Sunken balance weight device for straight section of railway continuous beam

By setting cast side brackets and balanced side brackets on the embedded connecting blocks on both sides of the bridge pier and placing the weight platform with pull rods, the problems of high safety risks and low craftsmanship in the traditional counterweight method are solved, and the low position at the bottom of the bridge pier is achieved The convenience of placing weights and the improvement of construction efficiency.

CN222008654UActive Publication Date: 2024-11-15THE FIRST ENG CO LTD OF CHINA RAILWAY NO 12 BUREAU GRP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420122049.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-17
Publication Date
2024-11-15
Estimated Expiration
2034-01-17

AI Technical Summary

Technical Problem

In the construction of a straight line section of the bridge side span, the traditional counterweight method requires transporting a large amount of load to a high place, which poses safety risks, difficulty in operation, low craftsmanship and high cost.

Method used

A sinking balance weight device for linear sections of railway continuous beams was designed. The cast side bracket and the balanced side bracket were set on the embedded connecting blocks on both sides of the bridge pier, and the counterweight platform was placed at the low position at the bottom of the bridge pier by using a pull rod. , conveniently place weight blocks, reducing lifting height and safety risks.

Benefits of technology

The convenience of placing weight blocks at the low position at the bottom of the bridge pier is achieved, the safety risks and costs of construction are reduced, and the construction efficiency is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222008654U_ABST
    Figure CN222008654U_ABST
Patent Text Reader

Abstract

A railway continuous beam straight-line segment sinking type balance weight device comprises a pouring side bracket, a balance side bracket, a pull rod and embedded connecting blocks symmetrically embedded in the two sides of a bridge pier, and the pouring side bracket and the balance side bracket are symmetrical to each other and connected to the embedded connecting blocks on the two sides of the bridge pier respectively. The pouring side bracket supports the continuous beam below the side span continuous beam, the upper end of the pull rod is connected to the balance side bracket, the lower end of the pull rod is connected with a balance weight platform in a free drooping mode, the distance between the balance weight platform and the bottom ground of a pier is 0-1 m, and a plurality of balance weights are placed on the balance weight platform. The pull rod is arranged, the upper end of the pull rod is connected to the balance side bracket, the lower end of the pull rod is freely connected with the balance weight platform in a drooping mode, and the distance between the balance weight platform and the bottom ground of the pier is 0-1 m, so that the balance weight platform falls to the low position of the pier bottom, a balance weight is conveniently placed on the balance weight platform, labor and time are saved, and the safety risk is low.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of railway construction, and in particular relates to a sinking type balancing counterweight device for a straight section of a railway continuous beam. Background Art

[0002] When constructing the straight section of the side span of a bridge, in order to ensure the safety of the structure during construction, it is usually necessary to apply counterweights using the principle of mechanical balance. The traditional way of applying counterweights is to pile counterweights on the triangular corbel brackets set on both sides of the top of the pier, that is, to apply a load equal to the weight of the cantilever concrete on the triangular corbel brackets on the symmetrical side of the cast-in-place section of the side span.

[0003] However, during construction, a large amount of counterweights need to be transported to the top of the pier. The lifting height is high, the safety risk is high, the operation is difficult for personnel, the work efficiency is low, and the cost is high. Utility Model Content

[0004] In view of the problems existing in the prior art, the utility model aims to provide a sinking balancing counterweight device for the straight section of a railway continuous beam.

[0005] In order to solve the above problems, the utility model adopts the following technical solutions:

[0006] A sunken balancing counterweight device for a straight section of a railway continuous beam comprises a casting side bracket, a balancing side bracket, a tie rod and embedded connection blocks symmetrically embedded on both sides of a pier. The casting side bracket and the balancing side bracket are symmetrical to each other and are respectively connected to the embedded connection blocks on both sides of the pier. The casting side bracket supports the continuous beam below the side span continuous beam. The upper end of the tie rod is connected to the balancing side bracket, and the lower end of the tie rod is freely hanging and connected to a counterweight platform. The counterweight platform is 0m-1m away from the ground at the bottom of the pier, and a number of counterweight blocks are placed on the counterweight platform.

[0007] Preferably, the embedded connecting block includes an upper embedded connecting block and a lower embedded connecting block, and there is an upper embedded connecting block and a lower embedded connecting block on each side of the pier, the upper embedded connecting block is above the lower embedded connecting block, and the upper embedded connecting blocks on both sides of the pier are interconnected inside the pier to form a whole.

[0008] Preferably, the balancing side bracket includes a first horizontal strut, a first diagonal strut and a first connecting rod, the first horizontal strut is horizontally arranged and one end is connected to the upper embedded connecting block by a screw, the first diagonal strut is inclined and one end is connected to the lower embedded connecting block, the first horizontal strut and the first diagonal strut are connected to each other at one end away from the pier, and a plurality of first connecting rods are connected between the first horizontal strut and the first diagonal strut to form a stable triangular bracket.

[0009] Preferably, a plurality of first distribution beams are arranged side by side at equal intervals on the upper surface of the first horizontal support rod, a plurality of vertical through holes are opened on the first distribution beam at equal intervals, the upper ends of a plurality of pull rods pass through the through holes on the first distribution beam, the upper ends of the pull rods are connected with upper clamping blocks, the upper clamping blocks are clamped on the upper surface of the first distribution beam, a plurality of lower distribution beams are arranged side by side at equal intervals below the counterweight platform, a plurality of vertical through holes are opened on the lower distribution beam at equal intervals, the positions and quantities of the through holes on the lower distribution beam correspond to those on the first distribution beam, the lower ends of the pull rods pass through the through holes on the lower distribution beam, the lower ends of the pull rods are connected with lower clamping blocks, the lower clamping blocks are clamped on the lower surface of the lower distribution beam.

[0010] Preferably, the pull rod is a precision-rolled threaded steel bar, the upper clamping block and the lower clamping block are sleeves with internal threads, and the upper clamping block and the lower clamping block are threadedly connected to the surface of the pull rod.

[0011] Preferably, the counterweight platform is 50 cm away from the ground at the bottom of the pier.

[0012] Preferably, the counterweight platform is composed of several steel templates with a length of 3m and a width of 2m, and the panel of the steel template is a 6mm thick steel plate.

[0013] Preferably, the casting side bracket includes a second horizontal strut, a second diagonal strut and a second connecting rod, the second horizontal strut is horizontally arranged and one end is connected to the upper embedded connecting block by a screw, the second diagonal strut is inclined and one end is connected to the lower embedded connecting block, the second horizontal strut and the second diagonal strut are connected to each other at one end away from the pier, and a plurality of second connecting rods are connected between the second horizontal strut and the second diagonal strut to form a stable triangular bracket.

[0014] Preferably, second distribution beams are arranged side by side at equal intervals on the upper surface of the second horizontal support rod, the second distribution beams include a plurality of transverse distribution beams and a plurality of longitudinal distribution beams, the longitudinal distribution beams and the transverse distribution beams are vertically overlapped and cross-arranged above the casting side bracket, and a plurality of unloading blocks are arranged between the second distribution beams and the casting side bracket.

[0015] Preferably, the counterweight block is a prefabricated cubic concrete block with a side length of one meter.

[0016] Beneficial effects of the utility model

[0017] Compared with the prior art, the advantages of the present invention are:

[0018] The utility model arranges a pull rod, the upper end of which is connected to a balancing side bracket, and the lower end of which hangs freely and is connected to a counterweight platform, the counterweight platform being 0m-1m away from the ground at the bottom of the pier, so that the counterweight platform is dropped to a low position at the bottom of the pier, which is convenient for placing a counterweight block on the counterweight platform, saving labor and time and having low safety risks. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the structure of the utility model;

[0020] Figure 2 for Figure 1 A partial enlarged view of the middle A;

[0021] Figure 3 for Figure 1 A partial enlarged view of point B in the middle;

[0022] Figure 4 for Figure 1 A partial enlarged view of point C in the middle. DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0024] In the description of the present invention, it should be noted that the terms "upper / lower end", "inner", "outer", "front end", "rear end", "two ends", "one end", "the other end" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0025] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "setting / sleeving", "sleeve connection", "connection", etc. should be understood in a broad sense. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0026] See also Figure 1-4The utility model provides a technical solution: a railway continuous beam straight section sinking balancing counterweight device, comprising a casting side bracket 1, a balancing side bracket 2, a tie rod 4 and embedded connection blocks 3 symmetrically embedded on both sides of the pier, the casting side bracket 1 and the balancing side bracket 2 are symmetrical to each other and are respectively connected to the embedded connection blocks 3 on both sides of the pier, the casting side bracket 1 forms a support for the continuous beam under the side span continuous beam, the upper end of the tie rod 4 is connected to the balancing side bracket 2, the lower end of the tie rod 4 is freely drooping and connected to a counterweight platform 5, the counterweight platform 5 is 0m-1m away from the ground at the bottom of the pier, and a plurality of counterweight blocks 6 are placed on the counterweight platform 5.

[0027] The utility model arranges a pull rod 4, the upper end of which is connected to a balancing side bracket 2, and the lower end of which hangs freely and is connected to a counterweight platform 5, the counterweight platform 5 being 0m-1m away from the ground at the bottom of the pier, so that the counterweight platform 5 is dropped to a low position at the bottom of the pier, which is convenient for placing a counterweight block 6 on the counterweight platform 5, thus saving labor and time and having low safety risks.

[0028] Furthermore, the embedded connection block 3 includes an upper embedded connection block 31 and a lower embedded connection block 32. The upper embedded connection block 31 and the lower embedded connection block 32 are respectively provided on both sides of the pier. The upper embedded connection block 31 is above the lower embedded connection block 32. The upper embedded connection blocks 31 on both sides of the pier are mutually connected to form a whole inside the pier. The upper embedded connection blocks 31 are mutually connected to form a whole inside the pier to strengthen the fixation and prevent the embedded connection blocks from being pulled out of the pier and falling off to cause danger. When subjected to the pulling force of the casting side bracket 1 and the balancing side bracket 2 on both sides, the two sides are subjected to uniform force and good balance.

[0029] Furthermore, the balancing side bracket 2 includes a first horizontal strut 21, a first diagonal strut 22 and a first connecting rod 23. The first horizontal strut 21 is horizontally arranged and one end is connected to the upper embedded connecting block 31 by a screw. The first diagonal strut 22 is tilted and one end is connected to the lower embedded connecting block 32. The first horizontal strut 21 and the first diagonal strut 22 are connected to each other at one end away from the pier. A plurality of first connecting rods 23 are connected between the first horizontal strut 21 and the first diagonal strut 22 to form a stable triangular bracket with high stability.

[0030] Further, a plurality of first distribution beams 24 are arranged side by side at equal intervals on the upper surface of the first horizontal support rod 21, a plurality of vertical through holes are opened on the first distribution beam 24 at equal intervals, the upper ends of a plurality of pull rods 4 pass through the through holes on the first distribution beam 24, the upper ends of the pull rods 4 are connected with upper clamping blocks 41, and the upper clamping blocks 41 are clamped on the upper surface of the first distribution beam 24, and a plurality of lower distribution beams 51 are arranged side by side at equal intervals below the counterweight platform 5, a plurality of vertical through holes are opened on the lower distribution beam 51 at equal intervals, and the positions and quantities of the through holes on the lower distribution beam 51 correspond to those on the first distribution beam 24, the lower ends of the pull rods 4 pass through the through holes on the lower distribution beam 51, the lower ends of the pull rods 4 are connected with lower clamping blocks 42, and the lower clamping blocks 42 are clamped on the lower surface of the lower distribution beam 51. By arranging the first distribution beam 24, the lower distribution beam 51, and the counterweight platform 5, the weight of the counterweight block 6 is evenly distributed on the balancing side bracket 2, so that the balancing side bracket 2 is subjected to uniform force.

[0031] Specifically, the pull rod 4 is a precision-rolled threaded steel bar, the upper clamping block 41 and the lower clamping block 42 are sleeves with internal threads, and the upper clamping block 41 and the lower clamping block 42 are threadedly connected to the surface of the pull rod 4 for easy installation.

[0032] Specifically, the counterweight platform 5 is 50 cm away from the ground at the bottom of the pier.

[0033] Specifically, the counterweight platform 5 is composed of several steel templates with a length of 3m and a width of 2m, and the panel of the steel template is a 6mm thick steel plate.

[0034] Furthermore, the casting side bracket 1 includes a second horizontal strut 11, a second diagonal strut 12 and a second connecting rod 13. The second horizontal strut 11 is horizontally arranged and one end is connected to the upper embedded connecting block 31 through a screw. The second diagonal strut 12 is inclined and one end is connected to the lower embedded connecting block 32. The second horizontal strut 11 and the second diagonal strut 12 are connected to each other at one end away from the pier. A plurality of second connecting rods 13 are connected between the second horizontal strut 11 and the second diagonal strut 12 to form a stable triangular bracket with high stability.

[0035] Furthermore, second distribution beams 14 are arranged side by side at equal intervals on the upper surface of the second horizontal support rod 11. The second distribution beams 14 include a plurality of transverse distribution beams and a plurality of longitudinal distribution beams. The longitudinal distribution beams and the transverse distribution beams are vertically overlapped and cross-arranged above the casting side bracket 1. A plurality of unloading blocks 15 are arranged between the second distribution beam 14 and the casting side bracket 1. The weight of the continuous beam is evenly distributed by arranging the second distribution beam 14, so that the casting side bracket 1 is evenly stressed. The unloading blocks 15 are arranged to facilitate the lifting and lowering of the second distribution beam 14, and to facilitate the installation and disassembly of the second distribution beam 14.

[0036] Specifically, the counterweight block 6 is a prefabricated cubic concrete block with a side length of one meter. During construction, the weight required for counterweighting on the counterweight side can be calculated and placed during the concrete pouring process of the straight section of the side span of the bridge.

[0037] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions. The sentence "includes an element defined by ... does not exclude the existence of other identical elements in the process, method, article or device including the element".

[0038] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A railway continuous beam straight section sinking balance weight device, characterized in that: The invention comprises a casting side bracket (1), a balancing side bracket (2), a tie rod (4) and embedded connection blocks (3) symmetrically embedded on both sides of the pier. The casting side bracket (1) and the balancing side bracket (2) are symmetrical to each other and are respectively connected to the embedded connection blocks (3) on both sides of the pier. The casting side bracket (1) supports the continuous beam below the side span continuous beam. The upper end of the tie rod (4) is connected to the balancing side bracket (2). The lower end of the tie rod (4) is freely drooping and connected to a counterweight platform (5). The counterweight platform (5) is 0m-1m away from the ground at the bottom of the pier. A plurality of counterweight blocks (6) are placed on the counterweight platform (5).

2. The railway continuous beam straight section sinking balancing weight device according to claim 1 is characterized in that: The embedded connection block (3) comprises an upper embedded connection block (31) and a lower embedded connection block (32), and an upper embedded connection block (31) and a lower embedded connection block (32) are respectively provided on both sides of the pier, and the upper embedded connection block (31) is above the lower embedded connection block (32), and the upper embedded connection blocks (31) on both sides of the pier are mutually connected inside the pier to form a whole.

3. The railway continuous beam straight section sinking balancing weight device according to claim 2 is characterized in that: The balancing side bracket (2) comprises a first horizontal brace (21), a first diagonal brace (22) and a first connecting rod (23); the first horizontal brace (21) is arranged horizontally and one end of the first diagonal brace (22) is connected to an upper pre-buried connecting block (31) via a screw rod; the first diagonal brace (22) is arranged obliquely and one end of the first diagonal brace (22) is connected to a lower pre-buried connecting block (32); the ends of the first horizontal brace (21) and the first diagonal brace (22) away from the pier are connected to each other; and a plurality of first connecting rods (23) are connected between the first horizontal brace (21) and the first diagonal brace (22) to form a stable triangular bracket.

4. The railway continuous beam straight section sinking balancing weight device according to claim 3 is characterized in that: A plurality of first distribution beams (24) are arranged side by side at equal intervals on the upper surface of the first horizontal support rod (21), a plurality of vertical through holes are opened on the first distribution beam (24) at equal intervals, the upper ends of a plurality of pull rods (4) pass through the through holes on the first distribution beam (24), the upper ends of the pull rods (4) are connected to upper clamping blocks (41), the upper clamping blocks (41) are clamped on the upper surface of the first distribution beam (24), a plurality of lower distribution beams (51) are arranged side by side at equal intervals below the counterweight platform (5), a plurality of vertical through holes are opened on the lower distribution beam (51) at equal intervals, the positions and numbers of the through holes on the lower distribution beam (51) correspond to those on the first distribution beam (24), the lower ends of the pull rods (4) pass through the through holes on the lower distribution beam (51), the lower ends of the pull rods (4) are connected to lower clamping blocks (42), the lower clamping blocks (42) are clamped on the lower surface of the lower distribution beam (51).

5. The railway continuous beam straight section sinking balancing weight device according to claim 4, characterized in that: The pull rod (4) is a precision-rolled threaded steel bar, the upper clamping block (41) and the lower clamping block (42) are sleeves with internal threads, and the upper clamping block (41) and the lower clamping block (42) are threadedly connected to the surface of the pull rod (4).

6. The railway continuous beam straight section sinking balancing weight device according to claim 1, characterized in that: The counterweight platform (5) is 50 cm away from the ground at the bottom of the pier.

7. The railway continuous beam straight section sinking balancing weight device according to claim 1, characterized in that: The counterweight platform (5) is composed of a number of steel templates with a length of 3m and a width of 2m, and the panel of the steel template is a 6mm thick steel plate.

8. The railway continuous beam straight section sinking balancing weight device according to claim 2, characterized in that: The casting side bracket (1) comprises a second horizontal support rod (11), a second oblique support rod (12) and a second connecting rod (13); the second horizontal support rod (11) is arranged horizontally and one end is connected to the upper embedded connecting block (31) through a screw rod; the second oblique support rod (12) is arranged obliquely and one end is connected to the lower embedded connecting block (32); the second horizontal support rod (11) and the second oblique support rod (12) are connected to each other at one end away from the pier; and a plurality of second connecting rods (13) are connected between the second horizontal support rod (11) and the second oblique support rod (12) to form a stable triangular bracket.

9. The railway continuous beam straight section sinking balancing weight device according to claim 8, characterized in that: Second distribution beams (14) are arranged side by side at equal intervals on the upper surface of the second horizontal support rod (11), the second distribution beams (14) comprising a plurality of transverse distribution beams and a plurality of longitudinal distribution beams, the longitudinal distribution beams and the transverse distribution beams being vertically overlapped and cross-arranged above the casting side bracket (1), and a plurality of unloading blocks (15) are arranged between the second distribution beams (14) and the casting side bracket (1).

10. The railway continuous beam straight section sinking balancing weight device according to claim 1, characterized in that: The counterweight block (6) is a prefabricated cubic concrete block with a side length of one meter.