Post-cast strip supporting and adjusting tool
By designing a rear casting tape support adjustment tool combining galvanized steel pipes and groove flanges, the problems of long construction cycles and inconvenient material turnover of traditional support tools are solved, height adjustment and efficient material turnover are achieved, construction efficiency and convenience of use are improved sex.
Patent Information
- Application Number
- CN202420269954.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-04
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-02-04
AI Technical Summary
Traditional rear-pouring belt support tools have a long construction cycle and are inconvenient for material turnover, which affects construction efficiency and road traffic.
A rear casting tape support adjustment tool is designed, using a combination of galvanized steel pipes, grooved flanges, wide plate belts, high-strength bolts and fixing nuts to achieve support height adjustment and efficient material turnover.
The height adjustment of the rear casting tape support tool and efficient material turnover are achieved, and construction efficiency and convenience of use are improved.
Smart Images

Figure CN222009722U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of post-casting strip supports, in particular to a post-casting strip support adjustment tool. Background Art
[0002] Due to the large overall volume of settlement post-casting strips and temperature post-casting strips, the large number of regional divisions, the long construction volume and construction period, the use of traditional steel pipes, wooden squares, and formwork supports is large, and efficient material turnover cannot be achieved. It also affects the passage of construction roads in the garage and the construction of pipe complexes. Based on the above reasons, in order to improve work efficiency, a post-casting strip support adjustment tool was proposed after repeated research and experience summary during the project construction to solve the above problems. Utility Model Content
[0003] The utility model aims to provide a post-casting strip support adjustment tool to solve the problems of long construction period and inconvenience in turnover proposed in the above-mentioned background technology.
[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a post-cast strip support adjustment tool, comprising a galvanized steel pipe, a second groove flange is installed at the top of the galvanized steel pipe, and a wide plate strip is installed at the top of the second groove flange, and a first groove flange is installed at the bottom end of the galvanized steel pipe, high-strength bolts are movably provided inside the first groove flange, and fixing nuts are movably provided on the outer side walls of the high-strength bolts.
[0005] Preferably, the bottom ends of the high-strength bolts are fixed with steel plates, the bottom ends of the steel plates are fixed with the basement floor, and a post-cast strip body is arranged inside the basement floor.
[0006] Preferably, a plurality of the fixing nuts are provided, and the plurality of the fixing nuts are arranged up and down with respect to the first groove flange.
[0007] Preferably, four groups of high-strength bolts are provided, and the four groups of high-strength bolts are distributed in a ring shape inside the first groove flange.
[0008] Compared with the prior art, the utility model has the following beneficial effects: the post-casting belt support adjustment tool can not only adjust the support height, but also realize efficient material turnover, and is more practical;
[0009] (1) By providing components such as high-strength bolts and a post-casting strip body, the post-casting strip support tool can rotate the post-casting strip body on the outer side wall of the high-strength bolt according to the actual supported height in actual use, and adjust the first groove flange installed on the outer side wall of the post-casting strip body to a suitable position height, thereby adjusting the post-casting strip support work to a corresponding support height for support use;
[0010] (2) By providing the first groove flange and the second groove flange, the galvanized steel pipe can be assembled through the first groove flange and the second groove flange to form a supporting tool for supporting the post-cast strip. If it needs to be disassembled later, the galvanized steel pipe can be disassembled by disassembling the first groove flange and the second groove flange for turnover use, which is more convenient to use. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 This is a front view structural schematic diagram of the utility model;
[0012] Figure 2 This is a schematic diagram of the front view structure of the wide plate strip of the utility model;
[0013] Figure 3 This is a schematic diagram of the front view structure of the steel plate of the utility model;
[0014] Figure 4 It is a schematic diagram of the top view structure of the galvanized steel pipe of the utility model.
[0015] In the figure: 1. galvanized steel pipe; 2. high-strength bolts; 3. first groove flange; 4. steel plate; 5. main body of post-cast strip; 6. basement floor; 7. fixing nuts; 8. wide plate strip; 9. second groove flange. DETAILED DESCRIPTION
[0016] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0017] See also Figure 1-4 The utility model provides an embodiment: a post-casting strip support adjustment tool, comprising a galvanized steel pipe 1, a second groove flange 9 is installed at the top of the galvanized steel pipe 1, and a wide plate strip 8 is installed at the top of the second groove flange 9;
[0018] The bottom end of the galvanized steel pipe 1 is installed with a first groove flange 3, the interior of the first groove flange 3 is movably provided with a high-strength bolt 2, and the outer side wall of the high-strength bolt 2 is movably provided with a fixing nut 7;
[0019] The bottom ends of the high-strength bolts 2 are all fixed with steel plates 4, and the bottom ends of the steel plates 4 are fixed with basement floor plates 6, and the interior of the basement floor plates 6 is provided with a post-casting strip body 5;
[0020] A plurality of fixing nuts 7 are provided, and the plurality of fixing nuts 7 are arranged up and down with respect to the first groove flange 3, so as to facilitate adjustment of the supporting height of the high-strength bolt 2, and achieve better use effect;
[0021] Four groups of high-strength bolts 2 are arranged, and the four groups of high-strength bolts 2 are distributed in a ring shape inside the first groove flange 3. The high-strength bolts 2 distributed in a ring shape have stronger supporting force for the first groove flange 3 and the galvanized steel pipe 1 thereon, and the support is more stable.
[0022] Working principle: After the above materials are brought in for use in the adjustment tool, the utility model is cut in accordance with the design size, and the lengths are 2.8m, 2.9m, 3m, 3.4m, and 3.45m respectively. The upper and lower parts are connected with the galvanized steel pipe 1 by the first groove flange 3 and the second groove flange 9 of the DN100 type, and then the M16 type high-strength bolts 2 are connected with the first groove flange 3 and the second groove flange 9, and the adjustable base is realized by fixing the flanges with two post-casting belt bodies 5. At the same time, 250mm* The 250mm*5mm steel plate 4 is directly used as a pad and placed on the ground. During the normal erection of the formwork support frames on both sides of the post-casting strip, an adjustment tool is set at 150mm away from the edge of the post-casting strip with a length spacing of ≤3000mm along the length of the post-casting strip. The upper template of the adjustment tool adopts a 300mm wide full-length plate template. After the support frame is erected, the support height is adjusted using the adjustment tool. After pouring is completed, the formwork frame is normally dismantled under permitted conditions to achieve efficient material turnover. The adjustment tool will be dismantled after the pouring of the post-casting strip is completed.
[0023] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.
Claims
1. A post-casting strip support adjustment tool, comprising a galvanized steel pipe (1), Features: The top end of the galvanized steel pipe (1) is installed with a second groove flange (9), and the top end of the second groove flange (9) is installed with a wide plate (8), and the bottom end of the galvanized steel pipe (1) is installed with a first groove flange (3), and the interior of the first groove flange (3) is movably provided with high-strength bolts (2), and the outer side walls of the high-strength bolts (2) are movably provided with fixing nuts (7).
2. A post-casting strip support adjustment tool according to claim 1, Features: The bottom ends of the high-strength bolts (2) are all fixed with steel plates (4), and the bottom ends of the steel plates (4) are fixed with a basement floor plate (6), and a post-cast strip body (5) is arranged inside the basement floor plate (6).
3. A post-casting strip support adjustment tool according to claim 2, Features: A plurality of fixing nuts (7) are provided, and the plurality of fixing nuts (7) are arranged up and down with respect to the first groove flange (3).
4. A post-casting strip support adjustment tool according to claim 1, Features: Four groups of high-strength bolts (2) are provided, and the four groups of high-strength bolts (2) are distributed in a ring shape inside the first groove flange (3).