Water heating pool for concrete mixing in winter

By using intelligent control switches and heaters in the concrete mixing water heating pool, combined with external insulation materials, the problem of poor heating effect of concrete mixing water in the existing technology is solved, and rapid and effective concrete heating is achieved, which improves the Construction performance and component quality.

CN222096551UActive Publication Date: 2024-12-03THE THIRD CONSTR OF CHINA CONSTR EIGHTH ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420374441.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-28
Publication Date
2024-12-03
Estimated Expiration
2034-02-28

AI Technical Summary

Technical Problem

The existing concrete mixing water heating effect is poor, resulting in low concrete temperature in winter, prone to segregation problems, affecting construction performance and component quality.

Method used

A winter concrete mixing water heating pool including a reservoir, maintenance port, heater, pump, intelligent control switch and insulation material was designed. The heating temperature and pumping water are automatically adjusted through the intelligent control switch, combined with external insulation material , ensure that the mixing water reaches 40~50℃.

Benefits of technology

It achieves rapid heating, meets the production needs of 1000m³ concrete, improves the winter concrete construction performance, and ensures component quality and durability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222096551U_ABST
    Figure CN222096551U_ABST
Patent Text Reader

Abstract

The utility model discloses a water heating pool for concrete mixing in winter, which comprises a water storage pool, an access hole is arranged on the water storage pool, an access ladder stand is arranged on the pool wall of the access hole of the water storage pool, and a heater, a water suction pump and a connecting pipe are respectively arranged in the water storage pool. The heater, the water suction pump and the connecting pipe are convenient to overhaul and maintain through the overhaul crawling ladder, the heater is hung on a heater hanging frame to be fixed, the heater hanging frame is embedded in a top plate of the water storage pool, and an intelligent control switch is arranged on the water storage pool. The intelligent control switch can automatically control the heating temperature of the heater and the water pumping of the water pump in a working state; the water storage tank is further provided with a water inlet and a water outlet, the water inlet and the water outlet are used for storing, storing and draining water in the water storage tank, the working performance of concrete in winter can meet the construction requirement in winter, the heating speed is high, and the requirement for 1000-meter concrete production can be met within a short time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of concrete winter heating technology, and in particular to a heating water tank for concrete mixing water in winter. Background Technology

[0002] More and more engineering projects are now carrying out concrete construction work in winter. Compared with summer weather conditions, the workability of concrete is significantly reduced in winter due to the low temperature. In order to ensure that the temperature of the mixed concrete reaches the required level for construction, it is necessary to heat and insulate the mixing water to improve the workability of the concrete in winter.

[0003] Most of the self-built mixing plants are open-type water storage tanks. The water used for mixing in the tanks is not heated effectively, resulting in the concrete temperature at discharge after the start of the process being only 15°C. Furthermore, the concrete is prone to segregation, making it difficult to guarantee the workability of the concrete and the quality of the poured concrete components, which may affect the durability of the structure. Utility Model Content

[0004] The purpose of this utility model is to address the shortcomings of existing technologies by providing a heating water tank for concrete mixing in winter. The tank includes a storage tank with an inspection port. An inspection ladder is installed on the tank wall above the inspection port. Inside the tank are a heater, a water pump, and connecting pipes. The inspection ladder facilitates the maintenance and repair of these components. The heater is suspended and fixed on a heater suspension frame embedded in the top plate of the tank. An intelligent control switch is installed on the tank, which automatically controls the heating temperature of the heater and the pumping of water. The tank also has an inlet and an outlet for storing and draining water.

[0005] Preferably, the water storage tank includes a first water tank and a second water tank connected to each other. The first water tank serves as a backup water tank for heating and heat preservation of the mixing water. The heated hot water in the second water tank is directly supplied to the mixing tower for use. When the intelligent control switch is in operation, it can pump and distribute the water in the first and second water tanks of the water storage tank.

[0006] Preferably, the water storage tank is wrapped with thermal insulation material.

[0007] Preferably, the heater suspension bracket is pre-embedded in the top plate of the water storage tank and equipped with suspension hooks to facilitate the installation and fixing of the heater.

[0008] In summary, this utility model has the following beneficial effects: This utility model discloses a heating water tank for concrete mixing in winter, including a water storage tank, inspection port, water outlet, water inlet, water pump, connecting pipe, heater, intelligent switch, ladder, external insulation, water temperature controller float, and inspection port cover. During concrete mixing in winter, it can provide mixing water at 40~50℃, ensuring that the workability of concrete in winter meets the construction needs. The heating speed is relatively fast, and it can meet the production of 1000m³ of concrete in a short time. Attached Figure Description

[0009] The accompanying drawings are provided to further illustrate the present invention and form part of the specification. They are used together with the embodiments of the present invention to explain the present invention, but do not constitute a limitation thereof. In the drawings:

[0010] Figure 1 This is a schematic plan view of the water storage tank of this utility model;

[0011] Figure 2 This is a schematic cross-sectional view of the water storage tank of this utility model.

[0012] In the diagram: 1. Water storage tank; 2. Inspection port; 3. Insulation material; 4. Inspection ladder; 5. Heater; 6. Heater suspension frame; 7. Water pump; 8. Connecting pipe; 9. Intelligent control switch; 10. Water inlet; 11. Drain. Detailed Implementation

[0013] The technical solution of this utility model will be described in detail below with reference to the accompanying drawings, but the protection scope of this utility model is not limited to the described embodiments.

[0014] Reference Figure 1 and Figure 2 This utility model discloses a heating water tank for concrete mixing in winter, comprising a water storage tank 1, an inspection port 2 (including a manhole cover), insulation material 3, an inspection ladder 4, a heater 5, a heater suspension frame 6, a water pump 7, a connecting pipe 8, an intelligent control switch 9, an inlet 10, and an outlet 11. The water storage tank 1 is divided into a first water tank and a second water tank, and is externally wrapped with insulation material 3. Inspection ports 2 (including manhole covers) are respectively provided in the first and second water tanks of the water storage tank 1. An inspection ladder 4 is provided on the wall of the inspection port 2 to facilitate the inspection and maintenance of the heater 5, the water pump 7, and the connecting pipe 8 inside the water storage tank 1. The heater 5 is suspended and fixed on the heater 5 suspension frame, which is pre-embedded in the top plate of the water storage tank 1. The intelligent control switch 9 can automatically control the heating temperature of the heater 5 and the water pump 7 to pump water when in operation. The inlet 10 and the outlet 11 are used for storing water and draining water from the water storage tank 1.

[0015] In this invention, the intelligent control switch 9, when in operation, can preset the start time of heating and adjust the preheating temperature to automatically heat and maintain the temperature of the mixing water in the water storage tank 1, thereby ensuring that the temperature of the mixing water meets the construction requirements. Furthermore, the intelligent control switch 9, when in operation, can pump and distribute water from the first and second water tanks divided into the water storage tank 1.

[0016] The heater 5 suspension bracket is pre-embedded in the top plate of the water storage tank 1, and is equipped with a suspension hook to facilitate the installation and fixing of the heater 5.

[0017] The inspection port 2 (including the manhole cover), inspection ladder 4, water inlet 10, and drainage outlet 11 form an inspection and maintenance system, which facilitates the inspection and maintenance of the heater 5, heater 5 suspension frame, water pump 7, and connecting pipe 8 inside the water storage tank 1.

[0018] The insulation material 3 is wrapped around the outside of the water storage tank 1 to reduce the rate of temperature drop of the mixing water and achieve the insulation effect.

[0019] The water storage tank 1 is divided into a first water tank and a second water tank. Before each operation, the first and second water tanks work together to heat the water in the tanks. After the water is heated to the temperature required for construction, the first water tank is used as a backup water tank for heating and heat preservation of the mixing water. The heated hot water in the second water tank is directly supplied to the mixing plant for use.

[0020] Working Principle: When using the heating water tank for concrete mixing in winter, the outside of the tank is wrapped with insulation material 3 to keep the mixing water warm and reduce the rate of temperature drop. Before each operation, the first and second water tanks work together to heat the water in the tanks. After heating to the construction temperature, the first water tank serves as a backup water tank for heating and insulation of the mixing water, while the pre-heated hot water from the second water tank is directly supplied to the mixing plant. The heating time and temperature of the heater 5 are controlled by the intelligent control switch 9, and the water in the first and second water tanks is adjusted by the water pump 7 inside the tank to promptly deliver the heated water to the mixing plant. This facilitates the inspection and maintenance of the heater 5, water pump 7, and connecting pipes 8 inside the water storage tank 1.

[0021] As described above, although the present invention has been shown and described with reference to specific preferred embodiments, it should not be construed as limiting the present invention itself. Various changes in form and detail may be made thereto without departing from the spirit and scope of the present invention as defined in the appended claims.

Claims

1. A heating pool for concrete mixing water in winter, characterized by: It includes a water tank, which is provided with an inspection port, and a maintenance ladder is provided on the pool wall of the inspection port. A heater, a water pump and a connecting pipe are respectively provided inside the water tank, and the inspection ladder is used to facilitate the inspection and maintenance of the heater, the water pump and the connecting pipe. The heater is suspended and fixed on a heater hanging frame, and the heater hanging frame is pre-buried in the top plate of the water tank. The water tank is provided with an intelligent control switch, and the intelligent control switch can automatically control the heating temperature of the heater and the pumping of water by the water pump in a working state; the water tank is also provided with a water inlet and a drain, and the water inlet and the drain are used to store and drain water from the water tank.

2. A heating pool for concrete mixing water in winter according to claim 1, characterized in that: The water reservoir comprises a first water tank and a second water tank which are connected to each other. The first water tank is used as a backup water tank to heat and keep the mixing water warm. The heated hot water in the second water tank is directly supplied to the mixing plant for use. When the intelligent control switch is in working state, it can pump and allocate water in the first water tank and the second water tank divided by the water reservoir.

3. A heating pool for winter concrete mixing water according to claim 2, characterized in that: The outside of the water reservoir is wrapped with heat-insulating material.

4. A heating pool for concrete mixing water in winter according to claim 3, characterized in that: The heater hanging frame is pre-buried on the top plate of the water storage tank and is provided with a hanging hook to facilitate the installation and fixation of the heater.