Super high-rise sewage centralized utilization system

By setting up a hanging bucket and a filter net on the top of the building and combining with the treatment of the three-level sedimentation tank, the problems of sediment and sand and gravel in wastewater during construction are solved, and the effective utilization of the building water circulation system and the conservation of water resources are achieved.

CN221999181UActive Publication Date: 2024-11-15GUANGZHOU HONGDA ENG CONSULTING GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420196291.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-25
Publication Date
2024-11-15
Estimated Expiration
2034-01-25

AI Technical Summary

Technical Problem

During the construction process, the construction wastewater is mixed with sediment and sand, and the existing technology is difficult to effectively deal with and utilize, resulting in waste of water resources and pollution problems.

Method used

Design a centralized utilization system for ultra-high-rise sewage, including setting up a hanging bucket and a water outlet pipe on the top of the building, and a filter net is installed at the upper end of the water outlet pipe. The wastewater is filtered and enters the sedimentation tank. The sedimented water is used to flush water in the bathroom on the lower floors of the building. , the filter net blocks silt, sand and gravel, and the sewage pipelines are introduced into the ground for treatment.

Benefits of technology

Effectively utilize wastewater on high-rise buildings, reduce external water diversion, save water resources, and prevent debris from blocking pipelines, achieving effective purification and resource utilization of building water circulation systems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221999181U_ABST
    Figure CN221999181U_ABST
Patent Text Reader

Abstract

The utility model discloses a super high-rise sewage centralized utilization system, building wastewater mainly refers to wastewater formed by concrete tailings for flushing a pump pipe in the building construction process, the wastewater is doped with a lot of silt and gravel, and non-drinking miscellaneous water used within a certain range can be obtained after proper treatment. A lifting hopper is arranged in a high floor of a building, a water outlet pipe and a filter screen are arranged in the lifting hopper, building waste water is guided into the lifting hopper, the waste water in the lifting hopper can overflow into the water outlet pipe and then is guided into a settling pond to be settled, and the settled miscellaneous water is guided into a toilet of a lower-layer building of the building through a pipeline to be used for flushing. The filter screen is erected on the water outlet pipe and can effectively block silt, sand and gravel and prevent sundries from blocking a pipeline, the whole system reasonably utilizes waste water generated during high-rise buildings, external water diversion applied to building construction is reduced, and water resources are saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building sewage utilization systems, in particular to a super-high-rise sewage centralized utilization system. Background Art

[0002] Construction wastewater mainly refers to the wastewater generated by concrete tailings from flushing pump pipes during the construction process. This wastewater is mixed with a lot of mud, sand and gravel. After proper treatment, it can be used as non-drinking miscellaneous water within a certain range.

[0003] In the process of reducing the discharge and pollution level of construction sewage and protecting precious natural water resources, it is of utmost importance to comprehensively consider the utilization, purification and discharge of various water resources and establish a complete building water circulation system. Utility Model Content

[0004] Therefore, in order to solve the above problems, the purpose of the utility model is to provide a super-high-rise sewage centralized utilization system, including a bucket, which is arranged on the top floor of the building, and an outlet pipe is passed through the lower end surface of the bucket. The upper end of the outlet pipe protrudes relative to the bottom surface of the bucket, and the upper end of the outlet pipe is connected to a filter screen, and the upper end of the filter screen is higher than the upper end of the outlet pipe. The lower end of the outlet pipe is connected to a sedimentation tank, and the output end of the sedimentation tank is connected to a temporary toilet through a pipeline, and the temporary toilet is arranged on the lower floor of the building.

[0005] Preferably, the outlet pipe is connected to the sedimentation tank through a corrugated pipe and a galvanized chute square pipe.

[0006] Preferably, the filter screen is funnel-shaped.

[0007] Preferably, two temporary toilets are provided for every five floors.

[0008] Preferably, a floor drain is provided in the outer frame floor decking of the high floors of the building, and the floor drain is connected to the sedimentation tank through a drainage pipe.

[0009] Preferably, the sedimentation tank is a three-stage sedimentation tank.

[0010] Preferably, it also includes a sewage pipe, the water inlet end of the sewage pipe is connected to the drainage end of the temporary toilet and the upper floor of the building, and the drainage end of the sewage pipe is arranged on the ground.

[0011] The beneficial effects of the utility model are:

[0012] A bucket is arranged in the high floors of the building, and an outlet pipe and a filter are set in the bucket. Construction wastewater is introduced into the bucket, and the wastewater in the bucket can overflow into the outlet pipe, and then be introduced into the sedimentation tank for sedimentation. The miscellaneous water after sedimentation is introduced into the toilet of the lower building of the building through a pipe for flushing. The filter net is installed on the outlet pipe to effectively block mud, sand and gravel, and prevent debris from clogging the pipe. The whole system rationally utilizes the wastewater generated in high-rise buildings, reduces the water diversion from the outside used in construction, and saves water resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0014] Figure 1 It is a schematic diagram of the structure of the utility model;

[0015] Figure 2 It is a structural schematic diagram of the bucket;

[0016] Figure 3 It is a schematic diagram of the structure of the bellows;

[0017] Figure 4 It is a structural diagram of the outer frame floor decking;

[0018] Explanation of the numbers in the attached figures: 1. Bucket; 2. Outlet pipe; 21. Corrugated pipe; 22. Galvanized chute square pipe; 3. Filter screen; 4. Sedimentation tank; 5. Temporary toilet; 6. Sewage pipe; 7. External frame floor decking; 71. Floor drain.

[0019] The realization of the purpose, functional features and advantages of the utility model will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION

[0020] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0021] In the description of the present application, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present application. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0022] Unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0023] Example:

[0024] Figure 1-Figure 4 The utility model shows a super high-rise sewage centralized utilization system provided by the utility model, which can be used in the construction of multi-story buildings, usually with more than twenty-five floors. A hanging bucket 1 is set in the high-rise building under construction, and an outlet pipe 2 is passed through the lower end surface of the hanging bucket 1. The upper end of the outlet pipe 2 protrudes relative to the bottom surface of the hanging bucket 1, and the upper end of the outlet end is connected with a filter screen 3. The construction wastewater accumulated in the hanging bucket 1 can overflow to the outlet pipe 2 when it rises to a certain height. The mud, sand and gravel mixed in the construction wastewater will be blocked by the filter screen 3 and will not enter the outlet pipe 2. The lower end of the outlet pipe 2 is connected with a sedimentation tank 4. After entering the outlet pipe 2, the construction wastewater is introduced into the sedimentation tank 4 for sedimentation. The miscellaneous water output end of the sedimentation tank 4 is connected to a temporary toilet 5 through a pipeline. The miscellaneous water after sedimentation treatment in the sedimentation tank 4 enters the temporary toilet 5 along the pipeline for flushing.

[0025] A lifting lug is arranged on the upper end of the bucket 1, and the bucket 1 can be lifted and moved by using a crane in combination with a hook.

[0026] The outlet pipe 2 is connected to the sedimentation tank 4 through a corrugated pipe 21 and a galvanized chute square pipe 22. The corrugated pipe 21 can be bent to form a curved pipe, which can change the flow direction of the filtered wastewater. The galvanized chute square pipe 22 is adapted to the structure of the sedimentation tank 4, and the end of the galvanized chute square pipe 22 can be overlapped on the flat surface of the sedimentation tank 4.

[0027] The filter screen 3 is in the shape of a funnel which is wide at the top and narrow at the bottom. The lower end of the filter screen 3 is mounted on the upper end of the water outlet pipe 2 through a support frame, and the support frame is in contact with the outer edge of the water outlet pipe 2 .

[0028] In this embodiment, two temporary toilets 5 are arranged on every five floors in the construction building, which can meet the needs of construction workers.

[0029] In addition to wastewater from construction, rainwater can also be used in actual construction sites. Rainwater is mainly accumulated on the outer frame floor decking 7 of the high floors of the building, so a floor drain 71 is set on the outer frame floor decking 7. The floor drain 71 is connected to the sedimentation tank 4 through a drainage pipe. After sedimentation, the rainwater can also be used as miscellaneous water.

[0030] The sedimentation tank 4 is specifically a tertiary sedimentation tank 4, which can effectively treat filtered construction wastewater and rainwater.

[0031] The silt, sand and gravel and other impurities blocked by the filter 3 will eventually accumulate in the bucket 1. After the bucket 1 has been used for a period of time, the accumulated silt, sand and gravel need to be poured out, so a sewage pipe 6 is set up separately. The diameter of the sewage pipe 6 is large and not easily blocked. The input end of the sewage pipe 6 is connected to the drainage end of the high floor of the building and the temporary toilet 5. The excrement in the temporary toilet 5 is mixed with the silt, sand and gravel generated by the high floors of the building and discharged along the sewage pipe 6 to the bottom floor of the building, that is, the ground, and finally landfilled or treated separately.

[0032] The high floor of the building referred to in this embodiment usually corresponds to the top floor under construction in a multi-story building, that is, the top floor of the building, and can also be the second or third floor at the top of the building under construction.

[0033] Working principle:

[0034] During the construction process, the concrete tailings from flushing the pump pipe are poured into the bucket 1. The waste water filtered by the filter screen 3 in the bucket 1 overflows from the upper end of the outlet pipe 2 into the outlet pipe 2, and then flows into the corrugated pipe 21 through the outlet pipe 2, and finally flows into the sedimentation tank 4 along the galvanized chute square pipe 22. After sedimentation treatment in the sedimentation tank 4, it becomes miscellaneous water, and then is introduced into the temporary toilet 5 from the sedimentation tank 4 through a pipeline.

[0035] The above description is only an optional embodiment of the present invention, and does not limit the patent scope of the present invention. All equivalent structural changes made by using the contents of the present invention specification and drawings under the inventive concept of the present invention, or directly / indirectly applied in other related technical fields are included in the patent protection scope of the present invention.

Claims

1. A super high-rise sewage centralized utilization system, characterized in that: The invention comprises a hanging bucket (1), wherein the hanging bucket (1) is arranged on the top floor of a building, a water outlet pipe (2) is passed through the lower end surface of the hanging bucket (1), the upper end of the water outlet pipe (2) protrudes relative to the bottom surface of the hanging bucket (1), the upper end of the water outlet pipe (2) is connected to a filter screen (3), the upper end of the filter screen (3) is higher than the upper end of the water outlet pipe (2), the lower end of the water outlet pipe (2) is connected to a sedimentation tank (4), and the output end of the sedimentation tank (4) is connected to a temporary toilet (5) through a pipeline.

2. The super high-rise sewage centralized utilization system according to claim 1 is characterized in that: The water outlet pipe (2) is connected to the sedimentation tank (4) via a corrugated pipe (21) and a galvanized chute square pipe (22).

3. The super high-rise sewage centralized utilization system according to claim 1 is characterized in that: The filter screen (3) is funnel-shaped.

4. The super high-rise sewage centralized utilization system according to claim 1 is characterized in that: The temporary toilets (5) are arranged with two for every five floors.

5. The super high-rise sewage centralized utilization system according to claim 1 is characterized in that: A floor drain (71) is provided in the outer frame floor slab (7) of the top floor of the building, and the floor drain (71) is connected to the sedimentation tank (4) through a drainage pipe.

6. The super high-rise sewage centralized utilization system according to claim 1 is characterized in that: The sedimentation tank (4) is a three-stage sedimentation tank (4).

7. The super high-rise sewage centralized utilization system according to claim 1 is characterized in that: It also includes a sewage pipe (6), the water inlet end of the sewage pipe (6) is connected to the drainage end of the temporary toilet (5) and the top floor of the building, and the drainage end of the sewage pipe (6) is arranged on the ground.