Boiler water cooling wall measuring hole unblocking device
By designing a boiler water-cooled wall test hole unclogging device that is easy to disassemble and replace, and using an electric cylinder to drive the unclogging head to move, the problem of the unclogging parts of the existing device being inconvenient to disassemble and replace is solved, thereby improving the unclogging efficiency and the service life of the device.
Patent Information
- Application Number
- CN202323372685.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-12
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2033-12-12
AI Technical Summary
The existing boiler water-cooled wall test hole unclogging device is not easy to disassemble and replace the unclogging parts, and it is prone to damage after long-term use, affecting the unclogging effect.
A boiler water-cooled wall test hole unclogging device was designed, comprising an electric cylinder, a connecting mechanism, a moving rod, a moving plate, a support plate, and a disassembly mechanism. The moving rod is driven by the electric cylinder to move the unclogging head. The unclogging head is designed to be detachable for easy replacement, and the combination of a limit ring and a fixing rod improves stability.
It enables convenient disassembly and replacement of the unblocking head, solves the problem of damage to the unblocking parts affecting the unblocking effect, and improves the service life and unblocking efficiency of the device.
Smart Images

Figure CN222068549U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of boiler coking and slagging prevention, in particular to a boiler water-cooled wall measuring hole clearing device. Background Art
[0002] The coking and slagging problem of power station boilers has always been an important issue that affects the normal and safe operation of boilers. Due to the heat absorption of the water-cooled wall, the temperature in the furnace tends to gradually decrease from the center of the flame to the water-cooled wall. As the temperature decreases, the ash in the fuel gradually changes from the liquid softening state at high temperature to a solid or semi-molten state. When the heated surface is cooled, it will adhere to the heated surface. At the same time, the volatile substances in the coal powder particles during combustion will gasify and enter the flue gas. When the heated surface is cooled, it will adhere to the heated surface flushed by the flue gas, or condense on the fly ash surface and then adhere to the heated surface, forming an initial sticky layer, providing conditions for the growth of the coke slag layer. The coking and slagging situation is related to many factors such as fuel composition, furnace operation status, etc. The commonly used means are purging, high-pressure water washing or manual dredging, but the steam soot blowing is relatively low in fullness, leaving some dead corners, and the manual slag cleaning efficiency is low.
[0003] The patent document with the announcement number: CN216606223U discloses "a boiler water-cooled wall measuring hole clearing device", which involves putting a clearing piece together with a sampling tube, so that the clearing does not affect the gas extraction; and because the clearing piece hits the obstruction from the inside of the measuring hole tube to clear the blockage, the influence on the sampling tube is minimal; when the sampling tube has a large air extraction resistance, the clearing piece is used to make a reciprocating motion to remove the obstruction on the measuring hole, dredge the measuring hole, and then extract gas for sampling.
[0004] Although the device clears the blockage and unclogs the side hole through a clearing piece, the clearing piece itself will be easily affected by long-term reciprocating work, resulting in damage. The device is not convenient for replacing the clearing piece, which can easily affect the subsequent use effect. Therefore, it is necessary to provide a boiler water-cooled wall measuring hole clearing device that is easy to disassemble the clearing piece. Utility Model Content
[0005] In order to solve the above technical problems, the utility model provides a boiler water-cooled wall measuring hole clearing device which is convenient for disassembling the clearing parts.
[0006] The utility model provides a boiler water-cooled wall measuring hole clearing device, a boiler water-cooled wall measuring hole clearing device, characterized in that it comprises an electric cylinder, a connecting mechanism is provided at the bottom of the electric cylinder, a moving rod is provided at the bottom of the connecting mechanism, a moving plate is provided at the bottom of the moving rod, a threaded block is threadedly connected to the inner cavity of the moving plate, a supporting plate is provided at the bottom of the threaded block, a disassembly mechanism is provided at the bottom of the supporting plate, and a sampling tube is provided at the outer side of the moving rod.
[0007] In order to achieve the effect of facilitating the connection between the mobile and electric cylinders, the utility model provides a boiler water-cooled wall measuring hole clearing device. Preferably, the connecting mechanism includes a first connecting plate, a second connecting plate is arranged below the first connecting plate, threaded rods are arranged in the inner cavities of the first connecting plate and the second connecting plate, nuts are threadedly connected to the outer sides of the threaded rods, the top of the first connecting plate is fixedly connected to the bottom of the electric cylinder, and the bottom of the second connecting plate is fixedly connected to the top of the mobile rod.
[0008] In order to achieve the purpose of replacing the clearing head, the utility model provides a boiler water-cooled wall measuring hole clearing device. Preferably, the disassembly mechanism includes a clearing head, the inner cavity of the support plate is equipped with a clearing head, the bottom of the support plate is fixedly connected with a support plate, and the inner cavity of the support plate is threadedly connected with a fixing rod.
[0009] In order to achieve the purpose of limiting the sampling tube, the utility model provides a boiler water-cooled wall measuring hole clearing device. Preferably, the outside of the moving rod and the outside of the moving plate are fixedly connected with a limiting ring, and the outer side of the sampling tube is slidably connected with the inner cavity of the limiting ring.
[0010] In order to improve the stability of the clearing head during use, the utility model provides a boiler water-cooled wall measuring hole clearing device. Preferably, the inner cavity of the movable plate is slidably connected to a limit rod, the bottom of the limit rod is snap-connected to a limit block, and the bottom of the limit block is fixedly connected to the top of the support plate.
[0011] In order to improve the stability of the moving rod, the utility model provides a boiler water-cooled wall measuring hole clearing device. Preferably, both sides of the moving rod are fixedly connected with fixed blocks, and the bottom of the fixed block is fixedly connected to the top of the moving plate.
[0012] Compared with the prior art, the beneficial effects of the utility model are:
[0013] When replacing a single clearing head, the fixing rods on both sides of the clearing head can be twisted out of the outer threaded grooves of the clearing head to release the fixation of the clearing head, making it convenient for staff to disassemble and replace the damaged clearing head. This solves the problem that the current boiler water-cooled wall measuring hole clearing device is inconvenient to disassemble and replace the clearing parts, and the clearing parts are easily damaged after long-term use, thus affecting the clearing effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 A schematic structural diagram of a preferred embodiment of a boiler water wall measuring hole clearing device provided by the utility model;
[0015] Figure 2 This is a structural cross-sectional view of the support plate of the utility model;
[0016] Figure 3 It is a structural cross-sectional view of the utility model at A;
[0017] Figure 4 It is a structural schematic diagram of the connection mechanism of the utility model.
[0018] Numbers in the figure: 1. electric cylinder; 2. connecting mechanism; 201. first connecting plate; 202. second connecting plate; 203. threaded rod; 204. nut; 3. moving rod; 4. moving plate; 5. threaded block; 6. support plate; 7. disassembly mechanism; 701. clearing plug; 702. support plate; 703. fixing rod; 8. limiting ring; 9. sampling tube; 10. limiting rod; 11. limiting block; 12. fixing block. DETAILED DESCRIPTION
[0019] The utility model is further described below in conjunction with the accompanying drawings and implementation modes.
[0020] Please refer to Figure 1 , Figure 2 , Figure 3 and Figure 4 ,in Figure 1 A schematic structural diagram of a preferred embodiment of a boiler water wall measuring hole clearing device provided by the utility model; Figure 2 This is a structural cross-sectional view of the support plate of the utility model; Figure 3 It is a structural cross-sectional view of the utility model at A; Figure 4 A boiler water wall measuring hole clearing device comprises an electric cylinder 1, a connecting mechanism 2 is arranged at the bottom of the electric cylinder 1, a moving rod 3 is arranged at the bottom of the connecting mechanism 2, a moving plate 4 is arranged at the bottom of the moving rod 3, a threaded block 5 is threadedly connected to the inner cavity of the moving plate 4, a supporting plate 6 is arranged at the bottom of the threaded block 5, a disassembly mechanism 7 is arranged at the bottom of the supporting plate 6, and a sampling tube 9 is arranged at the outer side of the moving rod 3.
[0021] In the specific implementation process, Figure 1 and Figure 4 As shown, the connecting mechanism 2 includes a first connecting plate 201, a second connecting plate 202 is arranged below the first connecting plate 201, a threaded rod 203 is arranged in the inner cavity of the first connecting plate 201, a nut 204 is threadedly connected to the outer side of the threaded rod 203, the top of the first connecting plate 201 is fixedly connected to the bottom of the electric cylinder 1, and the bottom of the second connecting plate 202 is fixedly connected to the top of the moving rod 3.
[0022] It should be noted that: the electric cylinder 1 is moved to the second connecting plate 202 through the first connecting plate 201, and then the threaded rod 203 is twisted into the inner cavity of the first connecting plate 201 and the second connecting plate 202, and the nut 204 is twisted into the outside of the threaded rod 203 to complete the connection between the electric cylinder 1 and the moving rod 3, so that the electric cylinder 1 can drive the moving rod 3 to move and drive the clearing head 701 to move.
[0023] like Figure 2 and Figure 3 As shown, the disassembly mechanism 7 includes a clearing head 701, the inner cavity of the support plate 6 is equipped with the clearing head 701, the bottom of the support plate 6 is fixedly connected to a support plate 702, and the inner cavity of the support plate 702 is threadedly connected to a fixing rod 703.
[0024] The outside of the moving rod 3 and the outside of the moving plate 4 are both fixedly connected with a limiting ring 8 , and the outside of the sampling tube 9 is slidably connected with the inner cavity of the limiting ring 8 .
[0025] The inner cavity of the moving plate 4 is slidably connected to a limiting rod 10 , the bottom of the limiting rod 10 is snap-connected to a limiting block 11 , and the bottom of the limiting block 11 is fixedly connected to the top of the supporting plate 6 .
[0026] Both sides of the moving rod 3 are fixedly connected with fixed blocks 12 , and the bottom of the fixed block 12 is fixedly connected to the top of the moving plate 4 .
[0027] It should be noted that: one end of the sampling tube 9 is passed through the interior of the limiting ring 8 in turn to limit the sampling tube 9, and the support plate 6 is moved to the bottom of the movable plate 4. By rotating the threaded block 5 on the top of the support plate 6, the threaded block 5 is driven to twist into the threaded groove at the bottom of the movable plate 4 for fixation, and then the limiting rod 10 is inserted through the movable plate 4 and then inserted into the top groove of the limiting block 11, thereby improving the connection stability between the movable plate 4 and the support plate 6, and the cleaning plug 701 is inserted into the installation groove at the bottom of the support plate 6, and then the fixing rod 703 is twisted into the inner cavity of the support plate 702, and then twisted into the threaded groove on the outside of the cleaning plug 701 to fix the cleaning plug 701. When a single cleaning plug 701 is replaced, the fixing rods 703 on both sides of the cleaning plug 701 can be twisted out of the threaded groove on the outside of the cleaning plug 701 to release the fixation of the cleaning plug 701, so that the staff can disassemble and replace the damaged cleaning plug 701.
[0028] The working principle of a boiler water wall measuring hole clearing device provided by the utility model is as follows:
[0029] When using the device, the electric cylinder 1 can be moved to the second connecting plate 202 through the first connecting plate 201, and then the threaded rod 203 is twisted into the inner cavity of the first connecting plate 201 and the second connecting plate 202, and then the nut 204 is twisted into the outside of the threaded rod 203 to complete the connection between the electric cylinder 1 and the moving rod 3, so that the electric cylinder 1 can drive the moving rod 3 to move and drive the clearing plug 701 to move, and move the support plate 6 to the bottom of the moving plate 4. By rotating the threaded block 5 on the top of the support plate 6, the threaded block 5 is driven to twist into the threaded groove at the bottom of the moving plate 4 for fixing, and the clearing plug 701 is inserted into the bottom of the support plate 6. The cleaning head 701 is fixed to the groove and then the fixing rod 703 is twisted into the inner cavity of the support plate 702, and then twisted into the threaded groove on the outside of the cleaning head 701 to fix the cleaning head 701. Then, the electric cylinder 1 cooperates with the moving rod 3 to drive the cleaning head 701 to move, thereby impacting the blockage and completing the clearing of the blockage inside the side hole tube, which is convenient for the sampling tube 9 to perform sampling. When replacing a single cleaning head 701, the fixing rods 703 on both sides of the cleaning head 701 can be twisted out of the threaded groove on the outside of the cleaning head 701 to release the fixation of the cleaning head 701, which is convenient for the staff to disassemble and replace the damaged cleaning head 701.
[0030] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A boiler water wall hole measuring and clearing device, It is characterized in that The invention comprises an electric cylinder (1), wherein a connecting mechanism (2) is arranged at the bottom of the electric cylinder (1), a moving rod (3) is arranged at the bottom of the connecting mechanism (2), a moving plate (4) is arranged at the bottom of the moving rod (3), a threaded block (5) is threadedly connected to the inner cavity of the moving plate (4), a supporting plate (6) is arranged at the bottom of the threaded block (5), a disassembly mechanism (7) is arranged at the bottom of the supporting plate (6), and a sampling tube (9) is arranged on the outer side of the moving rod (3).
2. The boiler water wall hole measuring and clearing device according to claim 1, It is characterized in that The connecting mechanism (2) comprises a first connecting plate (201), a second connecting plate (202) is arranged below the first connecting plate (201), a threaded rod (203) is arranged in the inner cavity of the first connecting plate (201), a nut (204) is threadedly connected to the outer side of the threaded rod (203), the top of the first connecting plate (201) is fixedly connected to the bottom of the electric cylinder (1), and the bottom of the second connecting plate (202) is fixedly connected to the top of the moving rod (3).
3. The boiler water wall hole measuring and clearing device according to claim 1, It is characterized in that The disassembly mechanism (7) comprises a clearing head (701), the inner cavity of the support plate (6) is provided with the clearing head (701), the bottom of the support plate (6) is fixedly connected to a support plate (702), and the inner cavity of the support plate (702) is threadedly connected to a fixing rod (703).
4. The boiler water wall hole measuring and clearing device according to claim 1, It is characterized in that The outside of the moving rod (3) and the outside of the moving plate (4) are both fixedly connected to a limiting ring (8), and the outside of the sampling tube (9) is slidably connected to the inner cavity of the limiting ring (8).
5. The boiler water wall hole measuring and clearing device according to claim 1, It is characterized in that The inner cavity of the movable plate (4) is slidably connected to a limit rod (10), the bottom of the limit rod (10) is snap-connected to a limit block (11), and the bottom of the limit block (11) is fixedly connected to the top of the support plate (6).
6. The boiler water wall hole measuring and clearing device according to claim 1, It is characterized in that Both sides of the moving rod (3) are fixedly connected with fixed blocks (12), and the bottom of the fixed block (12) is fixedly connected to the top of the moving plate (4).