Industrial boiler biomass gasification supply equipment

By combining clamping and dust removal components, the problems of unstable chimney fixation and incomplete dust removal are solved, achieving both chimney stability and efficient dust removal.

CN222001138UActive Publication Date: 2024-11-15KAIPING CIC ENERGY IND CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420106060.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-16
Publication Date
2024-11-15
Estimated Expiration
2034-01-16

AI Technical Summary

Technical Problem

The existing dust removal devices for the chimneys of biomass gasification supply equipment in industrial boilers cannot be effectively fixed, resulting in shaking and poor dust removal performance.

Method used

The design combines a clamping assembly and a dust removal assembly. The clamping assembly uses a screw and a spring to drive the clamping plate to fix the chimney, while the dust removal assembly uses a rotary motor and an electric telescopic rod to drive the scraper to clean the dust on the inner wall of the chimney.

Benefits of technology

It achieves stable fixation of the chimney and efficient dust removal, improves the dust removal effect, avoids chimney shaking, and quickly cleans dust from the inner wall.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222001138U_ABST
    Figure CN222001138U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of equipment dust removal, in particular to industrial boiler biomass gasification supply equipment which comprises a base, the upper end of the base is in threaded connection with three bolts, the outer surface of the base is fixedly connected with three supporting assemblies in a clamped mode through the three bolts, and the middle of the upper end of the base is fixedly connected with a containing cylinder. Vertical plates are fixedly connected to the left portion and the right portion of the upper end of the containing cylinder, clamping assemblies are connected to the outer side faces of the two vertical plates in a penetrating mode, a mounting plate is jointly and fixedly connected to the upper ends of the three supporting assemblies, and a dust removal assembly is connected to the middle of the upper end of the mounting plate in a penetrating mode. According to the biomass gasification supply equipment for the industrial boiler, the dust removal assembly is arranged, a plurality of electric telescopic rods are driven to rotate through a rotating motor, so that a plurality of wall scraping plates are driven to rotate on the inner wall face of the chimney, dust adhering to the inner wall face of the chimney can be effectively and rapidly hung off, and the dust removal efficiency is improved. And the dust removal effect of the chimney is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of equipment dust removal, in particular to an industrial boiler biomass gasification supply device. Background Art

[0002] Biomass energy is the fourth largest energy source after coal, oil and natural gas, accounting for a certain proportion of the world's energy consumption; and biomass combustion achieves zero emission in terms of total CO2, eliminating the root cause of the greenhouse effect. Therefore, biomass energy will become an important part of future sustainable energy.

[0003] Biomass gasification combustion equipment is a new energy-saving product specially used to process waste wood and crop waste and convert it into combustible gas. The core technology of the product is to use the biomass gasification device to heat and decompose the biomass waste, so that it volatilizes carbon monoxide and hydrocarbons and converts them into combustible gas, which is called biomass gas. This combustible gas extracted from biomass is a new type of clean and advanced renewable energy that can be used for boilers or other burners. However, the existing industrial boiler biomass gasification supply equipment still has the following shortcomings: 1. The existing chimney dust removal device for industrial boiler biomass gasification supply equipment cannot clamp and fix the chimney when in use, which makes the chimney easy to shake during dust removal, thereby affecting the dust removal work of the chimney; 2. The existing chimney dust removal device for industrial boiler biomass gasification supply equipment cannot quickly clean the dust adhering to the inner wall of the chimney when in use, making the dust cleaning effect poor. Therefore, we propose an industrial boiler biomass gasification supply equipment. Utility Model Content

[0004] The main purpose of the utility model is to provide an industrial boiler biomass gasification supply device, which can effectively solve the problems in the background technology.

[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:

[0006] An industrial boiler biomass gasification supply device includes a base, characterized in that: three bolts are threadedly connected to the upper end of the base, three support assemblies are fixedly clamped on the outer surface of the base by three bolts, a placement tube is fixedly connected to the middle part of the upper end of the base, the upper left part and the upper right part of the placement tube are fixedly connected to vertical plates, the outer side surfaces of the two vertical plates are interspersed with clamping assemblies, the upper ends of the three support assemblies are commonly fixedly connected to a mounting plate, and a dust removal assembly is interspersed with the middle part of the upper end of the mounting plate.

[0007] Preferably, the dust removal assembly includes a rotating motor, a mounting head is fixedly installed on the output end of the rotating motor, a mounting rod is fixedly connected to the lower end of the mounting head, a plurality of electric telescopic rods are fixedly connected to the outer surface of the mounting rod, a scraper plate is fixedly installed on the ends of the plurality of electric telescopic rods away from the mounting rod, the lower end of the rotating motor is fixedly connected to the upper end of the mounting plate, and the output end of the rotating motor passes through the upper end of the mounting plate and extends to the lower end of the mounting plate.

[0008] Preferably, a plurality of the electric telescopic rods are distributed in a rectangular array on the outer surface of the mounting rod, and a gap exists between the lower end of the mounting rod and the lower inner wall surface of the placement tube.

[0009] Preferably, the support assembly includes a mounting block, the left end of the mounting block on the left side is fixedly connected to a support rod, the movable plate on the upper end of the support rod is sleeved with an extension rod, the upper part of the left end of the support rod on the left side is threadedly connected to a limiting rod, and the right end of the mounting block on the left side is fixedly clamped to the outer surface of the base.

[0010] Preferably, the clamping assembly includes a screw rod, the right end of the screw rod on the left side is movably connected to a clamping plate, the outer surface of the clamping plate is fixedly connected to a spring, the left end of the spring on the left side is fixedly connected to the right end of the corresponding vertical plate, and the right end of the screw rod on the left side is threadedly connected to the left end of the corresponding vertical plate.

[0011] Preferably, a circular hole is opened in the middle of the outer surface of the clamping plate, and the right part of the screw on the left side is sleeved in the circular hole.

[0012] Compared with the prior art, the utility model has the following beneficial effects:

[0013] 1. In the utility model, by setting a clamping assembly, the chimney of the industrial boiler biomass gasification supply equipment is placed in the placement tube and the mounting rod is sleeved in the chimney, and the two screws are rotated successively, and the corresponding two springs are extended to drive the corresponding two clamping plates to move respectively, until the two clamping plates are tightly clamped on the outer surface of the chimney, so as to clamp and fix the chimney, avoid shaking of the chimney when the dust is removed, and effectively improve the stability of the chimney during dust removal, thereby improving the dust removal effect.

[0014] 2. In the utility model, by setting a dust removal component, when the chimney is fixed, the corresponding scraper plates are driven to move by the electric telescopic rods until the outer surfaces of all the scraper plates are in contact with the inner wall of the chimney, and then the rotating motor is started to drive a plurality of electric telescopic rods to rotate, thereby driving a plurality of scraper plates to rotate on the inner wall of the chimney, which can effectively and quickly drop the dust adhering to the inner wall of the chimney, thereby improving the dust removal effect of the chimney, which is practical and effective. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is a schematic diagram of the overall structure of an industrial boiler biomass gasification supply device of the utility model;

[0016] Figure 2 This is a structural schematic diagram of a support assembly of an industrial boiler biomass gasification supply device of the utility model;

[0017] Figure 3 This is a structural schematic diagram of a clamping assembly of an industrial boiler biomass gasification supply device of the utility model;

[0018] Figure 4 This is a structural schematic diagram of a dust removal component of an industrial boiler biomass gasification supply device according to the utility model.

[0019] In the figure: 1. base; 2. bolt; 3. support assembly; 4. placement tube; 5. vertical plate; 6. clamping assembly; 7. mounting plate; 8. dust removal assembly; 31. mounting block; 32. support rod; 33. extension rod; 34. limit rod; 61. screw rod; 62. clamping plate; 63. spring; 81. rotating motor; 82. mounting head; 83. mounting rod; 84. electric telescopic rod; 85. scraper plate. DETAILED DESCRIPTION

[0020] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.

[0021] In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "two ends", "one end", "the other end" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0022] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "connected", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0023] See also Figure 1-4 , the utility model provides a technical solution:

[0024] An industrial boiler biomass gasification supply device includes a base 1, characterized in that: three bolts 2 are threadedly connected to the upper end of the base 1, three support assemblies 3 are fixedly clamped on the outer surface of the base 1 by the three bolts 2, a placement tube 4 is fixedly connected to the middle of the upper end of the base 1, and vertical plates 5 are fixedly connected to the upper left and upper right parts of the placement tube 4. The outer sides of the two vertical plates 5 are interspersed with clamping assemblies 6, and the upper ends of the three support assemblies 3 are commonly fixedly connected to a mounting plate 7, and a dust removal assembly 8 is interspersed with the middle of the upper end of the mounting plate 7.

[0025] In this embodiment, the dust removal assembly 8 includes a rotating motor 81, and a mounting head 82 is fixedly installed at the output end of the rotating motor 81. The lower end of the mounting head 82 is fixedly connected to a mounting rod 83, and the outer surface of the mounting rod 83 is fixedly connected to a plurality of electric telescopic rods 84. The rotating motor 81 and the electric telescopic rods 84 are both set as traditional structures in the prior art and are not the innovation points of the present utility model. A scraper plate 85 is fixedly installed at one end of the plurality of electric telescopic rods 84 away from the mounting rod 83. The lower end of the rotating motor 81 is fixedly connected to the upper end of the mounting plate 7, and the output end of the rotating motor 81 passes through the upper end of the mounting plate 7 and extends to the lower end of the mounting plate 7.

[0026] In this embodiment, a plurality of electric telescopic rods 84 are distributed in a rectangular array on the outer surface of the mounting rod 83, and there is a gap between the lower end of the mounting rod 83 and the lower inner wall of the placement tube 4; the support assembly 3 includes a mounting block 31, the left end of the left mounting block 31 is fixedly connected to a support rod 32, the upper end of the support rod 32 is sleeved with an extension rod 33, the upper left end of the left support rod 32 is threadedly connected to a limiting rod 34, and the outer surface of the limiting rod 34 is provided with a threaded groove, which can effectively realize the limiting fixation of the extension rod 33, and the left mounting block 31 is fixedly connected to the left end of the support rod 32. The right end is fixedly connected to the outer surface of the base 1; the clamping assembly 6 includes a screw 61, the right end of the left screw 61 is movably connected to a clamping plate 62, the outer surface of the clamping plate 62 is fixedly connected to a spring 63, the screw 61 is located in the corresponding spring 63 and there is a gap with the inner wall surface of the corresponding spring 63, the left end of the left spring 63 is fixedly connected to the right end of the corresponding vertical plate 5, and the right end of the left screw 61 is threadedly connected to the left end of the corresponding vertical plate 5; a circular hole is opened in the middle of the outer surface of the clamping plate 62, and the right part of the left screw 61 is sleeved in the circular hole.

[0027] It should be noted that the utility model is an industrial boiler biomass gasification supply equipment. During specific use, the three limit rods 34 are rotated to remove, and then the three extension rods 33 are respectively extended upward in the corresponding three support rods 32 until they are extended to the point where the chimney of the industrial boiler biomass gasification supply equipment can be placed in the placement tube 4. When the heights of the three extension rods 33 are adjusted, the chimney of the industrial boiler biomass gasification supply equipment is placed in the placement tube 4 and the mounting rod 83 is sleeved in the chimney. Then the three extension rods 33 are respectively retracted downward until the mounting rod 83 is sleeved in the chimney at a suitable height. The three limit rods 34 are then respectively threadedly connected to the corresponding support rods 32 until they are tightly against the corresponding three extension rods 33. The two screws 61 are rotated in succession to cooperate with the corresponding two springs 63 to extend. The two corresponding clamping plates 62 are driven to move respectively until the two clamping plates 62 are tightly clamped on the outer surface of the chimney, so as to clamp and fix the chimney and avoid the chimney from shaking when the dust is removed. The stability of the chimney during dust removal can be effectively improved, thereby improving the dust removal effect. When the chimney is fixed, the corresponding scraper plates 85 are driven to move respectively by the electric telescopic rod 84 until the outer surfaces of all scraper plates 85 are in contact with the inner wall surface of the chimney, and then the rotating motor 81 is started. The rotating motor 81 drives several electric telescopic rods 84 to rotate, thereby driving several scraper plates 85 to rotate on the inner wall surface of the chimney, which can effectively and quickly remove the dust adhered to the inner wall surface of the chimney, thereby improving the dust removal effect of the chimney of the industrial boiler biomass gasification supply equipment, which is practical and effective.

[0028] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.

Claims

1. An industrial boiler biomass gasification supply device, comprising a base (1), characterized in that: The upper end of the base (1) is threadedly connected with three bolts (2), and the outer surface of the base (1) is fixedly connected with three support assemblies (3) by means of the three bolts (2). A placement tube (4) is fixedly connected to the middle of the upper end of the base (1), and vertical plates (5) are fixedly connected to the upper left and upper right parts of the placement tube (4). The outer side surfaces of the two vertical plates (5) are interlaced with clamping assemblies (6), and the upper ends of the three support assemblies (3) are commonly fixedly connected with a mounting plate (7), and a dust removal assembly (8) is interlaced with the middle of the upper end of the mounting plate (7).

2. The industrial boiler biomass gasification supply equipment according to claim 1, characterized in that: The dust removal component (8) comprises a rotating motor (81), a mounting head (82) is fixedly mounted on the output end of the rotating motor (81), a mounting rod (83) is fixedly connected to the lower end of the mounting head (82), a plurality of electric telescopic rods (84) are fixedly connected to the outer surface of the mounting rod (83), and a scraper plate (85) is fixedly mounted on one end of the plurality of electric telescopic rods (84) away from the mounting rod (83), the lower end of the rotating motor (81) is fixedly connected to the upper end of the mounting plate (7), and the output end of the rotating motor (81) passes through the upper end of the mounting plate (7) and extends to the lower end of the mounting plate (7).

3. The industrial boiler biomass gasification supply equipment according to claim 2, characterized in that: A plurality of the electric telescopic rods (84) are distributed in a rectangular array on the outer surface of the mounting rod (83), and a gap exists between the lower end of the mounting rod (83) and the lower inner wall surface of the placement cylinder (4).

4. The industrial boiler biomass gasification supply equipment according to claim 2, characterized in that: The support assembly (3) comprises a mounting block (31), the left end of the mounting block (31) on the left side is fixedly connected to a support rod (32), the upper end of the support rod (32) is sleeved with an extension rod (33), the upper left end of the support rod (32) on the left side is threadedly connected to a limiting rod (34), and the right end of the mounting block (31) on the left side is fixedly clamped to the outer surface of the base (1).

5. The industrial boiler biomass gasification supply equipment according to claim 2, characterized in that: The clamping assembly (6) comprises a screw rod (61), the right end of the screw rod (61) on the left side is movably connected to a clamping plate (62), the outer surface of the clamping plate (62) is fixedly connected to a spring (63), the left end of the spring (63) on the left side is fixedly connected to the right end of the corresponding vertical plate (5), and the right end of the screw rod (61) on the left side is threadedly connected to the left end of the corresponding vertical plate (5).

6. The industrial boiler biomass gasification supply equipment according to claim 5, characterized in that: A circular hole is formed in the middle of the outer surface of the clamping plate (62), and the right part of the screw rod (61) on the left side is sleeved in the circular hole.