer 1, this part of the groundwater will flow to the two longitudinal drainage pipes II22 through the drainage of multiple annular drainage pipes II42, and then be diverted to flow through two transverse drainage pipes II32, and flow to the central ditch 5 of the tunnel through each transverse drainage pipe II32. This is the third waterproof line.
[0032] In the specific implementation process, the two ends of the two longitudinal drainage pipes I21 and the two longitudinal drainage pipes II22 are both 1m beyond the tunnel opening, and each longitudinal drainage pipe I21 and each longitudinal drainage pipe II22 are connected by a two-way pipe; the two transverse drainage pipes I31 are 6m apart, the two adjacent annular drainage pipes I41 are 5m apart, and the two transverse drainage pipes II32 are 9m apart; the multiple annular drainage pipes II42 are fixed to the inner surface of the arched corrugated steel initial support layer 1 with the help of special clamps;
[0033] The two longitudinal drainage pipes I21 are both φ100HDPE double-wall corrugated pipes, the two transverse drainage pipes I31 are both φ100HDPE corrugated pipes, the two longitudinal drainage pipes II22, the two transverse drainage pipes II32, and the multiple annular drainage pipes II42 are all φ50HDPE double-wall corrugated pipes. This type of pipe has the significant advantages of high pressure resistance, good toughness and good durability; the rubber waterstop 12 adopts a 1cm thick 50-degree rubber waterstop strip; the bolts adopt M20 high-strength bolts; the connecting steel plate 13 adopts a 9mm thick steel plate.
[0034] A longitudinal drainage pipe inspection well is set up at the tee pipe every 50m to check and clear the pipes; the longitudinal drainage pipe group, transverse drainage pipe group, annular drainage pipe group and tee pipe are wrapped with non-woven permeable geotextile to prevent mud and sand from entering the pipe due to damage to the pipe surface during construction; if the pipe is found to be blocked, it can be cleared from the longitudinal drainage pipe inspection well.
[0035] In the description of the present invention, it is necessary to understand that the indicated orientation or positional relationship is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0036] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A drainage system for the initial corrugated steel support structure of a highway tunnel. Features: It comprises an arched corrugated steel primary support layer (1), a longitudinal drainage pipe group, a transverse drainage pipe group and an annular drainage pipe group; The arched corrugated steel initial support layer (1) comprises a plurality of corrugated steels (11), which are laid out into the arched corrugated steel initial support layer (1) by means of longitudinal lap bolts and circumferential bolt splicing; a rubber water stop strip (12) is provided between two corrugated steels (11) that are butt-jointed by longitudinal lap bolts and circumferential bolt splicing; and a waterproof mortar (14) is filled between the arched corrugated steel initial support layer (1) and the external tunnel surrounding rock; The longitudinal drainage pipe group includes two longitudinal drainage pipes I (21) and two longitudinal drainage pipes II (22); the transverse drainage pipe group includes two transverse drainage pipes I (31) and two transverse drainage pipes II (32); the annular drainage pipe group includes a plurality of annular drainage pipes I (41) and a plurality of annular drainage pipes II (42); Two longitudinal drainage pipes I (21) are respectively arranged at the two outer arch feet of the arched corrugated steel initial support layer (1), and a plurality of water permeable holes are opened in the upper half arc of each longitudinal drainage pipe I (21); two transverse drainage pipes I (31) are evenly distributed in the tunnel, and one end of each transverse drainage pipe I (31) passes through the arched corrugated steel initial support layer (1) and is connected to the longitudinal drainage pipe I (21) on the corresponding side, and the other end of each transverse drainage pipe I (31) extends to the central ditch (5) of the tunnel; multiple annular drainage pipes I (41) are evenly arranged on the outer surface of the arched corrugated steel initial support layer (1), and the two ends of each annular drainage pipe I (41) extend above the longitudinal drainage pipe I (21) on the corresponding side; Two longitudinal drainage pipes II (22) are respectively arranged at the two inner arch feet of the arched corrugated steel initial support layer (1); two transverse drainage pipes II (32) are evenly distributed in the tunnel, and one end of each transverse drainage pipe II (32) is connected to the longitudinal drainage pipe II (22) on the corresponding side, and the other end of each transverse drainage pipe II (32) extends to the tunnel center ditch (5); multiple annular drainage pipes II (42) are evenly arranged on the inner surface of the arched corrugated steel initial support layer (1), and the two ends of each annular drainage pipe II (42) are respectively connected to the longitudinal drainage pipe II (22) on the corresponding side.
2. A drainage system for a corrugated steel primary support structure of a highway tunnel according to claim 1, Features: A connection steel plate (13) is prefabricated and welded to the edge of each corrugated steel (11), and each connection steel plate (13) is provided with a connection hole. When two adjacent corrugated steels (11) are spliced and fixed by bolts passing through the two connection holes, a rubber water stop strip (12) is arranged between the two bolted connection steel plates (13), and waterproof mortar (14) is filled between the corrugated steel (11) and the external tunnel surrounding rock.
3. A drainage and waterproofing system for a corrugated steel primary support structure of a highway tunnel according to claim 1, Features: The multiple annular drainage pipes I (41) are all spring semicircular drainage pipes.
4. A drainage and waterproofing system for a corrugated steel primary support structure of a highway tunnel according to claim 1, Features: Each transverse drainage pipe I (31) is connected to the longitudinal drainage pipe I (21) on the corresponding side through a tee pipe. When each transverse drainage pipe I (31) is connected to the tee pipe, a 45° elbow is used to assist in installation. Both ends of each annular drainage pipe II (42) are respectively connected to the longitudinal drainage pipe II (22) on the corresponding side through a tee pipe.