Liftable simple trolley for tunnel excavation

By designing a simple tunnel excavation truck that can be lifted and lowered, and using a height-adjustable structure and support system, the waste of materials and time caused by diversification of sections in the existing technology is solved, and the practicality and safety of construction are improved.

CN222045770UActive Publication Date: 2024-11-22SINOHYDRO BUREAU 6 CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323654265.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-31
Publication Date
2024-11-22
Estimated Expiration
2033-12-31

AI Technical Summary

Technical Problem

Due to the diversification of sections in existing concealed excavation projects, multiple excavation trolleys that meet different cross-sectional sizes are needed, resulting in waste of materials and waste of labor time.

Method used

A simple tunnel excavation trolley with liftable height adjustment is designed, and the supporting pipe and support plate are used to cooperate with the inner column of the outer pipe and the inner pipe of the movable pipe. , the coordination between the adjustment pipe and the adjustment plate meets the construction needs of different variable sections and large sections.

Benefits of technology

The height adjustment of the trolley body and the stability of the support platform are achieved, which meets different construction needs, improves the practicality and safety of construction, and reduces material waste and manual time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222045770U_ABST
    Figure CN222045770U_ABST
Patent Text Reader

Abstract

The utility model discloses a liftable simple trolley for tunnel excavation, which comprises a trolley main body, the trolley main body comprises a bottom longitudinal beam and upright post outer pipes, a plurality of first connecting beams are arranged between the upright post outer pipes on the same side, a plurality of second connecting beams are arranged between the upright post outer pipes on the two sides, and movable inner pipes are arranged in the upright post outer pipes in a sliding manner; a movable platform is arranged at the top of the movable inner pipe, the stand column outer pipe and the movable inner pipe are both provided with bolt holes and bolt steel bars, a lifting platform is arranged on the movable platform, a supporting platform is arranged on the stand column outer pipe, the supporting platform comprises a supporting pipe and a supporting plate, an adjusting pipe and an adjusting plate are arranged in the supporting pipe in a sliding mode, and a fastening bolt is arranged between the adjusting pipe and the supporting pipe. The trolley body is designed in a height-adjustable mode, the height of the trolley body is adjusted in the mode that the movable inner pipe is embedded in the stand column outer pipe, locking is conducted in the mode that the bolt holes and the bolt steel bars are used, and the practicability of the trolley body is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel construction, and more specifically, to a simple trolley for tunnel excavation which can be lifted and lowered. Background Art

[0002] With the vigorous promotion of urban modernization and the rapid development of rail transit, subway construction technology is also in a rapid development stage. When open-cut construction is adopted, it often causes serious interference to the surrounding ground commerce and transportation. Therefore, underground tunneling stations will gradually become the main direction of construction. The tunneling method is to dig holes underground without digging the ground. Mining method and shield method are both tunneling methods.

[0003] In the prior art, due to the diversity of the dark excavation cross-section during the dark excavation process, a dark excavation entrance and exit often have a variety of variable-section constructions, resulting in the processing of a variety of excavation trolleys that meet the cross-sectional dimensions, or multiple modifications to the trolleys, which not only wastes materials, but also consumes a lot of manpower and time. Utility Model Content

[0004] In view of the problems existing in the prior art, the utility model provides a simple trolley for tunnel excavation which can be raised and lowered to solve the technical problems mentioned in the background technology.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a simple trolley for tunnel excavation that can be raised and lowered, comprising a trolley body, the trolley body comprising a bottom longitudinal beam, two of the bottom longitudinal beams being symmetrically arranged, a plurality of column outer tubes being arranged on the bottom longitudinal beam, a plurality of first connecting beams being arranged between the column outer tubes on the same side, a plurality of second connecting beams being arranged between the column outer tubes on both sides, a movable inner tube being slidably arranged in the column outer tube, a movable platform being arranged on the top of the movable inner tube, pin holes and pin steel bars being arranged on the column outer tube and the movable inner tube, a lifting platform being arranged on the movable platform, a supporting platform being arranged on the column outer tube, the supporting platform comprising a supporting tube and a supporting plate, an adjusting tube and an adjusting plate being slidably arranged in the supporting tube, and a fastening bolt being arranged between the adjusting tube and the supporting tube.

[0006] The utility model is further configured such that a lifting and reinforcing beam is provided at the bottom of the second connecting beam to improve the integrity of the trolley body.

[0007] The utility model is further configured that the movable platform and the lifting platform are provided with scaffolding boards to facilitate construction by workers.

[0008] The utility model is further configured such that a first reinforcing beam is provided between the outer tube of the column and the first connecting beam, and a second reinforcing beam is provided between the outer tube of the column and the second connecting beam, thereby improving the integrity of the trolley body.

[0009] The utility model is further configured that the movable platform and the adjusting pipe are both provided with guardrails to improve construction safety.

[0010] The utility model is further configured that a support rod is provided between the support tube and the outer tube of the column to improve the stability of the support platform.

[0011] Compared with the prior art, the utility model has the following beneficial effects:

[0012] 1. The optimized trolley body is processed and manufactured on site. In order to ensure that the trolley body can meet the construction needs of both the step method and the full-section method, the trolley body is designed to be height-adjustable. The height of the trolley body is adjusted by nesting the movable inner tube in the outer tube of the column, and locked by means of pin holes and pin steel bars, which improves the practicality of the trolley body.

[0013] 2. Through the coordination of support pipes and support plates, and adjustment pipes and adjustment pipes, it can meet the construction of upper and lower steps with different variable cross-sections and large cross-sections, and is very convenient to transport and use.

[0014] 3. By setting up a lifting platform on the movable platform, the excavation needs of the triangular guide pits on the left and right sides of the station can be met. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is a schematic diagram of the overall structure of the trolley body of the utility model;

[0016] Figure 2 This is a schematic diagram of the matching structure of the trolley body and the lifting platform in the utility model;

[0017] Figure 3 It is a schematic diagram of the coordination structure of the bottom longitudinal beam, the column outer tube, the first connecting beam, the second connecting beam, the movable inner tube, the movable platform and the supporting platform in the utility model;

[0018] Figure 4 It is a schematic diagram of the matching structure of the support tube, the support plate, the adjustment tube, the adjustment plate and the fastening bolts in the utility model;

[0019] Figure 5 It is a schematic diagram of the matching structure of the outer tube of the central column, the movable inner tube, the latch hole and the latch steel bar of the utility model.

[0020] In the figure: 1. trolley body; 2. bottom longitudinal beam; 3. column outer tube; 4. first connecting beam; 5. second connecting beam; 6. movable inner tube; 7. movable platform; 8. latch hole; 9. latch steel bar; 10. lifting platform; 11. supporting platform; 12. supporting pipe; 13. supporting plate; 14. adjusting pipe; 15. adjusting plate; 16. fastening bolts; 17. lifting reinforcement beam; 18. scaffolding board; 19. first reinforcement beam; 20. second reinforcement beam; 21. guardrail; 22. support rod. DETAILED DESCRIPTION

[0021] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present utility model will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0022] It should be noted that, unless otherwise specified, all technical and scientific terms used in this application have the same meanings as commonly understood by ordinary technicians in the technical field to which this application belongs.

[0023] In the present invention, unless otherwise specified, directions such as "up" and "down" are usually used in reference to the directions shown in the drawings, or in reference to the vertical, perpendicular or gravity direction; similarly, for ease of understanding and description, "left" and "right" are usually used in reference to the left and right shown in the drawings; "inside" and "outside" refer to the inside and outside relative to the outline of each component itself, but the above-mentioned directions are not used to limit the present invention.

[0024] See also Figure 1-5 A simple trolley for tunnel excavation that can be lifted and lowered comprises a trolley body 1, the trolley body 1 comprises a bottom longitudinal beam 2, two bottom longitudinal beams 2 are symmetrically arranged, a plurality of column outer tubes 3 are arranged on the bottom longitudinal beam 2, a plurality of first connecting beams 4 are arranged between the column outer tubes 3 on the same side, a plurality of second connecting beams 5 are arranged between the column outer tubes 3 on both sides, a movable inner tube 6 is slidably arranged in the column outer tube 3, a movable platform 7 is arranged on the top of the movable inner tube 6, a latch hole 8 and a latch steel bar 9 are arranged on the column outer tube 3 and the movable inner tube 6, a lifting platform 10 is arranged on the movable platform 7, a support platform 11 is arranged on the column outer tube 3, and a support The platform 11 includes a support tube 12 and a support plate 13. An adjusting tube 14 and an adjusting plate 15 are slidably provided inside the support tube 12. A fastening bolt 16 is provided between the adjusting tube 14 and the support tube 12. A lifting reinforcement beam 17 is provided at the bottom of the second connecting beam 5. A scaffolding board 18 is provided on the movable platform 7 and the lifting platform 10. A first reinforcement beam 19 is provided between the outer tube 3 of the column and the first connecting beam 4. A second reinforcement beam 20 is provided between the outer tube 3 of the column and the second connecting beam 5. Guardrails 21 are provided on the movable platform 7 and the adjusting tube 14. A support rod 22 is provided between the support tube 12 and the outer tube 3 of the column.

[0025] In this embodiment, the column outer tube 3 adopts φ160 seamless tube, the movable inner tube 6 adopts φ144 seamless tube, the first connecting beam 4 adopts I16 I-steel, and the second connecting beam 5 adopts I18 I-steel. When assembling the trolley body 1, the column outer tube 3 is welded to the bottom longitudinal beam 2, the first connecting beam 4 is welded between the column outer tubes 3 on the through side, and the second connecting beam 5 is welded between the column outer tubes 3 on both sides. A first reinforcing beam 19 is arranged between the first connecting beam 4 and the column outer tube 3, and a second reinforcing beam 20 is arranged between the second connecting beam 5 and the column outer tube 3. Scaffolding boards 18 are laid on the movable platform 7 and the lifting platform 10, and guardrails 21 are arranged on the movable platform 7 and the adjusting pipe 14.

[0026] More specifically, when excavating the station and carrying out the top construction of the main tunnel of the station, in order to meet the construction needs of the step method and the full-section method, it is necessary to continuously adjust the height of the movable platform 7, move the protruding length of the movable inner tube 6 on the outer tube 3 of the column, align the pin hole 8, and fix the height of the movable plate through the pin steel bar 9, so as to adjust the height of the movable platform 7 for work, and at the same time move the adjustment tube 14 in the support tube 12, so as to drive the adjustment plate 15 to move, and through the cooperation of the support plate 13 and the adjustment plate 15, the support area of ​​the support platform 11 is increased to facilitate construction, and when it is necessary to excavate the triangular guide pits on both sides of the station, the movable platform 7 on the trolley body 1 is moved down, and the lifting platform 10 is installed on the movable platform 7 by welding or bolting, and then the guide pit construction is carried out.

[0027] When assembling the trolley body 1, the column outer tube 3 is welded to the bottom longitudinal beam 2, the first connecting beam 4 is welded between the column outer tubes 3 on the through side, the second connecting beam 5 is welded between the column outer tubes 3 on both sides, a first reinforcing beam 19 is arranged between the first connecting beam 4 and the column outer tube 3, a second reinforcing beam 20 is arranged between the second connecting beam 5 and the column outer tube 3, scaffolding boards 18 are laid on the movable platform 7 and the lifting platform 10, and guardrails 21 are arranged on the movable platform 7 and the adjustment pipe 14. When excavating the station, when the main tunnel of the station is top-lifted, in order to meet the construction needs of the step method and the full-section method, the movable platform needs to be continuously adjusted. 7, move the extended length of the movable inner tube 6 on the column outer tube 3, align the pin holes 8, and fix the height of the movable plate through the pin steel bar 9, thereby adjusting the height of the movable platform 7 for work, and at the same time move the adjusting tube 14 in the supporting tube 12, thereby driving the adjusting plate 15 to move, and through the cooperation of the supporting plate 13 and the adjusting plate 15, the supporting area of ​​the supporting platform 11 is increased, which is convenient for construction. When it is necessary to excavate the triangular guide pits on both sides of the station, the movable platform 7 on the trolley body 1 is moved down, and the lifting platform 10 is installed on the movable platform 7 by welding or bolting, and then the guide pit construction is carried out.

[0028] In all the schemes mentioned above, the connection between two parts can be selected according to actual conditions by welding, bolt and nut matching connection, bolt or screw connection or other well-known connection methods, which are not described here one by one. In the above, all fixed connections are preferably welded. Although the embodiments of the utility model have been shown and described, it can be understood by ordinary technicians in this field that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principle and spirit of the utility model. The scope of the utility model is defined by the attached claims and their equivalents.

Claims

1. A simple trolley for tunnel excavation that can be raised or lowered, comprising a trolley body (1), characterized in that: The trolley body (1) comprises a bottom longitudinal beam (2), two of which are symmetrically arranged, a plurality of column outer tubes (3) are arranged on the bottom longitudinal beam (2), a plurality of first connecting beams (4) are arranged between the column outer tubes (3) on the same side, a plurality of second connecting beams (5) are arranged between the column outer tubes (3) on both sides, a movable inner tube (6) is slidably arranged inside the column outer tube (3), a movable platform (7) is arranged on the top of the movable inner tube (6), and the column outer tube (3) is provided with a plurality of first connecting beams (4) and a plurality of second connecting beams (5) are arranged between the column outer tubes (3) on both sides. ) and the movable inner tube (6) are provided with a latch hole (8) and a latch steel bar (9), the movable platform (7) is provided with a lifting platform (10), the column outer tube (3) is provided with a support platform (11), the support platform (11) comprises a support tube (12) and a support plate (13), an adjustment tube (14) and an adjustment plate (15) are slidably provided in the support tube (12), and a fastening bolt (16) is provided between the adjustment tube (14) and the support tube (12).

2. The simple trolley for tunnel excavation that can be raised and lowered according to claim 1 is characterized in that: A lifting and reinforcing beam (17) is provided at the bottom of the second connecting beam (5).

3. The simple trolley for tunnel excavation that can be raised and lowered according to claim 1 is characterized in that: The movable platform (7) and the lifting platform (10) are provided with scaffolding boards (18).

4. The simple trolley for tunnel excavation that can be raised and lowered according to claim 1 is characterized in that: A first reinforcing beam (19) is provided between the column outer tube (3) and the first connecting beam (4), and a second reinforcing beam (20) is provided between the column outer tube (3) and the second connecting beam (5).

5. The simple trolley for tunnel excavation that can be raised and lowered according to claim 1 is characterized in that: The movable platform (7) and the regulating pipe (14) are both provided with protective railings (21).

6. The simple trolley for tunnel excavation that can be raised and lowered according to claim 1 is characterized in that: A support rod (22) is provided between the support tube (12) and the column outer tube (3).