Protection device for preventing deformation and separation of oil pipe at junction of hydraulic dam foundation
By installing protective devices for sand, low-foam plastic plates and micro-expanded concrete at the base joints of the hydraulic dam, the deformation and fragmentation problem caused by uneven settlement of the oil pipe is solved, ensuring the safe operation of the hydraulic dam and the construction requirements of hydraulic construction. .
Patent Information
- Application Number
- CN202420235636.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-31
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-01-31
AI Technical Summary
At the base joint of the hydraulic dam, the oil pipe is prone to deform and split due to uneven settlement, resulting in oil leakage, affecting the water ecology and safe operation.
A protective device is designed, including laying sand and low-foam plastic plates in the oil pipe groove, setting up micro-expanded concrete and fixing units at the joints, and strengthening the structure with inserts and rubber water stops to prevent the oil pipe from deforming and splitting.
It effectively prevents deformation and splitting of oil pipes under uneven settlement, ensures the safe operation of hydraulic dams, and provides a new protection mode for hydraulic construction projects.
Smart Images

Figure CN222008986U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of water conservancy oil pipe protection, and in particular relates to a protection device for preventing the oil pipe at the seam of a hydraulic dam foundation from being deformed and cut. Background Art
[0002] On wide rivers, large-span hydraulic dams are prone to uneven settlement. Usually, a separate bottom plate with strong ability to adapt to foundation settlement and deformation is selected, and foundation replacement and other treatment methods are used to increase the rigidity of the foundation to meet the design requirements. At the construction joints of the hydraulic dam bottom plate, the oil pipes are prone to deformation due to uneven settlement, causing cracks, resulting in oil leakage from the hydraulic dam, affecting the water ecology and affecting the safe operation of the hydraulic dam. Utility Model Content
[0003] The utility model aims to provide a protective device to prevent deformation and cracking of oil pipes at the seam of hydraulic dam foundation, and effectively avoid deformation and cracking of oil pipes caused by rigid connection when uneven settlement at the seam occurs.
[0004] The technical scheme adopted by the utility model is a protective device for preventing the oil pipe from being deformed and cut at the seam of the hydraulic dam foundation, comprising a foundation cushion layer, a hydraulic dam bottom plate foundation is cast on the upper surface of the foundation cushion layer, an oil pipe groove is opened in the hydraulic dam bottom plate foundation, an oil pipe groove is laid in the oil pipe groove, protective mechanisms are arranged on the upper and lower sides of the oil pipe at the seam, and a plurality of deformation joints are opened in the hydraulic dam bottom plate foundation, and each deformation joint is arranged perpendicular to the oil pipe.
[0005] The utility model is also characterized in that:
[0006] The protection mechanism includes sand and a first low-foam plastic plate arranged in sequence. The first low-foam plastic plate is arranged close to the oil pipe, micro-expansion concrete is poured on the sand surface above the oil pipe, and fixing units are connected to both ends of the first low-foam plastic plate.
[0007] The fixing unit comprises slots arranged at two ends of the first low-foam plastic plate, each slot is coated with special plastic glue, and lead wires are connected between the opposite slots.
[0008] The width of the expansion joint is 2cm.
[0009] The expansion joint is filled with the embedded 651 type rubber waterstop, and the expansion joint is filled with the second low foam plastic board. The expansion joint is smoothed with 1:2 waterproof mortar 2cm away from the joint.
[0010] Several dowel bars with a diameter of 25 mm are embedded in the bottom plate foundation of the hydraulic dam. The longitudinal spacing of the dowel bars is 20 cm and the transverse spacing is 30 cm. The dowel bars pass through the oil pipe groove.
[0011] The total laying thickness of the sand is not less than 30cm, and the particle size of the sand is 0.5mm~1mm.
[0012] The thickness of the first low-foam plastic plate and the second low-foam plastic plate are both 2 cm, and the overlapping lengths of the first low-foam plastic plate and the second low-foam plastic plate on both sides of the oil pipe at the seam are both 25 cm to 35 cm.
[0013] The beneficial effect of the utility model is that the protective device for preventing the oil pipe from being deformed and cut at the seam of the hydraulic dam foundation can form effective protection at the seam of the oil pipe groove, which not only meets the construction requirements of the hydraulic dam pipe bed foundation, but also serves as a new mode for eliminating deformation and cuts caused by uneven settlement, which will bring guiding value to the implementation of hydraulic construction projects; spreading sand in the oil pipe groove and wrapping low-foam plastic plates above and below the oil pipe at the seam can effectively avoid deformation and cuts of the oil pipe caused by rigid connection during uneven settlement, thereby protecting the oil pipe well and ensuring the safe operation of the hydraulic dam. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a structural schematic diagram of a protective device for preventing the oil pipe from deforming and splitting at the seam of a hydraulic dam foundation according to the utility model;
[0015] Figure 2 It is an enlarged view of the riding seam position;
[0016] Figure 3 It is a schematic diagram of the local connection structure of the oil pipe at the seam;
[0017] Figure 4 yes Figure 1 sectional view of .
[0018] In the figure, 1. oil pipe groove, 2. first low-foam plastic board, 3. hydraulic dam bottom plate foundation, 4. expansion joint, 5. oil pipe, 6. second low-foam plastic board, 7. sand, 8. foundation cushion, 9. inserted reinforcement, 10. water stop, 11. mortar, 12. micro-expansive concrete, 13. notch, 14. special glue for plastic, 15. lead wire. DETAILED DESCRIPTION
[0019] The utility model is described in detail below with reference to the accompanying drawings and specific implementation modes.
[0020] The utility model is a protective device for preventing the oil pipe from deforming and breaking at the seam of the hydraulic dam foundation. Figure 1As shown, it includes a foundation cushion layer 8, a hydraulic dam bottom plate foundation 3 is cast on the upper surface of the foundation cushion layer 8, an oil pipe groove 1 is opened in the hydraulic dam bottom plate foundation 3, an oil pipe 5 is laid in the oil pipe groove 1, and protective mechanisms are provided on the upper and lower sides of the oil pipe 5 at the joint, and a plurality of deformation joints 4 are opened in the hydraulic dam bottom plate foundation 3, and each deformation joint 4 is arranged perpendicular to the oil pipe 5. The cross section of the oil pipe groove 1 is set as a U-shaped structure, and the U-shaped oil pipe groove 1 serves as the pipe bed of the oil pipe. The oil pipe groove 1 is reserved with a depth of not less than 60 cm when casting the hydraulic dam bottom plate foundation 3, and the width is determined according to the number of oil pipes 5. According to actual conditions, multiple layers of oil pipes 5 can be arranged in the oil pipe groove 1.
[0021] Example 1
[0022] A protective device for preventing deformation and splitting of an oil pipe at a seam of a hydraulic dam foundation comprises a foundation cushion layer 8, a hydraulic dam bottom plate foundation 3 is cast on the upper surface of the foundation cushion layer 8, an oil pipe groove 1 is opened in the hydraulic dam bottom plate foundation 3, an oil pipe 5 is laid in the oil pipe groove 1, protective mechanisms are arranged on the upper and lower sides of the oil pipe 5 at the seam, and a plurality of deformation joints 4 are opened in the hydraulic dam bottom plate foundation 3, and each deformation joint 4 is arranged perpendicular to the oil pipe 5.
[0023] like Figure 2-3 As shown, the protection mechanism includes sand 7 and a first low-foam plastic plate 2 arranged in sequence, the first low-foam plastic plate 2 is arranged close to the oil pipe 5, the sand surface above the oil pipe 5 is poured with micro-expansion concrete 12, and the two ends of the first low-foam plastic plate 2 are connected with fixing units. After the micro-expansion concrete 12 is poured, the oil pipe groove 1 can be filled, and the thickness of the micro-expansion concrete 12 is not less than 30cm. The micro-expansion concrete 12 can expand to a certain extent during the hydration period by relying on the action of the expansion agent, and the hydraulic dam bottom plate foundation 3 and the second-phase concrete are consolidated into a whole through the pre-embedded dowel bars 9.
[0024] The fixing unit includes slots 13 opened at both ends of the first low-foam plastic board 2, each slot 13 is coated with special plastic glue 14, and lead wire 15 is connected between the opposite slots 13. The lead wire has a diameter of 2mm to 5mm. Sand 7 is spread in the oil pipe slot 1, and the first low-foam plastic board 2 is laid on the oil pipe 5 at the seam. Dust and impurities in the slot 13 are removed to ensure that the inside is clean. An appropriate amount of special plastic glue 14 is spread inside the slot 13, and the lead wire 15 is inserted to fix it. Micro-expansion concrete 12 is poured on the sand 7 to form a whole. If there are multiple layers of oil pipes 5 in the oil pipe slot 1, a layer of sand 7 and the first low-foam plastic board 2 is first laid in the oil pipe slot 1, a layer of oil pipe 5 is placed, and then a layer of the first low-foam plastic board 2 and sand 7 are laid, and then the laying is continued in the above order. The oil pipes 5 are neatly arranged and the sand 7 is evenly laid.
[0025] Example 2
[0026] A protective device for preventing deformation and splitting of an oil pipe at a seam of a hydraulic dam foundation comprises a foundation cushion layer 8, a hydraulic dam bottom plate foundation 3 is cast on the upper surface of the foundation cushion layer 8, an oil pipe groove 1 is opened in the hydraulic dam bottom plate foundation 3, an oil pipe 5 is laid in the oil pipe groove 1, protective mechanisms are arranged on the upper and lower sides of the oil pipe 5 at the seam, and a plurality of deformation joints 4 are opened in the hydraulic dam bottom plate foundation 3, and each deformation joint 4 is arranged perpendicular to the oil pipe 5.
[0027] The protection mechanism includes sand 7 and a first low-foam plastic plate 2 arranged in sequence. The first low-foam plastic plate 2 is arranged close to the oil pipe 5. Micro-expansive concrete 12 is poured on the sand surface above the oil pipe 5. Both ends of the first low-foam plastic plate 2 are connected with fixing units.
[0028] The fixing unit includes slots 13 opened at both ends of the first low-foam plastic plate 2 , each slot 13 is coated with a special plastic glue 14 , and lead wires 15 are connected between the opposite slots 13 .
[0029] like Figure 4 As shown, the width of the deformation joint 4 is 2 cm.
[0030] The deformation joint 4 is filled with a second low-foam plastic board 6, and the deformation joint 4 is smoothed with a 1:2 waterproof mortar 11 at a distance of 2 cm from the seam. The water stop 10 is used for water stopping.
[0031] Example 3
[0032] A protective device for preventing deformation and splitting of an oil pipe at a seam of a hydraulic dam foundation comprises a foundation cushion layer 8, a hydraulic dam bottom plate foundation 3 is cast on the upper surface of the foundation cushion layer 8, an oil pipe groove 1 is opened in the hydraulic dam bottom plate foundation 3, an oil pipe 5 is laid in the oil pipe groove 1, protective mechanisms are arranged on the upper and lower sides of the oil pipe 5 at the seam, and a plurality of deformation joints 4 are opened in the hydraulic dam bottom plate foundation 3, and each deformation joint 4 is arranged perpendicular to the oil pipe 5.
[0033] The protection mechanism includes sand 7 and a first low-foam plastic plate 2 arranged in sequence. The first low-foam plastic plate 2 is arranged close to the oil pipe 5. Micro-expansive concrete 12 is poured on the sand surface above the oil pipe 5. Both ends of the first low-foam plastic plate 2 are connected with fixing units.
[0034] The fixing unit includes slots 13 opened at both ends of the first low-foam plastic plate 2 , each slot 13 is coated with a special plastic glue 14 , and lead wires 15 are connected between the opposite slots 13 .
[0035] The width of the deformation joint 4 is 2 cm.
[0036] The deformation joint 4 is filled with a second low-foam plastic board 6, and the deformation joint 4 is smoothed with a 1:2 waterproof mortar 11 at a distance of 2 cm from the seam. The water stop 10 is used for water stopping.
[0037] Several dowel bars 9 with a diameter of 25 mm are embedded in the hydraulic dam bottom plate foundation 3. The longitudinal spacing of the dowel bars 9 is 20 cm and the transverse spacing is 30 cm. The dowel bars 9 pass through the oil pipe groove 1. When the U-shaped oil pipe groove 1 is reserved for pouring the hydraulic dam bottom plate foundation 3, the dowel bars 9 should be embedded in advance. The dowel bars 9 are three-level threaded dowel bars. The dowel bars 9 are 110 cm long and embedded in the first-stage concrete for 100 cm. The side wall is exposed for 10 cm. The embedded dowel bars 9 can improve the integrity of the consolidation of the pressure dam bottom plate foundation 3 and the micro-expansion concrete 12.
[0038] The total laying thickness of the sand 7 is not less than 30 cm, and the particle size of the sand 7 is 0.5 mm to 1 mm.
[0039] The thickness of the first low-foam plastic plate 2 and the second low-foam plastic plate 6 are both 2 cm, and the overlap length of the first low-foam plastic plate 2 and the second low-foam plastic plate 6 on both sides of the oil pipe 5 at the seam is 25 cm to 35 cm. Since the bottom plates on both sides are prone to uneven settlement, the first low-foam plastic plate 2 and the second low-foam plastic plate 6 have strong adaptability to deformation, which can better protect the oil pipe 5 from deformation and cracking. The first low-foam plastic plate 2 and the second low-foam plastic plate 6 have a separate closed-cell bubble structure, and the honeycomb holes are evenly distributed on the surface. They are tightly integrated with the concrete mixture and can change with the expansion and contraction of the concrete. They have high expansion and contraction strength, do not absorb water, and are resistant to corrosion, aging, high and low temperatures.
[0040] The construction process of the protective device for preventing the oil pipe from deforming and splitting at the seam of the hydraulic dam foundation according to the utility model is as follows:
[0041] a. Foundation excavation: excavate the tooth grooves at the front and rear ends of the foundation according to the slope ratio of 1:1, and compact the original soil layer;
[0042] b. Pouring of cushion layer: pour a 10cm thick C15 concrete foundation cushion layer 8 on the excavation surface;
[0043] c. Reserve U-shaped oil pipe groove 1: Cast the hydraulic dam bottom plate foundation 3 on the foundation cushion 8 to reserve a U-shaped oil pipe groove 1 of not less than 60cm deep, and bury dowel bars 9 with a diameter of 25mm with a longitudinal spacing of 20cm and a transverse spacing of 30cm.
[0044] d. Oil pipe installation: The oil pipe 5 is made of seamless hydraulic fluid pipe, and the pipe joint is made of stainless steel. The pipeline is arranged in the U-shaped oil pipe groove 1, and then welded, the welding slag is removed, and the oxide scale and impurities in the pipe are removed before arrangement.
[0045] e. Sanding treatment: After the oil pipe 5 is arranged, sand with a particle size of 0.5 mm to 1 mm is evenly laid in the oil pipe groove 1;
[0046] f. Lay low-foam plastic boards on the upper and lower sides of the seam: overlap the first low-foam plastic boards 2 with a thickness of 2 cm on both sides of the oil pipe 5 at the seam, and the lengths are 25 cm to 35 cm respectively. Fix the first low-foam plastic board 2 with a lead wire 15 with a diameter of 2 mm to 5 mm. Use an electric drill or a suitable drill bit to make notches 13 at the selected positions at both ends of the first low-foam plastic board 2, and pass the lead wire 15 through. Remove dust and impurities in the hole or notch to ensure that the inside is clean. Apply a proper amount of plastic special glue 14 on the surface of the lead wire 15 and the inside of the notch 13. Carefully pass the lead wire 15 through the notch 13 and ensure that it is in close contact with the first low-foam plastic board 2. In order to further fix the lead wire 15, use pliers or other tools to bend it so that it can more firmly bind the first low-foam plastic board 2;
[0047] g. Treatment of deformation joints: Use embedded 651 type rubber water stop 10 to stop water, fill the joint with L-600 second low foam plastic board 6, and smooth the 2cm joint with 1:2 waterproof mortar 11;
[0048] h. Pouring of micro-expansive concrete: After the sand 7 is laid, pour C25 micro-expansive concrete 12 to strengthen the bonding between layers. Finally, perform surface maintenance to keep the dam surface clean and tidy and its anti-corrosion performance.
[0049] The utility model discloses a protective device for preventing deformation and splitting of oil pipes at the seam of hydraulic dam foundation, which can effectively protect the oil pipes at the seam of hydraulic dam foundation, has simple structure, controllable cost and convenient use, and has certain application value in the field of hydraulic dam for river management.
Claims
1. A protective device for preventing deformation and splitting of the oil pipe at the seam of the hydraulic dam foundation, characterized in that: The invention comprises a foundation cushion layer (8), the upper surface of which is cast with a hydraulic dam bottom plate foundation (3), an oil pipe groove (1) is provided in the hydraulic dam bottom plate foundation (3), an oil pipe (5) is laid in the oil pipe groove (1), protective mechanisms are provided on the upper and lower sides of the oil pipe (5) at the joint, and a plurality of deformation joints (4) are provided in the hydraulic dam bottom plate foundation (3), and each of the deformation joints (4) is arranged perpendicular to the oil pipe (5).
2. The protective device for preventing the oil pipe from being deformed and split at the seam of the hydraulic dam foundation according to claim 1 is characterized in that: The protection mechanism comprises sand (7) and a first low-foam plastic plate (2) which are arranged in sequence, wherein the first low-foam plastic plate (2) is arranged close to the oil pipe (5), micro-expansion concrete (12) is poured on the surface of the sand above the oil pipe (5), and fixing units are connected to both ends of the first low-foam plastic plate (2).
3. The protective device for preventing the oil pipe from being deformed and split at the seam of the hydraulic dam foundation according to claim 2 is characterized in that: The fixing unit comprises slots (13) opened at both ends of the first low-foam plastic plate (2), each of the slots (13) is coated with special plastic glue (14), and lead wires (15) are connected between the opposite slots (13).
4. The protective device for preventing deformation and splitting of the oil pipe at the seam of the hydraulic dam foundation according to claim 1 is characterized in that: The width of the deformation joint (4) is 2 cm.
5. The protective device for preventing the oil pipe from being deformed and split at the seam of the hydraulic dam foundation according to claim 4 is characterized in that: The deformation joint (4) is provided with an embedded 651 type rubber water stop (10), the deformation joint (4) is filled with a second low-foam plastic board (6), and the deformation joint (4) is smoothed with a 1:2 waterproof mortar (11) at a distance of 2 cm from the joint opening.
6. The protective device for preventing the oil pipe from being deformed and split at the seam of the hydraulic dam foundation according to claim 1 is characterized in that: A plurality of dowel bars (9) with a diameter of 25 mm are embedded in the hydraulic dam bottom plate foundation (3). The longitudinal spacing of the dowel bars (9) is 20 cm and the transverse spacing is 30 cm. The dowel bars (9) pass through the oil pipe groove (1).
7. The protective device for preventing the oil pipe from being deformed and split at the seam of the hydraulic dam foundation according to claim 2 is characterized in that: The total laying thickness of the sand (7) is not less than 30 cm, and the particle size of the sand (7) is 0.5 mm to 1 mm.
8. The protective device for preventing the oil pipe from being deformed and split at the seam of the hydraulic dam foundation according to claim 2 is characterized in that: The thickness of the first low-foam plastic plate (2) and the second low-foam plastic plate (6) are both 2 cm, and the overlapping length of the first low-foam plastic plate (2) and the second low-foam plastic plate (6) on both sides of the oil pipe (5) at the seam is 25 cm to 35 cm.