Anti-interference structure of hot bending furnace and curved glass processing device
By setting up spaced suction components and suction channels in the hot bending furnace, the temperature and dust interference problems are solved, and the molding quality of 3D curved glass is improved.
Patent Information
- Application Number
- CN202420843035.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-22
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-04-22
AI Technical Summary
The mutual temperature interference and dust interference in each area in the hot bending furnace affect the molding yield of 3D curved glass, which is difficult to effectively solve in the existing technology.
Design an anti-interference structure of a hot bending furnace, by setting a spaced suction assembly between the preheating chamber section and the hot-pressing forming chamber section, the temperature interference is reduced by using the suction channel and the suction pump body, and the heat-pressing forming chamber is reduced. A spaced suction assembly is provided between the section and the cooling chamber section to achieve timely extraction of dust.
It effectively reduces temperature interference in various areas in the hot bending furnace, reduces wear and dust interference of graphite molds, and improves the molding yield of 3D curved glass.
Smart Images

Figure CN222099778U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of glass processing, in particular to an anti-interference structure of a hot bending furnace and a curved glass processing device. Background Art
[0002] The hot bending process is one of the most core processes in the 3D curved glass manufacturing process, and it is also one of the difficulties. The specific process operation is: placing the flat glass blank with finely carved shapes and holes in a graphite mold, and then putting the graphite mold into a hot bending furnace, and then preheating, hot pressing and cooling in sequence, so that the flat glass blank is formed into 3D curved glass in the mold. For example, the Chinese invention patent with application number 201710125013.5 uses a preheating device set in the molding chamber to gradually preheat the mold and the flat glass blank in the mold, and then uses a hot pressing device set in the molding chamber to further heat the mold and the flat glass blank, and then the mold is The flat glass blank is hot-pressed and formed, and finally the hot-pressed 3D curved glass is cooled and formed by a cooling device arranged in the molding chamber. The preheating device, hot-pressing device and cooling device in the molding chamber are closely arranged one by one. Since the temperatures of the preheating device, hot-pressing device and cooling device are different, the temperatures of the areas where the closely arranged preheating device, hot-pressing device and cooling device are located are easy to interfere with each other, which affects the temperature control of the graphite mold and the flat glass blank. In addition, since graphite is easily worn and dust is generated during mold closing, the molding of the flat glass blank is affected, and then the molding yield of the 3D curved glass is affected. Utility Model Content
[0003] The purpose of the utility model is to overcome the shortcomings of the prior art and provide an anti-interference structure of a hot bending furnace and a curved glass processing device which can reduce the mutual interference of temperatures in various areas of the hot bending furnace and reduce the interference of dust in the hot bending furnace.
[0004] The purpose of this utility model is achieved through the following technical solutions:
[0005] An anti-interference structure of a hot bending furnace, comprising a hot bending furnace, wherein the hot bending furnace is provided with a forming cavity, wherein the forming cavity comprises a preheating cavity section, a hot pressing forming cavity section and a cooling cavity section which are connected in sequence, and the anti-interference structure of the hot bending furnace further comprises at least two interval suction assemblies;
[0006] Each of the interval suction components comprises an interval body and a suction pump body, and at least one suction channel is provided on the interval body of each of the interval suction components;
[0007] The interval main body of the interval suction assembly is arranged at the connection between the preheating cavity section and the hot pressing forming cavity section and is connected to the hot bending furnace, and one end of the corresponding suction channel is respectively connected to the preheating cavity section and the hot pressing forming cavity section, and the corresponding suction pump body is connected to the hot bending furnace and is connected to the other end of the corresponding suction channel;
[0008] The spacing body of the other spacing suction assembly is arranged at the connection between the hot pressing forming cavity section and the cooling cavity section and is connected to the hot bending furnace, and one end of the corresponding suction channel is respectively connected to the hot pressing forming cavity section and the cooling cavity section, and the corresponding suction pump body is connected to the hot bending furnace and is connected to the other end of the corresponding suction channel.
[0009] In one of the embodiments, the spacer body is a heat insulating body.
[0010] In one embodiment, the spacer body is a rock wool board insulation body, a polyurethane foam board insulation body, a polystyrene board insulation body or a glass fiber board insulation body.
[0011] In one embodiment, the number of the interval suction components is at least five, the interval body of each interval suction component is connected to the heat bending furnace, and the suction pump body of each interval suction component is connected to the heat bending furnace;
[0012] The preheating chamber section includes at least four preheating chamber sub-segments connected in sequence, and a spacing body of the spacing suction assembly is arranged at the connection between every two of the preheating chamber sub-segments, one end of the corresponding suction channel is respectively connected with the two adjacent preheating chamber sub-segments, and the corresponding suction pump body is connected with the other end of the corresponding suction channel.
[0013] In one embodiment, the number of the interval suction assemblies is at least six, the interval body of each interval suction assembly is connected to the heat bending furnace, and the suction pump body of each interval suction assembly is connected to the heat bending furnace;
[0014] The hot pressing forming cavity segment includes at least five hot pressing forming cavity sub-segments connected in sequence, and a spacing body of the spacing suction assembly is arranged at the connection between every two of the hot pressing forming cavity sub-segments, one end of the corresponding suction channel is respectively connected with the two adjacent hot pressing forming cavity sub-segments, and the corresponding suction pump body is connected with the other end of the corresponding suction channel.
[0015] In one embodiment, the number of the interval suction assemblies is at least seven, the interval body of each of the interval suction assemblies is connected to the heat bending furnace, and the suction pump body of each of the interval suction assemblies is connected to the heat bending furnace;
[0016] The cooling chamber segment includes at least six cooling chamber sub-segments connected in sequence, and a spacing body of the spacing suction assembly is arranged at the connection between every two cooling chamber sub-segments, one end of the corresponding suction channel is respectively connected with the two adjacent cooling chamber sub-segments, and the corresponding suction pump body is connected with the other end of the corresponding suction channel.
[0017] In one embodiment, the number of the suction channels opened on the interval body of each interval suction assembly is two or more, the two or more suction channels are evenly arranged on the corresponding interval body, and one end of each suction channel is connected to the corresponding suction pump body;
[0018] The other end of each suction channel of the spacing body of one of the spacing suction components is respectively connected to the preheating cavity section and the hot pressing molding cavity section, and the other end of each suction channel of the spacing body of the other spacing suction component is respectively connected to the hot pressing molding cavity section and the cooling cavity section.
[0019] In one embodiment, the spacing body of each spacing suction assembly is used to be arranged in a spaced-apart manner relative to the graphite mold.
[0020] A curved glass processing device, comprising a preheating structure, a hot pressing forming structure, a cooling structure and an anti-interference structure of the hot bending furnace described in any of the above embodiments, wherein the preheating structure is arranged at the preheating cavity section and connected to the hot bending furnace, the hot pressing forming structure is arranged at the hot pressing forming cavity section and connected to the hot bending furnace, and the cooling structure is arranged at the cooling cavity section and connected to the hot bending furnace;
[0021] The spacing body of the spacing suction assembly disposed at the connection between the preheating cavity section and the hot pressing molding cavity section is sandwiched between the preheating structure and the hot pressing molding structure, and the corresponding suction channels are respectively disposed away from the preheating structure and the hot pressing molding structure;
[0022] The spacing body of the spacing suction assembly arranged at the connection between the hot pressing forming cavity section and the cooling cavity section is clamped between the hot pressing forming structure and the cooling structure, and the corresponding suction channels are respectively arranged to avoid the hot pressing forming structure and the cooling structure.
[0023] In one embodiment, the spacing body of one of the spacing suction components is arranged at the bottom of the preheating cavity section and the bottom of the hot pressing molding cavity section, and the spacing body of the other spacing suction component is arranged at the bottom of the hot pressing molding cavity section and the bottom of the cooling cavity section.
[0024] Compared with the prior art, the utility model has at least the following advantages:
[0025] The anti-interference structure of the hot bending furnace of the utility model enables the spacing body of one spacing suction component to be arranged at the connection between the preheating cavity section and the hot pressing forming cavity section, and the spacing body of the other spacing suction component to be arranged at the connection between the hot pressing forming cavity section and the cooling cavity section, so that the two spacing bodies respectively space the preheating cavity section, the hot pressing forming cavity section and the cooling cavity section, thereby reducing the mutual interference of the temperatures of various areas in the hot bending furnace, and further reducing the influence of the temperature control of the graphite mold and the flat glass blank. Further, one end of one suction channel is respectively connected with the preheating cavity section and the hot pressing forming cavity section, one end of the other suction channel is respectively connected with the hot pressing forming cavity section and the cooling cavity section, and the other end of each suction channel is connected with the suction pump body, thereby realizing the timely extraction and cleaning of dust generated by the graphite mold in the hot bending furnace, reducing the interference of dust in the hot bending furnace, and further reducing the influence on the forming of the flat glass blank, and better ensuring the forming yield of 3D curved glass. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.
[0027] Figure 1 It is an anti-interference structure of a hot bending furnace according to one embodiment of the utility model;
[0028] Figure 2 for Figure 1 A partial view of the anti-interference structure of the hot bending furnace shown;
[0029] Figure 3 for Figure 1 A partial enlarged view of the anti-interference structure of the hot bending furnace shown in FIG.
[0030] Figure 4 for Figure 1 A partial cross-sectional view of the anti-interference structure of the hot bending furnace shown;
[0031] Figure 5 This is a schematic structural diagram of a curved glass processing device according to one embodiment of the utility model;
[0032] Figure 6 for Figure 5 A partial view of the curved glass processing device shown. DETAILED DESCRIPTION
[0033] In order to facilitate the understanding of the present invention, the present invention will be described more comprehensively with reference to the relevant drawings. The drawings provide preferred embodiments of the present invention. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thoroughly and comprehensively understood.
[0034] It should be noted that when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only and do not represent the only implementation method.
[0035] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art in the technical field of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.
[0036] The present application provides an anti-interference structure of a heat bending furnace. The anti-interference structure of the heat bending furnace includes a heat bending furnace and at least two interval suction assemblies. The heat bending furnace is provided with a forming cavity, and the forming cavity includes a preheating cavity section, a hot pressing forming cavity section and a cooling cavity section which are connected in sequence. Further, each interval suction assembly includes an interval body and a suction pump body, and at least one suction channel is provided on the interval body of each interval suction assembly. Further, the interval body of one interval suction assembly is arranged at the connection of the preheating cavity section and the hot pressing forming cavity section and is connected to the heat bending furnace, and one end of the corresponding suction channel is respectively connected to the preheating cavity section and the hot pressing forming cavity section, and the corresponding suction pump body is connected to the heat bending furnace and is connected to the other end of the corresponding suction channel. Further, the interval body of another interval suction assembly is arranged at the connection of the hot pressing forming cavity section and the cooling cavity section and is connected to the heat bending furnace, and one end of the corresponding suction channel is respectively connected to the hot pressing forming cavity section and the cooling cavity section, and the corresponding suction pump body is connected to the heat bending furnace and is connected to the other end of the corresponding suction channel.
[0037] The anti-interference structure of the above-mentioned heat bending furnace enables the spacing body of one spacing suction component to be arranged at the connection between the preheating chamber section and the hot pressing forming chamber section, and the spacing body of the other spacing suction component to be arranged at the connection between the hot pressing forming chamber section and the cooling chamber section, so that the two spacing bodies respectively space the preheating chamber section, the hot pressing forming chamber section and the cooling chamber section, thereby reducing the mutual interference of the temperatures of various areas in the heat bending furnace, and thereby reducing the influence of the temperature control of the graphite mold and the flat glass blank. Further, one end of one suction channel is respectively connected with the preheating chamber section and the hot pressing forming chamber section, and one end of the other suction channel is respectively connected with the hot pressing forming chamber section and the cooling chamber section, while the other end of each suction channel is connected with the suction pump body, thereby realizing the timely extraction and cleaning of dust generated by the graphite mold in the heat bending furnace, reducing the interference of dust in the heat bending furnace, and thereby reducing the influence on the forming of the flat glass blank, and better ensuring the forming yield of 3D curved glass.
[0038] In order to better understand the anti-interference structure of the hot bending furnace of the present application, the anti-interference structure of the hot bending furnace of the present application is further explained below:
[0039] Please also read Figures 1 to 4 , an anti-interference structure 10 of a heat bending furnace in one embodiment includes a heat bending furnace 100 and at least two interval suction assemblies 200. The heat bending furnace 100 is provided with a forming cavity 101, and the forming cavity 101 includes a preheating cavity section 102, a hot pressing forming cavity section 103 and a cooling cavity section 104 which are connected in sequence. Further, each interval suction assembly 200 includes an interval body 210 and a suction pump body (not shown), and at least one suction channel 201 is provided on the interval body 210 of each interval suction assembly 200. Further, the interval body 210 of one interval suction assembly 200 is arranged at the connection between the preheating cavity section 102 and the hot pressing forming cavity section 103 and connected to the heat bending furnace 100, and one end of the corresponding suction channel 201 is respectively connected to the preheating cavity section 102 and the hot pressing forming cavity section 103, and the corresponding suction pump body is connected to the heat bending furnace 100 and connected to the other end of the corresponding suction channel 201. Furthermore, the spacing body 210 of another spacing suction assembly 200 is arranged at the connection between the hot pressing forming cavity section 103 and the cooling cavity section 104 and is connected to the heat bending furnace 100, and one end of the corresponding suction channel 201 is respectively connected to the hot pressing forming cavity section 103 and the cooling cavity section 104, and the corresponding suction pump body is connected to the heat bending furnace 100 and is connected to the other end of the corresponding suction channel 201.
[0040] The anti-interference structure 10 of the above-mentioned hot bending furnace 100 makes the spacer body 210 of one spacer suction assembly 200 be arranged at the connection between the preheating cavity section 102 and the hot pressing molding cavity section 103, and the spacer body 210 of the other spacer suction assembly 200 is arranged at the connection between the hot pressing molding cavity section 103 and the cooling cavity section 104, that is, the two spacer bodies 210 respectively space the preheating cavity section 102, the hot pressing molding cavity section 103 and the cooling cavity section 104, thereby reducing the mutual interference of the temperatures of various regions in the hot bending furnace 100, thereby reducing the graphite mold and the flat glass In order to control the temperature of the glass blank, one end of one suction channel 201 is connected to the preheating chamber section 102 and the hot pressing molding chamber section 103 respectively, and one end of the other suction channel 201 is connected to the hot pressing molding chamber section 103 and the cooling chamber section 104 respectively, and the other end of each suction channel 201 is connected to the suction pump body, so that the dust generated by the graphite mold in the hot bending furnace 100 can be timely extracted and cleaned, the interference of the dust in the hot bending furnace 100 is reduced, and the influence on the molding of the flat glass blank is reduced, thereby better ensuring the molding yield of the 3D curved glass.
[0041] In one embodiment, the spacer body is a heat-insulating body. Further, the spacer body is a rock wool board heat-insulating body, a polyurethane foam board heat-insulating body, a polystyrene board heat-insulating body or a glass fiber board heat-insulating body, which better achieves the reduction of the mutual interference of the temperature of each area in the hot bending furnace, thereby reducing the influence of the temperature control of the graphite mold and the flat glass blank, and better ensures the molding yield of the 3D curved glass.
[0042] Please also read Figures 1 to 4 In one embodiment, the number of the interval suction assemblies 200 is at least five, the interval main body 210 of each interval suction assembly 200 is connected to the heat bending furnace 100, and the suction pump body of each interval suction assembly 200 is connected to the heat bending furnace 100. Further, the preheating chamber section 102 includes at least four preheating chamber sub-sections 105 connected in sequence, and a interval main body 210 of the interval suction assembly 200 is arranged at the connection between every two preheating chamber sub-sections 105, one end of the corresponding suction channel 201 is respectively connected to the two adjacent preheating chamber sub-sections 105, and the corresponding suction pump body is connected to the other end of the corresponding suction channel 201, so as to better achieve the reduction of the mutual interference of the temperature of each area in the heat bending furnace 100, thereby reducing the influence of the temperature control of the graphite mold and the flat glass blank, and better ensuring the molding yield of the 3D curved glass.
[0043] Please also read Figures 1 to 4In one embodiment, the number of the interval suction assemblies 200 is at least six, and the interval main body 210 of each interval suction assembly 200 is connected to the heat bending furnace 100, and the suction pump body of each interval suction assembly 200 is connected to the heat bending furnace 100. Further, the hot pressing molding cavity segment 103 includes at least five hot pressing molding cavity sub-segments 106 that are connected in sequence, and a interval main body 210 of the interval suction assembly 200 is arranged at the connection between every two hot pressing molding cavity sub-segments 106, and one end of the corresponding suction channel 201 is respectively connected to the two adjacent hot pressing molding cavity sub-segments 106, and the corresponding suction pump body is connected to the other end of the corresponding suction channel 201, so as to better achieve the reduction of the mutual interference of the temperature of each area in the heat bending furnace 100, thereby reducing the influence of the temperature control of the graphite mold and the flat glass blank, and better ensuring the molding yield of the 3D curved glass.
[0044] Please also read Figures 1 to 4 In one embodiment, the number of the interval suction assemblies 200 is at least seven, the interval main body 210 of each interval suction assembly 200 is connected to the heat bending furnace 100, and the suction pump body of each interval suction assembly 200 is connected to the heat bending furnace 100. Further, the cooling cavity segment 104 includes at least six cooling cavity sub-segments 107 connected in sequence, and a interval main body 210 of the interval suction assembly 200 is arranged at the connection between every two cooling cavity sub-segments 107, one end of the corresponding suction channel 201 is respectively connected to the two adjacent cooling cavity sub-segments 107, and the corresponding suction pump body is connected to the other end of the corresponding suction channel 201, so as to better achieve the reduction of the mutual interference of the temperature of each area in the heat bending furnace 100, thereby reducing the influence of the temperature control of the graphite mold and the flat glass blank, and better ensuring the molding yield of the 3D curved glass.
[0045] Please also read Figures 1 to 4 In one embodiment, the number of suction channels 201 opened on the spacing body 210 of each spacing suction assembly 200 is two or more, and the two or more suction channels 201 are evenly arranged on the corresponding spacing body 210, and one end of each suction channel 201 is connected to the corresponding suction pump body. Furthermore, the other end of each suction channel 201 of the spacing body 210 of one spacing suction assembly 200 is respectively connected to the preheating cavity section 102 and the hot pressing molding cavity section 103, and the other end of each suction channel 201 of the spacing body 210 of another spacing suction assembly 200 is respectively connected to the hot pressing molding cavity section 103 and the cooling cavity section 104, which better ensures the suction channel 201 to have a good effect of extracting and cleaning the dust generated by the graphite mold.
[0046] In one of the embodiments, the spacing body of each spacing suction assembly is used to avoid the graphite mold, which can better reduce the impact on the preparation efficiency of the 3D curved glass while ensuring the molding yield of the 3D curved glass.
[0047] Please also read Figure 5 to Figure 6 The present application provides a curved glass processing device 10A. The curved glass processing device 10A comprises a preheating structure 20, a hot pressing molding structure 30, a cooling structure 40 and a hot bending furnace 100 of any of the above embodiments. The anti-interference structure 10 of the hot bending furnace 100, the preheating structure 20 is arranged at the preheating cavity section 102 and connected to the hot bending furnace 100, the hot pressing molding structure 30 is arranged at the hot pressing molding cavity section 103 and connected to the hot bending furnace 100, and the cooling structure 40 is arranged at the cooling cavity section 104 and connected to the hot bending furnace 100. Further, the spacing body 210 of the spacing suction assembly 200 arranged at the connection between the preheating cavity section 102 and the hot pressing molding cavity section 103 is sandwiched between the preheating structure 20 and the hot pressing molding structure 30, and the corresponding suction channel 201 is arranged to avoid the preheating structure 20 and the hot pressing molding structure 30, respectively. Furthermore, the spacing body 210 of the spacing suction assembly 200 arranged at the connection between the hot pressing molding cavity section 103 and the cooling cavity section 104 is clamped between the hot pressing molding structure 30 and the cooling structure 40, and the corresponding suction channel 201 is respectively arranged to avoid the hot pressing molding structure 30 and the cooling structure 40.
[0048] The above-mentioned curved glass processing device 10A adopts the anti-interference structure 10 of the heat bending furnace 100, which better ensures the molding yield of 3D curved glass.
[0049] Please also read Figure 5 to Figure 6 In one embodiment, the spacing body 210 of one spacing suction assembly 200 is arranged at the bottom of the preheating chamber section 102 and the bottom of the hot pressing molding chamber section 103, and the spacing body 210 of the other spacing suction assembly 200 is arranged at the bottom of the hot pressing molding chamber section 103 and the bottom of the cooling chamber section 104. Since graphite dust is more likely to accumulate at the bottom of the hot bending furnace 100, the spacing body 210 is arranged at the bottom of the molding cavity 101, which better ensures the suction channel 201 to extract and clean the dust generated by the graphite mold.
[0050] Compared with the prior art, the utility model has at least the following advantages:
[0051] The anti-interference structure 10 of the hot bending furnace 100 of the utility model makes the spacer body 210 of one spacer suction assembly 200 be arranged at the connection between the preheating cavity section 102 and the hot pressing molding cavity section 103, and the spacer body 210 of the other spacer suction assembly 200 is arranged at the connection between the hot pressing molding cavity section 103 and the cooling cavity section 104, that is, the two spacer bodies 210 respectively space the preheating cavity section 102, the hot pressing molding cavity section 103 and the cooling cavity section 104, thereby reducing the mutual interference of the temperature of each area in the hot bending furnace 100, thereby reducing the graphite mold flat In order to control the temperature of the flat glass blank, one end of one suction channel 201 is connected to the preheating chamber section 102 and the hot pressing forming chamber section 103, and one end of the other suction channel 201 is connected to the hot pressing forming chamber section 103 and the cooling chamber section 104, respectively. The other end of each suction channel 201 is connected to the suction pump body, thereby realizing the timely extraction and cleaning of dust generated by the graphite mold in the hot bending furnace 100, reducing the interference of dust in the hot bending furnace 100, and further reducing the influence on the forming of the flat glass blank, and better ensuring the forming yield of 3D curved glass.
[0052] The above-mentioned embodiments only express several implementation methods of the utility model, and the description is relatively specific and detailed, but it cannot be understood as limiting the scope of the utility model patent. It should be pointed out that for ordinary technicians in this field, several modifications and improvements can be made without departing from the concept of the utility model, which all belong to the protection scope of the utility model. Therefore, the protection scope of the utility model patent shall be based on the attached claims.
Claims
1. An anti-interference structure of a hot bending furnace, comprising a hot bending furnace, wherein the hot bending furnace is provided with a forming cavity, wherein the forming cavity comprises a preheating cavity section, a hot pressing forming cavity section and a cooling cavity section which are connected in sequence, It is characterized in that The anti-interference structure of the hot bending furnace also includes at least two interval suction assemblies; Each of the interval suction components comprises an interval body and a suction pump body, and at least one suction channel is provided on the interval body of each of the interval suction components; The interval main body of the interval suction assembly is arranged at the connection between the preheating cavity section and the hot pressing forming cavity section and is connected to the hot bending furnace, and one end of the corresponding suction channel is respectively connected to the preheating cavity section and the hot pressing forming cavity section, and the corresponding suction pump body is connected to the hot bending furnace and is connected to the other end of the corresponding suction channel; The spacing body of the other spacing suction assembly is arranged at the connection between the hot pressing forming cavity section and the cooling cavity section and is connected to the hot bending furnace, and one end of the corresponding suction channel is respectively connected to the hot pressing forming cavity section and the cooling cavity section, and the corresponding suction pump body is connected to the hot bending furnace and is connected to the other end of the corresponding suction channel.
2. The anti-interference structure of the hot bending furnace according to claim 1, It is characterized in that The spacer body is a heat insulating body.
3. The anti-interference structure of the hot bending furnace according to claim 1, It is characterized in that The partition body is a rock wool board insulation body, a polyurethane foam board insulation body, a polystyrene board insulation body or a glass fiber board insulation body.
4. The anti-interference structure of the hot bending furnace according to claim 1, It is characterized in that The number of the interval suction components is at least five, the interval main body of each of the interval suction components is connected to the heat bending furnace, and the suction pump body of each of the interval suction components is connected to the heat bending furnace; The preheating chamber section includes at least four preheating chamber sub-segments connected in sequence, and a spacing body of the spacing suction assembly is arranged at the connection between every two of the preheating chamber sub-segments, one end of the corresponding suction channel is respectively connected with the two adjacent preheating chamber sub-segments, and the corresponding suction pump body is connected with the other end of the corresponding suction channel.
5. The anti-interference structure of the hot bending furnace according to claim 1, It is characterized in that The number of the interval suction components is at least six, the interval main body of each interval suction component is connected to the heat bending furnace, and the suction pump body of each interval suction component is connected to the heat bending furnace; The hot pressing forming cavity segment includes at least five hot pressing forming cavity sub-segments connected in sequence, and a spacing body of the spacing suction assembly is arranged at the connection between every two of the hot pressing forming cavity sub-segments, one end of the corresponding suction channel is respectively connected with the two adjacent hot pressing forming cavity sub-segments, and the corresponding suction pump body is connected with the other end of the corresponding suction channel.
6. The anti-interference structure of the hot bending furnace according to claim 1, It is characterized in that The number of the interval suction components is at least seven, the interval main body of each of the interval suction components is connected to the heat bending furnace, and the suction pump body of each of the interval suction components is connected to the heat bending furnace; The cooling chamber segment includes at least six cooling chamber sub-segments connected in sequence, and a spacing body of the spacing suction assembly is arranged at the connection between every two cooling chamber sub-segments, one end of the corresponding suction channel is respectively connected with the two adjacent cooling chamber sub-segments, and the corresponding suction pump body is connected with the other end of the corresponding suction channel.
7. The anti-interference structure of the hot bending furnace according to claim 1, It is characterized in that The number of the suction channels opened on the interval body of each interval suction assembly is two or more, the two or more suction channels are evenly arranged on the corresponding interval body, and one end of each suction channel is connected to the corresponding suction pump body; The other end of each suction channel of the spacing body of one of the spacing suction components is respectively connected to the preheating cavity section and the hot pressing molding cavity section, and the other end of each suction channel of the spacing body of the other spacing suction component is respectively connected to the hot pressing molding cavity section and the cooling cavity section.
8. The anti-interference structure of the hot bending furnace according to claim 1, It is characterized in that The spacing body of each spacing suction assembly is used for avoiding the graphite mold.
9. A curved glass processing device, It is characterized in that The invention comprises a preheating structure, a hot pressing forming structure, a cooling structure and an anti-interference structure of a hot bending furnace according to any one of claims 1 to 8, wherein the preheating structure is arranged at the preheating cavity section and connected to the hot bending furnace, the hot pressing forming structure is arranged at the hot pressing forming cavity section and connected to the hot bending furnace, and the cooling structure is arranged at the cooling cavity section and connected to the hot bending furnace; The spacing body of the spacing suction assembly disposed at the connection between the preheating cavity section and the hot pressing molding cavity section is sandwiched between the preheating structure and the hot pressing molding structure, and the corresponding suction channels are respectively disposed away from the preheating structure and the hot pressing molding structure; The spacing body of the spacing suction assembly arranged at the connection between the hot pressing forming cavity section and the cooling cavity section is clamped between the hot pressing forming structure and the cooling structure, and the corresponding suction channels are respectively arranged to avoid the hot pressing forming structure and the cooling structure.
10. The curved glass processing device according to claim 9, It is characterized in that The spacing body of one of the spacing suction components is arranged at the bottom of the preheating cavity section and the bottom of the hot pressing molding cavity section, and the spacing body of the other spacing suction component is arranged at the bottom of the hot pressing molding cavity section and the bottom of the cooling cavity section.