Slope vertical drainage ditch and slope lattice beam integrated structure
By designing an integrated structure of vertical drainage ditch and lattice beam on the slope supported by the anchor (cable) lattice beam, the cross anchoring of the main rib and the reinforced steel bar are solved, and the construction difficulty and structural stability are achieved. Convenient vertical drainage and overall structural integrity.
Patent Information
- Application Number
- CN202420745091.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-11
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-04-11
AI Technical Summary
On slopes supported by anchor rod (cable) lattice beams, it is difficult for the prior art to achieve convenient vertical drainage ditch construction, and vertical drainage ditches will damage the overall structural stability of the lattice beams.
A integrated structure of vertical drainage ditch on the slope and lattice beam on the slope surface was designed. Vertical drainage ditch was set at the undulating position of the slope top line of the high slope, and the main reinforcement of the lattice beam and the side walls of the vertical drainage ditch were used. Cross-anchoring, combined with reinforcement of reinforcement of steel bars, forms a unified overall structure, avoiding trench casting.
Convenient vertical drainage ditches construction is achieved, the overall structural integrity of the lattice beam is ensured, the problem of water flow erosion is solved, and the stability of the slope is improved.
Smart Images

Figure CN222083590U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of slope engineering, and more specifically, to an integrated structure of a slope vertical drainage ditch and a slope surface lattice beam. Background Art
[0002] Slope projects are often located in mountainous areas. The back edge of the slope is often affected by the original mountain terrain to form a water collection point, and atmospheric precipitation or surface runoff gathers at the top of the slope. The accumulation of water at the top of the slope will cause erosion and loosening of the top rock and soil, and even cause collapse or landslides of the slope. Therefore, slope projects often set up effective slope top interception ditches to prevent rainwater from directly scouring the slope surface and reduce the possibility of rock and soil erosion, so as to ensure the integrity and stability of the slope rock and soil and reduce the risk of landslides.
[0003] However, due to the ups and downs of the original terrain, the top line of the slope often follows the ups and downs of the original terrain, and there is no uniform top elevation. In this way, there will be a relative lowest point at the top of the slope, which is the water collection point of the top of the slope. If it is not drained, the water will gather at the top of the slope and erode the rock and soil of the slope, causing irreversible consequences. For the lowest point of the top of the slope in the middle section of the slope, the project often sets a vertical drainage ditch on the slope surface to guide the water gathered at the top of the slope through the slope surface to the drainage ditch at the foot of the slope, and finally drain the water smoothly. At the same time, setting up vertical drainage ditches on the slope surface can reduce the scouring effect of water flow on the slope surface, protect the integrity of the rock and soil on the slope surface, and prevent landslides.
[0004] For slopes with flat surface, vertical drainage ditches can be made by cutting grooves on the slope surface and spraying the whole surface. However, for slopes supported by anchor rods (cables) lattice beams, the slope surface is no longer a flat surface due to the presence of the lattice beams. The method of cutting grooves on the slope surface to make vertical drainage ditches is difficult to implement on site. At the same time, the vertical drainage ditches will also split the lattice beams as a whole, which is not conducive to the stress stability of the overall structure. Therefore, there is an urgent need for a vertical drainage ditch method suitable for slopes supported by anchor rods (cables) lattice beams, which takes into account both construction convenience and structural integrity. Utility Model Content
[0005] The utility model aims to overcome the deficiencies in the prior art and provides an integrated structure of a slope vertical drainage ditch and a slope lattice beam.
[0006] In a first aspect, a vertical drainage ditch on a slope and an integrated structure of a lattice beam on a slope are provided, comprising: a high slope, a vertical drainage ditch, a lattice beam, a slope bridleway, a plain concrete cushion layer and main reinforcement of the lattice beam;
[0007] Among them, the top line of the high slope is undulating, and the vertical drainage ditch is arranged at the lowest position of the top of the high slope; the high slope is supported by the lattice beam; a plain concrete cushion layer is arranged at the bottom of the high slope; the lattice beam includes vertical lattice beams and horizontal lattice beams; the main reinforcement of the lattice beam includes upper main reinforcement of the lattice beam and lower main reinforcement of the lattice beam; the vertical drainage ditch is arranged parallel to the vertical lattice beam, and intersects with the horizontal lattice beam, and is anchored into the side wall of the vertical drainage ditch through the upper main reinforcement of the lattice beam at the intersection; the lower main reinforcement of the lattice beam passes through the bottom plate of the vertical drainage ditch.
[0008] Preferably, reinforcing steel bars are provided on the bottom plate of the vertical drainage ditch, the diameter of the reinforcing steel bars is the same as the main bars of the lattice beam, and the reinforcing steel bars are anchored into the lattice beam.
[0009] Preferably, structural steel bars are arranged in the vertical drainage ditch, and the structural steel bars include lateral bending-resistant steel bars, longitudinal full-length steel bars and reinforcing stirrups.
[0010] In a second aspect, a construction method of an integrated structure of a vertical drainage ditch on a slope and a lattice beam on a slope as described in any one of the first aspects is provided, comprising:
[0011] Step 1: construct a plain concrete cushion at the bottom of the high slope lattice beam;
[0012] Step 2, determining the position of the vertical drainage ditch 2 at the relatively lowest position of the ups and downs of the top line of the high slope;
[0013] Step 3, anchoring the upper main reinforcement of the lattice beam into the side wall of the vertical drainage ditch, and making the lower main reinforcement 11 of the lattice beam pass through the bottom plate of the vertical drainage ditch;
[0014] Step 4: Install reinforcing steel bars on the bottom plate of the vertical drainage ditch and anchor the reinforcing steel bars into the lattice beam;
[0015] Step 5: Use formwork to integrally cast the vertical drainage ditch and lattice beam, and the integrated structure is finally formed.
[0016] Preferably, in step 5, the vertical drainage ditch and the horizontal lattice beam are cast as an integral structure.
[0017] The beneficial effects of the utility model are as follows: the vertical drainage ditch of the present application does not need to be cast and grooved, and can be directly constructed on the slope. The main reinforcement of the lattice beam at the intersection of the vertical drainage ditch and the horizontal lattice beam is anchored into the side wall of the vertical drainage ditch, and at the same time, connecting reinforcement steel bars are added to the bottom plate of the drainage ditch and anchored into the lattice beam, so that the lattice beam and the vertical drainage ditch form a unified whole, which not only solves the vertical drainage problem, but also ensures the integrity of the support structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1It is a typical slope elevation drawing of an integrated structure of a slope vertical drainage ditch and a slope lattice beam;
[0019] Figure 2 It is a typical cross-sectional view of an integrated structure of a slope vertical drainage ditch and a slope lattice beam;
[0020] Figure 3 This is a typical cross-sectional reinforcement diagram of an integrated structure of a slope vertical drainage ditch and a slope lattice beam;
[0021] Explanation of the reference numerals in the accompanying drawings: high slope 1, vertical drainage ditch 2, lattice beam 3, vertical lattice beam 301, horizontal lattice beam 302, slope walkway 4, plain concrete cushion layer 5, lateral bending reinforcement 6, longitudinal full-length reinforcement 7, reinforcing stirrups 8, reinforcing reinforcement 9, upper main reinforcement of lattice beam 10, lower main reinforcement of lattice beam 11. DETAILED DESCRIPTION
[0022] The utility model is further described below in conjunction with the embodiments. The description of the following embodiments is only used to help understand the utility model. It should be pointed out that for ordinary people in this technical field, the utility model can also be modified in some ways without departing from the principle of the utility model, and these improvements and modifications also fall within the scope of protection of the claims of the utility model.
[0023] Embodiment 1:
[0024] like Figures 1 to 3 As shown, Example 1 of the present application provides an integrated structure of a slope vertical drainage ditch and a slope lattice beam, including: a high slope 1, a vertical drainage ditch 2, a lattice beam 3, a slope walkway 4, a plain concrete cushion layer 5 and main reinforcement of the lattice beam.
[0025] Among them, the top line of the high slope 1 is undulating, and there is a relatively lowest point in the middle section. The vertical drainage ditch 2 is set at the relatively lowest position of the top of the high slope 1. The high slope 1 is supported by anchor rod (cable) lattice beam 3. For example, the vertical drainage ditch 2 has a net section width of b (mm), a height of h (mm), and a wall thickness of 200mm (the size of the vertical drainage ditch is selected according to actual needs). Its starting point is set at the relatively lowest position in the middle section of the top line of the high slope 1, connected to the top intercepting ditch, and the end leads water to the drainage ditch at the foot of the slope. The vertical drainage ditch 2 is arranged parallel to the vertical lattice beam on the facade, and the positions do not conflict with each other. In addition, a 100mm thick plain concrete cushion layer 5 is provided at the bottom of the lattice beam 3 on the slope surface of the high slope.
[0026] The lattice beam 3 includes a vertical lattice beam 301 and a horizontal lattice beam 302; the main reinforcement of the lattice beam includes an upper main reinforcement 10 and a lower main reinforcement 11 of the lattice beam; the vertical drainage ditch 2 intersects with the horizontal lattice beam 302, and the upper main reinforcement 10 of the lattice beam needs to be bent and anchored, and at the intersection, the upper main reinforcement 10 of the lattice beam is anchored into the side wall of the vertical drainage ditch, for example, anchored into the side wall 35d of the vertical drainage ditch (d is the diameter of the lattice beam main reinforcement); the lower main reinforcement 11 of the lattice beam passes through the bottom plate of the vertical drainage ditch 2 and is arranged throughout the length.
[0027] Reinforced steel bars 9 are provided on the bottom plate of the vertical drainage ditch 2 and are evenly arranged along the width direction of the lattice beam. The diameter of the reinforced steel bars 9 is the same as the main bars of the lattice beam, and both sides need to be anchored into the lattice beam for not less than 35d to enhance the strength of the connection node.
[0028] The vertical drainage ditch 2 is provided with structural steel bars to enhance the structural rigidity and prevent cracks or structural damage caused by later slope deformation, thereby affecting slope drainage and the overall stability of the slope. Specifically, the structural steel bars include lateral bending steel bars 6, longitudinal full-length steel bars 7 and reinforcing stirrups 8. The longitudinal full-length steel bars 7 are φ10 (HPB300) with a spacing of 200mm; the lateral bending steel bars 6 are φ12 (HRB400) with a spacing of 200mm; the reinforcing stirrups (8) are φ10 (HPB300) with a spacing of 400mm x400mm, and are arranged in a plum blossom shape.
[0029] After the above measures are implemented, the vertical drainage ditch (2) and the lattice beam (3) are integrally cast using formwork, and the integrated structure is finally formed.
[0030] Embodiment 2:
[0031] Based on Example 1, Example 2 of the present application provides a construction method for an integrated structure of a slope vertical drainage ditch and a slope lattice beam, including:
[0032] Step 1: construct a plain concrete cushion layer 5 at the bottom of the lattice beam 3 of the high slope 1.
[0033] Step 2: Determine the position of the vertical drainage ditch 2 at the relatively lowest position of the ups and downs of the top line of the high slope 1.
[0034] Step 3: The upper main reinforcement 10 of the lattice beam is anchored into the side wall of the vertical drainage ditch, and the lower main reinforcement 11 of the lattice beam passes through the bottom plate of the vertical drainage ditch 2.
[0035] Step 4: Install reinforcing steel bars 9 on the bottom plate of the vertical drainage ditch 2 and anchor the reinforcing steel bars 9 into the lattice beam 3.
[0036] Step 5: Formwork is used to integrally cast the vertical drainage ditch 2 and the lattice beam 3, and the integrated structure is finally formed.
[0037] In step 5, the vertical drainage ditch 2 and the horizontal lattice beam 302 are cast as an integral structure, and there is no need to cut grooves on the vertical drainage ditch 2 separately.
[0038] Specifically, the method provided in this embodiment is a method corresponding to the device provided in Embodiment 1. Therefore, the parts in this embodiment that are the same or similar to those in Embodiment 1 can be referenced to each other and will not be repeated in this application.
[0039] In summary, compared with setting up vertical drainage ditches by cutting grooves on the slope surface, the effect of this application on the slope support of anchor rod (cable) lattice beams is positive and obvious. This application avoids the construction inconvenience caused by cutting grooves between lattice beams, and by integrating the support structure and the drainage structure, it not only solves the vertical drainage problem, but also ensures the integrity of the support structure, which is extremely suitable for the slope supported by anchor rod (cable) lattice beams.
Claims
1. An integrated structure of a slope vertical drainage ditch and a slope lattice beam, characterized in that: include: High side slope (1), vertical drainage ditch (2), lattice beam (3), side slope bridleway (4), plain concrete cushion layer (5) and main reinforcement of lattice beam; The top line of the high slope (1) is undulating, and the vertical drainage ditch (2) is arranged at the lowest position of the top of the high slope (1); the high slope (1) is supported by the lattice beam (3); a plain concrete cushion layer (5) is arranged at the bottom of the high slope (1); the lattice beam (3) comprises a vertical lattice beam (301) and a horizontal lattice beam (302); the main reinforcement of the lattice beam comprises an upper main reinforcement (10) of the lattice beam and a lower main reinforcement (11) of the lattice beam; the vertical drainage ditch (2) is arranged in parallel with the vertical lattice beam (301) and intersects with the horizontal lattice beam (302), and is anchored into the side wall of the vertical drainage ditch at the intersection position through the upper main reinforcement (10) of the lattice beam; the lower main reinforcement (11) of the lattice beam passes through the bottom plate of the vertical drainage ditch (2).
2. The integrated structure of the vertical drainage ditch and slope lattice beam of claim 1 is characterized in that: A reinforcing steel bar (9) is arranged on the bottom plate of the vertical drainage ditch (2). The diameter of the reinforcing steel bar (9) is the same as the main reinforcement of the lattice beam and is anchored into the lattice beam (3).
3. The integrated structure of the vertical drainage ditch and slope lattice beam of claim 2 is characterized in that: Structural steel bars are arranged in the vertical drainage ditch (2), and the structural steel bars include lateral bending-resistant steel bars (6), longitudinal full-length steel bars (7) and reinforcing stirrups (8).