Mountain photovoltaic support and pile foundation of mountain photovoltaic support
Through the design of mountain photovoltaic bracket pile foundations with staged construction and layered casting, the problem of steel column design and pre-embedding methods affecting the construction progress is solved, and an efficient and reliable pile foundation structure is achieved, which improves construction efficiency and structural strength.
Patent Information
- Application Number
- CN202420102538.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-15
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2034-01-15
AI Technical Summary
In the construction of mountain photovoltaic brackets, the steel column design and embedding methods in the existing technology have time occupation that seriously affects the construction progress, and the embedded bolts have the risk of post-pile head damage in the later stage. The direct insertion and embedding method is ideal, but the process is complex and difficult to improve Construction efficiency and structural strength.
The mountain photovoltaic bracket pile foundation design is adopted for staged construction, including a primary casting body and a secondary casting body. The first steel column member is pre-embedded in the primary casting body. The second steel column member is connected with the first steel column member, and Fixed by fasteners, the secondary casting body is poured along the outside of the sleeve to the elevation of the casting pile foundation to ensure connection reliability and structural strength.
The staged construction operation is achieved, the construction efficiency is improved, and the structural strength and connection reliability of the pile foundation are ensured through layered casting and fastener fixation, avoiding the complexity of synchronous construction of high-strength steels and reducing construction costs.
Smart Images

Figure CN221972468U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of photovoltaic bracket construction, in particular to a mountain photovoltaic bracket and a pile foundation of the mountain photovoltaic bracket. Background Art
[0002] Photovoltaic power stations have developed rapidly as an important support for green and clean energy. When photovoltaic power stations are located in mountainous areas, it is often necessary to consider the complementarity of agriculture and light. The height of the components from the ground is usually more than 2m. Photovoltaic bracket arrays often use single-column bracket solutions for the convenience and economy of construction. Mountain projects need to consider a large wind pressure correction coefficient in accordance with the requirements of the specifications, resulting in the column specifications exceeding the conventional wall thickness or cross-section. The conventional practice is to directly use cast-in-place piles with a height of 0.5m to 1.2m above the ground, and this practice either uses embedded bolts or direct insertion of columns. However, there is a risk of damage to the pile head in the later stage of embedded bolts, and the direct insertion of columns is more ideal.
[0003] In the existing technology, the direct insertion of columns requires the production of steel columns and their embedding into the cast-in-place pile foundation during the foundation construction phase. However, the design requirements for mountain steel columns mostly use zinc-magnesium-aluminum high-strength steel, and the design, procurement, production and transportation of zinc-magnesium-aluminum high-strength steel take a lot of time, seriously affecting the construction progress.
[0004] Therefore, how to solve the above technical problems and design a new type of pile foundation for mountain photovoltaic support is the current problem. Utility Model Content
[0005] The purpose of the utility model is to provide a mountain photovoltaic bracket and a pile foundation of the mountain photovoltaic bracket, which can realize phased construction operations, improve construction efficiency, and ensure the structural strength of the pile foundation.
[0006] To achieve the above-mentioned purpose, the utility model provides a pile foundation of a mountain photovoltaic support, including a cast-in-place pile foundation and a steel column, the cast-in-place pile foundation includes a primary casting body and a secondary casting body, and the steel column includes a first steel column component and a second steel column component;
[0007] The primary casting body is cast below the ground and protrudes above the ground, the lower section of the first steel column component is pre-buried in the primary casting body, the upper section of the first steel column component protrudes from the primary casting body, and the protruding height is less than or equal to the cast-in-place pile foundation elevation;
[0008] The second steel column member is sleeved and connected to the first steel column member, and the sleeves of the two are fixed by fasteners. The secondary casting body is cast along the outer side of the sleeve and from the top of the primary casting body to the cast-in-place pile foundation elevation.
[0009] Preferably, the second steel column member is a C-shaped steel material, and the secondary casting body is poured into the cavity located inside the C-shaped opening of the C-shaped steel material.
[0010] Preferably, the secondary cast body is self-compacting concrete.
[0011] Preferably, the first steel column member is a steel pipe.
[0012] Preferably, the second steel column component is made of zinc-magnesium-aluminum high-strength steel.
[0013] Preferably, a plurality of vertically distributed through holes are provided at the sleeve, and the fasteners are connected through the through holes.
[0014] Preferably, the embedded length of the first steel column component is 1 / 3-1 / 2 of the total length of the first steel column component.
[0015] Preferably, a steel cage is placed inside the primary casting body, the top of the steel cage protrudes 30-50 mm above the ground, a cross-support steel bar is arranged on the top of the steel cage, and the first steel column member is welded and fixed to the cross-support steel bar.
[0016] Preferably, the bottom of the steel cage is placed 100 mm above the bottom of the primary casting body.
[0017] The utility model also provides a mountain photovoltaic support, comprising the pile foundation as described above.
[0018] Compared with the above-mentioned background technology, the pile foundation of the mountain photovoltaic support provided by the utility model pre-buries the lower section of the first steel column component into the primary casting body, and the upper section of the first steel column component protrudes from the primary casting body, and the protruding height is less than or equal to the cast-in-place pile foundation elevation. There are no special requirements for the wall thickness and material of the first steel column component. From the perspective of construction technology, it can be directly purchased, processed and pre-buried by the construction unit. After the second steel column component is transported to the construction site, the second steel column component and the first steel column component are sleeved and connected, and the sleeves of the two are fixed by fasteners, and the secondary casting body is cast along the outside of the sleeve and from the top of the primary casting body to the cast-in-place pile foundation elevation, that is, the outer wall of the first steel column component is wrapped with the secondary casting body, which can not only ensure the connection reliability of the first steel column component and the second steel column component, but also ensure the durability of the connection position. It can be seen that the second steel column component serves as an intermediate connecting piece to connect the upper and lower parts, and finally can be installed with the mountain support column to form a mountain photovoltaic support.
[0019] Therefore, the pile foundation of the utility model abandons the method of simultaneous construction of high-strength steel and conventional embedded steel columns in the prior art, and instead adopts a method of sequential construction to achieve phased construction operations, improve construction efficiency, and ensure the structural strength of the pile foundation. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings in the following description are only embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0021] Figure 1 A schematic diagram of a primary cast body and a first steel column member in a pile foundation of a mountain photovoltaic support provided by an embodiment of the utility model;
[0022] Figure 2 for Figure 1 A schematic diagram of a second steel column member installed;
[0023] Figure 3 A partial schematic diagram of the pile foundation of a mountain photovoltaic support provided by an embodiment of the utility model;
[0024] Figure 4 for Figure 3 A top view of
[0025] Figure 5 A schematic diagram of a mountain photovoltaic support provided by an embodiment of the utility model;
[0026] Figure 6 A schematic diagram of another mountain photovoltaic support provided by an embodiment of the utility model;
[0027] in;
[0028] 100-pile foundation, 1-cast-in-place pile foundation, 11-primary casting body, 12-secondary casting body, 2-steel column, 21-first steel column member, 22-second steel column member, 3-fastener;
[0029] 200-Bracket column. DETAILED DESCRIPTION
[0030] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0031] In order to enable those skilled in the art to better understand the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0032] The utility model provides a pile foundation 100 of a mountain photovoltaic support, see attached Figure 1 To Attachment Figure 4 The pile foundation 100 includes a cast-in-place pile foundation 1 and a steel column 2 . The cast-in-place pile foundation 1 includes a primary cast body 11 and a secondary cast body 12 . The steel column 2 includes a first steel column component 21 and a second steel column component 22 .
[0033] Please see attached Figure 1 The primary casting body 11 is cast below the ground and protrudes from the ground. The lower section of the first steel column member 21 is pre-buried in the primary casting body 11. The upper section of the first steel column member 21 protrudes from the primary casting body 11, and the protruding height is less than or equal to the cast-in-place pile foundation elevation. The primary casting body 11 and the first steel column member 21 can both be arranged in a vertical shape.
[0034] Please see attached Figure 2 The second steel column component 22 is sleeved and connected with the first steel column component 21, and the sleeved part of the two is fixed by a fastener 3. The fastener 3 can be specifically a component such as a clamp. After the first steel column component 21 and the second steel column component 22 are sleeved, the sleeved part of the first steel column component 21 and the second steel column component 22 is fixedly connected by a clamp.
[0035] Please see attached Figure 3 The secondary casting body 12 is cast along the outer side of the sleeve and from the top of the primary casting body 11 to the cast-in-place pile foundation elevation, wherein the first steel column component 21 and the second steel column component 22 can both extend upward in the vertical direction, and the top of the second steel column component 22 is used to install the mountain support column 200.
[0036] It can be seen that the secondary casting body 12 is cast on the outside of the first steel column component 21, and wraps the socket joint of the first steel column component 21 and the second steel column component 22. The secondary casting body 12 can also be vertical, and its top is located at the elevation of the cast-in-place pile foundation. With this arrangement, the secondary casting body 12 and the primary casting body 11 can form a whole. In addition to using the fasteners 3 to fix the socket joint of the first steel column component 21 and the second steel column component 22, the secondary casting body 12 is used for casting and fixing, which further improves the connection reliability of the first steel column component 21 and the second steel column component 22.
[0037] In some embodiments, the second steel column member 22 is a C-shaped steel material, and the secondary casting body 12 is poured into the cavity located inside the C-shaped opening of the C-shaped steel material.
[0038] Please see attached Figure 4The second steel column member 22 is a C-shaped steel material, and its side wall has an opening. From the top view of the second steel column member 22, the second steel column member 22 has a C-shaped opening, and the secondary casting body 12 is poured into the cavity inside the C-shaped opening.
[0039] Please refer to the attached Figure 3 In the case where the first steel column member 21 is a hollow member, the second steel column member 22 is sleeved on the outside of the first steel column member 21, and the secondary cast body 12 can be cast into the inside of the first steel column member 21 through the C-shaped opening, so that the structural strength of the first steel column member 21 can be further strengthened to ensure the overall strength of the pile foundation. Of course, the secondary cast body 12 cast inside the first steel column member 21 can be flush with the cast-in-place pile foundation elevation to increase the structural strength.
[0040] In the case where the first steel column component 21 is a solid component, the secondary casting body 12 can only be cast into the interior of the second steel column component 22 through the C-shaped opening and form a whole with the top of the first steel column component 21, thereby further improving the connection reliability between the first steel column component 21 and the second steel column component 22.
[0041] In some embodiments, the secondary cast body 12 is self-compacting concrete; it can be seen that no matter the secondary cast body 12 is cast along the outside of the sleeve of the first steel column member 21 and the second steel column member 22 and from the top of the primary cast body 11 to the elevation of the cast-in-place pile foundation, or is cast into the cavity inside the C-shaped mouth, no vibration operation is required, which simplifies the construction process, ensures the connection reliability of the first steel column member 21 and the second steel column member 22, and also ensures the durability of the pile foundation.
[0042] In some embodiments, the first steel column member 21 is a steel pipe, such as a conventional square steel pipe, that is, the lower section of the steel pipe is pre-buried in the primary casting body 11, and the upper section of the steel pipe protrudes from the primary casting body 11. In view of the wide application of steel pipes, the use of steel pipes can effectively reduce the difficulty of obtaining materials for pile foundations during construction, which helps to reduce the cost of lifting. In addition, the steel pipes can be purchased by the construction unit itself, which greatly speeds up the progress of foundation construction. During construction, there is no need to arrange longitudinal reinforcement and stirrups within the range of the square steel pipe, which can save a certain amount of steel.
[0043] In some embodiments, the second steel column component 22 is made of zinc-magnesium-aluminum high-strength steel, which has higher strength than conventional steel pipes. As a component used to install the mountain support column 200, the use of zinc-magnesium-aluminum high-strength steel can effectively ensure the support strength and improve the service life.
[0044] In some embodiments, a plurality of vertically distributed through holes are provided at the sleeves of the first steel column member 21 and the second steel column member 22, and the fasteners 3 are connected through the through holes.
[0045] The first steel column member 21 may be provided with a first connection hole, and the second steel column member 22 may be provided with a second connection hole corresponding to the position of the first connection hole. A plurality of first connection holes may be sequentially arranged along the length direction of the first steel column member 21. Similarly, a plurality of second connection holes may be sequentially arranged along the length direction of the second steel column member 22, and the first connection holes and the second connection holes are connected by fasteners 3. The fasteners 3 may be specifically components such as bolts. When the first steel column member 21 and the second steel column member 22 are connected in place, the positions of the first connection holes and the second connection holes correspond. By using the fasteners 3 to penetrate one or more relative connection holes, the first steel column member 21 and the second steel column member 22 can be reliably connected. At the same time, the connection height can be adjusted according to the design elevation.
[0046] In some embodiments, the embedded length of the first steel column component 21 is 1 / 3-1 / 2 of the total length of the first steel column component 21, that is, the length of the first steel column component 21 inside the primary casting body 11 is 1 / 3-1 / 2 of its total length, and 1 / 3-1 / 2 of the length of the first steel column component 21 extends into the interior of the primary casting body 11, so that the primary casting body 11 and the first steel column component 21 can be ensured to be connected in place, further improving the structural strength of the pile foundation 100.
[0047] In some embodiments, a steel cage is placed inside the primary casting body 11, the top of the steel cage protrudes 30-50 mm from the ground, cross-support steel bars are arranged on the top of the steel cage, and the first steel column member 21 is welded and fixed to the cross-support steel bars.
[0048] The steel cage is placed inside the primary casting body 11. On the one hand, it can improve the structural strength of the primary casting body 11. On the other hand, cross-support steel bars are set on the top of the steel cage, and then the cross-support steel bars and the first steel column member 21 are welded and fixed, that is, it is used to install the first steel column member 21. The top of the steel cage protrudes 30-50mm from the ground, providing sufficient space for the installation of the cross-support steel bars to ensure that the installation of the first steel column member 21 is stable and reliable.
[0049] In some embodiments, the bottom of the steel cage is placed 100 mm above the bottom of the primary casting body 11, and a certain distance is maintained between the bottom of the steel cage and the bottom of the primary casting body 11 to reduce the displacement and deformation of the primary casting body 11, while ensuring the strength of the primary casting body 11 to avoid the occurrence of problems such as hollowing and cracks.
[0050] The utility model also provides a mountain photovoltaic bracket, see attached Figure 5 and attached Figure 6 The mountain photovoltaic support includes the pile foundation 100 described above, and a support column 200 is installed on the top of the second steel pipe 3 of the pile foundation 100, that is, the top of the second steel pipe 3 is connected to the bottom of the support column 200, and the support column 200 can be set in a vertical shape.
[0051] Attached Figure 5 The second steel pipe 3 is shorter and the support column 200 is longer. At this time, the bottom of the support column 200 is close to the pile foundation 100, and the overall height of the pile foundation 100 is shorter. Figure 6 It shows a situation where the second steel pipe 3 is longer and the support column 200 is shorter. At this time, the top of the second steel pipe 3 is closer to the photovoltaic panel. Of course, according to the actual situation, the specific form of the pile foundation 100 can also be other, which will not be expanded here.
[0052] This article uses specific examples to illustrate the principles and implementation methods of the utility model. The above examples are only used to help understand the method and core ideas of the utility model. It should be pointed out that for ordinary technicians in this technical field, without departing from the principles of the utility model, the utility model can also be improved and modified, and these improvements and modifications also fall within the scope of protection of the claims of the utility model.
Claims
1. A pile foundation for a mountain photovoltaic support, comprising a cast-in-place pile foundation (1) and a steel column (2), It is characterized in that The cast-in-place pile foundation (1) comprises a primary cast body (11) and a secondary cast body (12), and the steel column (2) comprises a first steel column component (21) and a second steel column component (22); The primary cast body (11) is cast below the ground and protrudes above the ground, the lower section of the first steel column component (21) is pre-buried in the primary cast body (11), and the upper section of the first steel column component (21) protrudes from the primary cast body (11), and the protruding height is less than or equal to the cast-in-place pile foundation elevation; The second steel column member (22) and the first steel column member (21) are sleeved and connected, and the sleeves of the two are fixed by fasteners (3). The secondary casting body (12) is cast along the outer side of the sleeve and from the top of the primary casting body (11) to the cast-in-place pile foundation elevation.
2. The pile foundation of the mountain photovoltaic support according to claim 1, It is characterized in that The second steel column component (22) is a C-shaped steel material, and the secondary casting body (12) is cast into a cavity located inside the C-shaped opening of the C-shaped steel material.
3. The pile foundation of the mountain photovoltaic support according to claim 2, It is characterized in that The secondary cast body (12) is self-compacting concrete.
4. The pile foundation of the mountain photovoltaic support according to claim 1, It is characterized in that The first steel column component (21) is a steel pipe.
5. The pile foundation of the mountain photovoltaic support according to claim 1, It is characterized in that The material of the second steel column component (22) is zinc-magnesium-aluminum high-strength steel.
6. The pile foundation of the mountain photovoltaic support according to any one of claims 1 to 5, It is characterized in that The sleeve is provided with a plurality of vertically distributed through holes, and the fasteners (3) are connected through the through holes.
7. The pile foundation of the mountain photovoltaic support according to any one of claims 1 to 5, It is characterized in that The embedded length of the first steel column component (21) is 1 / 3-1 / 2 of the total length of the first steel column component (21).
8. The pile foundation of the mountain photovoltaic support according to any one of claims 1 to 5, It is characterized in that A steel cage is placed inside the primary casting body (11), the top of the steel cage protruding 30-50 mm above the ground, a cross-support steel bar is arranged on the top of the steel cage, and the first steel column member (21) is welded and fixed to the cross-support steel bar.
9. The pile foundation of the mountain photovoltaic support according to claim 8, It is characterized in that The bottom of the steel cage is placed 100 mm above the bottom of the primary casting body (11).
10. A mountain photovoltaic bracket, It is characterized in that It comprises a pile foundation as described in any one of claims 1 to 9 above.