Modular hoisting temporary supporting frame based on tower crane standard knot

The modular temporary support frame is assembled through the standard section of the tower crane, which solves the problems of low frequency of use and high cost of removal of existing temporary support frames, and achieves efficient and safe steel structure construction support and low-cost removal.

CN221988035UActive Publication Date: 2024-11-12SHANGHAI SHENGXIN CONSTR ENG CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420556122.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-21
Publication Date
2024-11-12
Estimated Expiration
2034-03-21

AI Technical Summary

Technical Problem

The existing temporary support frames are used in steel structure construction with low frequency and high cost, and the dismantling process requires the cooperation of two cranes, which increases the construction cost.

Method used

The standard section of the tower crane is assembled to form a modular temporary support frame, which ensures stability through cable and air rope connection and steel support reinforcement, and adjustable non-standard segments are set up to meet different height requirements, simplifying the removal process.

Benefits of technology

It improves the efficiency and safety of the support frame, reduces transportation and leasing costs, reduces the cost of mechanical removal, and realizes the ability of a single crane to remove the support frame.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221988035U_ABST
    Figure CN221988035U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of hoisting equipment, in particular to a modularized hoisting temporary support frame based on tower crane standard knots, which consists of a plurality of tower crane standard knots which are superposed along the height direction; when the height of the stacked tower crane standard knots is smaller than or equal to 30 m, the tower crane standard knots are connected and fixed through cable ropes to form an integral structure; and when the height of a plurality of the tower crane standard knots after being overlapped is greater than 30 meters, the middle parts of the latticed columns of the plurality of the tower crane standard knots are welded and reinforced by adopting a steel bracket. The utility model has the advantages that idle standard knots of a tower crane on the market are used as a support frame system of a steel structure, so that the safety of the support frame is guaranteed; a ladder stand for personnel to go up and down is arranged, so that the safety of personnel in mounting and going up and down in the construction process is fully guaranteed; the service cycle is short, the transportation cost and the rental cost are low, and the market promotion benefit is good; and meanwhile, the support frame can be smoothly disassembled by utilizing double-hook lifting of the truck cranes, and two truck cranes do not need to be moved out of the frame body, so that the mechanical cost is saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of hoisting equipment, in particular to a modular hoisting temporary supporting frame based on a tower crane standard section. Background Art

[0002] Temporary support frames are required for the segmented hoisting of large-span steel beams, the arching requirements of large-span steel beams, and the construction of cantilevered steel beams. Temporary support frames serve as support points for segmented hoisting of steel beams and as construction platforms for positioning and welding; temporary supports serve as support platforms for the overall hoisting of large-span steel beams and the elevation positioning of cantilevered steel beams.

[0003] Temporary support frames are often made of lattice columns during steel structure construction and installation. Lattice columns are calculated and manufactured in combination with different projects. The frequency and versatility of use make it difficult to ensure their efficiency for multiple uses. The one-time investment is often high, and the probability of turnover is low. When the temporary support frame is erected at a high height, a reliable connection must be set in the middle section to ensure the stability of the support frame. Two cranes are required to dismantle the support frame, which increases the construction cost. Summary of the invention

[0004] The purpose of the utility model is to provide a modular hoisting temporary support frame based on tower crane standard sections according to the above-mentioned deficiencies of the prior art, which is convenient for construction by assembling the temporary support frame using tower crane standard sections.

[0005] The purpose of this utility model is achieved by the following technical solutions:

[0006] A modular temporary support frame for hoisting based on a tower crane standard section, characterized in that: the temporary support frame is composed of a plurality of tower crane standard sections, and the plurality of tower crane standard sections are stacked in a height direction;

[0007] When the height of several tower crane standard sections after stacking is less than or equal to 30 meters, the several tower crane standard sections are connected and fixed by cables to form an integral structure; when the height of several tower crane standard sections after stacking is greater than 30 meters, the middle part of the lattice columns of several tower crane standard sections are welded and reinforced with steel brackets.

[0008] Lifting points matching the lifting equipment are respectively arranged on both sides of the tower crane standard section.

[0009] The temporary support frame also includes a non-standard section, and the height of the non-standard section is adjustable.

[0010] The lattice column of the non-standard segment is provided with a telescopic structure, and the height of the non-standard segment is adjusted by telescoping the telescopic structure.

[0011] The advantages of the utility model are: utilizing the idle standard sections of tower cranes on the market as the support frame system of the steel structure to ensure the safety of the support frame; being equipped with a ladder for personnel to go up and down to fully ensure the safety of personnel installing and going up and down during the construction process; having a short service life, and relatively low transportation and rental costs, and having very good market promotion benefits; at the same time, utilizing the double hooks of a truck crane to lift the support frame smoothly, without the need for two truck cranes to move out the frame, thus saving machinery costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a structural schematic diagram of the utility model. DETAILED DESCRIPTION

[0013] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:

[0014] like Figure 1 As shown, the marks 1-4 in the figure respectively represent: steel beam 1, tower crane standard section 2, main hook 3, and auxiliary hook 4.

[0015] Example: Figure 1 As shown, the modular lifting temporary support frame based on the standard section of the tower crane in this embodiment can be used for the segmented lifting of large-span steel beams, the arching requirements of large-span steel beams and the construction of cantilevered steel beams. It can be used as a support point for the segmented lifting of steel beams, a construction platform for positioning and welding, and can also be used as a support platform for the overall lifting of large-span steel beams and the elevation positioning of cantilevered steel beams.

[0016] Specifically, the modular temporary support frame for hoisting based on the tower crane standard section in this embodiment includes a plurality of tower crane standard sections 2, which are in the form of lattice columns. The plurality of tower crane standard sections 2 are stacked in the height direction, so as to build a temporary support frame with a height matching the construction requirements. When using the tower crane standard section 2, the finite element software MIDAS is used to verify the standard section of the tower crane to ensure the structural performance and safety, and the ladder cage thereof is used as a passage for people to go up and down.

[0017] Due to the height required for construction, the connection of the tower crane standard section 2 in this embodiment has the following conditions:

[0018] When several tower crane standard sections 2 are stacked, if the overall height is within 30 meters, the guy rope is used for stability. If it exceeds 30 meters, the tower crane standard section 2 needs to be welded with a steel bracket in the middle of the lattice column. Specifically, an attachment frame is set in the middle of the support frame formed by several tower crane standard sections 2 and connected with a connector to ensure the stability of the support frame.

[0019] When this embodiment is used, a conversion platform beam is installed on a temporary support frame composed of several tower crane standard sections 2, and a leveling pad is placed on the platform beam to ensure that the elevation of the steel beam meets the design requirements. After the steel beam is installed in place, two jacks need to be set on the conversion steel platform to unload it, and then the pad is pulled out.

[0020] like Figure 1 As shown, in this embodiment, the assembly and disassembly of several tower crane standard sections 2 can be achieved by a crane. On both sides of the tower crane standard section 2, there are respectively provided lifting points matching the main hook 3 and the auxiliary hook 4 of the crane, and the main hook 3 and the auxiliary hook 4 are provided on the steel beam 1, and can move along the steel beam 1.

[0021] When the tower crane standard section 2 is shifted and hoisted out, the following steps are included:

[0022] (1) The main hook 3 and the auxiliary hook 4 lift the tower crane standard section 2 and move it horizontally out of the support frame along the steel beam 1;

[0023] (2) Loosen the wire rope of the auxiliary hook 4 to make the wire rope of the main hook 3 bear force;

[0024] (3) Lower the wire rope of the main hook 3 to lift the tower crane standard section 2 to the ground, lay it flat and lift it out. Repeat the above steps to complete the removal of the support frame.

[0025] In this embodiment, in addition to the tower crane standard section 2, an additional non-standard section can be set to meet the construction requirements of different heights. The non-standard section also adopts the same lattice structure system as the tower crane standard section 2, and various types of retractable structures are set at the rods in the vertical direction, such as a sleeve-type retractable structure, so that the non-standard stage is highly adjustable within a certain range. When the height of the temporary support frame required by the construction cannot be obtained by combining the tower crane standard section 2, the non-standard section can be assembled on the top and adaptively adjusted to make the overall temporary support frame meet the construction height requirements.

[0026] Although the above embodiments have described the concepts and embodiments of the purpose of the utility model in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the utility model without departing from the scope of the claims, so they are not described one by one here.

Claims

1. A modular temporary support frame for hoisting based on a tower crane standard section, characterized in that: The temporary support frame is composed of a plurality of tower crane standard sections, and the plurality of tower crane standard sections are stacked in the height direction; When the height of several tower crane standard sections after stacking is less than or equal to 30 meters, the several tower crane standard sections are connected and fixed by cables to form an integral structure; when the height of several tower crane standard sections after stacking is greater than 30 meters, the middle part of the lattice columns of several tower crane standard sections are welded and reinforced with steel brackets.

2. According to claim 1, a modular temporary support frame for hoisting based on a tower crane standard section is characterized in that: Lifting points matching the lifting equipment are respectively arranged on both sides of the tower crane standard section.

3. The modular temporary support frame for hoisting based on the tower crane standard section according to claim 1 is characterized in that: The temporary support frame also includes a non-standard section, and the height of the non-standard section is adjustable.

4. The modular temporary support frame for hoisting based on the tower crane standard section according to claim 3 is characterized by: The lattice column of the non-standard segment is provided with a telescopic structure, and the height of the non-standard segment is adjusted by telescoping the telescopic structure.

Citation Information

Cited By

  • Steel arch rib installation support system rapid positioning device, system and construction method