By setting specific connection blocks and connection structures on the slope protection bricks of water conservancy projects, the installation difficulty of slope protection plates and soil erosion are solved, and convenient installation and high stability slope protection effect are achieved.
Patent Information
- Application Number
- CN202420519101.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-18
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2034-03-18
AI Technical Summary
It is difficult to accurately grasp the position of the slope protection plate during installation of existing water conservancy projects, resulting in excessive interference or gaps, affecting the fixing effect, and there are problems such as straight joints leading to soil erosion.
Design a slope protection structure for water conservancy projects. By setting lower connection blocks, upper connection blocks, connecting blocks and connecting grooves on the four side walls of slope protection bricks, horizontally adjacent bricks are adjacent to the upper connection blocks and vertically through the lower connection blocks. The brick body cooperates with the connecting grooves to form an integral structure, and arc notches and arc grooves are provided at the corners to fix the piles, reducing straight joints and improving stability.
It realizes convenient installation of slope protection plates, reduces soil erosion, improves the stability and drainage efficiency of slope protection bricks, and ensures slope protection effect.
Smart Images

Figure CN221956642U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of slope protection, in particular to a water conservancy project slope protection structure. Background Art
[0002] In water conservancy projects, slope protection is a crucial engineering measure. It is not only used to protect the stability and safety of water conservancy facilities such as river banks and embankments, but also effectively reduce the erosion of land by water flow and protect the ecological balance of the surrounding environment. With the acceleration of urbanization and the impact of climate change, the demand for slope protection in water conservancy projects is increasing day by day, becoming an important part of ensuring water resource security and ecological environment.
[0003] A Chinese utility model patent with publication number CN112392003A discloses a water conservancy project slope protection, including a slope body, a plurality of slope protection boards laid on the slope body, anchor rods arranged on the slope protection boards, the anchor rods are plugged into the slope body, and one end of the anchor rods away from the slope body is pre-buried in the slope protection boards. The slope protection boards are fixed by moving the anchor rods to plug into the slope body.
[0004] With respect to the above-mentioned related technologies, the inventors believe that there are the following defects: when installing the slope protection board, the above-mentioned scheme needs to insert the anchor rod into the slope before the slope protection board can fit with the slope. In this way, it is difficult to grasp the position between the slope protection boards when laying multiple slope protection boards, which often causes the slope protection boards to interfere with each other or the gap is too large. At this time, it is necessary to knock the slope protection boards to make the side walls of adjacent slope protection bricks fit together, but this will cause the anchor rod to shift in the slope, affecting the fixation of the slope protection board; in addition, there is a straight seam between two adjacent slope protection boards, and rainwater or water flow can easily enter from the straight seam, causing soil erosion at the joint, causing the slope protection board to sag and affecting the slope protection effect. Utility Model Content
[0005] In order to solve the above problems, the utility model provides a water conservancy project slope protection structure.
[0006] The above technical purpose of the utility model is achieved through the following technical solutions: a water conservancy project slope protection structure, including a plurality of slope protection bricks spliced with each other, and fixed piles nailed into the slope body are arranged at the intersection corners of four adjacent slope protection bricks, the slope protection bricks include a brick body, the lower half of one side wall of the brick body protrudes outward and is provided with a lower connecting block, the upper half of the side wall of the brick body on the side opposite to the lower connecting block protrudes outward and is provided with an upper connecting block, and the lower half of the side wall of the brick body located between the lower connecting block and the upper connecting block protrudes outward and is provided with a connecting block, The lower half of the side wall of the brick body on one side opposite to the connecting block is recessed inwardly and is provided with a connecting groove that cooperates with the connecting block. The lower connecting block is vertically provided with a first arc notch at the corners at both ends away from the brick body, and the upper connecting block is provided with an arc groove toward the brick body at the corners at both ends away from the brick body. The arc groove and the lower half of the corresponding corner of the brick body form a step shape, and a second arc notch is vertically provided on the corner of the lower half of the brick body located at the step. The arc radii of the first arc notch and the second arc notch are consistent, and the corresponding central angle of the arc is 90 degrees.
[0007] By adopting the above technical scheme, lower connecting blocks, upper connecting blocks, connecting blocks and connecting grooves are respectively arranged on the four side walls of the brick body, the lower connecting blocks and upper connecting blocks of two horizontally adjacent slope protection bricks cooperate with each other, and the connecting blocks and connecting grooves of two vertically adjacent slope protection bricks cooperate with each other, so that a number of slope protection bricks are spliced into a whole, and the slope protection bricks are directly laid on the slope body, and it is only necessary to cooperate with each other between the two adjacent brick bodies, which is convenient for installation; there is no long connecting seam between the two adjacent slope protection bricks that directly passes through the slope body, so that no water flow will directly wash onto the slope body to cause soil erosion, thereby ensuring the slope protection effect; and by setting the first arc notch and the second arc notch, a round hole is formed at the corner of the slope protection brick when a number of slope protection bricks are spliced, and then the fixing pile is nailed into the slope body from the round hole to fix the slope protection brick on the slope body, thereby improving the overall stability of the slope protection brick.
[0008] Furthermore, the thickness of the lower connecting block and the upper connecting block is half of the thickness of the brick body.
[0009] By adopting the above technical solution, the thickness of the lower connecting block and the upper connecting block is set to half the thickness of the brick body. On the one hand, the overall thickness of the lower connecting block and the upper connecting block after matching is consistent with the thickness of the brick body, and there will be no empty layer phenomenon; on the other hand, the lower connecting block and the upper connecting block can be tightly fitted together, which can prevent water from washing onto the slope from the connection.
[0010] Furthermore, the width of the lower connecting block is greater than the width of the upper connecting block, and the lower connecting blocks of two adjacent slope protection bricks cooperate with the upper connecting blocks to form a drainage groove.
[0011] By adopting the above technical solution, the width of the lower connecting block is set to be greater than the width of the upper connecting block, so that the lower connecting blocks of two adjacent slope protection bricks cooperate with the upper connecting blocks to form a drainage ditch, thereby draining rainwater and water on the slope from the drainage ditch.
[0012] Furthermore, the fixed pile includes a pile body and an end cover, the radius of the pile body is consistent with the radius of the first arc notch, the radius of the end cover is consistent with the radius of the arc groove, and the thickness of the end cover is consistent with the height of the wall of the arc groove.
[0013] By adopting the above technical solution, the pile body and the end cover are arranged, so that after the pile body is nailed into the slope,
[0014] The end cap is pressed on the corner joint of the slope protection brick to stably fix the slope protection brick on the slope.
[0015] Furthermore, the pile body includes a straight cylinder portion and a pointed portion, the lower end cylinder wall of the straight cylinder portion is divided into four vertical arc walls, wherein the bottom ends of two relatively arc walls are fixedly connected to the pointed portion, and the inner sides of the other two arc walls are provided with oblique wedge-shaped push blocks, and an inner rod is provided in the cylinder cavity of the straight cylinder portion, the upper end of the inner rod is passed through the end cover, and the lower end is overall in a cone shape with a taper consistent with the inclination of the push block.
[0016] By adopting the above technical solution, a straight tube part, a pointed part, an arc wall, a push block and an inner rod are provided. After the pile body is nailed into the soil layer, the inner rod is moved downward by knocking, thereby pushing the push block to squeeze the arc wall outward, thereby increasing the contact area between the arc wall and the soil layer and increasing the stability of the pile body.
[0017] Furthermore, a circular groove is provided on the end cover, a through hole is provided at the bottom of the circular groove, the upper end of the inner rod passes through the inner hole and the end is lower than the upper end surface of the end cover, the rod diameter of the part of the inner rod located in the circular groove gradually increases from the bottom surface of the circular groove to the groove mouth of the circular groove, and a drainage outlet is opened on the groove wall of the circular groove.
[0018] By adopting the above technical solution, the diameter of the inner rod located in the circular groove is set to gradually increase from the bottom surface of the circular groove to the groove opening of the circular groove, so that after the inner rod is knocked into the hole, an interference fit is formed, so that the inner rod will not rebound. By setting a drain port, water can be discharged after flowing into the circular groove.
[0019] Furthermore, a vertical planting opening is provided at the center of the slope protection brick pile body, and a protective net is provided at the bottom of the planting opening.
[0020] By adopting the above technical solution, setting the planting opening and the protection net, plants can be planted in the planting opening to increase soil and water conservation, reduce water erosion on the soil, prevent soil and water loss, and protect water sources. When the plant is just planted and the root system is not yet developed, the soil is fixed by the protection net.
[0021] In summary, the utility model has the following beneficial effects: in the present application, lower connecting blocks, upper connecting blocks, connecting blocks and connecting grooves are respectively arranged on the four side walls of the brick body, and the lower connecting blocks and upper connecting blocks of two horizontally adjacent slope protection bricks cooperate with each other, and the connecting blocks and connecting grooves of two vertically adjacent slope protection bricks cooperate with each other, so that a plurality of slope protection bricks are spliced into a whole, and the slope protection bricks are directly laid on the slope body, and it is only necessary to cooperate with each other between the two adjacent brick bodies, which is convenient for installation; there is no long connecting seam between the two adjacent slope protection bricks that directly passes through the slope body, so that no water flow will directly wash onto the slope body to cause soil erosion, thereby ensuring the slope protection effect; and by setting the first arc notch and the second arc notch, a plurality of slope protection bricks are spliced to form a circular hole at the corner of the slope protection brick, and then the fixing pile is nailed into the slope body from the circular hole to fix the slope protection brick on the slope body, thereby improving the overall stability of the slope protection brick. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the utility model;
[0023] Figure 2 This is a schematic diagram of the splicing structure of four slope protection bricks in the embodiment of the utility model;
[0024] Figure 3 This is a schematic diagram of the structure of the slope protection bricks of the utility model embodiment;
[0025] Figure 4 This is a schematic structural diagram of the slope protection bricks of the utility model embodiment from another angle;
[0026] Figure 5 It is a structural schematic diagram of a fixed pile in an embodiment of the utility model;
[0027] Figure 6 It is a cross-sectional schematic diagram of a fixed pile according to an embodiment of the utility model.
[0028] In the figure: 1. slope protection brick; 2. fixed pile; 10. brick body; 11. lower connecting block; 12. upper connecting block; 13. connecting block; 14. connecting groove; 15. first arc notch; 16. arc groove; 17. second arc notch; 18. drainage groove; 19. round hole; 20. pile body; 21. straight tube; 22. pointed part; 23. arc wall; 24. push block; 25. inner rod; 30. end cover; 31. circular groove; 32. drainage outlet; 40. planting outlet; 41. protection net. DETAILED DESCRIPTION
[0029] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application; obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments, and all other embodiments obtained by ordinary technicians in this field based on the embodiments in the present application without making creative work are within the scope of protection of the present application.
[0030] like Figure 1-6 As shown, an embodiment of the present application discloses a water conservancy project slope protection structure, including slope protection bricks 1 and fixed piles 2. The slope protection is laid on the slope. When laying, two adjacent slope protection bricks 1 are spliced with each other, and the joints of four adjacent slope protection bricks 1 are fixed by fixed piles 2 to form a whole, thereby improving the stability of the slope protection bricks 1.
[0031] Specifically, the slope protection brick 1 includes a brick body 10, and a lower connecting block 11 is provided on the lower half of one side wall of the brick body 10, and the thickness of the lower connecting block 11 is half the thickness of the brick body 10. An upper connecting block 12 is provided on the upper half of the side wall of the brick body 10 on the side opposite to the lower connecting block 11, and the thickness of the upper connecting block 12 is half the thickness of the brick body 10. When paving, the lower connecting block 11 and the upper connecting block 12 of two laterally adjacent slope protection bricks 1 cooperate with each other to form a transverse whole. The thickness of the lower connecting block 11 and the upper connecting block 12 is set to half the thickness of the brick body 10. On the one hand, the overall thickness of the lower connecting block 11 and the upper connecting block 12 after cooperation is consistent with the thickness of the brick body 10, and there will be no empty layer phenomenon; on the other hand, the lower connecting block 11 and the upper connecting block 12 can be tightly fitted, so that water can be prevented from washing onto the slope from the connection. Furthermore, the width of the lower connecting block 11 is set to be greater than the width of the upper connecting block 12, so that after the lower connecting block 11 of two horizontally adjacent slope protection bricks 1 cooperate with the upper connecting block 12, there will be a gap between the upper connecting block 12 and the brick body 10 of the adjacent slope protection brick 1, so that the side wall of the upper connecting block 12, the side wall of the brick body 10 and the upper side of the lower connecting block 11 together form a vertically arranged drainage groove 18, so that rainwater and water on the slope bank can be discharged along the drainage groove 18, thereby improving drainage efficiency. The lower half of the side wall of the brick body 10 located between the lower connecting block 11 and the upper connecting block 12 is provided with a connecting block 13 protruding outward, and the lower half of the side wall of the brick body 10 on the side opposite to the connecting block 13 is provided with a connecting groove 14 that cooperates with the connecting block 13. When installing the two vertically adjacent slope protection bricks 1, the connecting block 13 and the connecting groove 14 cooperate with each other, thereby forming a vertical whole. When paving, the connecting block 13 faces the downhill direction of the slope. Through the cooperation of the upper connecting block 12 and the lower connecting block 11 and the cooperation of the connecting block 13 and the connecting groove 14, a plurality of slope protection bricks 1 are spliced into a whole. The slope protection bricks 1 are directly laid on the slope. It is only necessary to cooperate with each other between two adjacent brick bodies 10, which is convenient for installation. There is no long connection seam between two adjacent slope protection bricks 1 that directly passes through the slope, so that no water flow will directly wash onto the slope to cause water and soil loss, thereby ensuring the slope protection effect.
[0032] A first arc notch 15 is vertically arranged at the corners of both ends of the lower connecting block 11 away from the brick body 10, and an arc groove 16 is opened toward the brick body 10 at the corners of both ends of the upper connecting block 12 away from the brick body 10. The arc groove 16 forms a step shape with the lower half of the corresponding corner of the brick body 10, and a second arc notch 17 is vertically arranged on the lower half corner of the brick body 10 located at the step. The arc radius of the first arc notch 15 and the second arc notch 17 are consistent and the central angle of the arc is 90 degrees. In this way, after the four adjacent slope protection bricks 1 are spliced, the first arc notches 16 of two bricks and the second arc notches 17 of the other two bricks together form a circular hole 19. At the same time, the arc grooves 16 of the two bricks are also spliced together to form a large groove.
[0033] The fixed pile 2 includes a pile body 20 and an end cap 30. The pile body 20 includes a straight tube portion 21 and a tip portion 22. The radius of the straight tube portion 21 is consistent with the radius of the first arc notch 15 and the second arc notch 17, so that the straight tube portion 21 can pass through the circular hole 19 formed by the two first arc notches 15 and the two second arc notches 16 to reach the slope. The lower end wall of the straight tube portion 21 is divided into four vertical arc walls 23, wherein the bottom ends of the two arc walls 23 are fixedly connected to the tip portion 22, so that the pile body 20 is easier to be nailed into the soil layer. An oblique wedge-shaped push block 24 is arranged on the inner side of the other two arc walls 23, and an inner rod 25 is arranged in the cylinder cavity of the straight cylinder part 21. The upper end of the inner rod 25 passes through the end cover 30, and the lower end is generally conical with the same taper as the push block 24. In this way, by knocking the inner rod 25 to move downward, the push block 24 can be pushed outward to cause the arc wall 23 to deform and push outward, thereby increasing the contact area between the arc wall 23 and the soil layer, and increasing the stability of the pile body 20.
[0034] A circular groove 31 is provided on the end cover 30, and a through hole is provided at the bottom of the circular groove 31. The upper end of the inner rod 25 passes through the inner hole and the end is lower than the upper end surface of the end cover 30. The rod diameter of the portion of the inner rod 25 located in the circular groove 31 gradually increases from the bottom surface of the circular groove 31 to the notch direction of the circular groove 31, so that after the inner rod 25 is knocked into the through hole, an interference fit is formed, so that the inner rod 25 will not rebound. A drainage port 32 is also provided on the groove wall of the circular groove 31. When specifically set, the bottom of the drainage port 32 is in a horizontal state, so that water can be discharged after flowing into the circular groove 31. The radius of the end cover 30 is consistent with the radius of the arc groove 16, so that after the fixing pile 2 is nailed in, the outer wall of the end cover 30 contacts the arc groove 16. The thickness of the end cover 30 is consistent with the height of the groove wall of the arc groove 16, so that after the fixing pile 2 is nailed in, its top surface is flush with the top surface of the end cover 30, which is more beautiful.
[0035] A vertical planting opening 40 is provided at the center of the pile body 20 of the slope protection brick 1, and a protective net 41 is provided at the bottom of the planting opening 40. Plants can be planted in the planting opening 40 to increase soil and water conservation, reduce water erosion on the soil, prevent soil and water loss, and protect water sources. When the plant is just planted and the root system is not yet developed, the soil is fixed by the protective net 41.
[0036] The use principle of a water conservancy project slope protection structure in this embodiment is as follows: when the slope protection bricks 1 are laid on the slope, the lower connecting blocks 11 and the upper connecting blocks 12 of two adjacent slope protection bricks 1 in the horizontal direction cooperate with each other, and the connecting blocks 13 and the connecting grooves 14 of two adjacent slope protection bricks 1 in the vertical direction cooperate with each other, so that a number of slope protection bricks 1 are spliced into a whole, so that a circular hole 19 will be formed at the corner after the adjacent four slope protection bricks 1 are spliced. Then, the fixing pile 2 is nailed into the slope through the circular hole 19, and the end cover 30 presses down the splicing of the adjacent four slope protection bricks 1 to fix the slope protection brick 1 on the slope. Then, by knocking the inner rod 25 downward, the inner rod 25 pushes the push block 24 outward, and the arc wall 23 is deformed and pushed outward, increasing the contact area between the arc wall 23 and the soil layer, thereby improving the stability of the entire slope protection structure.
[0037] The above is only a preferred embodiment of the present invention. The protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.
Claims
1. A water conservancy project slope protection structure, characterized by: The invention comprises a plurality of slope protection bricks (1) connected to each other, wherein a fixing pile (2) driven into the slope body is arranged at the intersection corners of four adjacent slope protection bricks (1), wherein the slope protection brick (1) comprises a brick body (10), wherein a lower connecting block (11) is arranged on the lower half of one side wall of the brick body (10) protruding outward, and an upper connecting block (12) is arranged on the upper half of the side wall of the brick body (10) on the side opposite to the lower connecting block (11), and a connecting block (13) is arranged on the lower half of the side wall of the brick body (10) located between the lower connecting block (11) and the upper connecting block (12), and wherein the lower half of the side wall of the brick body (10) on the side opposite to the connecting block (13) is arranged on the lower half of the side wall of the brick body (10) protruding outward, and wherein the lower half of the side wall of the brick body (10) on the side opposite to the connecting block (13) is arranged on the lower half of the side wall of the brick body (10) protruding inward. The depression is provided with a connecting groove (14) matched with the connecting block (13); the lower connecting block (11) is vertically provided with a first arc notch (15) at the two end corners away from the brick body (10); the upper connecting block (12) is provided with an arc groove (16) at the two end corners away from the brick body (10) in the direction of the brick body (10); the arc groove (16) and the lower half of the corresponding corner of the brick body (10) form a step shape; the lower half corner of the brick body (10) located at the step is vertically provided with a second arc notch (17); the arc radii of the first arc notch (15) and the second arc notch (17) are consistent, and the corresponding central angle of the arc is 90 degrees.
2. A water conservancy project slope protection structure according to claim 1, characterized in that: The thickness of the lower connecting block (11) and the upper connecting block (12) are both half the thickness of the brick body (10).
3. A water conservancy project slope protection structure according to claim 1, characterized in that: The width of the lower connecting block (11) is greater than the width of the upper connecting block (12), and the lower connecting blocks (11) and the upper connecting blocks (12) of two adjacent slope protection bricks (1) cooperate to form a drainage groove (18).
4. The water conservancy project slope protection structure according to claim 1 is characterized in that: The fixed pile (2) comprises a pile body (20) and an end cover (30), the radius of the pile body (20) is consistent with the radius of the first circular arc notch (15), the radius of the end cover (30) is consistent with the radius of the circular arc groove (16), and the thickness of the end cover (30) is consistent with the height of the groove wall of the circular arc groove (16).
5. A water conservancy project slope protection structure according to claim 4, characterized in that: The pile body (20) comprises a straight tube portion (21) and a pointed portion (22). The lower end wall of the straight tube portion (21) is divided into four vertical arc walls (23), wherein the bottom ends of two relatively arc walls (23) are fixedly connected to the pointed portion (22), and the inner sides of the other two arc walls (23) are provided with oblique wedge-shaped push blocks (24). An inner rod (25) is provided in the tube cavity of the straight tube portion (21), wherein the upper end of the inner rod (25) passes through the end cover (30) and the lower end is in a cone shape whose taper is consistent with the inclination of the push block (24).
6. A water conservancy project slope protection structure according to claim 5, characterized in that: The end cover (30) is provided with a circular groove (31), the bottom of the circular groove (31) is provided with a through hole, the upper end of the inner rod (25) passes through the inner hole and the end is lower than the upper end surface of the end cover (30), the rod diameter of the portion of the inner rod (25) located in the circular groove (31) gradually increases from the bottom surface of the circular groove (31) to the groove opening of the circular groove (31), and a drainage outlet (32) is opened on the groove wall of the circular groove (31).
7. The water conservancy project slope protection structure according to claim 1 is characterized by: A vertically arranged planting opening (40) is provided at the center of the pile body (20) of the slope protection brick (1), and a protective net (41) is provided at the bottom of the planting opening (40).