Fastening mechanism for ferrous metal smelting rolled product
By designing an adjustable fixing ring and locking mechanism, the problem of insufficient applicability of existing fastening mechanisms to pipes of different sizes is solved, achieving stable connection and enhancing pipe fixing effect.
Patent Information
- Application Number
- CN202420536456.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-19
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-03-19
AI Technical Summary
Existing fastening mechanisms have limited applicability to pipes of different sizes, making it difficult to achieve stable fixing and connection.
A fastening mechanism is designed, comprising a fixed base and an adjustable fastening assembly. The fastening assembly consists of first and second fixed rings, the gap between the rings being adjustable via sliding mounting and locking elements, and equipped with an abutment element to enhance stability.
It enables stable fixing and connection of pipes of different sizes, increases the applicability of the fastening mechanism, and improves the installation stability of the pipes through the abutment parts.
Smart Images

Figure CN222010671U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of metal smelting and rolling products, and in particular to a fastening mechanism for ferrous metal smelting and rolling products. Background Art
[0002] Metal is a substance with luster, good electrical conductivity, thermal conductivity and mechanical properties, and a positive temperature coefficient of resistance. Metals are usually divided into two categories: ferrous metals and non-ferrous metals based on their color and properties. Ferrous metals mainly refer to iron and its alloys, such as steel, pig iron, iron alloys, cast iron, etc. Metals other than ferrous metals are called non-ferrous metals. Ferrous metal smelting rolled products refer to the processed products of iron and its alloys.
[0003] At present, most fasteners or fastening mechanisms are made of ferrous metal, which is a kind of ferrous metal smelting and rolling product. Fastening mechanism is a mechanical part used to fasten two or more parts into a whole.
[0004] For example, Chinese patent application No. 202021514756.5 discloses a metal sleeve fastener structure, including a base and a first end cover, a first end cover is provided at the upper end of the base, the base and the first end cover are fixedly connected by bolts, a second end cover is provided at the upper end of the first end cover, and a connecting bolt is provided at each of the left and right ends of the intersection of the first end cover and the second end cover, and a fastening mechanism is provided at the axis center of the second end cover, so that when the workpiece is fixed by the first end cover and the second end cover, if the size of the workpiece is small, it can be fixed by the fastening mechanism inside the second end cover.
[0005] When the above-mentioned metal sleeve fastener structure is used to connect pipe-type materials, it is convenient to stably fix smaller pipes. When the pipe size is larger, a metal sleeve fastener structure larger than the pipe size needs to be replaced to fix it, which makes the application scope of the metal sleeve fastener relatively limited. Utility Model Content
[0006] In order to facilitate the connection and fixation of pipes of different sizes, the present application provides a fastening mechanism for ferrous metal smelting and rolling products.
[0007] The present application provides a fastening mechanism for a ferrous metal smelting rolled product, which adopts the following technical solution:
[0008] It includes a fixed base and a fixed component adjustably installed on the fixed base, the fixed component includes a first fixed ring body slidably installed on one side of the fixed base and a second fixed ring body slidably installed on the other side of the fixed base and arranged opposite to the first fixed ring body, an installation gap for pipe installation is formed between the first fixed ring body and the second fixed ring body, a first locking piece for locking the first fixed ring body and a second locking piece for locking the second fixed ring body are provided on the fixed base; the first fixed ring body is provided with a first abutment piece pressed against the circumferential side wall of the pipe on the side facing the second fixed ring body, and the second fixed ring body is provided with a second abutment piece pressed against the circumferential side wall of the pipe on the side facing the first fixed ring body.
[0009] By adopting the above technical scheme, when the fastening mechanism of the ferrous metal smelting and rolling product is used to fix the connected pipe, the first fixed ring body and the second fixed ring body are slidably installed on the fixed base, so that an installation gap for the pipe to be fixed and passed through is formed between the first fixed ring body and the second fixed ring body, the first fixed ring body is fixedly installed on the fixed base by the first locking piece, and the second fixed ring body is fixedly installed on the fixed base by the second locking piece, so that the first abutment piece on the first fixed ring body is tightly pressed against the peripheral side wall of the pipe, and the second abutment piece on the second fixed ring body is abutted against the peripheral side wall of the pipe, thereby completing the fixing and docking of the pipe, and the structure can conveniently adjust the size of the installation gap between the first fixed ring body and the second ring body, thereby being able to adapt to pipes of more sizes and increasing the applicability of the fastening mechanism.
[0010] Optionally, a mounting groove is provided on the fixed base, a first limiting protrusion slidably inserted into the mounting groove is provided on the bottom side of the first fixed ring body, and a second limiting protrusion slidably inserted into the mounting groove is provided on the bottom side of the second fixed ring body.
[0011] By adopting the above technical scheme, when installing the first fixed ring body, the first limiting protrusion on the first fixed ring body is slidably inserted into the installation slide groove on the fixed base, and the first limiting protrusion cooperates with the installation slide groove to position and limit the installation of the first fixed ring body, thereby facilitating the installation of the first fixed ring body; when installing the second fixed ring body, the second limiting protrusion on the second fixed ring body is slidably inserted into the installation slide groove on the fixed base, and the second limiting protrusion cooperates with the installation slide groove to position and limit the installation of the second fixed ring body, thereby facilitating the installation of the second fixed ring body.
[0012] Optionally, a strip groove is provided on the fixed base, a first horizontal plate that fits with the fixed base is provided on the bottom side of the first fixed ring body, a first through hole that docks with the strip groove is provided on the first horizontal plate, and the first locking piece is configured as a bolt that passes through the first through hole and is threadedly tightened in the strip groove.
[0013] By adopting the above technical solution, when installing the first fixed ring body, the first horizontal plate is horizontally attached to the top surface of the fixed base, so that the first through hole is connected to the strip groove on the fixed base, and then the end of the first locking piece is passed through the first through hole and clamped in the strip groove. This installation method is relatively stable and easy to adjust.
[0014] Optionally, a second horizontal plate that fits with the fixed base is provided on the bottom side of the second fixing ring body, and a second through hole that docks with the strip groove is opened on the second horizontal plate. The second locking piece is configured as a bolt that passes through the second through hole and is threadedly tightened in the strip groove.
[0015] By adopting the above technical solution, when installing the second fixed ring body, the second horizontal plate is horizontally attached to the top surface of the fixed base, so that the second through hole is connected to the strip groove on the fixed base, and then the end of the second locking piece is passed through the second through hole and clamped in the strip groove. This installation method is more stable and easy to adjust.
[0016] Optionally, the first abutment member can be adjustably mounted on the first fixing ring body.
[0017] By adopting the above technical solution, when the pipe is inserted into the installation gap between the first fixed ring body and the second fixed ring body, a gap may be left between the first abutment member and the side wall of the pipe. Therefore, the first abutment member can be pressed tightly against the side wall of the pipe by adjusting the installation progress of the first abutment member, thereby improving the stability of the pipe installation.
[0018] Optionally, a first fixing hole is formed on the first fixing ring body, and a first mounting boss slidably installed in the first fixing hole is provided on the side of the first abutment member facing the first fixing ring body, and a first limiting ring is adjustably installed on the first mounting boss to abut against opposite sides of the first fixing ring body.
[0019] By adopting the above technical solution, when installing and adjusting the first abutment member, the first installation boss on the first abutment member is inserted into the first fixing hole on the first fixing ring body, and the first limiting ring on the first installation boss is adjusted to be tight against the opposite side walls of the first fixing ring body, thereby completing the adjustment and installation of the first abutment member.
[0020] Optionally, the second abutment member can be adjustably mounted on the second fixing ring body.
[0021] By adopting the above technical solution, when the pipe is inserted into the installation gap between the first fixed ring body and the second fixed ring body, a gap may be left between the second abutment member and the side wall of the pipe. Therefore, the second abutment member can be pressed tightly against the side wall of the pipe by adjusting the installation process of the second abutment member, thereby improving the stability of the pipe installation.
[0022] Optionally, a second fixing hole is formed on the second fixing ring body, and a second mounting boss slidably installed in the second fixing hole is provided on the side of the second abutment member facing the second fixing ring body, and a second limiting ring is adjustably installed on the second mounting boss to abut against opposite sides of the second fixing ring body.
[0023] By adopting the above technical solution, when installing and adjusting the second abutment member, the second mounting boss on the second abutment member is inserted into the second fixing hole on the second fixing ring body, and the second limiting ring on the second mounting boss is adjusted to be tight against the opposite side walls of the second fixing ring body, thereby completing the adjustment and installation of the second abutment member.
[0024] In summary, the present application includes at least one of the following beneficial technical effects:
[0025] The present application includes a fixed base and a fixed assembly adjustably mounted on the fixed base, wherein the fixed assembly includes a first fixed ring body and a second fixed ring body. When fixing and connecting the pipe, the first fixed ring body and the second fixed ring body are slidably mounted on the fixed base, so that the pipe can be inserted into the installation gap, thereby conveniently adjusting the size of the installation gap between the first fixed ring body and the second fixed ring body according to the size of the pipe;
[0026] The fixed base of the present application is provided with an installation slot, the first fixed ring body is provided with a first limiting protrusion, and the second fixed ring body is provided with a second limiting protrusion. The first limiting protrusion cooperates with the installation slot to position and limit the installation of the first fixed ring body, and the second limiting protrusion cooperates with the installation slot to position and limit the installation of the second fixed ring body.
[0027] The first abutment of the present application can be adjustably installed on the first fixed ring body, and the second abutment can be adjustably installed on the second fixed ring body. When the pipe is passed through the installation gap, the first abutment can be adjusted to press the first abutment against the peripheral side wall of the pipe, and the second abutment can be adjusted to press the second abutment against the peripheral side wall of the pipe, thereby achieving a more stable fixing effect on the pipe. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a schematic diagram of the overall structure of a fastening mechanism for a ferrous metal smelting and rolling product in an embodiment of the present application.
[0029] Figure 2It is a partial explosion diagram of a fastening mechanism of a ferrous metal smelting rolled product in an embodiment of the present application. Figure 1 .
[0030] Figure 3 It is a partial explosion diagram of a fastening mechanism of a ferrous metal smelting rolled product in an embodiment of the present application. Figure 2 .
[0031] Explanation of the accompanying drawings: 1. fixed base; 11. mounting groove; 12. strip groove; 2. fixing assembly; 3. first fixing ring body; 31. first limiting protrusion; 32. first horizontal plate; 321. first through hole; 33. first fixing hole; 4. second fixing ring body; 41. second limiting protrusion; 42. second horizontal plate; 421. second through hole; 43. second fixing hole; 5. mounting gap; 6. first locking member; 7. second locking member; 8. first abutment member; 81. first mounting boss; 82. first limiting ring; 9. second abutment member; 91. second mounting boss; 92. second limiting ring. DETAILED DESCRIPTION
[0032] The following is combined with Figure 1-3 This application is described in further detail.
[0033] The present application embodiment discloses a fastening mechanism for a ferrous metal smelting rolled product. Figure 1 The fastening mechanism of the ferrous metal smelting rolled product includes a fixed base 1 and a fixed component 2 which is adjustably mounted on the fixed base 1.
[0034] See also Figure 1 The fixing assembly 2 includes a first fixing ring body 3 slidably mounted on one side of the fixing base 1 and a second fixing ring body 4 slidably mounted on the other side of the fixing base 1 and arranged opposite to the first fixing ring body 3. In this embodiment, the fixing base 1 is configured as a square base, the first fixing ring body 3 is configured as a semicircular ring body slidably mounted on the left side of the fixing base 1, and the second fixing ring body 4 is configured as a semicircular ring body slidably mounted on the right side of the fixing base 1, and an installation gap 5 for pipe installation is formed between the first fixing ring body 3 and the second fixing ring body 4. The fixing base 1 is provided with a first locking member 6 for locking the first fixing ring body 3 and a second locking member 7 for locking the second fixing ring body 4. When using the fastening mechanism of the ferrous metal smelting rolled product to fix and connect pipes, adjust the installation positions of the first fixed ring body 3 and the second fixed ring body 4 on the fixed base 1 so that an installation gap 5 that is adapted to the size of the pipe to be connected and is used for the pipe to pass through is formed between the first fixed ring body 3 and the second fixed ring body 4. The first fixed ring body 3 is fixedly installed on the fixed base 1 by the first locking piece 6, and the second fixed ring body 4 is fixedly installed on the fixed base 1 by the second locking piece 7, thereby the pipes can be fixed and connected more stably.
[0035] See also Figure 2 , a mounting groove 11 is provided on the fixed base 1. A first limiting protrusion 31 is provided on the bottom side of the first fixed ring body 3 and is slidably inserted into the mounting groove 11, and a second limiting protrusion 41 is provided on the bottom side of the second fixed ring body 4 and is slidably inserted into the mounting groove 11. In this embodiment, the mounting groove 11 is provided along the length direction of the fixed base 1, and the cross section of the mounting groove 11 is set to be T-shaped, the first limiting protrusion 31 is set to be a T-shaped protrusion adapted to the mounting groove 11, and the second limiting protrusion 41 is set to be a T-shaped protrusion adapted to the mounting groove 11. When installing the first fixed ring body 3, the first limiting protrusion 31 on the first fixed ring body 3 is slidably inserted into the mounting groove 11 on the fixed base 1, and the first limiting protrusion 31 cooperates with the mounting groove 11 to position and limit the installation of the first fixed ring body 3, thereby facilitating the installation of the first fixed ring body 3. When installing the second fixed ring body 4, the second limiting protrusion 41 on the second fixed ring body 4 is slidably inserted into the installation slide groove 11 on the fixed base 1. The second limiting protrusion 41 cooperates with the installation slide groove 11 to position and limit the installation of the second fixed ring body 4, thereby facilitating the installation of the second fixed ring body 4.
[0036] See also Figure 2 , a strip groove 12 is provided on the fixed base 1. A first horizontal plate 32 that fits the fixed base 1 is provided on the bottom side of the first fixed ring body 3, and a first through hole 321 that docks with the strip groove 12 is provided on the first horizontal plate 32. The first locking member 6 is configured as a bolt that passes through the first through hole 321 and is threadedly tightened in the strip groove 12. In this embodiment, the first horizontal plates 32 that are integrally provided with the first fixed ring body 3 are provided on the front and rear opposite sides of the first fixed ring body 3, the extension direction of the strip groove 12 is parallel to the extension direction of the mounting slide groove 11, and the fixed base 1 is provided with a strip groove 12 on the front and rear opposite sides of the first fixed ring body 3, and a first through hole 321 corresponding to the strip groove 12 is provided on the first horizontal plates 32 on the front and rear opposite sides of the first fixed ring body 3. When installing the first fixed ring body 3, the first horizontal plate 32 is horizontally attached to the top surface of the fixed base 1, so that the first through hole 321 is connected to the strip groove 12 on the fixed base 1, and then the end of the first locking piece 6 is passed through the first through hole 321 and clamped in the strip groove 12. This installation method is more stable and easy to adjust.
[0037] See also Figure 2, a second horizontal plate 42 that fits with the fixed base 1 is provided on the bottom side of the second fixed ring body 4. A second through hole 421 that docks with the strip groove 12 is provided on the second horizontal plate 42. The second locking member 7 is configured as a bolt that passes through the second through hole 421 and is threadedly tightened in the strip groove 12. In this embodiment, the second fixed ring body 4 is provided with a second horizontal plate 42 that is integrally provided with the second fixed ring body 4 on both opposite front and rear sides, and the second fixed ring body 4 is provided with a second through hole 421 corresponding to the strip groove 12 on the second horizontal plate 42. When installing the second fixed ring body 4, the second horizontal plate 42 is horizontally attached to the top surface of the fixed base 1 so that the second through hole 421 is docked with the strip groove 12 on the fixed base 1, and then the end of the second locking member 7 is passed through the second through hole 421 and clamped in the strip groove 12. This installation method is relatively stable and convenient to adjust.
[0038] See also Figure 3 The first fixing ring body 3 is provided with a first abutting piece 8 pressed against the peripheral side wall of the pipe on the side facing the second fixing ring body 4. The second fixing ring body 4 is provided with a second abutting piece 9 pressed against the peripheral side wall of the pipe on the side facing the first fixing ring body 3. When the pipe is inserted into the installation gap 5 between the first fixing ring body 3 and the second fixing ring body 4, there may be a gap between the pipe and the first fixing ring body 3 and the second fixing ring body 4, so that the first abutting piece 8 and the second abutting piece 9 can be pressed against the peripheral side wall of the pipe to limit the position of the pipe, thereby further improving the stability of the pipe installation.
[0039] See also Figure 3 , the first abutment member 8 is adjustably mounted on the first fixing ring body 3. The first fixing ring body 3 is provided with a first fixing hole 33, and the first abutment member 8 is provided with a first mounting boss 81 which is slidably mounted in the first fixing hole 33 on one side of the first abutment member 8 facing the first fixing ring body 3, and the first mounting boss 81 is adjustably mounted with a first limiting ring 82 which abuts against the opposite sides of the first fixing ring body 3. In this embodiment, the first fixing hole 33 is provided as a threaded hole, the first mounting boss 81 is provided as a screw rod which is integrally provided with the first abutment member 8, and the first mounting boss 81 is threadedly matched with the first fixing hole 33, and the first limiting ring 82 is provided as a nut member which is threadedly mounted on the first mounting boss 81. When installing and adjusting the first abutment member 8, the first mounting boss 81 on the first abutment member 8 is inserted into the first fixing hole 33 on the first fixing ring body 3, and the first limiting ring 82 on the first mounting boss 81 is adjusted to abut against the opposite side walls of the first fixing ring body 3, thereby completing the adjustment installation of the first abutment member 8.
[0040] See also Figure 3, the second abutment member 9 is adjustably mounted on the second fixing ring body 4. The second fixing ring body 4 is provided with a second fixing hole 43, and the second abutment member 9 is provided with a second mounting boss 91 which is slidably mounted in the second fixing hole 43 on one side facing the second fixing ring body 4, and the second mounting boss 91 is adjustably mounted with a second limiting ring 92 which abuts against the opposite sides of the second fixing ring body 4. In this embodiment, the second fixing hole 43 is provided as a threaded hole, the second mounting boss 91 is provided as a screw rod which is integrally provided with the second abutment member 9, and the second mounting boss 91 is threadedly matched with the second fixing hole 43, and the second limiting ring 92 is provided as a nut which is threadedly mounted on the second mounting boss 91. When installing and adjusting the second abutment member 9, the second mounting boss 91 on the second abutment member 9 is inserted into the second fixing hole 43 on the second fixing ring body 4, and the second limiting ring 92 on the second mounting boss 91 is adjusted to abut against the opposite side walls of the second fixing ring body 4, thereby completing the adjustment and installation of the second abutment member 9.
[0041] The implementation principle of a fastening mechanism for a ferrous metal smelting rolled product in the embodiment of the present application is:
[0042] When the fastening mechanism of the ferrous metal smelting rolled product is used to fix and connect the pipe, the distance between the first fixing ring body 3 and the second fixing ring body 4 is adjusted according to the pipe diameter, so that the installation gap 5 between the first fixing ring body 3 and the second fixing ring body 4 is adapted to the pipe diameter of the pipe, the first fixing ring body 3 is fixed by the first locking member 6, the second fixing ring body 4 is fixed by the second locking member 7, the first abutment member 8 is adjusted so that the first abutment member 8 is tightly pressed against a side wall of the pipe, and the second abutment member 9 is adjusted so that the second abutment member 9 is tightly pressed against a side wall of the pipe, thereby completing the fixing and connection of the pipe.
[0043] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A fastening mechanism for ferrous metal smelting and rolling products, It is characterized in that The invention comprises a fixed base (1) and a fixed assembly (2) adjustably mounted on the fixed base (1), the fixed assembly (2) comprising a first fixed ring body (3) slidably mounted on one side of the fixed base (1) and a second fixed ring body (4) slidably mounted on the other side of the fixed base (1) and arranged opposite to the first fixed ring body (3), an installation gap (5) for installing a pipe is formed between the first fixed ring body (3) and the second fixed ring body (4), a first locking member (6) for locking the first fixed ring body (3) and a second locking member (7) for locking the second fixed ring body (4) are provided on the fixed base (1); the first fixed ring body (3) is provided with a first abutting member (8) pressed against the peripheral side wall of the pipe on the side facing the second fixed ring body (4), and the second fixed ring body (4) is provided with a second abutting member (9) pressed against the peripheral side wall of the pipe on the side facing the first fixed ring body (3).
2. A fastening mechanism for a ferrous metal smelting rolled product according to claim 1, It is characterized in that The fixed base (1) is provided with a mounting slot (11), the bottom side of the first fixed ring body (3) is provided with a first limiting protrusion (31) which is slidably inserted into the mounting slot (11), and the bottom side of the second fixed ring body (4) is provided with a second limiting protrusion (41) which is slidably inserted into the mounting slot (11).
3. A fastening mechanism for a ferrous metal smelting rolled product according to claim 1, It is characterized in that The fixed base (1) is provided with a strip groove (12); the bottom side of the first fixed ring body (3) is provided with a first horizontal plate (32) which is in contact with the fixed base (1); the first horizontal plate (32) is provided with a first through hole (321) which is connected with the strip groove (12); the first locking member (6) is provided as a bolt which passes through the first through hole (321) and is screwed into the strip groove (12).
4. A fastening mechanism for a ferrous metal smelting rolled product according to claim 3, It is characterized in that A second horizontal plate (42) is disposed on the bottom side of the second fixing ring body (4) and is in contact with the fixing base (1); a second through hole (421) is formed on the second horizontal plate (42) and is connected to the strip groove (12); and the second locking member (7) is configured as a bolt that passes through the second through hole (421) and is screwed into the strip groove (12).
5. The fastening mechanism for a ferrous metal smelting rolled product according to claim 1, It is characterized in that The first abutment member (8) is adjustably mounted on the first fixing ring body (3).
6. A fastening mechanism for a ferrous metal smelting rolled product according to claim 5, It is characterized in that The first fixing ring body (3) is provided with a first fixing hole (33); a first mounting boss (81) slidably mounted in the first fixing hole (33) is provided on a side of the first abutting member (8) facing the first fixing ring body (3); and first limiting rings (82) are adjustably mounted on the first mounting boss (81) to abut against opposite sides of the first fixing ring body (3).
7. The fastening mechanism for a ferrous metal smelting rolled product according to claim 1, It is characterized in that The second abutment member (9) is adjustably mounted on the second fixing ring body (4).
8. A fastening mechanism for a ferrous metal smelting rolled product according to claim 7, It is characterized in that The second fixing ring body (4) is provided with a second fixing hole (43); a second mounting boss (91) slidably mounted in the second fixing hole (43) is provided on the side of the second abutting member (9) facing the second fixing ring body (4); and second limiting rings (92) are adjustably mounted on the second mounting boss (91) to abut against opposite sides of the second fixing ring body (4).