Ecological water replenishing structure capable of replenishing water in reconstruction period and operation period

By setting up water replenishment pipes and regulating valve structures in the hydropower station tunnel, ecological water replenishment during the reconstruction and operation periods is achieved, the problem of changes in the drainage flow caused by the closure of the accident gate is solved, the stability and sustainability of the river ecosystem is ensured, and Reduces project costs and difficulty.

CN222044123UActive Publication Date: 2024-11-22POWERCHINA HUADONG ENG CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420324995.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-21
Publication Date
2024-11-22
Estimated Expiration
2034-02-21

AI Technical Summary

Technical Problem

During the reconstruction and operation of hydropower stations, the closing and opening of the accident gate leads to changes in the drainage flow, affecting the downstream river channels and ecological environment. Ecological water replenishment is required during the reconstruction and operation period to ensure the stability and sustainability of the river ecosystem.

Method used

Design an ecological water replenishment structure that combines water replenishment during reconstruction and operation period. By burying water replenishment pipes in the tunnel wall, setting up water intakes during initial storage reconstruction and permanent operation water intake, and installing an accident eccentric hemisphere valve on the water replenishment pipe. Maintain gate valves and working valves to regulate water intake flow, and ensure the realization of ecological water replenishment.

Benefits of technology

It effectively solves the problem of ecological water replenishment, ensures the basic ecological flow of the downstream rivers, maintains the living environment of aquatic organisms, reduces the difficulty and cost of engineering technology, and realizes the reliability and stability of ecological water replenishment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222044123U_ABST
    Figure CN222044123U_ABST
Patent Text Reader

Abstract

The utility model provides an ecological water supplementing structure capable of supplementing water in a reconstruction period and an operation period, a water supplementing pipe is embedded in a wall body of a tunnel, and a water taking port of the water supplementing pipe is respectively provided with an initial water storage reconstruction period water taking port and a permanent operation water taking port on the upstream side and the downstream side of an emergency gate shaft. The initial water storage reconstruction period water intake and the permanent operation water intake are in an independent operation type opening state in the reconstruction period and the operation period; a water outlet of the water replenishing pipe is formed in the downstream of the radial gate of the working radial gate chamber, and a working valve is arranged on the pipe section, opposite to the water outlet side, of the water replenishing pipe. The water replenishing pipeline is small in occupied space, the use site is not limited, the ecological water replenishing problem can be effectively solved, the basic ecological flow of a downstream river channel is guaranteed, the living environment of aquatic organisms is maintained, and the stability and sustainability of a river ecological system are guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of water conservancy and hydropower engineering, and in particular to an ecological water replenishment structure capable of replenishing water during both the reconstruction period and the operation period. Background Art

[0002] During the reconstruction and operation of the hydropower station, the closing and opening of the emergency gate will cause changes in the downstream flow rate. The changes in the downstream flow rate will have a certain impact on the downstream river channel and ecological environment. In order to protect the ecological environment and the ecological water demand, ecological water replenishment is required during the reconstruction and operation periods to ensure the stability and sustainability of the river ecosystem and promote the sustainable development of the hydropower station. Utility Model Content

[0003] The utility model aims to provide an ecological water replenishment structure which can ensure the basic ecological flow of the downstream river.

[0004] To this end, the utility model adopts the following technical solutions:

[0005] An ecological water replenishment structure for replenishing water during both the reconstruction period and the operation period, wherein a water replenishment pipe is buried in the wall of a tunnel, and the water intake of the water replenishment pipe is respectively provided with an initial water storage reconstruction period water intake and a permanent operation water intake on the upstream and downstream sides of an accident gate well, and the initial water storage reconstruction period water intake is in an open state during the reconstruction period and the permanent operation water intake is in an independently operating open state during the operation period; the water outlet of the water replenishment pipe is provided downstream of the arc gate of a working arc gate chamber, and a working valve is provided on the pipe section of the water replenishment pipe opposite to the water outlet.

[0006] Furthermore: an emergency eccentric semi-ball valve is provided on the water supply pipe section between the water intake during the initial water storage and reconstruction period and the permanent operation water intake to adjust the connection or closing of the water intake during the initial water storage and reconstruction period and the water supply pipe.

[0007] Furthermore: an adjustment channel cooperating with the emergency eccentric hemispherical valve is arranged in the tunnel, and a rotating operating rod located in the adjustment channel is arranged on the emergency eccentric hemispherical valve, and an operating panel is arranged on the rotating operating rod relative to the inner cavity of the tunnel.

[0008] Furthermore: a maintenance gate valve is provided on the pipe section of the permanent water intake to adjust the connection or closing between the permanent water intake and the water supply pipe.

[0009] Furthermore: the water intake during the initial water storage and reconstruction period should be no less than 1m away from the accident gate well, and the water intake during the permanent operation period should be no less than 2m away from the accident gate well.

[0010] Furthermore: an emergency valve is arranged on the pipe section of the water supply pipe upstream of the working valve.

[0011] Furthermore: the emergency valve and the working valve are installed on the water supply pipe section in the working arc gate chamber area.

[0012] Compared with the prior art, the utility model has the following beneficial effects:

[0013] The water supply pipe of the utility model occupies a small space and is not restricted in the use site. It can effectively solve the problem of ecological water supply, ensure the basic ecological flow of the downstream river, maintain the living environment of aquatic organisms, and ensure the stability and sustainability of the river ecosystem. At the same time, the implementation of the water supply pipe is relatively simple and requires a small investment. It can achieve ecological water supply without destroying other building structures, avoid engineering damage, and reduce engineering technical difficulty. It also has relatively low construction and maintenance costs, good sealing, and high reliability. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a cross-sectional schematic diagram of the utility model;

[0015] Figure 2 It is a plan view of the utility model;

[0016] Figure 3 It is an enlarged schematic diagram of the water intake structure of the utility model.

[0017] The markings in the attached figure are: 1-water supply pipe; 11-water intake during the initial water storage and reconstruction period; 12-permanent operation water intake; 121-maintenance gate valve; 13-water outlet; 2-accident eccentric hemispherical valve; 21-rotating operating lever; 22-operating panel; 3-working valve; 4-accident valve; 5-accident gate well; 6-working arc gate chamber; 7-regulating channel. DETAILED DESCRIPTION

[0018] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present invention.

[0019] like Figure 1-3 As shown, an ecological water replenishment structure with water replenishment during both the reconstruction period and the operation period, a water replenishment pipe 1 is buried in the wall of the tunnel, and the water replenishment pipe 1 has a water intake and a water outlet 13 connected to the internal cavity of the tunnel, and the remaining pipe sections are deeply buried in the tunnel wall; the water replenishment pipe 1 is provided with two water intakes, and an initial water storage reconstruction period water intake 11 and a permanent operation water intake 12 are respectively provided on the upstream and downstream sides of the accident gate well 5, and water is taken in the reconstruction period and the operation period respectively, so that the initial water storage reconstruction period water intake 11 is in the reconstruction period and the permanent operation water intake 12 is in the operation period in an independently operating open state; the outlet 13 of the water replenishment pipe 1 is arranged downstream of the arc gate of the working arc gate chamber 6, and a working valve 3 is provided on the pipe section of the water replenishment pipe 1 opposite to the water outlet 13.

[0020] In this embodiment, an accident eccentric semi-ball valve 2 is provided on the pipe section between the initial water storage reconstruction period water intake 11 and the permanent operation water intake 12 of the water supply pipe 1 to adjust the connection or closing of the initial water storage reconstruction period water intake 11 and the water supply pipe 1. The specific position of the accident eccentric semi-ball valve 2 is on the downstream side of the accident gate well 5, and the distance from the accident gate well 5 is about 1.5m.

[0021] At the same time, a steel pipe is pre-buried on the tunnel wall downstream of the accident gate shaft 5, so that an adjustment channel 7 is formed inside the steel pipe, and the adjustment channel 7 is connected to the location of the accident eccentric semi-ball valve 2. The accident eccentric semi-ball valve 2 is provided with a rotating operating rod 21 located in the adjustment channel 7, and an operating panel 22 is provided on the rotating operating rod 21 relative to the inner cavity of the tunnel. In order to facilitate the opening and closing operation of the accident eccentric semi-ball valve 2, the adjustment channel 7 can be connected to the inner cavity of the tunnel during the reconstruction period, and the adjustment channel 7 can be closed before the operation period.

[0022] In this embodiment, a maintenance gate valve 121 is provided on the pipe section of the permanent water intake 12 to adjust the connection or closing of the permanent water intake 12 and the water supply pipe 1. In particular, the pipe section of the permanent water intake 12 equipped with the maintenance gate valve 121 can be extended out of the tunnel wall during the reconstruction period to facilitate its operation, and the maintenance gate valve 121 can be removed during the operation period.

[0023] In this embodiment, the initial water storage reconstruction period water intake 11 is located on the upstream side of the accident gate well 5, and is not less than 1m away from the accident gate well 5; the permanent operation water intake 12 is located on the downstream side of the accident gate well 5, and is not less than 2m away from the accident gate well 5.

[0024] In this embodiment, an emergency valve 4 is provided on the pipe section upstream of the working valve 3 along the flow direction of the internal water body of the water supply pipe 1, and the emergency valve 4 and the working valve 3 are installed on the pipe section of the water supply pipe 1 within the area of ​​the working arc gate chamber 6 to facilitate maintenance and inspection.

[0025] See also Figure 1-3 During the reconstruction period and the operation period, the specific contents of the ecological water replenishment structure are as follows:

[0026] During the reconstruction period, the accident gate well 5 is closed, and the permanent operating water intake 12 located on the downstream side of the accident gate well 5 cannot draw water. The water supply pipe 1 draws water from the initial water storage reconstruction period water intake 11, the accident eccentric hemispherical valve 2 operates in full diameter, and the working valve 3 is opened for ecological water replenishment.

[0027] When the reconstruction is completed, the operating panel 22 is used to drive the rotating operating rod 21 to close the accident eccentric hemispherical valve 2, the operating panel 22 is removed and the rotating operating rod 21 that is higher than the tunnel side wall is cut off, and the embedded steel pipe is treated with epoxy mortar to close the regulating channel 7. After the accident eccentric hemispherical valve 2 is closed, the working valve 3 is closed, the inspection gate valve 121 located at the permanent operation water intake 12 is cut off, and the end of the pipe section originally exposed at the permanent operation water intake 12 and the tunnel side wall are polished flat.

[0028] During the operation period, the accident gate well 5 is opened, and the water begins to flow to the working arc gate chamber 6. Since the accident eccentric hemispherical valve 2 is closed, the water supply pipe 1 draws water from the permanent operation water intake 12 at this time. When the working arc gate chamber 6 is filled with water, the working valve 3 is opened to realize ecological water supply during the permanent operation period.

[0029] The above embodiment is only a preferred technical solution of the present invention. Those skilled in the art should understand that the technical solutions or parameters in the embodiments can be modified or replaced without departing from the principle and essence of the present invention, and all should be included in the protection scope of the present invention.

Claims

1. An ecological water replenishment structure that replenishes water during both the reconstruction period and the operation period, characterized by: A water supply pipe (1) is buried in the wall of the tunnel, and the water intake of the water supply pipe (1) is respectively provided with an initial water storage reconstruction period water intake (11) and a permanent operation water intake (12) on the upstream and downstream sides of the accident gate well (5), and the initial water storage reconstruction period water intake (11) is in an independently operated open state during the reconstruction period and the permanent operation water intake (12) is in an independently operated open state during the operation period; The water outlet (13) of the water supply pipe (1) is arranged downstream of the arc gate of the working arc gate chamber (6), and the water supply pipe (1) is provided with a working valve (3) on the pipe section opposite to the water outlet (13).

2. The ecological water replenishment structure according to claim 1, which has the function of replenishing water during both the reconstruction period and the operation period, is characterized in that: The water supply pipe (1) is provided with an emergency eccentric semi-ball valve (2) on the pipe section between the water intake (11) during the initial water storage and reconstruction period and the permanent operation water intake (12) to adjust the connection or closing between the water intake (11) during the initial water storage and reconstruction period and the water supply pipe (1).

3. The ecological water replenishment structure according to claim 2, which has the function of replenishing water during both the reconstruction period and the operation period, is characterized in that: An adjusting channel (7) cooperating with an emergency eccentric hemispherical valve (2) is arranged in the tunnel, a rotating operating rod (21) located in the adjusting channel (7) is arranged on the emergency eccentric hemispherical valve (2), and an operating panel (22) is arranged on the rotating operating rod (21) opposite to the inner cavity of the tunnel.

4. The ecological water replenishment structure according to claim 1, which has the function of replenishing water during both the reconstruction period and the operation period, is characterized in that: A maintenance gate valve (121) is provided on the pipe section of the permanent operation water intake (12) to adjust the connection or closing between the permanent operation water intake (12) and the water supply pipe (1).

5. The ecological water replenishment structure according to claim 1, which has the function of replenishing water during both the reconstruction period and the operation period, is characterized in that: The distance between the initial water storage reconstruction period water intake (11) and the accident gate well (5) is not less than 1 m, and the distance between the permanent operation water intake (12) and the accident gate well (5) is not less than 2 m.

6. The ecological water replenishment structure according to claim 1, which can replenish water during both the reconstruction period and the operation period, is characterized by: The water supply pipe (1) is provided with an emergency valve (4) on the pipe section upstream of the working valve (3).

7. The ecological water replenishment structure according to claim 6, which can replenish water during both the reconstruction period and the operation period, is characterized by: The emergency valve (4) and the working valve (3) are installed on a pipe section of the water supply pipe (1) in the area of ​​the working arc gate chamber (6).