Load short-circuit protection system of coal mine power supply system based on 5G communication
By adopting a load short-circuit protection system based on 5G communication in the coal mine power supply system, the detection device collects current and sends tripping signals through 5G communication, solving the problem of short-circuit detection of underground electrical equipment in coal mines, improving protection capabilities and reducing safety hazards.
Patent Information
- Application Number
- CN202420284090.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-06
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-02-06
AI Technical Summary
The underground environment of coal mines causes the insulation aging of electrical equipment, which is prone to short-circuit or phase loss. It is difficult for traditional protection devices to detect small amplitude short-circuit currents, which may lead to protection failure or mismoval, increasing safety hazards.
Design a load short-circuit protection system for coal mine power supply system based on 5G communication. The current amplitude is collected by the detection device at the nearest end of the line, and compared with the setting value. If it exceeds it, it will be determined as a short circuit and send a tripping signal to the protection device through 5G communication. Trip operation, the protection device is set at the end of the line, and tripping is performed after receiving the signal to ensure that the faulty equipment is removed in time.
It effectively solves the protection failure caused by long-distance power supply of coal mines, and improves the protection capacity of the end-of-line load through close-point detection and 5G remote communication, significantly reducing the potential for safety production.
Smart Images

Figure CN222089280U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of coal mine load short-circuit protection, and in particular to a coal mine power supply system load short-circuit protection system based on 5G communication. Background Art
[0002] In the coal mine power supply system, the humid underground environment and high working intensity of the equipment will accelerate the insulation aging of the electrical equipment, which is prone to short circuit or phase loss of the equipment. At the same time, the underground space is narrow and there are flammable materials such as gas and coal dust. If the faulty equipment is not removed in time when a fault occurs, it will cause serious coal mine safety accidents.
[0003] Due to environmental restrictions in coal mines, as the mining surface continues to extend, the power supply lines will become longer and longer, which will lead to a large total resistance and reactance of the short-circuit loop, resulting in a small short-circuit current at the end of the line. Traditional protection is difficult to detect short-circuit currents of small amplitudes, which may cause the protection device to refuse to operate when a fault occurs. Reducing the protection setting value will cause the protection device to malfunction due to normal voltage fluctuations of the equipment.
[0004] Therefore, designing a more reliable load short-circuit detection and protection system has become an urgent problem to be solved. Utility Model Content
[0005] The utility model aims to provide a load short-circuit protection system for a coal mine power supply system based on 5G communication, which overcomes the above-mentioned problems or at least partially solves the above-mentioned problems.
[0006] In order to achieve the above-mentioned purpose, the technical solution of the utility model is specifically implemented as follows:
[0007] The utility model provides a load short-circuit protection system for a coal mine power supply system based on 5G communication, comprising: a detection device and a protection device; wherein: the detection device is arranged at the proximal end of the coal mine power supply system line, and is used to collect the current amplitude of the load; the current amplitude is compared with the current setting value, and if the current amplitude always exceeds the setting value within the setting time, it is determined to be a short circuit, and a trip signal is sent to the protection device through 5G communication; the protection device is arranged at the end of the coal mine power supply system line, and is used to perform a trip operation after receiving the trip signal.
[0008] Wherein, the protection device is further used to receive a reset instruction and send a reset signal to the detection device; the detection device is further used to perform a reset operation after receiving the reset signal.
[0009] Wherein, the load is arranged at the end of the coal mine power supply system line.
[0010] The detection device collects the current amplitude of the load in the following manner: the detection device uses a current transformer, which is installed on a branch of the load to collect the current amplitude of the load.
[0011] The current setting value is 8 times the rated current of the load, and the setting time is 0.4 seconds.
[0012] Wherein, the detection device is also used to send a trip signal to the protection device via an optical fiber.
[0013] It can be seen that the coal mine power supply system load short-circuit protection system based on 5G communication provided by the utility model can effectively solve the problem of protection failure caused by long-distance power supply in coal mines, and improve the protection capability of important loads at the end of the line through near-point detection and 5G remote communication, thereby greatly reducing safety production hazards. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0015] Figure 1 A schematic diagram of the structure of a load short-circuit protection system for a coal mine power supply system based on 5G communication provided in an embodiment of the utility model;
[0016] Figure 2 A flow chart of a load short-circuit protection method for a coal mine power supply system based on 5G communication provided in an embodiment of the utility model. DETAILED DESCRIPTION
[0017] The exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided to enable a more thorough understanding of the present disclosure and to fully convey the scope of the present disclosure to those skilled in the art.
[0018] Figure 1 The schematic diagram of the structure of the load short-circuit protection system of the coal mine power supply system based on 5G communication provided by the embodiment of the utility model is shown in FIG. Figure 1 , the load short-circuit protection system of the coal mine power supply system based on 5G communication provided by the embodiment of the utility model includes:
[0019] Detection devices and protection devices; including:
[0020] The detection device is set at the near end of the coal mine power supply system line to collect the current amplitude of the load; compare the current amplitude with the current setting value, and if the current amplitude always exceeds the setting value within the setting time, it is judged as a short circuit, and the trip signal is sent to the protection device through 5G communication;
[0021] A protection device, which is arranged at the end of the coal mine power supply system line, is used to perform a tripping operation after receiving a tripping signal.
[0022] Specifically, the coal mine power supply system load short-circuit protection system based on 5G communication provided by the embodiment of the utility model is applied to the coal mine power supply system, and the power supply system includes a detection device and a protection device, and the detection device and the protection device communicate through a network connection. The detection device is set at the near end of the coal mine power supply system line, and the protection device is set at the end of the coal mine power supply system line, which can effectively solve the problem of protection failure caused by long-distance power supply in coal mines.
[0023] The protection device may be a host computer.
[0024] When a load short circuit event occurs, the detection device collects the current amplitude of the load branch in real time and determines whether the current amplitude exceeds the current setting value. If it exceeds the current setting value, the detection device starts timing. If the current amplitude is always higher than the current setting value within the setting time, it is judged as a short circuit. The detection device notifies the protection device of the short circuit. At this time, the detection device sends a tripping signal to the protection device via 5G communication, and the protection device trips.
[0025] As an optional implementation of the embodiment of the utility model, the protection device is further used to receive a reset instruction and send a reset signal to the detection device; the detection device is further used to perform a reset operation after receiving the reset signal.
[0026] Specifically, the protection device performs tripping after receiving the tripping signal sent by the detection device. After the staff completes the maintenance, the detection device is notified to reset, and the inspection device continues to detect the load current amplitude.
[0027] As an optional implementation of the embodiment of the utility model, the load is arranged at the end of the coal mine power supply system line.
[0028] As an optional implementation of the embodiment of the utility model, the detection device collects the current amplitude of the load in the following manner: the detection device uses a current transformer, which is installed on the branch of the load to collect the current amplitude of the load. By using the current transformer to collect the current amplitude, the real-time performance and accuracy are improved.
[0029] As an optional implementation of the embodiment of the utility model, the current setting value is 8 times the rated current of the load, and the setting time is 0.4 seconds.
[0030] As an optional implementation of the embodiment of the utility model, the detection device is also used to send the trip signal to the protection device via optical fiber. Of course, in addition to the 5G communication method, the detection device can also send signals via optical fiber as a transmission medium to ensure that the trip signal can be accurately sent to the protection device through a variety of communication methods, thereby improving the safety of short circuit detection.
[0031] It can be seen that the load short-circuit protection method and system of the coal mine power supply system based on 5G communication provided by the utility model can effectively solve the problem of protection failure caused by long-distance power supply in coal mines, and improve the protection capability of important loads at the end of the line through near-point detection and 5G remote communication, thereby greatly reducing safety production hazards.
[0032] Figure 2 The flowchart of the load short-circuit protection method of the coal mine power supply system based on 5G communication provided by the embodiment of the utility model is shown. The load short-circuit protection method of the coal mine power supply system based on 5G communication applies the above system. The following is only a brief description of the process of the load short-circuit protection method of the coal mine power supply system based on 5G communication. For other matters not covered, please refer to the relevant description in the load short-circuit protection system of the coal mine power supply system based on 5G communication, see Figure 2 The present utility model provides a method for protecting a coal mine power supply system load short circuit based on 5G communication, including:
[0033] S1, the detection device collects the current amplitude of the load;
[0034] S2, the detection device compares the current amplitude with the current setting value. If the current amplitude always exceeds the setting value within the setting time, it is determined to be a short circuit, and a trip signal is sent to the protection device through 5G communication;
[0035] S3, the protection device performs a tripping operation after receiving the tripping signal.
[0036] As an optional implementation manner of an embodiment of the utility model, the load short-circuit protection method for a coal mine power supply system based on 5G communication provided by an embodiment of the utility model also includes: the protection device receives a reset instruction and sends a reset signal to the detection device; the detection device performs a reset operation after receiving the reset signal.
[0037] As an optional implementation of the embodiment of the utility model, the load is arranged at the end of the coal mine power supply system line.
[0038] As an optional implementation of the embodiment of the utility model, the detection device collects the current amplitude of the load, including: the detection device uses a current transformer, which is installed on the branch of the load to collect the current amplitude of the load.
[0039] As an optional implementation of the embodiment of the utility model, the current setting value is 8 times the rated current of the load, and the setting time is 0.4 seconds.
[0040] As an optional implementation manner of an embodiment of the utility model, the load short-circuit protection method for a coal mine power supply system based on 5G communication provided by an embodiment of the utility model also includes: the detection device sends a tripping signal to the protection device via optical fiber.
[0041] It can be seen that the load short-circuit protection method of the coal mine power supply system based on 5G communication provided by the utility model can effectively solve the problem of protection failure caused by long-distance power supply in coal mines, and improve the protection capability of important loads at the end of the line through near-point detection and 5G remote communication, thereby greatly reducing safety production hazards.
[0042] The above are only embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included within the scope of the claims of the present application.
Claims
1. A coal mine power supply system load short circuit protection system based on 5G communication, characterized in that: include: Detection devices and protection devices; including: The detection device is arranged at the proximal end of the coal mine power supply system line and is used to collect the current amplitude of the load; Comparing the current amplitude with the current setting value, if the current amplitude always exceeds the setting value within the setting time, it is determined to be a short circuit, and a trip signal is sent to the protection device via 5G communication; The protection device is arranged at the end of the coal mine power supply system line, and is used to perform a tripping operation after receiving the tripping signal.
2. The system according to claim 1, wherein: The protection device is further configured to receive a reset instruction and send a reset signal to the detection device; The detection device is further configured to perform a reset operation after receiving the reset signal.
3. The system according to claim 1, wherein: The load is arranged at the end of the coal mine power supply system line.
4. The system according to claim 1, wherein: The detection device collects the current amplitude of the load in the following manner: The detection device adopts a current transformer, which is installed on the branch of the load to collect the current amplitude of the load.
5. The system according to claim 1, wherein: The current setting value is 8 times the rated current of the load, and the setting time is 0.4 seconds.
6. The system according to claim 1, wherein: The detection device is also used to send a trip signal to the protection device via an optical fiber.