Gas turbine power plant natural gas metering system and gas turbine power plant

By combining the functions of the trade metering station and the pressure regulating station, sharing the filter unit and verifying the measurement results using the reading difference of the ultrasonic flowmeter, the problems of functional duplication and resource waste in the existing technology are solved, and more efficient natural gas metering is achieved and maintenance.

CN222013215UActive Publication Date: 2024-11-15SHANDONG ELECTRIC POWER ENG CONSULTING INST CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420285999.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-06
Publication Date
2024-11-15
Estimated Expiration
2034-02-06

Smart Images

  • Figure CN222013215U_ABST
    Figure CN222013215U_ABST
Patent Text Reader

Abstract

The utility model discloses a gas turbine power plant natural gas metering system and a gas turbine power plant. The gas turbine power plant natural gas metering system comprises a filtering unit, a trade metering unit and a comparison metering unit. At least two branch pipelines are arranged in each unit, and the units are communicated through the branch pipelines; at least one filter is arranged on each branch pipeline in the filtering unit, at least one first ultrasonic flowmeter is arranged on each branch pipeline in the trade metering unit, and at least one second ultrasonic flowmeter is arranged on each branch pipeline in the comparison metering unit; the gas inlet end of each filter is communicated with the gas incoming main pipeline, and the gas outlet end of each filter is communicated with the gas inlet end of the first ultrasonic flowmeter; the air outlet end of the first ultrasonic flowmeter is communicated with the air inlet end of the second ultrasonic flowmeter, and the air outlet end of the second ultrasonic flowmeter is communicated with the air outlet main pipeline. Functional repetitive units of a trade metering station and a pressure regulating station are reasonably reduced, the occupied space and the investment cost can be saved, and daily operation and maintenance of a metering system are facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of natural gas metering, in particular to a natural gas metering system for a gas turbine power plant and a gas turbine power plant. Background Art

[0002] The statements in this section merely mention the background technology related to the present utility model and do not necessarily constitute the prior art.

[0003] Gas turbine power plants are large users of natural gas. Trade metering stations are used for natural gas trade settlement between gas companies and power plants. The main equipment of trade metering stations are filters and ultrasonic flow meters. The filter is used to filter impurities in natural gas, and the ultrasonic flow meter is used to measure natural gas consumption, which is used for trade settlement between gas companies and power plants.

[0004] The gas turbine power plant is equipped with a pressure regulating station, and a comparison metering unit is set up in the pressure regulating station. The main equipment in the comparison metering unit is an ultrasonic flowmeter, which is of the same brand and model as the ultrasonic flowmeter in the trade metering station. Its function is to calibrate whether the flowmeter in the trade metering station is accurate. If it is found that the ultrasonic flowmeter in the trade metering station is inaccurate or the ultrasonic flowmeter in the pressure regulating station is inaccurate, the flowmeter needs to be calibrated.

[0005] Gas turbine power plants consume a large amount of natural gas, so they have high requirements for the metering accuracy of natural gas flow meters. If the metering accuracy exceeds the allowable range, the deviation of the natural gas flow will be large, which will cause great losses to the gas company or the gas turbine power plant. The main function of the comparison metering unit in the pressure regulating station is to promptly detect inaccurate flow meters and send the flow meters for inspection and calibration.

[0006] In the prior art, the trade metering station is arranged outside the gas turbine power plant, built on a separate piece of land, or arranged inside the gas turbine power plant, close to the pressure regulating station, but surrounded by a fence to isolate it from the pressure regulating station.

[0007] Although the existing technology can realize the functions of natural gas trade measurement and comparison measurement, it has the following disadvantages:

[0008] 1. The filter units of the trade metering station and the pressure regulating station have duplicate functions, and setting up filter units for each station increases equipment investment.

[0009] 2. The trade metering station and the pressure regulating station are arranged separately, occupying a large area and causing waste of resources. Utility Model Content

[0010] In order to address the deficiencies of the prior art, the first aspect of the utility model provides a natural gas metering system for a gas turbine power plant, which "deeply integrates" the trade metering station and the pressure regulating station, that is, merges the functions and layouts, and reasonably reduces the functional duplication units of the trade metering station and the pressure regulating station, which can save floor space and investment costs and facilitate the daily operation and maintenance of the metering system.

[0011] In order to achieve the above objectives, the following solutions are provided:

[0012] A natural gas metering system for a gas turbine power plant, characterized in that it comprises a filtering unit, a trade metering unit and a comparison metering unit;

[0013] At least two branch pipelines are arranged in each unit, and each unit is connected through the branch pipelines;

[0014] At least one filter is provided on each branch pipeline in the filtration unit, at least one first ultrasonic flowmeter is provided on each branch pipeline in the trade metering unit, and at least one second ultrasonic flowmeter is provided on each branch pipeline in the comparison metering unit;

[0015] The air inlet end of each filter is connected to the main air supply line, and the air outlet end is connected to the air inlet end of the first ultrasonic flowmeter; the air outlet end of the first ultrasonic flowmeter is connected to the air inlet end of the second ultrasonic flowmeter, and the air outlet end of the second ultrasonic flowmeter is connected to the main air outlet line.

[0016] Furthermore, at least one isolation valve is provided at the air inlet and outlet of each filter.

[0017] Furthermore, at least one isolation valve is provided at the air inlet and the air outlet of each of the first ultrasonic flowmeter and the second ultrasonic flowmeter.

[0018] Furthermore, a blocking valve is provided at the air inlet end of each of the first ultrasonic flowmeter and the second ultrasonic flowmeter in parallel with a bypass slow-path ball valve.

[0019] Furthermore, in the comparison metering unit, adjacent branch pipelines are connected through a bridge pipeline, the first end of the bridge pipeline is connected to the outlet end of the second ultrasonic flowmeter of the air intake branch pipeline, and the second end of the bridge pipeline is connected to the inlet end of the second ultrasonic flowmeter of the air outlet branch pipeline.

[0020] Furthermore, at least one check valve is provided on the bridge pipeline.

[0021] Furthermore, at least one isolating valve is provided before the check valve of the bridge pipeline.

[0022] Furthermore, the ultrasonic flowmeters of each branch of the trade metering unit and the comparison metering unit are of the same model.

[0023] Furthermore, the measurement result is verified by the difference between the readings of the ultrasonic flowmeters in the trade measurement unit and the comparison measurement unit. If the deviation between the reading of any ultrasonic flowmeter and the other difference is greater than a set threshold, the measurement result is inaccurate.

[0024] The second aspect of the utility model provides a gas turbine power plant, which "deeply integrates" the trade metering station and the pressure regulating station, that is, merges the functions and layouts, reasonably reduces the functional duplication units of the trade metering station and the pressure regulating station, can save floor space and investment costs, and facilitates the daily operation and maintenance of the metering system.

[0025] In order to achieve the above objectives, the following solutions are provided:

[0026] A gas turbine power plant comprises the natural gas metering system for a gas turbine power plant described in the first aspect.

[0027] Compared with the prior art, the beneficial effects of the utility model are:

[0028] 1. "Deeply integrate" the trade metering station and the pressure regulating station, that is, merge the functions and layouts, and reasonably reduce the repeated functional units of the trade metering station and the pressure regulating station, which can save space and investment costs and facilitate the daily operation and maintenance of the metering system.

[0029] 2. The measurement result is verified by the difference between the readings of the ultrasonic flowmeter in the trade measurement unit and the comparison measurement unit. If the deviation between the reading of any ultrasonic flowmeter and the other difference is greater than the set threshold, the measurement result is inaccurate, which facilitates more accurate natural gas measurement. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] The drawings in the specification, which constitute a part of the present application, are used to provide further understanding of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute improper limitations on the present application.

[0031] Figure 1 This is the structure diagram of the traditional trade measurement station;

[0032] Figure 2 This is the structural diagram of a traditional pressure regulating station;

[0033] Figure 3 A schematic diagram of the structure of a natural gas metering system provided by an embodiment of the utility model;

[0034] Among them, 1. filtration unit, 101. first branch pipeline, 102. second branch pipeline, 103. first inlet main pipeline, 104. first outlet main pipeline, 2. trade metering unit, 201. third branch pipeline, 202. fourth branch pipeline, 203. second inlet main pipeline, 204. second outlet main pipeline, 3. comparison metering unit, 301. fifth branch pipeline, 302. sixth branch pipeline, 303. third inlet main pipeline, 304. third inlet main pipeline, 305. check valve, 306. ball valve, 4. first filter, 5. second filter, 401 , the first isolating valve, 402 the second isolating valve, 6, the first ultrasonic flow meter, 601, the third isolating valve, 602, the fourth isolating valve, 603, the first side injection slow-path ball valve, 7, the second ultrasonic flow meter, 701, the fifth isolating valve, 702, the sixth isolating valve, 703, the second side injection slow-path ball valve, 8, the third ultrasonic flow meter, 801, the seventh isolating valve, 802, the eighth isolating valve, 803, the third side injection slow-path ball valve, 9, the fourth ultrasonic flow meter, 901, the ninth isolating valve, 902, the tenth isolating valve, 903, the fourth side injection slow-path ball valve, 10, the bridge pipeline. DETAILED DESCRIPTION

[0035] It should be noted that the following detailed descriptions are exemplary and are intended to provide further explanation of the present application. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present application belongs.

[0036] It should be noted that the utility model is a construction scheme. As for the various equipment units involved therein, the specific structures for realizing the functions they should realize already exist in the prior art, and the protocols, software or programs involved in the work processing therebetween also already exist in the prior art. Those skilled in the art are fully aware that the utility model does not make any improvements to the units of each device, and therefore does not involve the content of the software, but relies on the organic integration of various components into a whole, that is, providing a construction scheme.

[0037] Explanation of terms

[0038] Trade metering station: used for natural gas trade settlement between gas companies and users. The main equipment of the trade metering station is the filtration unit and trade metering unit, among which the ultrasonic flow meter is used to measure the natural gas consumption of users;

[0039] Pressure regulating station: It is set up in the gas turbine power plant. The pressure regulating station contains many units such as filtration unit, comparison and metering unit, heating unit, pressure regulating unit, sewage discharge unit, etc. Its main function is to filter, meter, heat and pressure regulate the natural gas entering the gas turbine power plant before supplying it to the gas turbine (referred to as the gas turbine).

[0040] like Figure 1 and Figure 2 The figure shows an existing natural gas metering system of a gas turbine power plant, including a trade metering station and a pressure regulating station; the trade metering station includes a first filter unit and a first trade metering unit, and the output end of the first filter unit is connected to the input end of the first trade metering unit;

[0041] The pressure regulating station comprises a second filtering unit and a comparison and metering unit, wherein the output end of the second filtering unit is connected to the input end of the comparison and metering unit;

[0042] The working principle of its natural gas metering is as follows: the upstream natural gas passes through the input end of the first filter unit, and after being filtered, it is input into the ultrasonic flow meter in the first trade metering unit and output to the pressure regulating station, and after passing the second filter unit of the pressure regulating station, it is input into the comparison metering unit, and the measurement passing through the trade metering station is calibrated. After the calibration, it is output to the downstream natural gas units.

[0043] From the above scheme, we can see that traditional natural gas metering is done through trade metering stations and pressure regulating stations respectively. During metering, impurities in natural gas are filtered through two filtering processes. However, in general, impurities in natural gas can be basically filtered out after one filtration. If a secondary filtration is set at the pressure regulating station, on the one hand, the functions are repeated and related equipment needs to be invested, which increases the investment cost. On the other hand, the additional equipment requires the establishment of trade metering stations and pressure regulating stations respectively, which occupies a large area and further increases the investment cost.

[0044] In order to solve the drawbacks of the existing technical solutions, the utility model "deeply integrates" the trade metering station and the pressure regulating station, that is, merges the functions and layouts, arranges the trade metering unit of the trade metering station before the comparison metering unit of the pressure regulating station, cancels the filtering unit of the trade metering station, and shares the filtering unit with the pressure regulating station.

[0045] The content of the utility model is described below in the form of specific embodiments.

[0046] Example 1

[0047] like Figure 3 As shown, Embodiment 1 of the present utility model provides a natural gas metering system, including a filtering unit 1, a trade metering unit 2 and a comparison metering unit 3;

[0048] Each unit takes two branch pipelines as an example:

[0049] The filtering unit 1 comprises a first branch pipeline 101 and a second branch pipeline 102, a first filter 4 is arranged on the first branch pipeline 101, a second filter 5 is arranged on the second branch pipeline 102, the first ends of the first branch pipeline 101 and the second branch pipeline 102 are respectively connected to a first inlet main pipeline 103, the second ends of the first branch pipeline 101 and the second branch pipeline 102 are respectively connected to a first outlet main pipeline 104, and the first outlet main pipeline 104 is connected to the trade metering unit 2;

[0050] In this embodiment, first isolation valves 401 are provided before and after the first filter 4 of the first branch pipeline;

[0051] Second isolation valves 402 are provided before and after the second filter of the second branch pipeline.

[0052] The first isolating valve and the second isolating valve may be ball valves.

[0053] The trade metering unit 2 comprises a third branch pipeline 201 and a fourth branch pipeline 202, a first ultrasonic flowmeter 6 is arranged on the third branch pipeline 201, a second ultrasonic flowmeter 7 is arranged on the fourth branch pipeline 202, the first ends of the third branch pipeline 201 and the fourth branch pipeline 202 are respectively connected to the second inlet main pipeline 203, the second ends of the third branch pipeline 201 and the fourth branch pipeline 202 are respectively connected to the second outlet main pipeline 204, and the second outlet main pipeline 204 is connected to the comparison metering unit 3;

[0054] In this embodiment, a third isolation valve 601 is provided before the first ultrasonic flowmeter 6 of the third branch pipeline 201, and a fourth isolation valve 602 is provided after the third isolation valve 601. The third isolation valve 601 is connected in parallel with a first bypass slow-flow ball valve 603 through a pipeline.

[0055] A fifth isolating valve 701 is arranged before the second ultrasonic flowmeter 7 of the fourth branch pipeline 202, and a sixth isolating valve 702 is arranged after the fourth branch pipeline 202; the fifth isolating valve 701 is connected in parallel with a second bypass slow-path ball valve 703 through a pipeline.

[0056] The comparison metering unit 3 includes a fifth branch pipeline 301 and a sixth branch pipeline 302. The fifth branch pipeline 301 is provided with a third ultrasonic flowmeter 8, and the sixth branch pipeline 302 is provided with a fourth ultrasonic flowmeter 9. The first ends of the fifth branch pipeline 301 and the sixth branch pipeline 302 are respectively connected to the third gas inlet main pipeline 303, and the second ends of the fifth branch pipeline 301 and the sixth branch pipeline 302 are respectively connected to the third gas outlet main pipeline 304 and then transported to the downstream natural gas units.

[0057] The fifth branch pipeline 301 and the sixth branch pipeline 302 are connected via a bridge pipeline 10 . A check valve 305 is provided on the bridge pipeline 10 . At least one ball valve 306 is provided before the check valve 305 .

[0058] The first end of the bridge pipe 10 is communicated with the air outlet end of the third ultrasonic flowmeter 8 of the fifth branch pipe 301 , and the second end of the bridge pipe 10 is communicated with the air inlet end of the fourth ultrasonic flowmeter 9 of the sixth branch pipe 302 .

[0059] In this embodiment, a seventh isolation valve 801 and an eighth isolation valve 802 are arranged before and after the third ultrasonic flowmeter 8 of the fifth branch pipeline 301, and the seventh isolation valve 801 in front is connected in parallel with the third side injection slow-path ball valve 803 through a pipeline. A ninth isolation valve 901 and a tenth isolation valve 902 are arranged before and after the fourth ultrasonic flowmeter 9 of the sixth branch pipeline 302, and the ninth isolation valve 901 in front is connected in parallel with the fourth side injection slow-path ball valve 903 through a pipeline.

[0060] The working principle of the utility model is:

[0061] Take one of the working processes as an example:

[0062] Close the isolation valves before and after the second filter 5;

[0063] Close the fifth isolation valve 701, the sixth isolation valve 702, the first bypass slow-path ball valve 603, and the second bypass slow-path ball valve 703 of the trade metering unit;

[0064] Close the eighth isolation valve 802, the ninth isolation valve 901, the third bypass slow-path ball valve 803, and the fourth bypass slow-path ball valve 903 of the comparison metering unit;

[0065] The natural gas flows sequentially through the first filter 4 , the third isolation valve 601 , the first ultrasonic flow meter 6 , the fourth isolation valve 602 , the seventh isolation valve 801 , the third ultrasonic flow meter 8 , the ball valve 306 , the check valve 305 , the fourth ultrasonic flow meter 9 , and the tenth isolation valve 902 .

[0066] Compare the readings of the first ultrasonic flowmeter 6, the third ultrasonic flowmeter 8, and the fourth ultrasonic flowmeter 9. If the reading of one flowmeter deviates greatly from the other two, it proves that the flowmeter is not measuring accurately and needs to be dismantled for calibration.

[0067] Example 2

[0068] Embodiment 2 of the present utility model provides a gas turbine power plant, including a natural gas metering system for a gas turbine power plant as described in Embodiment 1 of the present utility model.

[0069] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A natural gas metering system for a gas turbine power plant, characterized in that: Includes filtering unit, trade measurement unit and comparison measurement unit; At least two branch pipelines are arranged in each unit, and each unit is connected through the branch pipelines; At least one filter is provided on each branch pipeline in the filtration unit, at least one first ultrasonic flowmeter is provided on each branch pipeline in the trade metering unit, and at least one second ultrasonic flowmeter is provided on each branch pipeline in the comparison metering unit; The air inlet end of each filter is connected to the main air supply line, and the air outlet end is connected to the air inlet end of the first ultrasonic flowmeter; the air outlet end of the first ultrasonic flowmeter is connected to the air inlet end of the second ultrasonic flowmeter, and the air outlet end of the second ultrasonic flowmeter is connected to the main air outlet line.

2. A natural gas metering system for a gas turbine power plant as claimed in claim 1, characterized in that: At least one isolation valve is provided at the air inlet and outlet ends of each filter.

3. A natural gas metering system for a gas turbine power plant as claimed in claim 1, characterized in that: At least one isolating valve is disposed at the air inlet and the air outlet of each of the first ultrasonic flowmeter and the second ultrasonic flowmeter.

4. A natural gas metering system for a gas turbine power plant as claimed in claim 3, characterized in that: The isolating valve provided at the air inlet end of each first ultrasonic flowmeter and the second ultrasonic flowmeter is connected in parallel with the bypass slow-flow ball valve.

5. A natural gas metering system for a gas turbine power plant as claimed in claim 1, characterized in that: In the comparison metering unit, adjacent branch pipelines are connected through a bridge pipeline, the first end of the bridge pipeline is connected to the outlet end of the second ultrasonic flowmeter of the air inlet branch pipeline, and the second end of the bridge pipeline is connected to the inlet end of the second ultrasonic flowmeter of the air outlet branch pipeline.

6. A natural gas metering system for a gas turbine power plant as claimed in claim 5, characterized in that: At least one check valve is arranged on the bridge pipeline.

7. A natural gas metering system for a gas turbine power plant as claimed in claim 6, characterized in that: At least one isolating valve is provided before the non-return valve of the bridge pipeline.

8. A natural gas metering system for a gas turbine power plant as claimed in claim 1, characterized in that: The ultrasonic flowmeter models of each branch of the trade metering unit and the comparison metering unit are the same.

9. A natural gas metering system for a gas turbine power plant as claimed in claim 1, characterized in that: The measurement result is verified by the difference between the readings of the ultrasonic flowmeter in the trade measurement unit and the comparison measurement unit. If the deviation between the reading of any ultrasonic flowmeter and the other difference is greater than the set threshold, the measurement result is inaccurate.

10. A gas turbine power plant, characterized in that: It comprises a natural gas metering system for a gas turbine power plant as described in any one of claims 1-9.