Fabricated building comprehensive pipeline structure based on BIM

Through BIM technology and the integrated pipeline structure of prefabricated buildings, different types of pipelines are integrated and mounting brackets and brackets are designed, the problems of waste of space and low installation efficiency of traditional building pipelines are solved, and efficient space utilization and convenient maintenance are achieved.

CN221943420UActive Publication Date: 2024-11-01ANHUI ELECTRIC POWER DESIGN INST CEEC
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421194671.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-29
Publication Date
2024-11-01
Estimated Expiration
2034-05-29

AI Technical Summary

Technical Problem

The separate laying of traditional building pipelines leads to problems such as waste of space, low installation quality and efficiency, and difficulty in maintenance, and lacks a unified layout and integration plan.

Method used

Adopt BIM-based comprehensive pipeline structure of prefabricated buildings, build three-dimensional models through BIM technology, plan pipeline paths, integrate different types of pipelines, design components such as mounting frames, auxiliary brackets and fixing rings to ensure easy installation and maintenance, and through buffer pads and damping rods reduce stress and vibration.

Benefits of technology

It improves the efficiency of building space utilization, installation accuracy, reduces costs, simplifies post-maintenance and transformation, and realizes flexible updates and optimization of pipeline structures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221943420U_ABST
    Figure CN221943420U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of constructional engineering, and particularly relates to a BIM (Building Information Modeling)-based fabricated building comprehensive pipeline structure which comprises a mounting frame mounted at the lower part of a floor slab, a closing plate mounted at the bottom of the mounting frame, and a spacing plate mounted in the mounting frame, the interior of the mounting frame is divided into a first mounting channel and a second mounting channel through the partition plate, auxiliary supports are arranged on the two sides of the mounting frame, side plates are mounted on the side faces of the auxiliary supports, different types of pipelines are integrated, the assembly type characteristic is achieved, mounting and overhauling are facilitated, a three-dimensional model is established through the BIM technology, pipeline paths are planned, collision is prevented, and the construction efficiency is improved. By means of the BIM technology, the utilization efficiency of building pipelines is improved, the utilization efficiency of building space is improved, the BIM technology can provide convenience for subsequent maintenance and transformation, and the pipeline structure can be easily updated and optimized by modifying the BIM model.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of building engineering, and specifically relates to a BIM-based assembled building integrated pipeline structure. Background Art

[0002] Building pipelines are an important part of construction projects, usually including water pipes, air ducts, electrical bridges and other parts. Traditional building pipelines are usually laid separately, and different types of pipelines are prone to collision. The lack of a unified layout causes space waste, resulting in reduced building space utilization, low installation quality and efficiency, and difficult maintenance. BIM technology and building information modeling provide a building digital twin model, which can use BIM to perform three-dimensional design of building pipelines and plan pipeline paths to avoid collisions. Therefore, it is necessary to set up a prefabricated building integrated pipeline structure based on BIM to integrate different types of pipelines to save building space to the maximum extent. At the same time, the integrated pipeline has the characteristics of prefabrication, easy installation, and some components are detachable, which is conducive to the later maintenance of pipelines. The BIM technology is used to establish a three-dimensional model of the integrated pipeline, and the size of the integrated pipeline is adjusted according to the needs of the building pipeline, and the pipeline path is planned to prevent collisions. At the same time, the engineering volume of the building integrated pipeline is counted to improve the accuracy of pipeline installation, which is conducive to reducing costs, improving the utilization efficiency of building pipelines, and improving the space utilization efficiency of buildings. Summary of the invention

[0003] In view of the shortcomings of the existing technology, the utility model provides a BIM-based prefabricated building integrated pipeline structure, which integrates different types of pipelines and has the characteristics of assembly, which is conducive to installation and maintenance. It also establishes a three-dimensional model through BIM technology, plans the pipeline path, prevents collisions, improves the utilization efficiency of building pipelines, improves the utilization efficiency of building space, and solves the problems in the above background.

[0004] To achieve the above objectives, the utility model is implemented through the following technical solutions: a BIM-based prefabricated building integrated pipeline structure, including a mounting frame installed at the bottom of the floor, a closing plate installed at the bottom of the mounting frame, a partition plate installed inside the mounting frame, the partition plate divides the interior of the mounting frame into a first mounting channel and a second mounting channel, auxiliary brackets are arranged on both sides of the mounting frame, and side panels are installed on the sides of the auxiliary brackets.

[0005] Preferably, a fixing ring is installed inside the first installation channel, a damping rod is connected to the fixing ring, the other end of the damping rod is connected to the second support rod, the other end of the second support rod is connected to the third connecting plate, and the third connecting plate is fixedly arranged on the mounting frame.

[0006] Preferably, the fixing ring comprises an upper fixing ring and a lower fixing ring, buffer pads are arranged inside the upper fixing ring and the lower fixing ring, and the upper fixing ring and the lower fixing ring are fixedly connected by a first bolt.

[0007] Preferably, the mounting frame is fixedly mounted on the lower part of the floor slab via a first screw, and a fixing block is provided between the mounting frame and the floor slab.

[0008] Preferably, a second connecting plate is provided on the top of the auxiliary bracket, a first supporting rod is connected to the second connecting plate, one end of the first supporting rod is connected to the first connecting plate, and the first connecting plate is fixedly arranged at the lower part of the floor slab.

[0009] Preferably, an L-shaped connector is fixedly installed on the upper side of the auxiliary bracket by a second bolt, the other side of the L-shaped connector is fixedly connected to the mounting frame by a second bolt, and a horizontal connector is fixedly installed on the lower side of the auxiliary bracket and the mounting frame by a second bolt.

[0010] Preferably, a fourth connecting plate is provided on the upper portion of the second installation channel, the fourth connecting plate is fixedly connected to the vertical plate, and the vertical plate is fixedly connected to the horizontal plate via a third bolt.

[0011] Preferably, the closing plate is fixedly mounted on the mounting frame by a second screw.

[0012] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention proposes a BIM-based prefabricated building integrated pipeline structure, which integrates different types of pipelines and has the characteristics of assembly, which is conducive to installation and maintenance. It also uses BIM technology to establish a three-dimensional model, plan the pipeline path, prevent collisions, improve the utilization efficiency of building pipelines, and improve the utilization efficiency of building space. BIM technology can also facilitate subsequent maintenance and renovation. By modifying the BIM model, the pipeline structure can be easily updated and optimized.

[0013] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 This is a schematic diagram of a BIM-based prefabricated building integrated pipeline structure.

[0015] In the figure: 1. floor; 2. mounting frame; 21. partition plate; 22. first screw rod; 23. L-shaped connector; 24. second bolt; 25. horizontal connector; 3. closing plate; 31. second screw rod; 4. first mounting channel; 41. fixing ring; 411. upper fixing ring; 412. lower fixing ring; 413. first bolt; 414. buffer pad; 42. damping rod; 43. second support rod; 44. third connecting plate; 5. second mounting channel; 51. fourth connecting plate; 52. vertical plate; 53. third bolt; 54. horizontal plate; 6. auxiliary bracket; 61. side plate; 62. second connecting plate; 63. first support rod; 64. first connecting plate; 7. fixing block. DETAILED DESCRIPTION

[0016] The following is a detailed description of the implementation of the utility model in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the utility model, but cannot be used to limit the scope of the utility model. All other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0017] refer to Figure 1As shown, a prefabricated building integrated pipeline structure based on BIM includes a mounting frame 2 installed at the bottom of a floor 1, a closing plate 3 is installed at the bottom of the mounting frame 2, a partition plate 21 is installed inside the mounting frame 2, and the partition plate 21 divides the inside of the mounting frame 2 into a first installation channel 4 and a second installation channel 5, and auxiliary brackets 6 are arranged on both sides of the mounting frame 2, and side panels 61 are installed on the sides of the auxiliary brackets 6. Specifically, a prefabricated building integrated pipeline structure based on BIM is designed to achieve efficient and accurate prefabrication and installation processes through BIM (Building Information Modeling) technology. The structure starts with the floor 1, which is the foundation of the entire pipeline structure. Through BIM technology, the load-bearing capacity and structural layout of the floor 1 can be accurately calculated and simulated to ensure the safety and stability of the pipeline structure installed later. At the bottom of the floor 1, a mounting frame 2 is installed. The design of the mounting frame 2 takes into account the layout, size and installation convenience of the pipeline, and is optimized through BIM technology to ensure its structural strength and stability. A closing plate 3 is installed at the bottom of the mounting frame 2. The main function of the closing plate 3 is to close the bottom of the mounting frame 2, prevent dust, debris, etc. from entering the interior of the mounting frame, and ensure the neatness and safety of the pipeline structure. A partition plate 21 is installed inside the mounting frame 2. The function of the partition plate 21 is to separate the interior of the mounting frame 2 into two independent channels, the first installation channel 4 and the second installation channel 5. This design allows different types of pipelines (such as water pipes, wire pipes, etc.) to be installed in two channels respectively, avoiding the confusion and intersection of pipelines, and improving the clarity of pipeline layout and the convenience of maintenance. Auxiliary brackets 6 are provided on both sides of the mounting frame 2. These auxiliary brackets 6 not only enhance the overall stability of the mounting frame 2, but also provide additional support for the fixing and installation of pipelines. Side panels 61 are installed on the sides of the auxiliary brackets 6. The main function of the side panels 61 is to prevent the pipeline from being displaced or slipping during installation and use, and also help to keep the pipeline structure neat and beautiful. Through the application of BIM technology, the design, manufacturing and installation processes of this prefabricated building integrated pipeline structure have been greatly optimized. BIM technology can accurately simulate each part of the pipeline structure, including its size, location, connection method, etc., to ensure accuracy and efficiency during the actual installation process. In addition, BIM technology can also facilitate subsequent maintenance and renovation. By modifying the BIM model, the pipeline structure can be easily updated and optimized.

[0018] refer to Figure 1As shown, a fixing ring 41 is installed inside the first installation channel 4, and a damping rod 42 is connected to the fixing ring 41. The other end of the damping rod 42 is connected to the second support rod 43, and the other end of the second support rod 43 is connected to the third connecting plate 44, and the third connecting plate 44 is fixedly arranged on the mounting frame 2. Specifically, a fixing ring 41 is installed inside the first installation channel 4. The material of the fixing ring 41 is usually selected from high-strength and corrosion-resistant materials to ensure that it can withstand the weight of the pipeline and the influence of the external environment for a long time. The fixing ring 41 is ensured to fit closely with the inner wall of the first installation channel 4 through precise design and installation, thereby providing a stable support point. One end of the damping rod 42 is connected to the fixing ring 41. This design allows the damping rod 42 to be fine-tuned according to the vibration or displacement of the pipeline, thereby reducing the stress generated by the pipeline due to external force. The material of the damping rod 42 is usually selected from materials with certain elasticity and damping properties, such as rubber or polymer composite materials, to provide appropriate buffering and shock absorption effects. The other end of the damping rod 42 is connected to the second support rod 43. As a key part of the entire support system, the length and angle of the second support rod 43 are carefully calculated and designed to ensure that it can provide stable and balanced support for the pipeline. The material of the second support rod 43 also needs to have high strength and corrosion resistance to meet the needs of different environments and working conditions. The other end of the second support rod 43 is connected to the third connecting plate 44, and the third connecting plate 44 is fixedly arranged on the mounting frame 2. This design enables the entire support system to be firmly fixed on the mounting frame 2 to avoid loosening or displacement during use. The third connecting plate 44 is usually fixed to the mounting frame 2 by welding, bolting or other reliable connection methods to ensure its stability and safety. Overall, the design of this support system fully considers the stability, safety and flexibility of the pipeline. Through the synergistic effect of the fixing ring 41, the damping rod 42, the second support rod 43 and the third connecting plate 44, a stable and balanced support can be provided for the pipeline, while reducing the stress and vibration caused by external forces. This design not only improves the service life and safety of the pipeline, but also reduces the cost of maintenance and replacement.

[0019] refer to Figure 1As shown, the fixing ring 41 includes an upper fixing ring 411 and a lower fixing ring 412, and a buffer pad 414 is arranged inside the upper fixing ring 411 and the lower fixing ring 412, and the upper fixing ring 411 and the lower fixing ring 412 are fixedly connected by a first bolt 413. Specifically, the fixing ring 41 consists of two parts, namely the upper fixing ring 411 and the lower fixing ring 412. This design allows for more flexibility and convenience during installation and removal, and is also convenient for maintenance and replacement. Buffer pads 414 are arranged inside the upper fixing ring 411 and the lower fixing ring 412. The function of the buffer pad 414 is mainly to provide additional protection and buffering for the pipeline, and prevent the pipeline from being worn or damaged due to direct contact with the fixing ring 41. The material of the buffer pad 414 is usually selected from soft, wear-resistant and elastic materials, such as rubber or silicone. The upper fixing ring 411 and the lower fixing ring 412 are fixedly connected by a first bolt 413. This connection method is simple and reliable, and can effectively connect the upper fixing ring 411 and the lower fixing ring 412 tightly together to form a complete fixing ring structure. The selection of the first bolt 413 needs to consider factors such as its strength, corrosion resistance and installation convenience to ensure the stability and safety of the fixing ring. During the installation process, the pipeline is first placed between the upper fixing ring 411 and the lower fixing ring 412, and then the upper fixing ring 411 and the lower fixing ring 412 are tightly connected together using the first bolt 413. During the connection process, it is necessary to ensure that the buffer pad 414 fits tightly with the pipeline to provide sufficient buffering and protection. After the installation is completed, the fixing ring 41 will be firmly connected to the mounting frame 2 through the damping rod 42, the second support rod 43 and the third connecting plate 44, providing stable and balanced support for the pipeline. By setting the upper fixing ring 411, the lower fixing ring 412 and the buffer pad 414, the fixing ring 41 can better adapt to pipelines of different diameters and shapes, and provide more stable and uniform support. At the same time, the presence of the buffer pad 414 can effectively reduce the stress caused by vibration or displacement of the pipeline and extend the service life of the pipeline. In addition, the modular design of the fixing ring 41 also makes its installation, disassembly and maintenance more convenient and efficient.

[0020] refer to Figure 1As shown, the mounting frame 2 is fixedly mounted on the lower part of the floor 1 by the first screw 22, and a fixing block 7 is arranged between the mounting frame 2 and the floor 1. Specifically, the mounting frame 2 is fixedly mounted on the lower part of the floor 1 by the first screw 22. This connection method ensures the stability and reliability of the mounting frame 2, so that it can remain stable when bearing the weight of the pipeline and the influence of the external environment. The selection of the first screw 22 needs to consider its material, strength and corrosion resistance to ensure the safety and reliability of long-term use. A fixing block 7 is also arranged between the mounting frame 2 and the floor 1. The function of the fixing block 7 is to further increase the connection strength and stability between the mounting frame 2 and the floor 1. The material and shape of the fixing block 7 need to be selected and designed according to the actual situation to ensure that it can effectively disperse and bear the load transmitted by the mounting frame 2. During installation, first determine the exact position of the mounting frame 2 on the floor 1, and drill a hole in the floor 1. Then, place the fixing block 7 between the floor 1 and the mounting frame 2, and use the first screw 22 to tightly connect the mounting frame 2, the fixing block 7 and the floor 1. During the connection process, it is necessary to ensure that the tightening force of the first screw 22 is moderate to avoid safety hazards caused by over-tightening or over-loosening. Through the coordinated use of the first screw 22 and the fixing block 7, the mounting frame 2 can be firmly installed at the bottom of the floor 1, providing a solid foundation for subsequent pipeline installation. This connection method is not only simple and easy, but also safe and reliable, and can meet the high requirements of prefabricated buildings for pipeline installation.

[0021] refer to Figure 1As shown, the top of the auxiliary bracket 6 is provided with a second connecting plate 62, and the second connecting plate 62 is connected to the first support rod 63, and one end of the first support rod 63 is connected to the first connecting plate 64, and the first connecting plate 64 is fixedly arranged at the lower part of the floor 1. Specifically, the auxiliary bracket 6, as an important supporting structure of the mounting frame 2, not only enhances the stability of the overall pipeline structure, but also provides additional fixing and supporting points. A second connecting plate 62 is provided at the top of the auxiliary bracket 6. The second connecting plate 62 serves as a connecting bridge, connecting the auxiliary bracket 6 and the first support rod 63, and plays a role of connecting the upper and lower parts. The first support rod 63 is connected to the second connecting plate 62, which is the main supporting component of the auxiliary bracket 6. The material and size selection of the first support rod 63 need to be determined according to the overall weight, stress conditions and installation environment of the pipeline structure to ensure that it has sufficient load-bearing capacity and stability. One end of the first support rod 63 is connected to the first connecting plate 64 by a certain connection method (such as welding, bolt connection, etc.). The first connecting plate 64 is fixedly arranged at the lower part of the floor 1, and it plays the role of firmly connecting the auxiliary bracket 6 to the floor 1. Through the first connecting plate 64, the auxiliary bracket 6 can effectively transfer the weight of the pipeline it bears to the floor 1, ensuring the stability and safety of the entire pipeline structure. This design makes the auxiliary bracket 6 not only have a supporting function, but also can disperse the weight of the pipeline structure to the floor 1 through the connection between the first support rod 63 and the first connecting plate 64, thereby reducing the local pressure of the floor 1 and improving the stability and durability of the entire structure. At the same time, this design also makes the installation and disassembly process more convenient and quick, and improves the construction efficiency.

[0022] refer to Figure 1As shown, the upper side of the auxiliary bracket 6 is fixedly installed with an L-shaped connector 23 by a second bolt 24, and the other side of the L-shaped connector 23 is fixedly connected to the mounting frame 2 by the second bolt 24. The auxiliary bracket 6 and the mounting frame 2 are fixedly installed with a horizontal connector 25 by the second bolt 24 on the lower side. Specifically, in order to enhance the connection stability and structural strength between the auxiliary bracket 6 and the mounting frame 2, we introduced a variety of connection methods during the design. On the upper side of the auxiliary bracket 6, we used an L-shaped connector 23 to ensure a stable connection between the two. One end of the L-shaped connector 23 is tightly fixed to the auxiliary bracket 6 by the second bolt 24, and the other end is also fixedly connected to the mounting frame 2 by the second bolt 24. This design not only provides support in the vertical direction, but also can resist the force in the horizontal direction to a certain extent, thereby increasing the stability of the entire structure. At the same time, in order to further improve the reliability and safety of the connection, we also designed a horizontal connector 25 on the lower side of the auxiliary bracket 6 and the mounting frame 2. The horizontal connector 25 is fixedly connected to the auxiliary bracket 6 and the mounting frame 2 respectively by the second bolt 24, forming a support structure in the horizontal direction. This design can effectively prevent the mounting frame 2 from shaking or shifting when subjected to external forces, thereby ensuring the stability and safety of the pipeline structure. In summary, through the coordinated use of the L-shaped connector 23 and the horizontal connector 25, we have achieved a stable connection between the auxiliary bracket 6 and the mounting frame 2. This connection method is not only simple and easy, but also has a stable structure, safety and reliability, and can meet the high requirements of prefabricated buildings for pipeline installation. At the same time, this design also has certain flexibility and scalability, and can be adjusted and modified according to actual needs.

[0023] refer to Figure 1As shown, a fourth connecting plate 51 is provided on the upper part of the second installation channel 5, and a vertical plate 52 is fixedly connected to the fourth connecting plate 51, and a horizontal plate 54 is fixedly connected to the vertical plate 52 by a third bolt 53. Specifically, a fourth connecting plate 51 is provided on the upper part of the second installation channel 5. The fourth connecting plate 51 not only plays a role of connection and support, but also serves as a fixing basis for subsequent installation components. It is made of high-strength, corrosion-resistant materials to ensure stable performance and reliable connection during long-term use. On the fourth connecting plate 51, we fixedly connect the vertical plate 52. The vertical plate 52 is vertically arranged with the fourth connecting plate 51, and a stable connection between the two is ensured by welding, bolt connection or other reliable connection methods. The height and width of the vertical plate 52 are determined according to actual needs and design requirements to meet the installation requirements of subsequent components. On the vertical plate 52, we further fixedly connect the horizontal plate 54 by a third bolt 53. The horizontal plate 54 is arranged parallel to the vertical plate 52 to form a horizontal support surface. This design not only increases the stability of the entire structure, but also facilitates the installation of subsequent components. The material of the horizontal plate 54 also needs to be selected from high-strength, corrosion-resistant materials to ensure its reliability and durability during use. Through the above design, the upper part of the second installation channel 5 forms a stable structure consisting of the fourth connecting plate 51, the vertical plate 52 and the horizontal plate 54. This structure not only provides additional support and fixing points for the installation of the pipeline, but also can flexibly adjust the position and direction of the pipeline according to actual needs. At the same time, due to the use of high-strength, corrosion-resistant materials and reliable connection methods, the entire structure has high stability and durability, and can meet the requirements of long-term use.

[0024] refer to Figure 1As shown, the closing plate 3 is fixedly mounted on the mounting frame 2 by the second screw 31. Specifically, the closing plate 3 is used to close or cover certain pipe parts that do not need to be directly accessed or exposed to ensure the safe, neat and efficient operation of the system. In this set of pipeline system, the closing plate 3 is designed to be fixedly mounted on the mounting frame 2 by the second screw 31. As a key component connecting the closing plate 3 and the mounting frame 2, the material, size and strength of the second screw 31 are carefully selected and designed to ensure the stability and reliability of the connection. During the installation process, it is first necessary to predetermine the installation position of the closing plate 3 on the mounting frame 2 and drill the corresponding installation hole at this position. Then, the second screw 31 is passed through the corresponding hole position on the closing plate 3 and screwed into the mounting hole on the mounting frame 2, and the screw is tightened using an appropriate tool (such as a screwdriver, a wrench, etc.) until the closing plate 3 is firmly fixed on the mounting frame 2. This installation method is not only simple and easy, but also highly flexible and adjustable. By adjusting the tightening degree of the second screw 31, it can be ensured that the connection between the closing plate 3 and the mounting frame 2 is tight and gapless, thereby effectively preventing dust, moisture or other impurities from entering the interior of the pipeline system and affecting the normal operation of the system. At the same time, this connection method is also convenient for subsequent maintenance and replacement work. When the closing plate 3 needs to be removed or replaced, it can be easily completed by simply rotating the second screw 31 in the opposite direction. In short, the second screw 31 is used to fix the closing plate 3 on the mounting frame 2, which not only ensures the safety and reliability of the pipeline system, but also improves the overall performance and operating efficiency of the system.

[0025] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A BIM-based prefabricated building integrated pipeline structure, comprising a mounting frame (2) mounted on the lower part of a floor slab (1), a closing plate (3) being mounted on the bottom of the mounting frame (2), characterized in that: A partition plate (21) is installed inside the mounting frame (2), and the partition plate (21) divides the inside of the mounting frame (2) into a first mounting channel (4) and a second mounting channel (5). Auxiliary brackets (6) are arranged on both sides of the mounting frame (2), and side plates (61) are installed on the sides of the auxiliary brackets (6).

2. The BIM-based prefabricated building integrated pipeline structure according to claim 1 is characterized in that: A fixing ring (41) is installed inside the first installation channel (4), a damping rod (42) is connected to the fixing ring (41), the other end of the damping rod (42) is connected to a second support rod (43), the other end of the second support rod (43) is connected to a third connecting plate (44), and the third connecting plate (44) is fixedly arranged on the installation frame (2).

3. The BIM-based prefabricated building integrated pipeline structure according to claim 2 is characterized in that: The fixing ring (41) comprises an upper fixing ring (411) and a lower fixing ring (412), a buffer pad (414) is provided inside the upper fixing ring (411) and the lower fixing ring (412), and the upper fixing ring (411) and the lower fixing ring (412) are fixedly connected by a first bolt (413).

4. The BIM-based prefabricated building integrated pipeline structure according to claim 3 is characterized in that: The mounting frame (2) is fixedly mounted on the lower part of the floor slab (1) via a first screw rod (22), and a fixing block (7) is provided between the mounting frame (2) and the floor slab (1).

5. The BIM-based prefabricated building integrated pipeline structure according to claim 4 is characterized in that: A second connecting plate (62) is provided on the top of the auxiliary bracket (6), a first supporting rod (63) is connected to the second connecting plate (62), one end of the first supporting rod (63) is connected to the first connecting plate (64), and the first connecting plate (64) is fixedly arranged at the bottom of the floor slab (1).

6. The BIM-based prefabricated building integrated pipeline structure according to claim 5 is characterized in that: An L-shaped connecting piece (23) is fixedly mounted on the upper side of the auxiliary bracket (6) via a second bolt (24); the other side of the L-shaped connecting piece (23) is fixedly connected to the mounting frame (2) via a second bolt (24); and a horizontal connecting piece (25) is fixedly mounted on the lower side of the auxiliary bracket (6) and the mounting frame (2) via a second bolt (24).

7. The BIM-based prefabricated building integrated pipeline structure according to claim 6 is characterized in that: A fourth connecting plate (51) is provided on the upper portion of the second installation channel (5), the fourth connecting plate (51) is fixedly connected to a vertical plate (52), and a horizontal plate (54) is fixedly connected to the vertical plate (52) via a third bolt (53).

8. The BIM-based prefabricated building integrated pipeline structure according to claim 7 is characterized in that: The closing plate (3) is fixedly mounted on the mounting frame (2) via a second screw rod (31).