Locking and consolidation structure for retaining wall of head section of manual hole digging pile
Through the combined structure of the pedestal and wall guard cylinder, combined with concrete casting and steel frame, the problem of easy displacement of the lock opening of the artificial hole is solved, and the stability of the side wall of the pile hole and construction safety are improved.
Patent Information
- Application Number
- CN202420277639.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-04
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2034-02-04
AI Technical Summary
The lock openings of artificial hole-drilled piles are susceptible to extrusion during construction, which affects construction stability and safety.
A combined structure of a pedestal and a wall guard cylinder is adopted, wherein the inner wall guard cylinder is hollow and open at both ends, extends into pile holes and abuts on the side walls. The pedestal and wall guard cylinder are poured integrally by concrete to form an integrated structure to enhance support and stability. It also has optional reinforced bar frames and protective nets to improve structural strength and safety.
Effectively prevent the shift of the table seat, improve the stability of the side wall of the pile hole and construction safety, and ensure the continuity and safety of the construction process.
Smart Images

Figure CN221956713U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of bored piles, and in particular to a first section wall protection locking consolidation structure of bored piles. Background Art
[0002] Manual bored piles refer to reinforced concrete piles that are dug by manpower and poured on site. Manual bored piles are generally thicker in diameter, and the thinnest is more than 800 mm. They can bear the main structure with fewer floors and greater pressure, and are widely used.
[0003] At present, during the construction of bored piles, it is necessary to cast a lock mouth at the pile hole. The lock mouth improves the stability of the pile hole and makes it easier for construction workers to set up equipment such as brackets and winches needed for digging holes at the pile hole.
[0004] However, the current lock mouth is usually cast with a concrete seat at the pile hole. During daily operations, when the lock mouth is squeezed by digging equipment or engineering vehicles, it is very easy to shift at the pile hole, affecting subsequent digging construction and affecting the safety of manual digging. Utility Model Content
[0005] In order to improve the problem that the locking mouth of a bored pile is prone to displacement, the present application provides a locking mouth consolidation structure for the first section of a bored pile retaining wall.
[0006] The present application provides a first section wall protection lock consolidation structure for artificial bored piles, which adopts the following technical solution:
[0007] A first section wall protection lock consolidation structure of a bored pile comprises a pedestal and a wall protection tube. The pedestal is arranged on the ground at the pile hole and is communicated with the pile hole. The wall protection tube is arranged on the pedestal. The wall protection tube is hollow inside and has openings at both ends. The wall protection tube extends into the pile hole and abuts against the side wall of the pile hole.
[0008] By adopting the above technical scheme, the pedestal is connected with the wall protection tube to form an integrated structure. The wall protection tube extends into the pile hole and abuts against the side wall of the pile hole. The wall protection tube supports the side wall of the pile hole to improve the stability of the side wall of the pile hole. At the same time, the wall protection tube is positioned at the pile hole on the pedestal to improve the stability of the pedestal. Even if the pedestal is squeezed, it is difficult to move, which effectively improves the problem of easy displacement of the locking mouth of the artificial bored pile.
[0009] Optionally, the pedestal and the wall protection tube are both concrete structures, and the pedestal and the wall protection tube are cast in one piece.
[0010] By adopting the above technical solution, the pedestal and the wall protection tube are integrally cast by using concrete, which makes it convenient for construction workers to construct the pedestal and the wall protection tube and makes the connection between the pedestal and the wall protection tube more stable.
[0011] Optionally, a steel bar frame is provided in the pedestal and the wall protection tube, and the steel bar frame is formed by binding a plurality of steel bars.
[0012] By adopting the above technical solution, the steel frame in the pedestal enhances the structural strength of the pedestal, and the steel frame in the wall protection tube enhances the structural strength of the wall protection tube, thereby enhancing the stability of the pedestal and the wall protection tube in supporting the pile hole.
[0013] Optionally, the steel bars of the steel bar frame in the wall protection tube are anchored on the steel bar frame in the pedestal.
[0014] By adopting the above technical solution, the connection stability between the back seat and the wall protection tube after concrete pouring is further improved by anchoring the steel bars in the wall protection tube to the steel frame in the pedestal.
[0015] Optionally, a protective net is provided on the pedestal, and the protective net shields the connection between the pedestal and the pile hole.
[0016] By adopting the above technical solution, the protective net covers the connection between the pedestal and the pile hole, preventing debris or construction workers from falling into the pile hole, thereby improving safety during the construction process.
[0017] Optionally, the protective net includes a first net body, a second net body and a locking piece, the first net body is abutted against a base, the second net body is slidably disposed on the first net body, and the locking piece is disposed on the second net body and is used to position the second net body on the first net body.
[0018] By adopting the above technical solution, the construction workers drive the second mesh body to slide in the direction close to the first mesh body, and then position the second mesh body on the first mesh body through the locking part, so as to adjust the coverage range of the protective net composed of the second mesh body and the first mesh body, thereby improving the applicability of the protective net to the protection requirements of different ranges.
[0019] Optionally, the locking member includes a positioning pin, which is slidably penetrated on the second net body, and the first net body is provided with a plurality of positioning holes for inserting the positioning pin at intervals along the sliding direction of the second net body on the first net body.
[0020] By adopting the above technical solution, after the construction personnel drive the second net body to slide on the first net body, they insert the positioning pin into the positioning hole on the first net body that is aligned with the positioning pin, and the second net body can be positioned on the first net body, which is convenient for the construction personnel to position the second net body on the first net body.
[0021] Optionally, a positioning component for positioning the first net body on the pedestal is provided on the first net body, and the positioning component includes a limiting hook and a limiting bolt. A plurality of limiting hooks are provided at both ends of the first net body, and the limiting bolt is threadedly provided on the limiting hook, and the limiting bolt abuts against the pedestal.
[0022] By adopting the above technical solution, after the construction personnel place the first net body on the pedestal, they rotate the limit bolts on the multiple limit hooks so that the multiple limit bolts are tightened against the pedestal, thereby positioning the first net body on the pedestal and improving the stability of the first net body on the pedestal.
[0023] In summary, the present application includes at least one of the following beneficial technical effects:
[0024] 1. The wall protection tube supports the side wall of the pile hole, improving the stability of the side wall of the pile hole. At the same time, the wall protection tube is positioned at the pile hole on the pedestal to improve the stability of the pedestal. Even if the pedestal is squeezed, it is difficult to move, which effectively improves the problem of easy displacement of the lock of the artificial bored pile;
[0025] 2. The construction workers drive the second mesh to slide in the direction close to the first mesh, and then position the second mesh on the first mesh through the locking piece, so as to adjust the coverage of the protective net composed of the second mesh and the first mesh, thereby improving the applicability of the protective net to the protection requirements of different ranges. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a structural schematic diagram of the locking consolidation structure of the first section of the bored pile wall in an embodiment of the present application.
[0027] Figure 2 It is a cross-sectional schematic diagram of an embodiment of the present application.
[0028] Figure 3 yes Figure 1 A partial enlarged schematic diagram of part A.
[0029] Figure numerals: 1. pedestal; 2. wall protection tube; 3. steel frame; 4. protective net; 41. first net body; 411. positioning hole; 42. second net body; 43. locking piece; 431. positioning pin; 5. positioning assembly; 51. limiting hook; 52. limiting bolt; 6. guide rod; 7. guide sleeve. DETAILED DESCRIPTION
[0030] The following is combined with Figure 1-3 This application is described in further detail.
[0031] The embodiment of the present application discloses a first section wall protection locking consolidation structure of a bored pile.
[0032] Reference Figure 1, Figure 2 The first section of the bored pile wall locking consolidation structure includes a pedestal 1, a wall protection tube 2 and a protection net 4.
[0033] Reference Figure 1 , Figure 2 The pedestal 1 is installed on the ground at the pile hole. An opening with the same diameter as the pile hole is reserved in the center of the pedestal 1. The pedestal 1 is connected with the pile hole through the opening in the center. A wall protection tube 2 is installed at the bottom of the pedestal 1. The wall protection tube 2 is hollow inside and has openings at both ends. The wall protection tube 2 is connected with the opening on the pedestal 1, and the wall protection tube 2 extends into the pile hole. The outer wall of the wall protection tube 2 abuts against the side wall of the pile hole.
[0034] Through the integrated structure of the pedestal 1 and the wall protection tube 2, the wall protection tube 2 extends into the interior of the pile hole and abuts against the side wall of the pile hole. The wall protection tube 2 can support the side wall of the pile hole and improve the stability of the side wall of the pile hole. At the same time, the wall protection tube 2 can position the pedestal 1 and position the pedestal 1 at the pile hole. Even if the pedestal 1 is squeezed, it is difficult to move at the pile hole, thereby improving the stability of the pedestal 1, thereby effectively improving the problem of easy displacement of the lock mouth of the artificial bored pile, avoiding affecting the construction of the artificial bored pile, and improving the safety of the construction process.
[0035] Referring to the figure, steel frames 3 are installed in the pedestal 1 and the wall protection tube 2. The steel frames 3 are formed by multiple steel bars tied together by tying wire. The steel bars of the steel frames 3 in the wall protection tube 2 extend to the steel frames 3 in the pedestal 1, and are tied to the steel bars of the steel frames 3 in the pedestal 1 by tying wire, thereby anchoring the steel frames 3 of the wall protection tube 2 to the steel frames 3 in the pedestal 1; the pedestal 1 and the wall protection tube 2 are both concrete structures, and the pedestal 1 and the wall protection tube 2 are enclosed by formwork and then integrally cast by concrete.
[0036] The construction workers first tie and form the steel bars of the pedestal 1 and the wall protection tube 2, and anchor the steel bars of the steel frame 3 of the wall protection tube 2 to the steel frame 3 in the pedestal 1. Then, the steel frame 3 of the pedestal 1 and the wall protection tube 2 is enclosed by a template, and concrete is poured into the template to form an integrally cast pedestal 1 and wall protection tube 2. The pedestal 1 and the wall protection tube 2 both have enhanced structural strength through the steel frame 3, and the steel bars of the steel frame 3 in the wall protection tube 2 are anchored to the steel frame 3 in the pedestal 1, thereby effectively improving the stability of the pedestal 1 and the wall protection tube 2 in supporting the pile hole, and effectively improving the connection stability of the pedestal 1 and the wall protection tube 2.
[0037] Reference Figure 1 , Figure 3A protective net 4 is installed on the pedestal 1, and the protective net 4 shields the opening connecting the pedestal 1 and the pile hole. The protective net 4 includes a first net body 41, a second net body 42 and a locking member 43. The first net body 41 is abutted and installed on the pedestal 1. In this embodiment, the second net body 42 is slidably installed on both sides of the first net body 41. A guide rod 6 is installed on the first net body 41 along the sliding direction of the second net body 42 on the first net body 41. A guide sleeve 7 is installed on the second net body 42. The guide rod 6 is slidably inserted into the guide sleeve 7. The guide rod 6 guides the guide sleeve 7, and then guides the sliding of the second net body 42, thereby improving the stability of the second net body 42 sliding on the first net body 41; the locking piece 43 is installed on the second net body 42, and the locking piece 43 is used to position the second net body 42 on the first net body 41. The locking piece 43 includes a positioning pin 431. In this embodiment, the positioning pin 431 is slidably penetrated on the guide sleeve 7, and a plurality of positioning holes 411 are spaced apart on the guide rod 6 along the length direction of the guide rod 6. The positioning holes 411 are used for the positioning pin 431 to pass through.
[0038] The construction personnel place the first mesh body 41 on the pedestal 1, then pull the second mesh body 42 to make the second mesh body 42 away from the first mesh body 41, and then insert the positioning pin 431 into the positioning hole 411 opposite to the positioning pin 431 at this time, so that the first mesh body 41 and the second mesh body 42 can cover the opening connecting the pedestal 1 and the pile hole, and the first mesh body 41 and the second mesh body 42 can protect the opening of the pedestal 1 to prevent debris or construction personnel from falling into the pile hole, thereby improving the safety during the construction process; and the construction personnel can also slide the second mesh body 42 in the direction close to the first mesh body 41, so that the second mesh body 42 is partially retracted into the first mesh body 41, and the cross-sectional size of the protection net 4 formed by the first mesh body 41 and the second mesh body 42 is adjusted, so that the first mesh body 41 and the second mesh body 42 can be applicable to the protection range required for different sizes, and it is convenient for the construction personnel to leave space on the side of the pile hole for the digging equipment to enter, which is convenient for the construction personnel to construct.
[0039] Reference Figure 1 A positioning assembly 5 is installed on the first net body 41, and the positioning assembly 5 includes a limiting hook 51 and a limiting bolt 52. Two limiting hooks 51 are installed at both ends of the length direction of the first net body 41, and one limiting bolt 52 is threadedly installed on one limiting hook 51. The limiting bolt 52 abuts against the outer wall of the base 1.
[0040] The construction personnel place the first net body 41 on the pedestal 1, and then tighten the multiple limiting bolts 52 so that the multiple limiting bolts 52 respectively abut against the outer walls of the pedestal 1 at different locations, thereby positioning the first net body 41 on the pedestal 1, effectively improving the stability of the first net body 41 on the pedestal 1, and ensuring the stability of the protective net 4 in protecting the pile hole.
[0041] The implementation principle of the locking consolidation structure of the first section of the bored pile wall protection in the embodiment of the present application is as follows: the construction personnel cast the pedestal 1 and the wall protection tube 2 in an integrated manner at the pile hole, so that the wall protection tube 2 abuts against the side wall of the pile hole. While the wall protection tube 2 supports the side wall of the pile hole, it can also position the pedestal 1 at the pile hole, thereby preventing the pedestal 1 from being displaced, improving the stability of the pedestal 1, and thereby improving the problem that the locking mouth of the bored pile is prone to displacement.
[0042] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A first section wall protection locking consolidation structure of a bored pile, characterized by: The utility model comprises a pedestal (1) and a wall protection tube (2), wherein the pedestal (1) is arranged on the ground at the pile hole, the pedestal (1) is communicated with the pile hole, the wall protection tube (2) is arranged on the pedestal (1), the wall protection tube (2) is hollow inside and has openings at both ends, and the wall protection tube (2) extends into the pile hole and abuts against the side wall of the pile hole.
2. The first section wall protection locking consolidation structure of a bored pile according to claim 1 is characterized by: The pedestal (1) and the wall protection tube (2) are both concrete structures, and the pedestal (1) and the wall protection tube (2) are cast in one piece.
3. The first section wall protection locking consolidation structure of a bored pile according to claim 2 is characterized by: A steel bar frame (3) is provided inside the pedestal (1) and the wall protection tube (2), and the steel bar frame (3) is formed by binding a plurality of steel bars.
4. The first section wall protection locking consolidation structure of a bored pile according to claim 3 is characterized by: The steel bars of the steel bar frame (3) in the wall protection tube (2) are anchored on the steel bar frame (3) in the pedestal (1).
5. The first section wall protection locking consolidation structure of a bored pile according to claim 1 is characterized by: A protective net (4) is provided on the pedestal (1), and the protective net (4) shields the connection between the pedestal (1) and the pile hole.
6. The first section wall protection locking consolidation structure of a bored pile according to claim 5, characterized in that: The protective net (4) comprises a first net body (41), a second net body (42) and a locking piece (43); the first net body (41) is arranged in contact with the pedestal (1); the second net body (42) is slidably arranged on the first net body (41); and the locking piece (43) is arranged on the second net body (42) and is used to position the second net body (42) on the first net body (41).
7. The first section wall protection locking consolidation structure of a bored pile according to claim 6 is characterized by: The locking member (43) comprises a positioning pin (431) which is slidably inserted into the second net body (42); a plurality of positioning holes (411) for inserting the positioning pin (431) are provided on the first net body (41) at intervals along a sliding direction of the second net body (42) on the first net body (41).
8. The first section wall protection locking consolidation structure of a bored pile according to claim 6 is characterized by: The first net body (41) is provided with a positioning assembly (5) for positioning the first net body (41) on the pedestal (1), the positioning assembly (5) comprising a limiting hook (51) and a limiting bolt (52), a plurality of the limiting hooks (51) are provided at both ends of the first net body (41), the limiting bolt (52) is threadedly arranged on the limiting hook (51), and the limiting bolt (52) abuts against the pedestal (1).