While-drilling pipe-following energy pile

By using drilling-assisted pipe energy piles in the ground source heat pump system and using heat conduction medium to store heat energy in the pile body, the problems of high construction difficulty and easy damage to the heat exchange pipe in the existing technology are solved, and high heat exchange and high bearing capacity are achieved ground source heat pump application.

CN222068921UActive Publication Date: 2024-11-26CHINA POWER ENG CONSULTING GRP CORP EAST CHINA ELECTRIC POWER DESIGN INST +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323216144.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-28
Publication Date
2024-11-26
Estimated Expiration
2033-11-28

AI Technical Summary

Technical Problem

The existing ground source heat pump system has problems such as high initial investment, high installation difficulty, low yield, and complex system in construction and application. In particular, the application of prefabricated pile buried pipe ground source heat pump technology in hard soil layers is limited, and the replacement of Heat pipes are prone to damage and difficult to connect, which affects construction efficiency and heat transfer efficiency.

Method used

Using drilling-assisted pipe energy piles, by injecting heat conduction medium between the pile body and the soil, heat energy is stored in the heat storage substances in the pile, including drilling-assisted pipe pile body, heat storage body, heat transfer medium, and Thermal medium conveying system, intelligent control system and heat exchange unit realize efficient heat exchange and energy storage.

Benefits of technology

Improve construction efficiency and heat exchange efficiency, reduce environmental pollution and damage risks caused by mud wall guarding, realize the installation and efficient heat exchange of large diameter heat exchange pipes, and the single pile has high bearing capacity, suitable for hard and weak The soil breaks the limitation of the low bearing capacity of traditional prefabricated energy piles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222068921U_ABST
    Figure CN222068921U_ABST
Patent Text Reader

Abstract

The utility model discloses a pipe-following-while-drilling energy pile. The pipe-following-while-drilling energy pile comprises a pipe-following-while-drilling pile body, a heat accumulator, a heat transfer medium, a heat transfer medium conveying system, a valve system and a heat exchange unit; the while-drilling pipe-following pile body is a hollow cylinder, the outer side face of the while-drilling pipe-following pile body is connected with peripheral soil through a cementing material, a sealed cavity is formed by the bottom and the inner side face of the while-drilling pipe-following pile body, and a grouting guide pipe is arranged in the side wall of the while-drilling pipe-following pile body. The heat accumulator is arranged in the closed cavity of the while-drilling pipe pile body; the heat exchange unit comprises a compressor, an evaporator, a condenser, an expansion valve and a pipeline system. The heat exchange unit is configured to achieve heat exchange between heat in the pile body and heat on the user side. The heat transfer medium conveying system is configured to communicate one or more while-drilling pipe pile bodies, and a fluid channel of the while-drilling pipe pile body, the valve system, the heat exchange unit, the valve system and the while-drilling pipe pile body is formed. The energy pile is high in construction efficiency and heat exchange efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the fields of building and energy integration and geothermal utilization, and in particular to a drilling-while-drilling energy pile. Background Art

[0002] Geothermal energy contained in geological environments such as surface water, groundwater, soil and rocks is a large amount of clean and renewable energy. The temperature of geothermal energy in summer is lower than the outdoor temperature, and the temperature of geothermal energy in winter is higher than the outdoor temperature. Through the heat exchange of the ground source heat pump system, the purpose of winter heating and summer cooling is achieved. However, the traditional construction process of the ground source heat pump system "drilling first and then burying the heat exchange pipe" has the disadvantages of high initial investment, difficult installation, low yield, and complex system, which restricts the large-scale promotion and application of geothermal energy in the field of building HVAC. The pile foundation buried pipe ground source heat pump technology is also called energy pile technology. It buries the heat exchange pipe directly in the pile foundation, greatly reducing the cost of additional drilling of the ground source heat pump system. The construction process is simple and the yield is high, which promotes the application of geothermal energy in the construction field.

[0003] According to the different types of pile foundations, pile foundation buried pipe ground source heat pump technology can be divided into cast-in-place pile buried pipe ground source heat pump technology and prefabricated pile buried pipe ground source heat pump technology. Although cast-in-place pile buried pipe ground source heat pump technology can be applied to hard strata and has high single pile bearing capacity and good heat exchange effect, mud wall protection can easily cause hole collapse; the disturbance caused by vibrating and compacting the poured concrete can easily cause the heat exchange tube to bend, deform or even break, the heat exchange tube to rupture and leakage caused by the joints.

[0004] Prefabricated pile buried pipe ground source heat pump technology can be divided into three categories: the first category, the heat exchange tube is located in the inner cavity of the prefabricated pile. This type of prefabricated pile buried pipe ground source heat pump technology relies on the pile type as a small diameter PHC pipe pile foundation (300-600mm) with hammering method and static pressure method as the construction process. After the pile is formed, the heat exchange tube is buried in the cavity of the pipe pile and backfilled with filling materials. The heat exchange tube under this technology is not easy to damage, easy to connect, and has a fast construction speed, but the pile diameter is small, the bearing capacity is not high, the depth of embedding in the soil is different, it is difficult to effectively embed in the rock layer, and it is difficult to use in the hard soil layer. When the hammering or static pressure method is used for construction, the inner cavity of the prefabricated pile is often filled with soil plugs. The depth of the soil plug varies with the type of soil layer, and the depth of the pile foundation embedded in the soil in different soil layers is different, resulting in different lengths of heat exchange tubes. It is difficult to mass produce, and the pile inner diameter is small and the size of the heat exchange tube is limited, which greatly reduces the construction efficiency and heat transfer efficiency. The second type is that the heat exchange tube is located in the pipe wall of the precast pile. This type of precast pile buried pipe ground source heat pump technology relies on the pile type is still a small diameter PHC pipe pile foundation (300-600mm) with hammering method and static pressure method as the construction process. During the precast pile manufacturing process, the heat exchange tube is pre-buried in the pipe wall of the precast pile, and then follows the pile foundation to the expected depth under the hammering or static pressure construction process. The heat exchange tube under this technology is not easy to be damaged and there is no problem of easy disturbance of the heat exchange tube, but the pile foundation of this type has a small diameter, low bearing capacity, and is difficult to use in hard soil layers. Precast piles generally need to be connected. During the connection process, the heat exchange tube is difficult to connect. The volume of the heat exchange tube occupies the concrete usage of the precast pile wall, resulting in a decrease in the strength of the pile body. Due to the limited wall thickness of the small diameter PHC pipe pile foundation (300-600mm) and in order to prevent a significant decrease in the strength of the pile body, the design value of the heat exchange tube diameter is generally small, resulting in a low heat exchange rate. The third type is that the heat exchange tube is located on the outer wall of the precast pile. This type of precast pile buried pipe ground source heat pump technology relies on pile-type static drilled root piles. That is, during the construction of static drilled root piles, heat exchange tubes of different arrangements are tied to the outer wall of the precast pile, and then sink to the designed soil layer depth with the precast pile. Since the operating space on the outer wall of the precast pile is large, the heat exchange tube can be large in diameter, the connection and binding process between the heat exchange tubes is simple, and the heat exchange efficiency is high. However, the static drilled root pile with heat exchange tube is easily disturbed by the soil when sinking in cement soil, resulting in distortion, cracks and even rupture, which affects the heat exchange quality of the precast pile buried pipe ground source heat pump technology. In addition, the binding of the heat exchange tube occurs before the pile is sunk, which seriously affects the construction efficiency of the static drilled root pile.

[0005] Therefore, developing an energy pile that can be constructed efficiently, extracts heat efficiently, and has long durability and high reliability is an issue that needs to be urgently addressed. Summary of the invention

[0006] The purpose of the present application is to provide a drilling and pipe-walking energy pile, which improves the construction efficiency while allowing the pile body to fully exchange heat with the surrounding rock and soil, and stores the thermal energy in the heat storage material in the pile for later use by injecting a heat-conducting medium between the pile body and the soil.

[0007] The present application discloses a drilling-while-pipe energy pile, comprising: a drilling-while-pipe pile body, a heat storage body, a heat transfer medium, a heat transfer medium delivery system, an intelligent control system, a valve system and a heat exchange unit;

[0008] The drilled-while-pipe pile body is a hollow cylinder, the outer side of which is connected to the surrounding soil through a cementitious material, the bottom and the inner side form a sealed closed cavity, and a grouting conduit is arranged inside the side wall;

[0009] The heat storage body is arranged in the closed cavity of the drilling-while-pipe pile body;

[0010] The heat exchange unit includes a compressor, an evaporator, a condenser, an expansion valve and a pipeline system, and the heat exchange unit is configured to achieve heat exchange between the pile body and the surrounding soil and the user side;

[0011] The heat transfer medium delivery system is configured to connect one or more drilling and pipe pile bodies, and form a fluid passage of drilling and pipe pile body-valve system-heat exchange unit-valve system-drilling and pipe pile body;

[0012] The intelligent control system is configured to regulate and optimize the operation of the entire drilling and pipe following energy pile.

[0013] In an optional embodiment, the intelligent control system regulates and optimizes the operation of the entire drilling and pipe following energy pile in the following ways: temperature control, demand response, and predictive maintenance.

[0014] In an optional embodiment, the heat transfer medium delivery system is configured to connect one or more drilling-while-drilling pipe pile bodies, wherein the heat exchange pipe arrangement of the heat transfer medium delivery system is selected from any one of the following: arranged in the inner cavity of the drilling-while-drilling pipe pile body, pre-buried in its side wall, and arranged along the pipe wall on the outer side of the drilling-while-drilling pipe pile body.

[0015] In an optional embodiment, the cementitious material includes a thermally conductive enhanced grouting body injected through the grouting conduit, and the thermally conductive enhanced grouting body is selected from any one or a combination of the following: cement-based phase change material grouting body, mineral-based grouting body and microbial phase change capsule grouting body.

[0016] In an optional embodiment, the heat storage body is selected from any one of the following or a combination thereof: water, a fixed phase change material, and a phase change material.

[0017] In an optional embodiment, the valve system includes any one of the following: a four-way valve, an electronic expansion valve, and a reversible cycle system.

[0018] In an optional embodiment, the fluid passage of the drilling-pipe pile body-valve system-heat exchange unit-valve system-drilling-pipe pile body further includes a flow meter, which is arranged in the valve system and / or the heat exchange unit.

[0019] In an optional embodiment, the heat exchange tube is arranged in sections, and each section is formed into a spiral shape.

[0020] In an optional embodiment, a support structure orthogonal to the extension direction of the heat exchange tube is provided inside the drilling-while-following pipe energy pile, and the support structure is connected to the heat exchange tube to fix and support the heat exchange tube.

[0021] In an optional embodiment, the value range of the inner diameter din of the drilling-while-drilling pile is: 400mm≤din≤1600mm.

[0022] In an optional embodiment, the thickness of the column side wall of the drilling-while-drilling pile body is t, and the value range of t is 50 mm≤t≤250 mm.

[0023] In an optional embodiment, the microbial phase change capsule grouting body is prepared by first mixing the phase change material with an emulsifier to form a microemulsion, and then mixing the microemulsion with a urease-producing microbial bacterial solution and a mixed solution containing a calcium source and urea.

[0024] In an optional embodiment, a sealing material is provided at the connection between the drilling rig and the pipe pile body.

[0025] In an optional embodiment, the sealing material is a sealing gasket or a sealing coating.

[0026] The present application also discloses a construction method of a drilling-while-pipe energy pile, comprising the following steps:

[0027] (S1) Construction of lower pile foundation structure;

[0028] (S2) Sealing test and inspection;

[0029] (S3) Arrangement of heat storage body and heat exchange tubes;

[0030] (S4) Construction of pile foundation superstructure and arrangement of heat transfer medium delivery system;

[0031] (S5) Installation of valve system, heat exchange unit and user-side equipment;

[0032] (S6) Debugging and operation.

[0033] In an optional embodiment, (S1) further includes the following steps:

[0034] (S1-1) Connecting the retractable drill bit to the auger rod;

[0035] (S1-2) allowing the auger rod together with the drill bit to extend through the inner cavity of the prefabricated hollow;

[0036] (S1-3) hoisting the auger rod, the retractable drill bit and the pipe pile at the same time and placing them at the pile position, and clamping the pipe pile with a ground pile clamp to prevent the pipe pile from sinking and shaking;

[0037] (S1-4) driving the auger rod to rotate, and at the same time the retractable drill head opens the enlarged wing plate to drill a hole, wherein the hole diameter is larger than the outer diameter of the pipe pile;

[0038] (S1-5) When the retractable drill bit drills into the soil layer to a certain depth, the pile clamp is released and the drilling continues. At this time, the pipe pile sinks synchronously with the drill bit under the action of a small pile sinking resistance, and the soil and rock debris generated by the drilling is discharged to the ground through the spiral drill rod in the internal cavity of the pipe pile, thereby ensuring that drilling, pile sinking, and soil removal are carried out synchronously;

[0039] (S1-6) performing pile side grouting through a grouting conduit pre-buried in the side of the pipe pile; and

[0040] While the pile side grouting is being carried out, the heat exchange tubes are arranged in sections through the internal cavity of the pipe pile, and each section of the heat exchange tube is provided with a spiral structure.

[0041] The present application also discloses a construction method of a drilling-while-pipe energy pile, comprising the following steps:

[0042] (1) During the production of large diameter (800-1400 mm) pipe piles, a grouting pipe 1 is pre-buried to facilitate grouting on the pile side later, a pile shoe 12 is welded at the pile end to facilitate soil discharge during pile sinking, and an end plate 5 is arranged at the pile top to facilitate pile connection;

[0043] (2) Connect the expandable and retractable drill bit 9 in the retracted state to the long spiral drill rod 6, and then extend the spiral drill rod together with the drill bit in the retracted state through the inner cavity of the pipe pile 7. Use a truck crane to lift the drill rod 6, the drill bit 9, and the pipe pile body 7 while drilling and place them at the pile position. Use a ground pile clamp to clamp the pipe pile 7 to prevent the pipe pile from sinking and shaking.

[0044] (3) The pile-drilling machine drives the spiral drill rod 6 to rotate clockwise while the expandable and retractable drill bit 9 opens the expansion wing plate to drill a hole. The hole diameter is 2 cm larger than the outer diameter of the pile. When the drill bit penetrates into the soil layer for about 3 m, the pile clamp is released and the drilling continues. At this time, the pile sinks synchronously with the drill bit under the action of a relatively small pile sinking resistance. The soil and rock debris generated by the drilling is discharged to the ground through the spiral drill rod in the inner cavity of the pile, thereby ensuring that drilling, pile sinking and soil removal are carried out synchronously;

[0045] (4) If the length of a single pile is not enough during the drilling process, it is necessary to connect the piles, that is, connect the pile body 2 with the drilled pile, and weld the end plates between the upper and lower piles 5. During the welding process, the pile side grouting pipe needs to be docked and sealed. The sealing method includes installing a sealing gasket or applying a sealing paint; to prevent leakage during the later pile side grouting, resulting in failure of the pile side grouting;

[0046] (5) When the drill rod reaches the designed elevation (usually embedded in the rock layer 0.5m), stop drilling, rotate the drill rod counterclockwise to shrink the drill bit, then pull out the shrunken drill bit and drill rod from the inner cavity of the pile, clean the pile end soil, pour 3m high bottom sealing concrete 13 to the pile end through the pile, and then insert the pile into the concrete, so that the pile end and the rock layer 11 are integrated, which greatly improves the pile end resistance;

[0047] (6) The above construction process results in a pile-soil gap 3 of about 10 mm between the hole wall and the outer wall of the pipe pile. Grouting needs to be performed on the pile side through a grouting pipe 1 pre-buried in the pipe wall of the pipe pile to form a grouting body 20 to fill the "pile-soil gap" and bond the soil around the pile, thereby greatly increasing the friction resistance;

[0048] (7) While the pile side grouting is being performed, the heat exchange tubes 17 are arranged in sections through the inner cavity of the pile body (the inner cavity diameter is relatively large, generally greater than 600 mm) by drilling. Each section of the heat exchange tube is provided with a spiral structure 16 to improve the heat exchange effect. The heat exchange tubes are connected and sealed with special joints 15. An inner support 14 is provided in the inner cavity of the pile corresponding to the spiral structure and connected to the heat exchange tube to bear the weight of the heat exchange tube and fix the heat exchange tube;

[0049] (8) After the heat exchange tube is installed, it needs to be treated for corrosion resistance. Then, the cavity of the drilled pile body is filled with heat exchange liquid 21 to improve the heat exchange efficiency. The heat exchange tube 17 is connected to the ground source heat pump system. The ground source heat pump system injects water from the water inlet 18 of the heat exchange tube. After sufficient heat exchange, the injected water is discharged from the water outlet 9 to adjust the indoor temperature, thereby achieving the purpose of warm in winter and cool in summer.

[0050] This application has at least the following beneficial technical effects:

[0051] (1) The drilling-while-drilling energy pile is used as an energy storage medium. Through the heat-conducting enhanced grouting body, the external heat and the heat of the underground rock and soil are stored in the heat storage body inside the pile to achieve the purpose of energy storage;

[0052] (2) The drilling and pipe energy pile adopts the drilling and pipe pile machine for drilling construction, and the pipe pile body is used for self-wall protection. The heat exchange tube is installed in the large space of the pipe pile. Therefore, the drilling and pipe energy pile has no environmental pollution caused by mud wall protection, no heat exchange tube damage caused by hole collapse and hammer static pressure, and the heat exchange tube is easy to operate. Heat exchange tubes of any shape can be arranged according to needs;

[0053] (3) The installation of the heat exchange tube of the drilling and pipe energy pile and the grouting on the pile side can be carried out simultaneously, with high construction efficiency; the heat exchange tube adopts a spiral structure and is in close contact with the heat exchange fluid, with high heat exchange efficiency; the internal support is used to fix and bear the weight of the heat exchange tube, and the construction process causes zero damage to the pile body, and the operation process causes zero corrosion damage to the pipe pile skeleton structure; the heat exchange tube is anti-corrosive treated and has strong durability;

[0054] (4) The drilling and pipe energy construction is fast, the unit bearing capacity cost is low, there is no mud wall protection, it is energy-saving and environmentally friendly, and it can be assembled in an integrated construction; the pile diameter is large and can be embedded in slightly weathered rock formations, the single pile bearing capacity is high (up to more than 2,000 tons), and it can be used in both hard and soft soils, breaking the limitation of traditional prefabricated energy piles with low bearing capacity and can only be used in soft soil formations.

[0055] A large number of technical features are recorded in the specification of this application, which are distributed in various technical solutions. If all possible combinations of technical features of this application (i.e., technical solutions) are to be listed, the specification will be too long. In order to avoid this problem, the various technical features disclosed in the above-mentioned invention content of this application, the various technical features disclosed in the various embodiments and examples below, and the various technical features disclosed in the accompanying drawings can be freely combined with each other to form various new technical solutions (these technical solutions should all be regarded as having been recorded in this specification), unless such a combination of technical features is technically infeasible. For example, in one example, feature A+B+C is disclosed, and in another example, feature A+B+D+E is disclosed, and features C and D are equivalent technical means that play the same role. Technically, only one can be used, and it is impossible to use them at the same time. Feature E can be combined with feature C technically. Then, the solution of A+B+C+D should not be regarded as having been recorded because it is technically infeasible, and the solution of A+B+C+E should be regarded as having been recorded. BRIEF DESCRIPTION OF THE DRAWINGS

[0056] Figure 1 It is a schematic diagram of the drilling and pipe energy pile sinking according to the present application;

[0057] Figure 2 It is a schematic diagram of the arrangement of heat exchange pipes of the drilling and pipe energy pile according to the present application;

[0058] Description of reference numerals:

[0059] 1- grouting conduit; 2- first drilling follow-up pipe pile body; 3- pile-soil gap; 4- grouting outlet; 5- end plate; 6- auger rod; 7- second drilling follow-up pipe pile body; 8- grouting outlet; 9- telescopic drill bit; 10- soil layer; 11- rock layer; 12- pile shoe; 13- bottom sealing concrete; 14- supporting structure; 15- special joint; 16- spiral structure; 17- heat exchange tube; 18- water inlet; 19- water outlet; 20- grouting body; 21- heat exchange fluid. DETAILED DESCRIPTION

[0060] After extensive and in-depth research, the inventors of this application have proposed a drill-and-pipe energy pile that perfectly integrates a safe and reliable energy storage system with the pile foundation system of highways and viaduct buildings, innovatively solving the problem of space limitations of energy storage systems in transportation network construction, making space utilization more intensive. Drilling-pile sinking-soil discharge are constructed simultaneously, and there is no mud discharge, which is energy-saving and environmentally friendly. The borehole diameter is about 2 cm larger than the outer diameter of the pipe pile (that is, there is a 1 cm thick pile-soil gap). After the inner cavity at the end of the pipe pile is sealed with concrete, the pile end and the rock layer are integrated, which greatly improves the pile end resistance. The grouting pipe pre-buried in the pipe wall of the pipe pile is used for pile side grouting. The slurry fills the pile-soil gap and bonds the soil around the pile, thereby greatly improving the pile side friction resistance.

[0061] The advantages of drilling and pipe energy piles include but are not limited to:

[0062] 1. The pile diameter is large and can be embedded in slightly weathered rock layers. The single pile has a high bearing capacity (up to more than 2,000 tons) and is applicable to both hard and soft soils;

[0063] 2. The diameter of the inner cavity of the pipe pile is large, and the inner cavity has enough space to install heat exchange tubes of various forms and sizes, and can be backfilled with filling materials mainly composed of construction waste to improve the heat transfer coefficient;

[0064] 3. Fast construction speed, low unit bearing capacity cost, no mud wall protection, energy saving and environmental protection, and integrated assembly construction; the drilling and pipe piles adopt non-soil squeezing construction technology, and there is no soil plugging effect.

[0065] In the following description, many technical details are provided to help readers better understand the present application. However, those skilled in the art can understand that the technical solution claimed in the present application can be implemented even without these technical details and various changes and modifications based on the following embodiments.

[0066] the term

[0067] As used herein, "energy pile", "pipe-following energy pile" and "pipe-following energy pile while drilling" can be used interchangeably, and all refer to the pipe-following energy pile while drilling of the present application.

[0068] The following is a brief description of some innovative aspects of the implementation methods of this application:

[0069] Drilling and pipe energy pile

[0070] The energy pile of the present application comprises a drilling and pipe pile body, a heat storage body, a heat transfer medium, a heat transfer medium delivery system, a valve system and a heat exchange unit. The drilling and pipe pile body is a large-diameter hollow cylinder with an inner diameter d in The optional value range is 400mm≤d in ≤1600mm. Preferably, 800mm≤d in ≤1600mm. More preferably, 1000mm≤d in ≤1600mm.

[0071] The thickness of the column side wall of the drilling pile body is t, and the preferred value range of t is 50mm≤t≤250mm; a grouting conduit is arranged inside the side wall. The grouting conduit can be an aluminum-plastic pipe with an inner diameter of 20mm and a wall thickness of 4mm.

[0072] The outer side of the drilling follow-up pipe pile body is connected to the surrounding soil through a cementitious material, and the cementitious material includes a heat-conducting enhanced grouting body injected through a grouting conduit, and the heat-conducting enhanced grouting body can be: a cement-based phase change material grouting body, a mineral-based grouting body, and a microbial phase change capsule grouting body, or a combination of one or more substances. In an optional embodiment, the microbial phase change capsule grouting body is a grouting body prepared by first mixing a phase change material with an emulsifier to form a microemulsion, and then mixing the microemulsion with a urease-producing microbial bacterial solution and a mixed solution containing a calcium source and urea.

[0073] The bottom and inner side of the pile body are formed into a sealed closed cavity. In one embodiment, the sealing is achieved by installing a bottom sealing body at the bottom of the pile body.

[0074] The closed cavity of the drilling and pipe pile body is sealed with a heat storage body, which can be water, a fixed phase change material, or a phase change material.

[0075] The heat exchange unit is configured to realize the heat exchange between the heat in the pile and the heat in the external heat exchange unit, including a compressor, an evaporator, a condenser, an expansion valve and a pipeline system. The heat transfer medium delivery system is configured to connect one or more drilling and pipe pile bodies, and form a fluid passage of drilling and pipe pile body-valve system-heat exchange unit-valve system-drilling and pipe pile body. The valve system may include a four-way valve. In an optional embodiment, the heat exchange pipe arrangement of the heat transfer medium delivery system is selected from any one of the following: arranged in the inner cavity of the drilling and pipe pile body, pre-buried in its side wall, and arranged along the pipe wall outside the drilling and pipe pile body. The heat exchange pipe is arranged in sections in the pile, and each section is formed into a spiral shape. In a preferred embodiment, a support structure orthogonal to the extension direction of the heat exchange pipe is arranged inside the drilling and pipe energy pile, and the support structure is connected to the heat exchange pipe, and fixes and supports the heat exchange pipe.

[0076] Construction method of drilling and pipe energy pile

[0077] The construction method of the above energy pile is as follows: Figure 1 and Figure 2 It is shown that the main components required during the construction process include: a grouting conduit 1, an end plate 5, a pipe pile body 7, and a pile shoe 12. In an optional embodiment, the grouting conduit 1 is buried in the side wall of the pipe pile body so as to facilitate pile side grouting later. A pile shoe 12 is welded to the end of the pipe pile body so as to discharge soil when sinking the pile. In a favorable embodiment, the pile shoe 12 is configured to directional discharge soil debris when sinking the pile. An end plate 5 is arranged on the top of the pipe pile body, and the end plate is used for connecting the piles between the pipe pile bodies. When it is necessary to connect the piles, the end plates 5 between the two pipe pile bodies can be welded, and the pile side grouting conduit 1 needs to be butt-jointed and sealed during the welding process. In a favorable embodiment, the contact part between the end plate 5 and the pipe pile body is sealed; the pipeline arranged in the pile is passed through the reserved hole of the end plate, and the reserved hole is sealed.

[0078] During the construction process, the spiral drill rod 6 for drilling is inserted into the internal cavity of the pile body, and the retractable drill bit 9 is connected to the spiral drill rod 6 and can be extended to drill holes in the pile body. The retractable drill bit includes two states: when the retractable drill bit is in the first state, that is, the retracted state, it is retracted in the internal cavity of the pile body; when the retractable drill bit is in the second state, that is, the working state, it extends from the internal cavity of the pile body and opens the expansion wing plate to drill holes. The borehole diameter is larger than the outer diameter of the pile body. In an advantageous embodiment, the borehole diameter is 2 cm larger than the outer diameter of the pile body.

[0079] The internal cavity of the drilling and pipe pile body is penetrated with a heat exchange tube. The heat exchange tube is arranged in sections, and each section is formed into a spiral shape to improve the heat exchange effect. The heat exchange tubes are connected and sealed with a special joint 15. In a preferred example, a support structure orthogonal to the extension direction of the heat exchange tube is arranged inside the drilling and pipe pile body, and the support structure is connected to the heat exchange tube, and fixes and supports the heat exchange tube. An internal support 14 is arranged in the internal cavity of the drilling and pipe pile body corresponding to the spiral structure, and it is connected to the heat exchange tube to bear the weight of the heat exchange tube and fix the heat exchange tube. After the installation of the heat exchange tube is completed, it needs to be treated with corrosion protection, and then the internal cavity of the drilling and pipe pile body is filled with heat exchange liquid 21 to improve the heat exchange efficiency. The heat exchange tube 17 is connected to the ground source heat pump system, and the ground source heat pump system is injected with water from the water inlet 18 of the heat exchange tube. After sufficient heat exchange, the injected water is discharged from the water outlet 9 to adjust the indoor temperature, thereby achieving the purpose of warm in winter and cool in summer.

[0080] In an optional embodiment, if Figure 1 The first drill-while-drilling pile body 2 and the second drill-while-drilling pile body 7 shown have large diameters and high bearing capacity, and the grouting conduit 1 is connected together by an end plate 5. The bottom grouting outlet 8 is a non-connecting port of the grouting conduit 1, which can be located at the bottom end of the bottom section of the drill-while-drilling pile body, or at the bottom end of a middle section of the drill-while-drilling pile body. The thermally conductive enhanced grouting body 20 passes through the grouting conduit 1 and is injected into the outside of the drill-while-drilling pile body from the bottom grouting outlet 8. The pile shoe is located at the bottom end of the bottom section of the drill-while-drilling pile body. The top cover plate is located at the top end of the top section of the drill-while-drilling pile body, and is provided with holes thereon for the grouting conduit to pass through.

[0081] In an advantageous embodiment, the main part of the heat transfer medium delivery pipeline can be arranged in the inner cavity of the while drilling pile body, or can be pre-buried in its side wall, or can be arranged along the outer wall of the pipe. The two ends of the heat transfer medium delivery pipeline are respectively connected to the two sides of the external heat exchange unit through the valve system, and the heat transfer medium is circulated in the heat transfer medium delivery pipeline by using a circulating pump, so as to realize the heat exchange between the periphery of the while drilling pile body and the heat in the external heat exchange unit.

[0082] In an advantageous embodiment, the diameter of the pile body can be greater than 800 mm, the inner wall is corrosion-resistant, and the bearing capacity can reach more than 1,000 tons, more advantageously, more than 1,500 tons. The top cover plate has corrosion-resistant properties and is provided with a hole for the heat transfer medium conveying pipe to pass through the hole.

[0083] In order to make the objectives, technical solutions and advantages of the present application clearer, the implementation methods of the present application will be further described in detail below in conjunction with the accompanying drawings.

[0084] Embodiment: Construction of drilling and pipe-based energy piles

[0085] Reference Figure 1 and Figure 2 The implementation plan for the construction of drilling and pipe energy piles is as follows:

[0086] (1) A large diameter (eg, 1400 mm) drilled-while-drilling pile body is selected. During the manufacturing process, a grouting conduit 1 is pre-buried in the side wall of the pile body to facilitate grouting of the pile side later.

[0087] A pile shoe 12 is welded at the pile end to facilitate soil removal during pile sinking, and an end plate 5 is arranged at the pile top to facilitate pile connection.

[0088] (2) The retractable drill bit 9 in the retracted state is connected to the long spiral drill rod 6, and then the spiral drill rod together with the retracted drill bit is extended through the inner cavity of the drilling pipe pile body 7. The drill rod 6, the drill bit 9 and the drilling pipe pile body 7 are lifted up by a truck crane and placed at the pile position. The second drilling pipe pile body 7 is clamped by a ground pile clamp to prevent the drilling pipe pile body from sinking and shaking.

[0089] (3) The drilling machine drives the spiral drill rod 6 to rotate clockwise, and the retractable drill bit 9 opens the enlarged wing plate to drill a hole. The diameter of the hole is 2 cm larger than the outer diameter of the drilling pile body. When the drill bit penetrates into the soil layer for about 3 m, the pile clamp is released and the drilling continues. At this time, the drilling pile body sinks synchronously with the drill bit under the action of a smaller pile sinking resistance. The soil and rock debris generated by the drilling is discharged to the ground through the spiral drill rod in the cavity of the drilling pile body, thereby ensuring that drilling, pile sinking and soil removal are carried out synchronously.

[0090] (4) During the drilling process, if the length of a single pile is not enough, it is necessary to connect the piles, that is, connect the first drilling follow-up pipe pile body 2, and weld the end plates between the upper and lower drilling follow-up pipe pile bodies 5. During the welding process, the pile side grouting conduit 1 needs to be docked and sealed to prevent leakage during the subsequent pile side grouting, resulting in failure of the pile side grouting.

[0091] (5) When the drill pipe reaches the designed elevation (generally embedded in the rock layer 0.5m), stop drilling, rotate the drill pipe counterclockwise to shrink the drill bit, and then pull the shrunken drill bit and drill pipe out of the inner cavity of the pile body.

[0092] After cleaning the pile end slag, pour 3m high bottom sealing concrete 13 to the pile end through the drilling and pipe pile body, and then insert the drilling and pipe pile body into the concrete, so that the pile end and the rock layer 11 are integrated, which greatly improves the pile end resistance;

[0093] (6) The above construction process results in a pile-soil gap 3 of about 10 mm between the hole wall and the outer wall of the drilled and pipe pile body. Grouting is required on the pile side through a grouting conduit 1 pre-buried in the wall of the drilled and pipe pile body to form a grouting body 20 to fill the "pile-soil gap" and bond the soil around the pile, thereby greatly increasing the friction resistance.

[0094] (7) While the pile side grouting is being performed, the heat exchange tubes 17 are arranged in sections through the inner cavity of the pile body (the inner cavity diameter is relatively large, generally greater than 600 mm), and each section of the heat exchange tube is provided with a spiral structure 16 to improve the heat exchange effect. The heat exchange tubes are connected and sealed with special joints 15. An inner support 14 is provided in the inner cavity of the pile body corresponding to the spiral structure, and is connected to the heat exchange tube to bear the weight of the heat exchange tube and fix the heat exchange tube;

[0095] (8) After the heat exchange tube is installed, it needs to be treated for corrosion resistance. Then, the cavity of the drilled pile body is filled with heat exchange liquid 21 to improve the heat exchange efficiency. The heat exchange tube 17 is connected to the ground source heat pump system. The ground source heat pump system injects water from the water inlet 18 of the heat exchange tube. After sufficient heat exchange, the injected water is discharged from the water outlet 9 to adjust the indoor temperature, thereby achieving the purpose of warm in winter and cool in summer.

[0096] It should be noted that in the application documents of this patent, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "including one" do not exclude the existence of other identical elements in the process, method, article or device including the elements. In the application documents of this patent, if it is mentioned that an action is performed according to an element, it means that the action is performed at least according to the element, which includes two situations: performing the action only according to the element and performing the action according to the element and other elements. Expressions such as multiple, multiple, and multiple include 2, 2 times, 2 kinds, and more than 2, more than 2 times, and more than 2 kinds.

[0097] This specification includes combinations of the various embodiments described herein. Individual references to "one embodiment" or a particular embodiment, etc., do not necessarily refer to the same embodiment; however, these embodiments are not mutually exclusive unless indicated as mutually exclusive or clear to those skilled in the art. It should be noted that the word "or" is used in this specification in a non-exclusive sense unless the context clearly indicates or requires otherwise.

[0098] All documents mentioned in this application are considered to be included in the disclosure of this application as a whole, so that they can be used as the basis for modification when necessary. In addition, it should be understood that after reading the above disclosure of this application, those skilled in the art can make various changes or modifications to this application, and these equivalent forms also fall within the scope of protection claimed in this application.

Claims

1. A drilling and pipe energy pile, It is characterized in that include: Drilling and pipe pile body, heat storage body, heat transfer medium, heat transfer medium transportation system, valve system and heat exchange unit; The drilled-while-pipe pile body is a hollow cylinder, the outer side of which is connected to the surrounding soil through a cementitious material, the bottom and the inner side form a sealed closed cavity, and a grouting conduit is arranged inside the side wall; The heat storage body is arranged in the closed cavity of the drilling-while-pipe pile body; The heat exchange unit includes a compressor, an evaporator, a condenser, an expansion valve and a pipeline system, and the heat exchange unit is configured to achieve heat exchange between the pile body and the surrounding soil and the user side; The heat transfer medium delivery system is configured to connect one or more drilling and tubular pile bodies, and form a fluid passage of drilling and tubular pile body-valve system-heat exchange unit-valve system-drilling and tubular pile body.

2. The drilling-while-drilling energy pile according to claim 1, It is characterized in that The heat transfer medium delivery system is configured to connect one or more drilling-while-drilling pipe pile bodies, wherein the heat exchange pipe arrangement of the heat transfer medium delivery system is selected from any one of the following: arranged in the inner cavity of the drilling-while-drilling pipe pile body, pre-buried in its side wall, and arranged along the pipe wall outside the drilling-while-drilling pipe pile body.

3. The drilling-while-drilling energy pile according to claim 1, It is characterized in that The valve system includes any one of the following: a four-way valve, an electronic expansion valve, and a reversible circulation system.

4. The drilling-while-drilling energy pile according to claim 2, It is characterized in that The heat exchange tube is arranged in sections, and each section is formed into a spiral shape.

5. The drilling-while-drilling energy pile according to claim 2 or 4, It is characterized in that A support structure orthogonal to the extension direction of the heat exchange tube is arranged inside the drilling-following pipe energy pile. The support structure is connected to the heat exchange tube and fixes and supports the heat exchange tube.

6. The drilling-while-drilling energy pile according to claim 1, It is characterized in that The inner diameter d of the drilling pile in The value range is: 400mm≤d in ≤1600mm.

7. The drilling-while-drilling energy pile according to claim 1, It is characterized in that The thickness of the column side wall of the drilling-while-pipe pile body is t, and the value range of t is 50mm≤t≤250mm.