Building construction blocking net

By designing a retractable combination structure of channel steel and crossbars, the problem of the large space occupied by the barrier net during transportation is solved, and it provides effective cushioning protection when impacted by falling objects.

CN222045160UInactive Publication Date: 2024-11-22HEBEI DACHENG ARCHITECTURAL DESIGN CONSULTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420687948.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-03
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing construction site fencing takes up a lot of space during transportation, and objects can easily fall through the edges. It also lacks storage functionality.

Method used

A construction barrier structure was designed, comprising channel steel, crossbars, collars, vertical pipes, pin holes, pin rods, and springs. The combination of collars and pin holes enables the deployment and retraction of the barrier, while the springs provide cushioning protection.

Benefits of technology

It enables convenient storage and transportation of the netting, and provides effective cushioning protection when impacted by falling objects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222045160U_ABST
    Figure CN222045160U_ABST
Patent Text Reader

Abstract

The utility model relates to a building construction blocking net which comprises two pieces of channel steel which are parallel to each other and horizontally arranged, two transverse rods and a blocking net body arranged between the two transverse rods. One end of the channel steel is welded with the mounting plate; lantern rings are arranged at the two ends of the cross rod, and the two lantern rings of the cross rod are located in grooves of the two pieces of channel steel correspondingly; vertical through pin holes are formed in the two ends of the channel steel, and a vertical pipe is arranged in the lantern ring in a sleeved mode and can slide in the channel steel. The building construction blocking net provided by the utility model can be stored, is convenient to transport, and is convenient and simple to unfold and store.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a building construction blocking net. Background Art

[0002] During construction, in order to prevent falling objects from high altitude from threatening workers and equipment on the ground, a barrier is generally set up horizontally on the building facade.

[0003] For example, the utility model patent with application number 202322348963.8 discloses a construction engineering building net, which is a rectangular frame surrounded by two brackets, a reel and a column, in which a blocking net is arranged. When catching falling objects, the reel can move to provide a buffer for the blocking net when catching falling objects, thereby reducing the loss of the blocking net. However, the device does not have a storage function, and will take up a large space during transportation. In addition, the blocking net is close to the edge of the two brackets, which makes it easy for fallen objects to leak. Utility Model Content

[0004] In order to solve the problems existing in the above technology, a construction fence is provided, comprising two parallel and horizontally arranged channel steels with notches arranged opposite to each other, and two cross bars, and a fence is arranged between the two cross bars;

[0005] A mounting plate is welded to one end of the channel steel, and a sealing plate is welded to the other end of the channel steel;

[0006] Rings are provided at both ends of the cross bar, and the two rings of the cross bar are respectively located in the grooves of the two channel steels;

[0007] Both ends of the channel steel are provided with vertically penetrating pin holes, a vertical pipe is sleeved in the sleeve ring, and the vertical pipe can slide in the channel steel.

[0008] Wherein, the two channel steels are respectively the first channel steel and the second channel steel;

[0009] A second spring is arranged on the vertical pipe located in the first channel steel and close to the sealing plate, and one end of the second spring away from the vertical pipe is connected to the sealing plate of the first channel steel;

[0010] The pin hole of the second channel steel close to the sealing plate is a strip hole, and both ends of the pin rod in the strip hole pass through the second channel steel;

[0011] A first spring is detachably provided at both ends of the pin rod, and an end of the first spring away from the pin rod is connected to an end of the second channel steel close to the sealing plate.

[0012] Wherein, both ends of the pin rod are provided with hanging rings, and the first spring is provided with a hook.

[0013] Wherein, a door-shaped frame is arranged on one of the sealing plates, and two ends of the door-shaped frame are pivotally connected to the middle part of the top surface and the middle part of the bottom surface of the sealing plate respectively.

[0014] Wherein, strip plates are arranged on the tops of the opposite surfaces of the two channel steels, the strip plates are connected to the channel steels through elastic hinges, and one end of the strip plates away from the channel steels is inclined downward.

[0015] The beneficial effects of the utility model are as follows: the construction barrier provided by the utility model can be stored, is convenient for transportation, and the unfolding and storing operations are convenient and simple. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The utility model is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0017] Figure 1 It is the front view of the utility model;

[0018] Figure 2 This utility model Figure 1 A magnified view of part A;

[0019] Figure 3 It is a schematic diagram of the structure inside the channel of the sealing plate end of the channel steel of the utility model;

[0020] Figure 4 It is a schematic diagram of the structure in the groove of the mounting plate end of the channel steel of the utility model;

[0021] Figure 5 It is a schematic diagram of the storage state of the utility model;

[0022] Figure 6 It is a schematic diagram of another embodiment of the utility model.

[0023] Description of Reference Numerals

[0024] 1. First channel steel, 11. Notch, 12. Strip plate, 13. Elastic hinge, 2. Second channel steel, 21. Strip hole, 3. Mounting plate, 4. Closing plate, 41. Door frame, 42. Vertical plate, 43. First spring, 5. Pin hole, 6. Cross bar, 61. Ring, 7. Vertical pipe, 8. Second spring, 9. Pin rod, 91. Hanging ring, 10. Blocking net. DETAILED DESCRIPTION

[0025] The following is a clear and complete description of the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings in the embodiments of the present invention. In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention can also be implemented in other ways different from those described herein, and those skilled in the art can make similar generalizations without violating the connotation of the present invention, so the present invention is not limited by the specific embodiments disclosed below.

[0026] like Figures 1 to 4 As shown in the figure, a construction fence provided by the embodiment comprises two parallel and horizontally arranged channel steels with notches 11 arranged opposite to each other, and two cross bars 6, a fence 10 is arranged between the two cross bars 6, and in the use state, as shown in FIG. Figure 1 As shown, two channel steels and two cross bars 6 form a rectangular structure;

[0027] A mounting plate 3 is welded to one end of the channel steel to fix it to the building facade, and a sealing plate 4 is welded to the other end of the channel steel;

[0028] Rings 61 are provided at both ends of the crossbar 6, and the two rings 61 of the crossbar 6 are respectively located in the grooves of the two channel steels;

[0029] Vertically penetrating pin holes 5 are provided at both ends of the channel steel, and a vertical pipe 7 is sleeved in the collar 61. The vertical pipe 7 can slide in the channel steel. Specifically, the height of the vertical pipe 7 is equal to or slightly smaller than the height of the channel steel groove, and its outer diameter is slightly smaller than the width of the channel steel groove, while the outer diameter of the sleeve 61 is equal to the width of the channel steel groove.

[0030] The two channel steels are the first channel steel 1 and the second channel steel 2;

[0031] The sleeves 61 are all located in the middle of the vertical pipe 61, and a second spring 8 is respectively arranged at the upper and lower parts of the side wall of the vertical pipe 61 located in the first channel steel 1 near the sealing plate 4, and one end of the second spring 8 away from the vertical pipe 7 is fixedly connected to the sealing plate 4 of the first channel steel 1;

[0032] The pin hole of the second channel steel 2 close to the sealing plate 4 is a strip hole 21, and both ends of the pin rod 9 in the strip hole 21 pass through the second channel steel 2;

[0033] Both ends of the pin rod 9 are welded with hanging rings 91, and the top and bottom of the second channel steel 2 close to the corresponding sealing plate 4 are welded with vertical vertical plates 42, and a first spring 43 is arranged on the vertical plate 42. A hook (not shown) is arranged at the end of the first spring 43 away from the vertical plate 42, and the hook is detachably connected to the hanging ring 91;

[0034] A door-shaped frame 41 is provided on the sealing plate 4 of the second channel steel 2 , and two ends of the door-shaped frame 41 are pivotally connected to the middle of the top surface and the middle of the bottom surface of the sealing plate 4 respectively.

[0035] When used in this application, its form is as follows Figure 1 As shown, pins are arranged in the two pin holes 5 at the upper left and lower left positions to fix the two ends of the cross bar 6 at the left side, and no pin is arranged inside the pin hole 5 at the upper right position, and the hooks of the two first springs 43 are connected to the two ends of the pin rod 9;

[0036] At this time, when a falling object falls on the blocking net 10, due to the elastic force of the first spring 43 and the second spring 8, the blocking net 10 is stressed. Figure 1 The cross bar 6 on the right side can move to the left to cushion and protect the blocking net 10, and then the spring rebounds to return the cross bar 6 to its original position.

[0037] When you need to put away the device, Figure 5 As shown, the hook of the first spring 43 is removed from the pin rod 8, and the pin rod 5 is taken out from the strip hole 21, and a pin is inserted into the upper left pin hole 5 to fix it. No pin is set in the lower left pin hole 5, and a pin is inserted into the lower right pin hole 5 to fix it. The two channel steels are brought close to each other, and then the door frame 41 is rotated to the right to cover the top of the second channel steel 2, and the storage of the device is completed. After storage, the blocking net 10 can be wrapped around the two channel steels, or the blocking net 10 can be folded and stored in any way.

[0038] like Figure 1 As shown, since the barrier 10 is only connected to two cross bars 6 on both sides, if the falling object falls on Figure 1 If the falling object is at the point D in the figure, the falling object may slide to the outside of the barrier 10. Therefore, in another embodiment, Figure 6 As shown, a strip plate 12 is arranged on the top of the opposite surface of the two channel steels, and the strip plate 12 is connected to the channel steel by an elastic hinge 13. The end of the strip plate 12 away from the channel steel is tilted downward so that the landing point is Figure 1 The falling object at point D is guided to a position away from the edge of the barrier 10, and due to the elasticity of the elastic hinge 13, when the two channel steels are close to each other, the two strip plates 12 abut against each other and gradually change to a vertical state, which will not affect the storage of the device.

[0039] Obviously, the described embodiments are only some embodiments of the utility model, not all embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

Claims

1. A construction barrier, characterized in that: It comprises two parallel and horizontally arranged channel steels with notches opposite to each other, and two cross bars, and a blocking net is arranged between the two cross bars; A mounting plate is welded to one end of the channel steel, and a sealing plate is welded to the other end of the channel steel; Rings are provided at both ends of the cross bar, and the two rings of the cross bar are respectively located in the grooves of the two channel steels; Both ends of the channel steel are provided with vertically penetrating pin holes, a vertical pipe is sleeved in the sleeve ring, and the vertical pipe can slide in the channel steel.

2. A construction barrier according to claim 1, characterized in that: The two channel steels are respectively a first channel steel and a second channel steel; A second spring is arranged on the vertical pipe located in the first channel steel and close to the sealing plate, and one end of the second spring away from the vertical pipe is connected to the sealing plate of the first channel steel; The pin hole of the second channel steel close to the sealing plate is a strip hole, and both ends of the pin rod in the strip hole pass through the second channel steel; A first spring is detachably provided at both ends of the pin rod, and an end of the first spring away from the pin rod is connected to an end of the second channel steel close to the sealing plate.

3. A construction barrier according to claim 2, characterized in that: Both ends of the pin rod are provided with hanging rings, and the first spring is provided with a hook.

4. A construction barrier according to any one of claims 1 to 3, characterized in that: A door-shaped frame is arranged on one of the sealing plates, and two ends of the door-shaped frame are respectively pivotally connected to the middle part of the top surface and the middle part of the bottom surface of the sealing plate.

5. A construction barrier according to any one of claims 1 to 3, characterized in that: Strip plates are arranged on the tops of the opposite surfaces of the two channel steels. The strip plates are connected to the channel steels through elastic hinges, and one end of the strip plates away from the channel steels is inclined downward.