Concrete pile foundation bearing capacity testing structure

By designing a combination of hydraulic jack assembly and expansion rod in the concrete pile foundation bearing capacity test structure, the problem of inconvenient pressure application in the existing testing mechanism is solved, and more flexible and efficient testing operations are achieved.

CN222044302UActive Publication Date: 2024-11-22GUNDAM CONSTR MANAGEMENT DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420673660.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-03
Publication Date
2024-11-22
Estimated Expiration
2034-04-03

AI Technical Summary

Technical Problem

The existing concrete pile foundation bearing capacity testing mechanism is not convenient for auxiliary expansion and pressure application as needed, which affects the flexibility and efficiency of testing operations.

Method used

A structure including hydraulic jack assembly, upper pressure frame, expansion rod, boom, counterweight hoist, pressure gauge and support base plate is designed. Through the combination of expansion rod and boom, pressure is facilitated and applied through auxiliary rod and auxiliary rod and The design of the inner support plate is convenient for the support assembly and use of hydraulic jack components.

Benefits of technology

It realizes convenient and easy to conduct auxiliary pressure application and fine-tuning tests as needed, improves the operational convenience and practicality of concrete pile foundation bearing capacity testing, and enhances the flexibility and efficiency of testing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222044302U_ABST
    Figure CN222044302U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of bearing capacity testing, in particular to a concrete pile foundation bearing capacity testing structure which comprises a hydraulic jack assembly, an upper pressing frame is assembled on the top of the hydraulic jack assembly, an expansion rod is assembled in the side end of the upper pressing frame in an inserted mode, and a hanging rod is assembled on the lower portion of the outer end of the expansion rod in an inserted mode. A counterweight hoisting hopper is hoisted at the bottom of the hoisting rod, a pressure gauge is assembled at the bottom of the hydraulic jack assembly, and a supporting bottom plate is assembled at the bottom of the pressure gauge. According to the utility model, auxiliary expansion pressure application can be conveniently carried out according to requirements, fine adjustment use test can be conveniently carried out according to concrete pile foundation test requirements, and the operation is more convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bearing capacity testing, in particular to a concrete pile foundation bearing capacity testing structure. Background Art

[0002] With the widespread application of concrete, concrete pouring is usually used in pile foundation construction. After pouring and forming, it is necessary to conduct a bearing capacity test on it in order to understand its bearing capacity and facilitate subsequent safe and stable use;

[0003] In this regard, China's patent application number: CN202122639105.X discloses a reinforced concrete pile foundation bearing capacity test structure, in which two rows of anchor rods are vertically arranged at the tops of two reinforced concrete piles, and a load-bearing pile is arranged between the two reinforced concrete piles; a truss beam is set up between the tops of the two reinforced concrete piles, and a shoulder beam is set up at both ends of the upper chord of the truss beam, and the upper ends of the two rows of anchor rods vertically penetrate the shoulder beam and are anchored to the top surface of the shoulder beam; two jacks are arranged at the top of the load-bearing pile, and the upper ends of the jacks are pressed against the lower chord of the truss beam;

[0004] However, the existing bearing capacity testing institutions are not convenient to carry out auxiliary expansion and pressure application as needed, which affects the needs of test operations;

[0005] Therefore, in order to solve the above problems, a concrete pile foundation bearing capacity test structure is proposed. Utility Model Content

[0006] The utility model aims to provide a concrete pile foundation bearing capacity testing structure to solve the problem in the above-mentioned background technology that the existing bearing capacity testing mechanism is inconvenient to perform auxiliary expansion and pressure application as needed, thus affecting the test operation needs.

[0007] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a concrete pile foundation bearing capacity testing structure, including a hydraulic jack assembly, wherein an upper pressure frame is installed on the top of the hydraulic jack assembly, an expansion rod is inserted and installed inside the side end of the upper pressure frame, a suspension rod is inserted and installed at the lower part of the outer end of the expansion rod, a counterweight bucket is installed at the bottom of the suspension rod, a pressure gauge is installed at the bottom of the hydraulic jack assembly, and a supporting base plate is installed at the bottom of the pressure gauge.

[0008] Preferably, auxiliary rods are installed at the corners around the supporting base plate, and an inner support plate is sleeved on the upper part of the auxiliary rod, and the side edge of the inner support plate is welded to the outer wall of the central side of the upper pressure frame.

[0009] Preferably, a pressure-bearing bottom plate is filled and supported between the hydraulic jack assembly and the pressure gauge, and a pressure-bearing top plate is filled and supported between the top of the hydraulic jack assembly and the center bottom of the upper pressure frame.

[0010] Preferably, the upper pressure frame is in a cross shape, the four groups of expansion rods are respectively inserted into the sides of the upper pressure frame, and the upper and lower ends of the suspension rods are assembled and fastened by fastening nuts and threaded sleeves.

[0011] Preferably, an auxiliary cross piece is arranged above the expansion rod, the auxiliary cross piece is arranged parallel to the counterweight bucket, and three groups of suspension rods are inserted through the counterweight bucket and the auxiliary cross piece, and a bucket inner cavity is opened inside the counterweight bucket.

[0012] Preferably, a hanging nut is threadedly sleeved on the upper end of the auxiliary rod, and a hanging thread corresponding to the hanging nut is opened on the upper end of the auxiliary rod.

[0013] Preferably, an assembly through hole corresponding to the auxiliary rod is opened inside the inner support plate, and the inner wall of the assembly through hole is arranged in an arc shape.

[0014] Compared with the prior art, the utility model has the following beneficial effects: the utility model facilitates auxiliary expansion and pressure application according to needs, facilitates fine-tuning and use testing according to the needs of concrete pile foundation testing, and makes the operation more convenient;

[0015] The utility model is provided with an upper pressure frame and an expansion rod, which is convenient for expanding the upper pressure frame, and then hoisting through the suspension rod and the counterweight bucket is convenient for counterweight testing, making the operation more convenient and efficient, and facilitating the bearing pressure test. Through this design, the convenience and practicality of the concrete pile foundation bearing capacity test structure are improved.

[0016] The utility model is provided with a pressure gauge and a supporting bottom plate, which facilitates the support and assembly of the bottom of the hydraulic jack assembly under the assembly of the auxiliary rod, and facilitates the subsequent support bearing pressure test of the hydraulic jack assembly. Through this design, the convenience and practicality of the concrete pile foundation bearing capacity test structure are improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of a front cross-section of the structure of the utility model;

[0018] Figure 2 It is a schematic top view of the structure of the utility model;

[0019] Figure 3 It is a top view cross-sectional schematic diagram of the local structure of the support base plate of the utility model;

[0020] Figure 4 For this utility model Figure 1 A schematic diagram of the structure enlargement in the middle;

[0021] Figure 5 For this utility model Figure 1 A magnified schematic diagram of the structure at B in the middle;

[0022] In the figure: 100, hydraulic jack assembly; 200, upper pressure frame; 210, expansion rod; 220, suspension rod; 221, fastening nut; 222, auxiliary cross piece; 230, counterweight bucket; 231, bucket inner cavity; 300, pressure gauge; 301, pressure bottom plate; 302, pressure top plate; 310, support bottom plate; 320, auxiliary rod; 321, lifting nut; 322, lifting thread; 330, inner support plate; 331, assembly through hole. DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0024] See also Figure 1-5 , an embodiment provided by the utility model:

[0025] A concrete pile foundation bearing capacity test structure includes a hydraulic jack assembly 100, an upper pressure frame 200 is installed on the top of the hydraulic jack assembly 100, an expansion rod 210 is inserted and installed inside the side end of the upper pressure frame 200, a suspension rod 220 is inserted and installed at the lower part of the outer end of the expansion rod 210, a counterweight bucket 230 is suspended at the bottom of the suspension rod 220, a pressure gauge 300 is installed at the bottom of the hydraulic jack assembly 100, and a supporting bottom plate 310 is installed at the bottom of the pressure gauge 300;

[0026] Furthermore, auxiliary rods 320 are installed at the corners around the supporting base plate 310, and an inner support plate 330 is sleeved on the upper part of the auxiliary rod 320. The side of the inner support plate 330 is welded to the outer wall of the center side of the upper pressure frame 200. Through this design, it is convenient to assist in lifting it, and it is convenient for the upper pressure frame 200 to assist in lifting the hydraulic jack assembly 100, which is convenient for subsequent use and testing;

[0027] Furthermore, a pressure-bearing bottom plate 301 is filled and supported between the hydraulic jack assembly 100 and the pressure gauge 300, and a pressure-bearing top plate 302 is filled and supported between the top of the hydraulic jack assembly 100 and the center bottom of the upper pressure frame 200. Through this design, it is convenient to support the hydraulic jack assembly 100 and the pressure gauge 300 and the upper pressure frame 200, so that it is not easy to be damaged in subsequent use;

[0028] Furthermore, the upper press frame 200 is in a cross shape, and the four groups of expansion rods 210 are respectively inserted on the sides of the upper press frame 200, and the upper and lower ends of the suspension rod 220 are assembled and fastened by threaded sleeves of fastening nuts 221. Through this design, it is easy to assemble the upper press frame 200, making it more convenient to use;

[0029] Furthermore, an auxiliary transverse piece 222 is arranged above the expansion rod 210, and the auxiliary transverse piece 222 is arranged parallel to the counterweight bucket 230, and three groups of suspension rods 220 are inserted through the counterweight bucket 230 and the auxiliary transverse piece 222, and a bucket inner cavity 231 is opened inside the counterweight bucket 230. Through this design, it is easy to stably hoist and assemble the counterweight bucket 230, making it more convenient to use;

[0030] Furthermore, a lifting nut 321 is threadedly sleeved on the upper end of the auxiliary rod 320, and a lifting thread 322 corresponding to the lifting nut 321 is opened on the upper end of the auxiliary rod 320. This design facilitates the assembly and fastening of the auxiliary rod 320, and facilitates the lifting and use of the auxiliary rod 320;

[0031] Furthermore, an assembly through hole 331 corresponding to the auxiliary rod 320 is opened inside the inner support plate 330, and the inner wall of the assembly through hole 331 is arranged in an arc shape. Through this design, the auxiliary assembly of the auxiliary rod 320 and the subsequent stable use are facilitated.

[0032] Working principle: During assembly and use, by taking the upper pressure frame 200, it is convenient to drive the support base plate 310 to support and assemble the pressure gauge 300 and the hydraulic jack assembly 100 with the cooperation of the inner support plate 330 and the auxiliary rod 320, and then place the support base plate 310 above the concrete pile foundation, and then unscrew the lifting nut 321 to facilitate the release of the limit of the auxiliary rod 320 and the inner support plate 330, making subsequent operations more convenient and not interfering with subsequent tests. According to test needs and the space near the test pile foundation, the side of the upper pressure frame 200 is expanded by pulling the expansion rod 210, which is convenient for subsequent counterweight assembly through the counterweight bucket 230, and convenient for assembly or fixed assembly around it according to needs, and convenient for subsequent testing by applying pressure through the lifting and lowering of the hydraulic jack assembly 100, making the test operation more convenient, and the operation ends here.

[0033] The above description is only a preferred embodiment of the utility model and does not limit the utility model in any form. Any ordinary technician in the industry can smoothly implement the utility model as shown in the drawings of the specification and described above. However, any equivalent changes, modifications and evolutions made by technicians familiar with the profession without departing from the scope of the technical solution of the utility model using the technical content disclosed above are all equivalent embodiments of the utility model. At the same time, any equivalent changes, modifications and evolutions made to the above embodiments based on the essential technology of the utility model are still within the protection scope of the technical solution of the utility model.

Claims

1. A concrete pile foundation bearing capacity testing structure, comprising a hydraulic jack assembly (100), Features: The top of the hydraulic jack assembly (100) is equipped with an upper pressure frame (200), the side end of the upper pressure frame (200) is internally inserted with an expansion rod (210), the lower part of the outer end of the expansion rod (210) is inserted with a suspension rod (220), the bottom of the suspension rod (220) is suspended with a counterweight bucket (230), the bottom of the hydraulic jack assembly (100) is equipped with a pressure gauge (300), and the bottom of the pressure gauge (300) is equipped with a supporting base plate (310).

2. A concrete pile foundation bearing capacity test structure according to claim 1, Features: Auxiliary rods (320) are installed at the corners around the supporting bottom plate (310), and an inner support plate (330) is sleeved on the upper part of the auxiliary rod (320). The side of the inner support plate (330) is welded to the outer wall of the central side of the upper pressing frame (200).

3. A concrete pile foundation bearing capacity testing structure according to claim 1, Features: A pressure-bearing bottom plate (301) is filled and supported between the hydraulic jack assembly (100) and the pressure gauge (300), and a pressure-bearing top plate (302) is filled and supported between the top of the hydraulic jack assembly (100) and the center bottom of the upper pressure frame (200).

4. A concrete pile foundation bearing capacity testing structure according to claim 1, Features: The upper pressing frame (200) is in a cross shape, and the four groups of expansion rods (210) are respectively inserted into the sides of the upper pressing frame (200), and the upper and lower ends of the suspension rod (220) are assembled and fastened by threaded sleeves of fastening nuts (221).

5. A concrete pile foundation bearing capacity testing structure according to claim 1, Features: An auxiliary transverse piece (222) is arranged above the expansion rod (210), and the auxiliary transverse piece (222) is arranged in parallel above the counterweight bucket (230). Three groups of suspension rods (220) are inserted through the counterweight bucket (230) and the auxiliary transverse piece (222), and a bucket inner cavity (231) is provided inside the counterweight bucket (230).

6. A concrete pile foundation bearing capacity testing structure according to claim 2, Features: A hanging nut (321) is threadedly sleeved on the upper end of the auxiliary rod (320), and a hanging thread (322) corresponding to the hanging nut (321) is formed on the upper end of the auxiliary rod (320).

7. A concrete pile foundation bearing capacity testing structure according to claim 2, Features: An assembly through hole (331) corresponding to the auxiliary rod (320) is provided inside the inner support plate (330), and the inner wall of the assembly through hole (331) is arranged in an arc shape.