Pre-buried channel used in tunnel
By combining the arc-shaped channel with horizontal and vertical connecting rods and binding it in the steel cage, the problems of low installation efficiency and inconvenient demolding of the pre-embedded channel are solved, achieving high-strength and efficient installation.
Patent Information
- Application Number
- CN202323575238.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2033-12-27
AI Technical Summary
The existing pre-embedded channels are inefficient during installation and inconvenient for demolding, especially the need to remove them after the secondary lining template is fixed.
Two arc-shaped channels are connected by several horizontal and vertical connecting rods to form an integral structure, which is then fixed in the steel cage by wire binding, thus avoiding the fixing and demolding process of the secondary lining formwork.
It improves the structural strength and installation efficiency of the pre-embedded channels, simplifies the construction process, and avoids the problem of inconvenient demolding.
Smart Images

Figure CN222066766U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel construction, in particular to a pre-buried channel used in a tunnel. Background Art
[0002] The embedded channel is a component pre-installed in the tunnel structure. It is pre-lapped with the steel grid and poured with concrete during the structure casting. It is used for lap joints when building the upper structure to facilitate the installation and fixation of the foundation of external engineering equipment (emergency platform, power cable bracket, lighting contact network bracket, water supply and drainage pipeline, telephone box, fire pipe and other facilities). In order to meet the needs of structural strength, the embedded channel is mostly made of metal materials. The embedded channel includes anchor nails fixedly connected to the back side of the embedded channel, thereby realizing the installation of external engineering equipment. As an important component of the shield tunnel, the embedded channel requires accurate installation position and maintains the same curvature with the inner surface of the steel mold at the bottom of the tunnel during the casting process. That is, the embedded channel needs to be vertically and accurately installed on the inner wall of the shield tunnel before casting.
[0003] At present, when installing the embedded channel, a single channel is adopted and fixed with the second lining template, and then installed by the second lining trolley. The single channel form has the problem of low installation efficiency, and the embedded channel is installed after being fixed with the second lining at the end of the second shift, which causes many inconveniences during demoulding. Summary of the invention
[0004] The purpose of the utility model is to provide a pre-embedded channel for use in a tunnel in accordance with the above-mentioned deficiencies of the prior art. The pre-embedded channel connects two arc-shaped channels into a whole through a plurality of transverse connecting rods, thereby improving the structural strength of the pre-embedded channel and the corresponding installation efficiency. The arc-shaped channel is pre-embedded by connecting the arc-shaped channel with a steel cage through a vertical connecting rod, thereby avoiding the problem of concrete pouring and demoulding after fixing the second lining formwork.
[0005] The purpose of this utility model is achieved by the following technical solutions:
[0006] A pre-buried groove for use in a tunnel, characterized in that the pre-buried groove comprises two arc-shaped grooves, a plurality of transverse connecting rods and a plurality of vertical connecting rods, the two arc-shaped grooves are arranged in parallel, each of the transverse connecting rods is arranged at intervals between the two arc-shaped grooves and both ends are respectively fixedly connected to the arc-shaped grooves, each of the vertical connecting rods is distributed at intervals on the outer arc surface of the arc-shaped groove, one end of the vertical connecting rod is welded and fixed to the outer arc surface of the arc-shaped groove, and the other end extends into and is fixed in a steel cage on the rock surface in the tunnel.
[0007] The arc-shaped channel is a rectangular tube body and an opening slit is formed on the inner arc surface of the rectangular tube body.
[0008] The binding end of the vertical connecting rod has a boss extending to both sides so as to be fixedly connected with the steel cage through iron wire.
[0009] A plug-in box is welded on the outer arc surface of the arc-shaped groove, and the end of the transverse connecting rod is inserted into the plug-in box. Screw holes are opened on both sides of the plug-in box and nuts are screwed in to fix the inserted end of the transverse connecting rod.
[0010] The utility model has the advantages of high structural strength of the double-row embedded grooves, high installation efficiency and convenient assembly; by pre-embedding in the steel cage in advance and fixing by wire binding, the problem of inconvenience of demoulding after fixing the second lining formwork with the embedded grooves can be avoided. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a schematic diagram of the pre-buried channel in the utility model being installed on the top of the tunnel surrounding rock;
[0012] Figure 2 It is a three-dimensional view of the embedded channel in the utility model;
[0013] Figure 3 It is a schematic diagram of the embedded channel and the steel cage being tied together by wire in the utility model;
[0014] Figure 4 It is a schematic diagram of the connection between the transverse connecting rod and the plug-in box on the arc-shaped groove in the utility model. DETAILED DESCRIPTION
[0015] The features of the present invention and other related features are further described in detail below through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:
[0016] like Figure 1-4 , the marks in the figure are: embedded groove 1, horizontal connecting rod 2, vertical connecting rod 3, arc groove 4, steel cage 5, iron wire 6, plug-in box 7, nut 8.
[0017] Example: Figure 1 , 2 As shown in , 3 and 4, this embodiment specifically relates to a pre-buried channel for use in a tunnel. The pre-buried channel 1 is pre-buried and arranged at the top of the tunnel surrounding rock to facilitate the installation and fixation of the foundation of external engineering equipment (emergency platform, power cable bracket, lighting contact network bracket, water supply and drainage pipeline, telephone box, fire protection pipe and other facilities). The pre-buried channel 1 includes two arc-shaped channels 4, a plurality of transverse connecting rods 2 and a plurality of vertical connecting rods 3.
[0018] like Figure 1 , 2As shown in Figures 3 and 4, the two arc-shaped grooves 4 are arranged in parallel and spaced a certain distance apart from each other, and each transverse link 2 is spaced between the two arc-shaped grooves 4 and its two ends are fixedly connected to the arc-shaped grooves 4 respectively. The fixed connection here means: a plug-in box 7 is fixedly welded on the outer arc surface of the arc-shaped groove 4, the opening of the plug-in box 7 points to the end of the transverse link 2, the inner cavity size of the plug-in box 7 is slightly larger than the end size of the transverse link 2, the end of the transverse link 2 is inserted into the plug-in box 7, and screw holes are respectively opened on the two side surfaces of the plug-in box 7. After the end of the transverse link 2 is inserted into the plug-in box 7, the nut 8 is screwed into the screw hole to tighten the end of the transverse link 2 to form a limit.
[0019] like Figure 1 , 2 , 3, 4, the arcuate groove 4, the transverse connecting rod 2 and the vertical connecting rod 3 are all made of metal materials, which can provide sufficient structural strength for the subsequent installation of engineering equipment. The arcuate groove 4 is a rectangular tube body, and the rectangular tube body has a certain curvature to adapt to the curvature of the inner wall of the tunnel surrounding rock. An opening seam is provided on the inner arc surface of the rectangular tube body so that the subsequent engineering equipment can be installed and connected in the open cavity of the arcuate groove 4. Each vertical connecting rod 3 is vertically arranged on the outer arc surface of the arcuate groove 4. One end of the vertical connecting rod 3 is welded and fixed to the outer arc surface of the arcuate groove 4, and the other end is extended into the steel cage 5 on the rock surface in the tunnel during installation for fixed connection. The fixed connection adopted here refers to binding and fixing by iron wire 6. In order to facilitate the binding of the vertical connecting rod 3, a boss extending to both sides is provided at the end of the vertical connecting rod 3 to facilitate the binding between the iron wire 6 and the vertical connecting rod 3.
[0020] like Figure 3 As shown, in addition to the connection between the vertical connecting rod 3 and the steel cage 5, the transverse connecting rod 2 is also tied and fixed to the steel cage 5 with iron wire 7. By binding the embedded channel 1 to the steel cage 5 in advance, the secondary lining formwork can be directly set during the subsequent pouring without fixing the embedded channel 1 to the secondary lining formwork, thereby avoiding the inconvenience of subsequent demoulding.
[0021] The advantages of this embodiment are: the double-row embedded groove structure has high strength, high installation efficiency and convenient assembly; by pre-embedding in the steel cage in advance and fixing it with wire tying, the problem of inconvenience in demoulding after fixing the second lining formwork with the embedded groove can be avoided.
Claims
1. A pre-buried channel for a tunnel, characterized in that The embedded groove includes two arc-shaped grooves, a plurality of transverse connecting rods and a plurality of vertical connecting rods. The two arc-shaped grooves are arranged in parallel. Each of the transverse connecting rods is arranged between the two arc-shaped grooves at intervals and both ends are fixedly connected to the arc-shaped grooves respectively. Each of the vertical connecting rods is distributed on the outer arc surface of the arc-shaped groove at intervals. One end of the vertical connecting rod is welded and fixed to the outer arc surface of the arc-shaped groove, and the other end extends into and is fixed in the steel cage on the rock surface in the tunnel.
2. The embedded channel for use in a tunnel according to claim 1, characterized in that The arc-shaped channel is a rectangular tube body and an opening slit is formed on the inner arc surface of the rectangular tube body.
3. The embedded channel for use in a tunnel according to claim 1, characterized in that The binding end of the vertical connecting rod has a boss extending to both sides so as to be fixedly connected with the steel cage through iron wire.
4. The embedded channel for use in a tunnel according to claim 1, characterized in that A plug-in box is welded on the outer arc surface of the arc-shaped groove, and the end of the transverse connecting rod is inserted into the plug-in box. Screw holes are opened on both sides of the plug-in box and nuts are screwed in to fix the inserted end of the transverse connecting rod.