Waterproof plate laying and hanging positioning device for super-large-section urban tunnel
By using the waterproof board lading device of laser positioning components in tunnel construction, the problems of difficulty in marking the tunnel surface and uneven line shape are solved, efficient and smooth five-wire marking are achieved, and construction quality and efficiency are improved.
Patent Information
- Application Number
- CN202420839644.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-22
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-04-22
AI Technical Summary
During tunnel construction, the marking of the waterproof board on the tunnel surface is affected by the excavation height at the bottom of the tunnel, and it is difficult to measure and mark the marking, resulting in incorrect marking of the work line. Traditional spray markings have uneven line shapes and pollute the environment, and the waterproof board line is blocked. Remarks are required, increasing labor intensity and construction complexity.
Design a waterproof board laid and positioning device including at least 5 positioning components with lasers, move in the height direction through the suspension tube and sliding collar system, and use the laser to emit horizontal marking lines to realize the wall on the five lines, simplifying the marking process And improve smoothness.
It improves the efficiency and construction quality of waterproof board laying, reduces labor intensity, reduces the problem of uneven line shapes, and reduces environmental pollution.
Smart Images

Figure CN222084522U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of tunnel construction, and in particular relates to a paving and hanging positioning device for waterproof panels in urban tunnels with super-large sections. Background Art
[0002] At present, during the tunnel construction process, it is necessary to carry out waterproof construction operations on the tunnel surface, which is generally achieved by laying waterproof boards on the inner surface of the tunnel. During the tunnel invert excavation and concrete structure construction, the "five lines on the wall" system is implemented, and red spray paint is used to indicate the "five lines", which provides a guarantee for the refined construction of the tunnel invert. Among them, the "five lines" refer to: geotextile wiring, waterproof board line, low side wall top line, longitudinal blind pipe line, and construction seam line. However, in actual construction, due to the high excavation height of the tunnel bottom, it is difficult to measure and mark, resulting in errors in the marking of the operation line, which directly affects the subsequent construction operations. During the marking process, multiple people are required to cooperate with the work, and multiple layers of waterproof operations are repeatedly marked. The labor intensity of on-site work is relatively high, and traditional spray marking will pollute the surrounding environment. In particular, during the waterproof board laying and hanging process, some waterproof board lines are blocked by the waterproof boards laid in the early stage, and the waterproof board lines need to be re-marked, and the spray marking has the problem of uneven line shape. Utility Model Content
[0003] In response to the above-mentioned problems in the prior art, the present application proposes a positioning device for laying and hanging waterproof panels in urban tunnels with extra-large cross-sections. By setting up at least 5 positioning components equipped with lasers, five lines can be marked on the wall simply and efficiently, providing a guarantee for the refined construction of the tunnel invert, especially improving the efficiency of laying and hanging waterproof panels and the construction quality.
[0004] The utility model proposes a positioning device for laying and hanging waterproof panels in urban tunnels with super-large sections, comprising: a frame and at least 5 positioning components; a crossbeam is arranged on the frame, and a suspension tube is arranged on the crossbeam; at least 5 positioning components are arranged on the suspension tube in sequence from top to bottom; the positioning component comprises a sliding ring, a support plate connected to the sliding ring, a locking piece and a laser arranged on the support plate; the sliding ring is sleeved on the suspension tube and movably cooperates along the height direction of the suspension tube; the locking piece is arranged on the sliding ring, and is used to lock and fix the sliding ring on the suspension tube; the laser is used to emit a horizontal mark.
[0005] Furthermore, the positioning assembly also includes a clamping member; the clamping member is arranged on a side of the support plate facing away from the sliding ring.
[0006] Furthermore, the clamping member includes a spring, a clamping plate and a sliding rod; a through hole is provided at one end of the support plate facing away from the sliding ring, one end of the sliding rod is inserted into the through hole, the other end of the sliding rod is connected to the clamping plate, and the spring is sleeved on the outside of the sliding rod between the clamping plate and the support plate.
[0007] Furthermore, the locking member includes a locking bolt; a threaded hole is provided on one side of the sliding ring, the locking bolt cooperates with the threaded hole, and one end of the locking bolt is pressed against the suspension tube.
[0008] Furthermore, a threaded section is provided on the suspension tube, and a height adjustment nut is matched on the threaded section of the suspension tube, and the height adjustment nut is located above the crossbeam.
[0009] Furthermore, limit plates are respectively provided at the upper end and the lower end of the suspension pipe.
[0010] Furthermore, a bottom plate is provided at the bottom of the frame, and wheels are provided at the bottom of the bottom plate.
[0011] Furthermore, a connecting ring is provided at one end of the crossbeam, and the positioning device further comprises a pull rod, a hook is provided at one end of the pull rod, and the hook is connected to the connecting ring.
[0012] The beneficial effect of the utility model is as follows: by arranging at least 5 positioning components in sequence along the height direction on the suspension tube of the beam, and using the 5 lasers of the 5 positioning components to respectively emit 5 horizontal marks on the tunnel wall, five lines on the wall are achieved. Compared with the traditional painting method, the marking effect is good, the line type is smooth, there is no need for repeated marking, and the labor intensity is reduced. It is particularly suitable for the laying and hanging positioning of waterproof boards. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 The utility model is a schematic diagram of the side structure of the device for laying and hanging waterproof panels in urban tunnels with super-large sections.
[0014] Figure 2 for Figure 1 Schematic diagram of the structure when the pull rod is in the drooping state.
[0015] Figure 3 for Figure 1 A schematic diagram of the top view structure of a positioning component.
[0016] Figure 4 for Figure 3 AA cross-sectional structure schematic diagram.
[0017] In the figure, 1-frame; 2-crossbeam; 3-suspension tube; 31-threaded section; 4-positioning assembly; 41-slip ring; 42-support plate; 43-locking piece; 44-laser; 45-spring; 46-clamp; 47-sliding rod; 5-height adjustment nut; 6-limiting plate; 7-bottom plate; 8-wheel; 9-pull rod; 10-connecting ring. DETAILED DESCRIPTION
[0018] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0019] like Figure 1-Figure 4 The device for laying and positioning waterproof panels in urban tunnels with super-large cross-sections shown in the figure comprises: a frame 1 and at least five positioning components 4. A crossbeam 2 is arranged on the frame 1, and a suspension pipe 3 is arranged on the crossbeam 2; at least five positioning components 4 are arranged on the suspension pipe 3 in sequence from top to bottom; the positioning component 4 comprises a sliding ring 41, a support plate 42 connected to the sliding ring 41, a locking member 43, and a laser 44 arranged on the support plate 42; the sliding ring 41 is sleeved on the suspension pipe 3 and is movably matched along the height direction of the suspension pipe 3; the locking member 43 is arranged on the sliding ring 41, and is used to lock and fix the sliding ring 41 on the suspension pipe 3; the laser 44 is used to emit a horizontal mark. Since there are five positioning components 4, there are also five corresponding lasers 44, and the five lasers 44 at different heights respectively emit five horizontal laser lines, which are projected on the tunnel wall to achieve five lines on the wall. According to the heights of geotechnical wiring, waterproof board lines, top surface lines of short side walls, longitudinal blind pipe lines and construction seams during construction, the heights of the five positioning components 4 are adjusted accordingly so that the laser line emitted by the laser 44 corresponds to the height of the five lines.
[0020] In some embodiments, there may be six positioning components 4, corresponding to six lasers 44 at different heights, to achieve six lines on the wall.
[0021] In order to ensure that the laser 44 is fixed firmly, the positioning assembly 4 further includes a clamping member; the clamping member is arranged on a side of the support plate 42 facing away from the sliding ring 41 .
[0022] The clamping member includes a spring 45, a clamping plate 46 and a sliding rod 47; a through hole is provided at one end of the support plate 42 facing away from the sliding collar 41, one end of the sliding rod 47 is inserted into the through hole, the other end of the sliding rod 47 is connected to the clamping plate 46, and the spring 45 is sleeved on the outside of the sliding rod 47 between the clamping plate 46 and the support plate 42. The spring 45 is not only sleeved on the sliding rod 47, but the two ends of the spring 45 are also connected to the clamping plate 46 and the support plate 42 respectively. When the clamping plate 46 is pulled away from the support plate 42, the spring 45 stretches, and the distance between the clamping plate 46 and the sliding collar 41 becomes larger, which is convenient for taking out the laser 44 on the support plate 42, or for placing the laser 44 on the support plate 42. When the clamping plate 46 is released, the spring 45 contracts, pulling the clamping plate 46 closer to the direction of the sliding collar 41, and the clamping plate 46 is pressed against one side of the laser 44, and the laser 44 is clamped between the clamping plate 46 and the sliding collar 41. The clamping member of this embodiment not only achieves clamping and fixing of the laser 44 , but also facilitates the disassembly and installation of the laser 44 .
[0023] The locking member 43 includes a locking bolt; a threaded hole is provided on one side of the sliding collar 41, and the locking bolt cooperates with the threaded hole, and one end of the locking bolt is pressed against the suspension pipe 3. By tightening the locking bolt, one end of the locking bolt is pressed against the suspension pipe 3, thereby fixing the sliding collar 41 at a specific height of the suspension pipe 3. Loosening the locking bolt so that the locking bolt and the suspension pipe 3 are spaced apart, the sliding collar 41 can move along the height or length direction of the suspension pipe 3, and the height of the sliding collar 41 can be flexibly adjusted, and the height of the sliding collar 41 directly affects the height of the laser 44, thereby realizing the adjustment of the height of the laser line projected on the wall.
[0024] The suspension tube 3 is provided with a threaded section 31, and the threaded section 31 of the suspension tube 3 is matched with a height adjustment nut 5, and the height adjustment nut 5 is located above the cross beam 2. In this embodiment, a vertical through hole is provided on the cross beam 2, and the suspension tube 3 passes through the hole and can move vertically relative to the cross beam 2, so as to quickly adjust the overall height of the five positioning components 4. Since the suspension tube 3 falls under the action of gravity, the adjustment nut is always located at the upper end of the cross beam 2. By rotating the adjustment nut, the matching position of the adjustment nut on the threaded section 31 of the suspension tube 3 is changed, so as to control the suspension tube 3 to stay at a certain height.
[0025] Of course, in order to prevent the suspension pipe 3 from being separated from the cross beam 2, the upper end and the lower end of the suspension pipe 3 are respectively provided with a limit plate 6. Under the action of the limit plate 6, the rising or falling space of the suspension pipe 3 relative to the cross beam 2 is limited.
[0026] A bottom plate 7 is provided at the bottom of the frame 1, and wheels 8 are provided at the bottom of the bottom plate 7. A connecting ring 10 is provided at one end of the cross beam 2, and the positioning device further comprises a pull rod 9, and a hook is provided at one end of the pull rod 9, and the hook is connected to the connecting ring 10. The construction personnel pull the pull rod 9 to drag the frame 1 to move in the tunnel.
[0027] The above are only preferred implementations of the utility model. The protection scope of the utility model is not limited to the above embodiments. All technical solutions under the idea of the utility model belong to the protection scope of the utility model. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the utility model should also be regarded as the protection scope of the utility model.
Claims
1. A device for laying and positioning waterproof panels in urban tunnels with super-large sections, characterized in that: include: A frame and at least 5 positioning components; the frame is provided with a crossbeam, and the crossbeam is provided with a suspension pipe; At least five positioning components are arranged on the suspension tube in sequence from top to bottom; the positioning component includes a sliding ring, a support plate connected to the sliding ring, a locking piece and a laser arranged on the support plate; the sliding ring is mounted on the suspension tube and movably cooperates along the height direction of the suspension tube; the locking piece is arranged on the sliding ring and is used to lock and fix the sliding ring on the suspension tube; the laser is used to emit a horizontal mark.
2. A device for laying and positioning waterproof panels in urban tunnels with super-large cross-sections according to claim 1, characterized in that: The positioning assembly also includes a clamping member; the clamping member is arranged on a side of the support plate that is away from the sliding ring.
3. A device for laying and positioning waterproof panels in urban tunnels with super-large sections according to claim 2, characterized in that: The clamping member includes a spring, a clamping plate and a sliding rod; a through hole is provided at one end of the support plate facing away from the sliding ring, one end of the sliding rod is inserted into the through hole, the other end of the sliding rod is connected to the clamping plate, and the spring is sleeved on the outside of the sliding rod between the clamping plate and the support plate.
4. The device for laying and hanging waterproof panels in urban tunnels with super-large sections according to claim 1 is characterized in that: The locking member comprises a locking bolt; a threaded hole is arranged on one side of the sliding ring, the locking bolt cooperates with the threaded hole, and one end of the locking bolt is pressed against the suspension tube.
5. The device for laying and hanging waterproof panels in urban tunnels with super-large sections according to claim 1 is characterized in that: The suspension tube is provided with a threaded section, the threaded section of the suspension tube is matched with a height adjustment nut, and the height adjustment nut is located above the crossbeam.
6. The device for laying and hanging waterproof panels in urban tunnels with super-large sections according to claim 1 is characterized in that: The upper end and the lower end of the suspension pipe are respectively provided with limit plates.
7. The device for laying and hanging waterproof panels in urban tunnels with super-large sections according to claim 1 is characterized in that: A bottom plate is arranged at the bottom of the frame, and wheels are arranged at the bottom of the bottom plate.
8. The device for laying and hanging waterproof panels in urban tunnels with super-large sections according to claim 1 is characterized in that: A connecting ring is arranged at one end of the crossbeam, and the positioning device further comprises a pull rod, a hook is arranged at one end of the pull rod, and the hook is connected to the connecting ring.