Building corridor supporting structure

By setting up a support group, support beam and double-layer tire cap structure at the bottom of the corridor, the load is directly transferred to the building frame column, which solves the problems of construction complexity and efficiency in the existing technology, and achieves efficient load transfer and structural support. , improves the construction efficiency of corridor installation.

CN222025514UActive Publication Date: 2024-11-19ZHONGYIFENG CONSTR GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420399670.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-01
Publication Date
2024-11-19
Estimated Expiration
2034-03-01

AI Technical Summary

Technical Problem

In large high-rise joint buildings, the construction is complicated during the assembly process of the steel corridor, resulting in low construction efficiency. The basement roof panel or the concrete on the roof of the skirt house needs to be reinforced back-top to support the load, affecting structural integrity.

Method used

Adopt the support group, support beam and tire cap structure. The support beam spans the leveling support of the support group. The load is directly transmitted to the building frame column through the tire cap structure, support beam and leveling support to avoid the beam and slab structure. Back-top reinforcement, using a double-layer tire cap structure to disperse the load to improve support strength.

Benefits of technology

It reduces the construction complexity, saves construction time, improves the construction efficiency of corridor installation, and avoids structural damage caused by concentrated stress, improving the load transfer efficiency of the building.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222025514U_ABST
    Figure CN222025514U_ABST
Patent Text Reader

Abstract

The utility model provides a building corridor supporting structure, and belongs to the technical field of building corridor mounting structures. The building corridor supporting structure comprises a plurality of support sets arranged on the top face of a target building and sequentially arranged in the length direction of a corridor, and each support set comprises a plurality of leveling supports sequentially arranged in the width direction of the corridor, the bottom face of each leveling support is matched with the top face of a target building in shape, the top faces are located at the same height, and each leveling support is aligned with a frame column of the target building in the vertical direction. The plurality of supporting beams are supported above the support groups in a one-to-one correspondence manner; each tire cap structure is arranged above the supporting beam, each tire cap structure is aligned with each leveling support in the vertical direction, and the tops of the tire cap structures are used for supporting the corridor. According to the building corridor supporting structure, the construction complexity of a corridor can be reduced, and the installation and construction efficiency of the corridor can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building corridor installation structures, in particular to a building corridor supporting structure. Background Art

[0002] The architectural form of a large high-rise connected structure will form two buildings arranged at intervals. In order to meet the functional requirements of this architectural form, high-altitude steel corridors are usually used to connect them. The bottom of the corridor is usually the basement roof or the skirt roof.

[0003] When assembling the corridor on the basement roof or the podium roof, a temporary support frame needs to be set up. Since the steel corridor is heavy, the concrete of the basement roof or the podium roof needs to be reinforced during assembly to avoid damage to the structure. In the prior art, when assembling the steel corridor, a lattice support frame is set at the beam-column node of the steel corridor, and the concrete structure of the basement roof or the podium roof below the support frame is reinforced with steel pipe columns, so that the load of the corridor is transferred to the bottom plate of the building.

[0004] However, the construction process of the supporting structure of the above-mentioned steel corridor requires setting a return structure at the concrete structure on the top of the building. This construction process is relatively complicated and the construction efficiency is low. Utility Model Content

[0005] One purpose of the utility model is to reduce the construction complexity of the corridor and improve the installation and construction efficiency of the corridor.

[0006] In particular, an embodiment of the present application provides a building corridor support structure, comprising:

[0007] A plurality of support groups are arranged at the top surface of the target building, the plurality of support groups are sequentially arranged along the length direction of the corridor, each of the support groups comprises a plurality of leveling supports sequentially arranged along the width direction of the corridor, the bottom surface of each leveling support is adapted to the shape of the top surface of the target building, the top surface is at the same height, and each of the leveling supports is vertically aligned with the frame column of the target building;

[0008] A plurality of support beams, one by one correspondingly supported on each of the support groups;

[0009] A plurality of tire cap structures are provided, each of the tire cap structures is arranged above the support beam, each of the tire cap structures is vertically aligned with each of the leveling supports, and the tops of the plurality of tire cap structures are used to support the corridor.

[0010] Optionally, the tire cap structure includes multiple layers of support structures stacked in sequence in the vertical direction, and the support structure located at the bottom layer includes a plurality of support seats arranged at intervals.

[0011] Optionally, the plurality of support seats at the bottom layer are arranged in sequence along the width direction of the corridor.

[0012] Optionally, the tire cap structure is a double-layer support structure and comprises:

[0013] A plurality of bottom steel sections are arranged in sequence along the width direction of the corridor;

[0014] A plurality of top-layer steel sections are located above the plurality of bottom-layer steel sections and are arranged in sequence along the length direction of the corridor, and the length direction of each of the top-layer steel sections is perpendicular to the length direction of each of the bottom-layer steel sections.

[0015] Optionally, the bottom steel section and the top steel section are both H-shaped steel sections.

[0016] Optionally, the cross-sectional dimensions of the bottom steel section and the top steel section are the same.

[0017] Optionally, the minimum height between the top surface of the tire cap structure and the top surface of the target building is greater than a preset value to facilitate the passage of a lifting vehicle at the bottom of the corridor.

[0018] Optionally, the leveling support is a concrete structure.

[0019] Optionally, the support beam is a Bailey beam.

[0020] According to the first aspect of the utility model, there is provided a building corridor support structure arranged at the bottom of the corridor, the structure comprising a support group, a support beam and a tire cap structure arranged in sequence in the vertical direction, the support beam spans across each leveling support of each support group, and in the vertical direction, each leveling support and each tire cap structure are aligned with the frame columns of the target building. Therefore, the load of the corridor is directly transmitted to the frame columns of the target building through the tire cap structure, the support beam and the leveling support in sequence, without the need to set a back-top reinforcement structure for the beam-slab structure of the target building, thereby reducing the construction complexity, saving construction time, and being able to improve the corridor installation construction efficiency.

[0021] According to the second aspect of the utility model, the tire cap structure includes a multi-layer support structure, and the support structure located at the bottom layer includes a plurality of support seats arranged at intervals. The plurality of support seats arranged at intervals can distribute the load of the corridor to the stress nodes of the support beams to avoid stress concentration and damage to the target building structure.

[0022] Furthermore, the tire cap structure is a double-layer structure, that is, multiple top-layer steel sections and multiple bottom-layer steel sections are arranged in sequence up and down, the length directions of the top-layer steel sections and the bottom-layer steel sections are perpendicular to each other, and the arrangement directions are opposite to each other. Multiple bottom-layer steel sections are used to disperse the load, and multiple top-layer steel sections are used to better support the support beam. The double-layer tire cap structure arranged in the above manner itself has a higher supporting strength and can better transmit force and provide support. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a structural schematic diagram of a building corridor support structure in the width direction of the corridor according to one embodiment of the utility model;

[0024] Figure 2 for Figure 1 A partial enlarged view of the middle A;

[0025] Figure 3 It is a schematic structural diagram of a building corridor support structure in the length direction of the corridor according to one embodiment of the utility model;

[0026] Figure 4 for Figure 3 A partial enlarged view of point B in the middle. DETAILED DESCRIPTION

[0027] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are described in detail below in conjunction with the accompanying drawings. It is to be understood that the specific embodiments described herein are only used to explain the present application, rather than to limit the present application. It should also be noted that, for ease of description, only some structures related to the present application are shown in the accompanying drawings, rather than all structures. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.

[0028] The terms "including" and "having" and any variations thereof in this application are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device comprising a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units not listed, or may optionally include other steps or units inherent to these processes, methods, products or devices.

[0029] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.

[0030] Figure 1 Schematic diagram of the structure of the building corridor support structure 100 in the width direction of the corridor 200 according to one embodiment of the utility model. Figure 2 for Figure 1 A partial enlarged view of point A in the middle. Figure 3It is a schematic structural diagram of a building corridor support structure 100 in the length direction of a corridor 200 according to an embodiment of the utility model. Figure 4 for Figure 3 A partial enlarged view of point B in the figure. Figure 3 As shown, in one embodiment of the present application, a supporting structure of a corridor 200 (generally a steel corridor) is provided at the bottom of the corridor 200. The building corridor supporting structure 100 includes a plurality of support groups 10, a plurality of support beams 20 and a plurality of tire cap structures 30. The plurality of support groups 10 are provided at the top surface 310 of the target building. The top surface 310 of the target building can be the basement roof or the skirt roof of a large high-rise connected building. The plurality of support groups 10 are arranged along the length direction of the corridor 200 ( Figure 3 b) are arranged in sequence, such as Figure 1 As shown, each support group 10 includes a plurality of support groups 11 along the width direction of the corridor 200 ( Figure 1 In one embodiment, the leveling support 11 is a concrete structure. The bottom surface of each leveling support 11 matches the shape of the top surface 310 of the target building, and the top surface is at the same height. Figure 1 As shown, the top surface 310 of the target building may be an arc-shaped top surface, and the bottom surface of the leveling support 11 needs to be set to a surface matching the arc-shaped top surface (see Figure 2 ). Each leveling support 11 is vertically aligned with the frame column 320 of the target building. The frame column 320 is the main vertical load-bearing member in the frame structure of the target building. It is used to bear the load from the beams and slabs and transfer the load to the foundation. It is the main load-bearing structure. Multiple support beams 20 are supported one by one on top of each support group 10. The support beams 20 here can be Bailey beams formed by Bailey sheets. Each tire cap structure 30 is arranged above the support beam 20. Each tire cap structure 30 is vertically aligned with each leveling support 11. The tops of multiple tire cap structures 30 are used to support the corridor 200.

[0031] The present embodiment provides a building corridor support structure 100 arranged at the bottom of the corridor 200, and the structure includes a support group 10, a support beam 20 and a tire cap structure 30 arranged in sequence in the vertical direction. The support beam 20 spans across each leveling support 11 of each support group 10. In the vertical direction, each leveling support 11 and each tire cap structure 30 are aligned with the frame column 320 of the target building. Therefore, the load of the corridor 200 is directly transmitted to the frame column 320 of the target building through the tire cap structure 30, the support beam 20 and the leveling support 11 in sequence, without the need to set a back-top reinforcement structure for the beam-slab structure of the target building, thereby reducing the construction complexity, saving construction time, and being able to improve the installation and construction efficiency of the corridor 200.

[0032] like Figure 2As shown, in one embodiment, the tire cap structure 30 includes a plurality of supporting structures stacked in sequence in the vertical direction, and the supporting structure at the bottom layer includes a plurality of support seats arranged at intervals. The plurality of support seats at the bottom layer are arranged in sequence along the width direction of the corridor 200. The support seats of this embodiment can be made of steel.

[0033] The tire cap structure 30 in this embodiment includes a multi-layer support structure. The support structure located at the bottom layer includes a plurality of support seats arranged at intervals. The plurality of support seats arranged at intervals can distribute the load of the corridor 200 to the stress nodes of the support beam 20 to avoid stress concentration and damage to the target building structure.

[0034] In one embodiment, if Figure 2 As shown, the tire cap structure 30 is a double-layer support structure and includes a plurality of bottom-layer steel sections 31 and a plurality of top-layer steel sections 32. The plurality of bottom-layer steel sections 31 are arranged in sequence along the width direction of the corridor 200. Figure 4 As shown, a plurality of top-layer steel sections 32 are located above a plurality of bottom-layer steel sections 31 and are sequentially arranged along the length direction of the corridor 200, and the length direction of each top-layer steel section 32 is perpendicular to the length direction of each bottom-layer steel section 31. Figure 2 and Figure 4 In the illustrated embodiment, the tire cap structure 30 includes three bottom steel sections 31 and two top steel sections 32. In other embodiments not shown, other numbers of bottom steel sections 31 and top steel sections 32 may be provided according to actual needs, and no limitation is made here. The bottom steel sections 31 and top steel sections 32 are both H-shaped steels. Of course, in other embodiments not shown, the bottom steel sections 31 and top steel sections 32 may also be cross-sectional profiles, such as rectangular steels, I-shaped steels, etc.

[0035] The tire cap structure 30 of this embodiment is a double-layer structure, that is, a plurality of top-layer steel sections 32 and a plurality of bottom-layer steel sections 31 are arranged in sequence up and down, the length directions of the top-layer steel sections 32 and the bottom-layer steel sections 31 are perpendicular to each other, and the arrangement directions are opposite to each other, the plurality of bottom-layer steel sections 31 are used to disperse the load, and the plurality of top-layer steel sections 32 are used to better support the support beam 20. The double-layer tire cap structure 30 arranged in the above manner itself has a higher supporting strength and can better transmit force and provide support.

[0036] In a further embodiment, the cross-sectional dimensions of the bottom steel section 31 and the top steel section 32 are the same, that is, the bottom steel section 31 and the top steel section 32 are made of the same type of steel, for example, both are HW300*150*6.5*9 steel sections (unit: mm), so there is no need to specially select the corresponding steel sections when connecting the bottom steel section 31 and the top steel section 32, which can improve the connection efficiency.

[0037] In one embodiment, the minimum height between the top surface of the tire cap structure 30 and the top surface of the target building is greater than a preset value so that the lifting vehicle 400 (see Figure 3 ) passage.

[0038] In one embodiment, if Figure 1 As shown, the support beam 20 is a Bailey beam. A Bailey beam is a beam structure formed by a plurality of Bailey plates forming a Bailey unit. When designing a Bailey beam, the position of the main force node can be determined according to the span of the leveling support 11 and the load of the corridor 200. For example, the longitudinal beam of the Bailey beam is aligned with the frame column 320 of the target building as much as possible, for example Figure 1 The left frame column 320 and the middle frame column 320 are both aligned with the longitudinal beams of the Bailey beam.

[0039] The above-mentioned embodiments only express several implementation methods of the utility model, and the description is relatively specific and detailed, but it cannot be understood as limiting the scope of the utility model patent. It should be pointed out that for ordinary technicians in this field, several modifications and improvements can be made without departing from the concept of the utility model, which all belong to the protection scope of the utility model. Therefore, the protection scope of the utility model patent shall be based on the attached claims.

Claims

1. A building corridor support structure, characterized in that: include: A plurality of support groups are arranged at the top surface of the target building, the plurality of support groups are sequentially arranged along the length direction of the corridor, each of the support groups comprises a plurality of leveling supports sequentially arranged along the width direction of the corridor, the bottom surface of each leveling support is adapted to the shape of the top surface of the target building, the top surface is at the same height, and each of the leveling supports is vertically aligned with the frame column of the target building; A plurality of support beams, one by one correspondingly supported on each of the support groups; A plurality of tire cap structures are provided, each of the tire cap structures is arranged above the support beam, each of the tire cap structures is vertically aligned with each of the leveling supports, and the tops of the plurality of tire cap structures are used to support the corridor.

2. The building corridor support structure according to claim 1, characterized in that: The tire cap structure includes multiple layers of support structures stacked in sequence in a vertical direction, and the support structure located at the bottom layer includes a plurality of support seats arranged at intervals.

3. The building corridor support structure according to claim 2, characterized in that: The plurality of support seats at the bottom layer are arranged in sequence along the width direction of the corridor.

4. The building corridor support structure according to claim 3, characterized in that: The tire cap structure is a double-layer support structure and includes: A plurality of bottom steel sections are arranged in sequence along the width direction of the corridor; A plurality of top-layer steel sections are located above the plurality of bottom-layer steel sections and are arranged in sequence along the length direction of the corridor, and the length direction of each of the top-layer steel sections is perpendicular to the length direction of each of the bottom-layer steel sections.

5. The building corridor support structure according to claim 4, characterized in that: The bottom steel section and the top steel section are both H-shaped steel sections.

6. The building corridor support structure according to claim 4, characterized in that: The cross-sectional dimensions of the bottom steel section and the top steel section are the same.

7. The building corridor support structure according to any one of claims 1 to 6, characterized in that: The minimum height between the top surface of the tire cap structure and the top surface of the target building is greater than a preset value to facilitate the passage of a lifting vehicle at the bottom of the corridor.

8. The building corridor support structure according to any one of claims 1 to 6, characterized in that: The leveling support is a concrete structure.

9. The building corridor support structure according to any one of claims 1 to 6, characterized in that: The support beam is a Bailey beam.