Underground diaphragm wall leakage detection equipment
By designing mobile devices and connection devices, the adjustable speed reduction and convenient disassembly and assembly of underground continuous wall leakage detection equipment is achieved, solving the problem of the inability to reuse and poor detection effect of existing equipment, reducing construction costs and increasing Construction efficiency.
Patent Information
- Application Number
- CN202420726757.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-10
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-10
AI Technical Summary
The existing underground continuous wall leakage detection equipment cannot be reused, resulting in increased construction costs and poor inspection results, affecting the construction process.
A device including a mobile device, a connecting device and a detection device is designed to achieve an adjustable speed reduction of the detection device through a translation slide and a lift slide, ensuring comprehensive inspection, and being detachable and easy to recover.
Comprehensive leakage detection of underground continuous walls has been achieved, which reduces construction costs, shortens construction cycles, and improves inspection efficiency.
Smart Images

Figure CN222065600U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of subway construction, in particular to underground continuous wall leakage detection equipment. Background Art
[0002] During the construction of subway deep foundation pits, since the groundwater level is higher than the deep foundation pit, water seepage will occur on the side walls of the deep foundation pit. Therefore, after the water in the deep foundation pit is drained, an underground continuous wall needs to be installed on the inner wall. However, if the seepage of the underground continuous wall is not properly controlled during the construction of the deep foundation pit, it will not only cause the soil settlement around the foundation pit and the tilt of the building, but also cause safety hazards in the foundation pit construction. Therefore, underground continuous wall leakage detection is required.
[0003] There are generally two types of existing underground continuous wall leakage detection equipment. One is to install the detection equipment together with the continuous wall. If the continuous wall is not demolished in the end, it will cause waste of materials and increase construction costs. The other is to use a small crane or manually pull the rope to send the detection equipment to the deep foundation pit, slowly lower it, and inspect the continuous wall. However, this method cannot control the descent rate, resulting in missed detection. If the descent is controlled little by little, the construction period will be increased.
[0004] Therefore, how to provide an underground continuous wall leakage detection device to solve the problem that the existing technology is not applicable to various construction sites and affects the construction progress is a technical problem that needs to be urgently solved by technical personnel in this field. Utility Model Content
[0005] To this end, the utility model provides an underground continuous wall leakage detection device to solve the problems in the prior art of increased construction costs and longer construction periods due to the fact that the existing detection equipment cannot be reused and the detection effect is poor.
[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0007] The utility model discloses an underground continuous wall leakage detection device, comprising:
[0008] The mobile device is arranged in pairs, one part is placed above the foundation, and the other part is attached to the inner surface of the underground continuous wall;
[0009] A first connecting device, slidably connected above the right moving device;
[0010] A second connecting device is slidably connected above the left moving device, and the right side of the second connecting device is inserted into the left end of the first connecting device;
[0011] A detection device, installed above the first connecting device;
[0012] A deep foundation pit is opened in the foundation, a plurality of underground continuous walls are attached to the inner surface of the deep foundation pit, and the first connecting device, the second connecting device and the detection device are all placed above the deep foundation pit.
[0013] In a possible implementation, the mobile device includes:
[0014] A translation slide, the bottom of which is installed above the foundation, and one end of the translation slide is connected to a translation assembly;
[0015] A lifting slide has one side surface attached to the inner surface of the underground continuous wall, a lifting assembly is connected to the lower end of the lifting slide, and the upper end is connected to the other end of the translation slide.
[0016] In a possible implementation, the translation component includes:
[0017] A connecting block is installed on one side of the translation slideway, and a translation motor is installed inside the connecting block;
[0018] The translation rod has one end passing through the connection block and the other end connected with an electromagnet. The translation rod body is transmission-connected to the output end of the translation motor. The translation rod is arranged above the translation slideway.
[0019] In a possible implementation, the lifting assembly includes:
[0020] A lifting motor is installed below the lifting slideway;
[0021] A lead screw is transmission-connected to the output end of the lifting motor, and the lead screw is arranged on the inner side of the lifting slideway.
[0022] In a possible implementation, the first connecting device includes:
[0023] A slider, slidably connected in the moving device;
[0024] Sleeves are arranged in pairs on both sides of the slider, one end of the sleeve is provided with a socket, a second connecting device is inserted into the socket, and a slot is provided below the other end of the sleeve;
[0025] Detection device connecting columns are arranged in pairs on the upper side of one end of the sleeve;
[0026] A connecting hole is arranged on the sliding block.
[0027] In a possible implementation, the second connecting device includes:
[0028] A connecting plate, one end of which is provided with a shifting block, wherein a hole slot is provided in the shifting block;
[0029] Insert blocks are arranged in pairs and installed at the other end of the connecting plate. The insert blocks are inserted in the first connecting device.
[0030] In a possible implementation, the detection device includes:
[0031] A mounting block, mounted above the first connecting device, with a small hole in the middle of the mounting block and a driving motor disposed inside the mounting block;
[0032] A moving rod passes through the small hole, one end of the moving rod is connected to a rotating motor, the other end of the moving rod is connected to a mounting piece, and the moving rod is drivingly connected to an output end of the driving motor;
[0033] The detection probe is installed on the outer surface of the mounting piece.
[0034] The utility model places two mobile devices on the foundation, and then makes the other end of the mobile device stick to the inner surface of the underground continuous wall. At this time, the two connecting devices are respectively placed above the two mobile devices, and the two connecting devices are translated and connected together through the mobile devices. After the connection is completed, the two mobile devices are moved downward again at the same time. At this time, the detection device installed on the first connecting device performs leakage detection on the underground continuous wall. Because the movement speed of the detection device is adjustable and monitorable, the entire continuous wall can be detected. Not only is the detection more comprehensive, but the entire equipment can be disassembled and assembled for easy recycling, which reduces the construction cost and speeds up the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] In order to more clearly illustrate the implementation of the utility model or the technical solution in the prior art, the following is a brief introduction to the drawings required for the implementation or the prior art description. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.
[0036] The structures, proportions, sizes, etc. illustrated in this specification are only used to match the contents disclosed in the specification so as to facilitate understanding and reading by persons familiar with the technology. They are not used to limit the conditions under which the present invention can be implemented, and therefore have no substantial technical significance. Any structural modification, change in proportion or adjustment of size shall still fall within the scope of the technical contents disclosed in the present invention without affecting the effects and purposes that can be achieved by the present invention.
[0037] Figure 1 A three-dimensional diagram of the underground continuous wall leakage detection device provided by the utility model;
[0038] Figure 2 A three-dimensional diagram of the mobile device provided by the utility model;
[0039] Figure 3 A three-dimensional diagram of the translation assembly provided by the utility model;
[0040] Figure 4 A three-dimensional diagram of the lifting assembly provided by the utility model;
[0041] Figure 5 A three-dimensional diagram of a first connecting device provided by the utility model;
[0042] Figure 6 A three-dimensional diagram of a second connecting device provided by the utility model;
[0043] Figure 7 A three-dimensional diagram of the detection device provided by the utility model;
[0044] In the figure: 1 first connecting device; 11 detection device connecting column; 12 connecting hole; 13 sleeve; 14 slot; 15 slider; 2 moving device; 21 translation assembly; 211 connecting block; 212 translation rod; 213 electromagnet; 22 translation slide; 23 lifting assembly; 231 lead screw; 232 lifting motor; 24 lifting slide; 3 detection device; 31 rotating motor; 32 moving rod; 33 mounting piece; 34 detection probe; 35 mounting block; 4 second connecting device; 41 plug block; 42 connecting plate; 43 slot. DETAILED DESCRIPTION
[0045] The following is a specific embodiment of the present invention. People familiar with the technology can easily understand the other advantages and functions of the present invention from the contents disclosed in this specification. Obviously, the described embodiment is a part of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0046] Please refer to Figure 1-Figure 7 Now, an underground continuous wall leakage detection device disclosed in the utility model is described. The utility model is composed of four parts, such as Figure 1, including a first connecting device 1, a moving device 2, a detection device 3 and a second connecting device 4, the moving devices 2 are arranged in pairs, one part is placed above the foundation, and the other part is attached to the inner surface of the underground continuous wall, the first connecting device 1 is slidably connected above the right moving device 2, the second connecting device 4 is slidably connected above the left moving device 2, the right side of the second connecting device 4 is inserted inside the left end of the first connecting device 1, the detection device 3 is installed above the first connecting device 1, a deep foundation pit is opened in the foundation, and several underground continuous walls are attached to the inner surface of the deep foundation pit, and the first connecting device 1, the second connecting device 4 and the detection device 3 are all placed above the deep foundation pit. When the device is in use, the two moving devices 2 are placed above the foundation respectively, and then the other end of the moving device 2 is attached to the inner wall of the underground continuous wall. At this time, the two connecting devices installed on the moving device 2 will push the two connecting components together under the control of the moving device 2. When the two connecting devices are connected together, the moving device 2 starts to move downward, and the detection device 3 moves downward accordingly, so that the underground continuous wall can be leaked.
[0047] In a specific embodiment, Figure 2 The mobile device 2 includes a translation component 21, a translation slide 22, a lifting component 23 and a lifting slide 24. The bottom of the translation slide 22 is installed above the foundation. One end of the translation slide 22 is connected to the translation component 21. One side of the lifting slide 24 is attached to the inner surface of the underground continuous wall. The lower end of the lifting slide 24 is connected to the lifting component 23, and the upper end is connected to the other end of the translation slide 22. The mobile device 2 is divided into two parts, translation and lifting. Before use, two connecting devices are installed on the translation slide 22. The two connecting devices are connected together by the push of the translation component 21, and then move downward after becoming a whole, in order to prevent the use of one connecting device due to the detection device 3 being too heavy, which may cause derailment during descent.
[0048] Based on the previous embodiment, Figure 3 The translation assembly 21 includes a connection block 211, a translation rod 212 and an electromagnet 213. The connection block 211 is installed on one side of the translation slide 22. A translation motor is installed inside the connection block 211. One end of the translation rod 212 passes through the connection block 211, and the other end is connected to the electromagnet 213. The translation rod 212 is connected to the output end of the translation motor through transmission. The translation rod 212 is arranged above the translation slide 22. The translation motor pushes out the first connection device 1 with the translation rod 212. The electromagnet 213 is used to absorb the two connection devices. When the two connection devices are connected and arrive on the lifting slide 24, the electromagnet 213 gradually reduces the suction force by reducing the current, so that the two connected connection devices start to move downward. At the same time, the electromagnet 213 will also absorb it when the lifting assembly 23 pushes it up, and pull the two connection devices back to the translation slide 22.
[0049] Based on the previous embodiment, Figure 4 The lifting assembly 23 includes a lead screw 231 and a lifting motor 232. The lifting motor 232 is installed below the lifting slide 24. The lead screw 231 is connected to the output end of the lifting motor 232. The lead screw 231 is arranged inside the lifting slide 24. The lifting speed of the first connecting device 1 and the second connecting device 4 can be controlled by the lifting motor 232 and the lead screw 231, so that the detection device 3 can perform a comprehensive detection of the underground continuous wall.
[0050] In a specific embodiment, Figure 5 The first connection device 1 includes a detection device connection column 11, a connection hole 12, a sleeve 13, a slot 14 and a slider 15. The slider 15 is slidably connected to the mobile device 2. The sleeves 13 are arranged in pairs on both sides of the slider 15. A socket is arranged at one end of the sleeve 13, and the second connection device 4 is inserted in the socket. The slot 14 is arranged below the other end of the sleeve 13. The detection device connection columns 11 are arranged in pairs on the upper side of one end of the sleeve 13, and the connection hole 12 is opened on the slider 15. The entire first connection device 1 is displaced by the movement of the slider 15 on the lifting slide 24 and the translation slide 22. When the connection hole 12 is aligned with the lead screw 231, the first connection device 1 starts to move up and down. The slot 14 is designed to connect the first connection device 1 to the mobile device 2.
[0051] In a specific embodiment, Figure 6 The second connection device 4 includes an insert block 41, a connection plate 42 and a hole slot 43. A moving block is installed at one end of the connection plate 42, and a hole slot 43 is opened in the moving block. The insert blocks 41 are arranged in pairs and installed at the other end of the connection plate 42. The insert blocks 41 are inserted into the first connection device 1. The design of the socket and the socket 41 is to install the two connection devices together. At the same time, according to the different widths of the deep foundation pit, the installation distances of the two moving devices 2 are different. At this time, the insertion depths of the insert blocks 41 are different, so the device can adapt to most deep foundation pits. The effect of the hole slot 43 is the same as that of the connection hole 12, which is to lift the second connection device 4.
[0052] In a specific embodiment, Figure 7The detection device 3 includes a rotating motor 31, a moving rod 32, a mounting member 33, a detection probe 34 and a mounting block 35. The mounting block 35 is installed above the first connecting device 1. A small hole is opened in the middle of the mounting block 35. A driving motor is arranged inside the mounting block 35. The moving rod 32 passes through the small hole. One end of the moving rod 32 is connected to the rotating motor 31, and the other end is connected to the mounting member 33. The moving rod 32 is transmission-connected to the output end of the driving motor, and the detection probe 34 is installed on the outer surface of the mounting member 33. The rotating motor 31 is used in conjunction with the moving rod 32 to rotate the mounting member 33, and the rotation of the mounting member 33 drives the detection probe 34 to perform rotational scanning. In this way, this design can comprehensively scan deep foundation pits of all shapes, and the design of a detection probe 34 makes the entire detection device 3 more lightweight. For deep foundation pits of different depths, if the moving device 2 is not sufficient to drive the detection device 3 to the bottom, the driving motor will drive the moving rod 32 to move downward again to complete the scanning of all positions. At the same time, the driving motor is designed to control the height of the mounting member 33 to prevent it from wearing against the translation track 22.
[0053] Although the utility model has been described in detail above with general descriptions and specific embodiments, it is obvious to those skilled in the art that some modifications or improvements can be made to the utility model. Therefore, these modifications or improvements made without departing from the spirit of the utility model are within the scope of protection claimed by the utility model.
Claims
1. An underground continuous wall leakage detection device, characterized in that: include: The moving device (2) is arranged in pairs, one part is placed above the foundation, and the other part is attached to the inner surface of the underground continuous wall; A first connecting device (1) is slidably connected above the right moving device (2); A second connecting device (4) is slidably connected above the left moving device (2), and the right side of the second connecting device (4) is inserted into the left end of the first connecting device (1); A detection device (3) installed above the first connecting device (1); A deep foundation pit is opened in the foundation, a plurality of underground continuous walls are attached to the inner surface of the deep foundation pit, and the first connecting device (1), the second connecting device (4) and the detection device (3) are all placed above the deep foundation pit.
2. The underground continuous wall leakage detection device according to claim 1, characterized in that: The mobile device (2) comprises: A translation slideway (22), the bottom of which is installed above the foundation, and one end of the translation slideway (22) is connected to a translation assembly (21); A lifting slideway (24) has one side surface attached to the inner surface of the underground continuous wall. The lower end of the lifting slideway (24) is connected to a lifting assembly (23), and the upper end is connected to the other end of the translation slideway (22).
3. The underground continuous wall leakage detection device according to claim 2, characterized in that: The translation assembly (21) comprises: A connecting block (211) is installed on one side of the translation slideway (22), and a translation motor is installed inside the connecting block (211); A translation rod (212) has one end passing through the connection block (211) and the other end connected to an electromagnet (213). The translation rod (212) is transmission-connected to the output end of the translation motor. The translation rod (212) is arranged above the translation slideway (22).
4. The underground continuous wall leakage detection device according to claim 2, characterized in that: The lifting assembly (23) comprises: A lifting motor (232) is installed below the lifting slideway (24); A lead screw (231) is transmission-connected to the output end of the lifting motor (232), and the lead screw (231) is arranged on the inner side of the lifting slideway (24).
5. The underground continuous wall leakage detection device according to claim 1, characterized in that: The first connecting device (1) comprises: A slider (15) slidably connected in the moving device (2); Sleeves (13) are arranged in pairs on both sides of the slider (15); one end of the sleeve (13) is provided with a socket, in which a second connecting device (4) is inserted; and a slot (14) is provided below the other end of the sleeve (13); Detection device connecting columns (11) are arranged in pairs on the upper side of one end of the sleeve (13); The connecting hole (12) is formed on the sliding block (15).
6. The underground continuous wall leakage detection device according to claim 1, characterized in that: The second connecting device (4) comprises: A connecting plate (42) is provided with a shift block at one end, wherein a hole groove (43) is provided in the shift block; The insert blocks (41) are arranged in pairs and are installed at the other end of the connecting plate (42). The insert blocks (41) are inserted into the first connecting device (1).
7. The underground continuous wall leakage detection device according to claim 1, characterized in that: The detection device (3) comprises: A mounting block (35) is mounted above the first connecting device (1), a small hole is opened in the middle of the mounting block (35), and a driving motor is arranged inside the mounting block (35); A moving rod (32) passes through the small hole, one end of the moving rod (32) is connected to the rotating motor (31), and the other end is connected to the mounting member (33), and the moving rod (32) is drivingly connected to the output end of the driving motor; A detection probe (34) is mounted on the outer surface of the mounting member (33).